Entitlement Summary Entitling this project will consist of concurrent permitting and design review. Preceding the entitlement process will be an exploratory, design, and outreach phase totaling four months.
Land Use Entitlement Process Pre-entitlement An exploratory, design, and outreach phase will precede the entitlement process .This phase will last four months and will be structured as follows: 1. 1st Round of outreach Reaching out to the community regarding this strategy for the site, potential uses for the site, and the community’s desires and concerns related to development in the neighborhood. The outreach includes networking with the following groups: •
Local business owners
•
Homeowners Associations
•
Wallingford Community Council Land Use Committee
•
Wallingford Chamber of Commerce
2. Develop initial massing and design explorations 3. 2nd Round of outreach •
Hold several follow up conversations with community members
4. Revising designs and contacting any individuals or groups that may have been identified in earlier conversations 5. 3rd Round of outreach (optional) •
Holding, if necessary, a potential additional round of final preentitlement community conversations
6. Revising designs/massing if necessary
22
Pre-entitlement Public Outreach Timeline