Prefeasibility Report of implementation of SUT in Vientiane

Page 1

Technical Assistance Consultant’s Report

Lao People's Democratic Republic: Prefeasibility Study Report TA 7243: Implementation of Asian City Transport Vientiane Sustainable Urban Transport Project Financed by the Asian Development Bank

For:

Ministry of Public Works and Transport Lao People's Democratic Republic

This consultant’s report does not necessarily reflect the views of ADB or the Government concerned, and the ADB and the Government cannot be held liable for its contents.


CURRENCY EQUIVALENTS (as of February 2011) Currency Unit – Kip (KN) KN 1.00 = $0.0001242 $1.00 = KN 8,043 ABBREVIATIONS ADB AM CCF CTA DMC DMF DOT DPWT DUPH EA EIRR EMP ESE EST FIRR GHG IEE IA JICA LDC LRM MPI MPWT NDF NEC NTP O&M PEA PDR PPTA STI SUT SUTF TA TDM UDAA VSBC VSUTP VUDAA WACC WREA

– – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – – –

Asian Development Bank Aide-Memoire Climate Change Fund Chief Technical Advisor Developing Member Country Design Monitoring Framework Department of Transport Department of Public Works and Transport Department of Urban Planning and Housing Executing Agency Economic Internal Rate of Return Environmental Management Plan Environmental Safeguards Expert Environmentally Sustainable Transport Financial Internal Rate of Return Green House Gases Initial Environmental Examination Implementing Agency Japan International Cooperation Agency Least Developed Countries Lao Resident Mission of ADB Ministry of Planning and Investment Ministry of Public Works and Transport Nordic Development Fund National Environmental Committee Notice to Proceed Operations and Maintenance Pilot EST Agency People’s Democratic Republic Project Preparation Technical Assistance Sustainable Transport Initiative Sustainable Urban Transport Sustainable Urban Transport Fund Technical Assistance Traffic Demand Management Urban Development Administration Authority Vientiane State Bus Company Vientiane Sustainable Urban Transport Project Vientiane Urban Development Administration Authority Weighted Average Cost of Capital Water Resources and Environmental Agency

NOTE: In this report, "$" refers to US dollars.


Figure 1.1 Vientiane Urban Area

3


CONTENTS Page I.

BACKGROUND

5

II.

THE PROJECT

6

A. Rationale

6

B. Project Components

8

C. Impact, Outcome, and Outputs

10

D. “Indicative” Investment and Financing Plans

10

E. Economic and Financial Assessments

11

F. Safeguard Issues

11

G. Expected Implementation Arrangements

11

III.

TECHNICAL ASSISTANCE

11

IV.

PROJECT PREPARATORY TECHNICAL ASSISTANCE

12

V.

PROCURMENT, RISKS AND NEXT STEPS

12

VI.

KEY PROJECT ISSUES TO BE ADDRESSED

14

APPENDICES 1

List of People Met

15

2

Problem Tree Issues

17

3

Proto – Design Monitoring Framework

18

4

Potential Institutional, Funding, Capacity Building and other Supporting Framework

21

5

Public Transport Improvements and Pilot Route Development

26

6

Traffic Management

35

7

Parking Survey and Analysis

78

8

Walkability Survey

93

9

Traffic Survey

103

10

Economic and Financial Assessments

107

11

Resettlement, Gender and other Social Safeguards

117

12

Rapid Environmental and IEE Assessments

147

13

Indicative Implementation Schedule

167

14

Stakeholder Workshop Comments and Project Response

168

4


I.

BACKGROUND

1. The regional project preparatory technical assistance (R-PPTA 7243): Preparing the Implementation of Asian City Transport – Promoting Sustainable Urban Transport in Asia Project was approved by the Board of the Asian Development Bank (ADB) on 19 February 2009, with an amount of $2,800,000 financed under the Climate Change Fund (CCF). The RPPTA aims to (i) promote urban economic development, and (ii) reduce local pollution and greenhouse gas emissions by developing sustainable urban transport systems that promote non-motorized and public transport while managing the use of private vehicles traffic 1. 2. Vientiane was selected as one of the three pilot cities under the R-PPTA. Kathmandu, Nepal and Davao City, Philippines were also included as pilot cities. An ADB reconnaissance mission (the Mission) 2 was fielded to Vientiane, Lao PDR in April 2010 3 in order to discuss the Vientiane Sustainable Urban Transport Project, VSUTP (the Project). The Mission’s purpose was to (i) confirm project subcomponents with Government; (ii) determine the relationship of such work with that of others donors, most notably JICA; and (iii) confirm the work schedule for the feasibility study under the R-PPTA. 3. This report has been prepared by a team of individual consultants 4, selected by the ADB in accordance with its guidelines. ADB does not have a specific format or template for this type of “scoping” TA. It is clear, though, that the output from this TA will most likely provide much of the basis for an eventual Concept Paper, and be used to assist in the scoping of the PPTA 5. In order to assist with these expected requirements, the presentation of this report has generally been patterned after the ADB Concept Paper template. T he intension is to make it easier to formulate and proceed with the next steps in project processing.

1

R-PPTA 7243 was part of the ADBs Sustainable Transport Initiative (STI) that was created in 2006. The purpose of the STI was to enhance transport sector interventions in order to develop sustainable urban transport (SUT) programs and projects that will provide demonstration/pilot cases for low carbon urban transport solutions and act as a catalyst for further SUT work in ADB’s lending portfolio. 2 The Mission comprised Jamie Leather, Principal Transport Specialist, RSID; Jim Lynch, Director SETU, and Phomma Chanthirath, Project Implementation Officer, LRM. 3 The Mission met officials of the Government including Ministry of Public Works and Transport (MPWT) and Vientiane Urban Development Administration Authority (VUDAA), the Department of Transport (DOT), and t he Department of Urban Planning and H ousing (DUPH). A n Aide Memoire (AM), dated 9 A pril 2010, acknowledged between the ADB and the Department of Planning and Coordination, MPWT, summarized the findings of the Mission. 4 The team consisted of: Urban Transport Specialist/Team Leader, International, Robert M. Anderson; Public Transport Specialist, International, Richard Mabbitt; Transport Economist/Financial Expert, International, Sudhisakdi Manibhandu; U rban Transport Specialist (National), Phongsavanh Inthavongsa; Public Transport Specialist (National) Saykham Soukvanheuang; Transport Economist/Financial Expert (National) Sumphorn Manodham; Social Development/Social Safeguard Expert (National), Chansamone Phengkhay; Environmental Safeguards Expert (National) Somvang Thammavongsa; and Social Development/Social Safeguards Expert (National), Minivanh Pholsena. 5 5 The PPTA is in the LRM pipeline for 2011. ADB. 2010. Indicative Pipeline, Table A2. Lao Resident Mission.

5


II.

A.

THE PROJECT

Rationale

4. The ADB is taking a leading role within the international development community in support of environmentally sustainable transport. It has recently issued its operational plan for sustainable transport (the Plan) outlining the form and thrust of its support for future bank operations in sustainable transport 6. The Plan was aligned with ADB’s Strategy 2020 7. The Strategy recognized transport as an integral part of most of the activities, goods and services required as DMCs strive to establish a sustainable pattern of development. The planning and implementation for future ADB sustainable transport operations has been divided into three phases. This VSUTP is part of Phase 1 (2010 -2011), i.e. “studies and pilot testing of new types of sustainable transport operations”. In a wider sense this two year initial phase is designed to carry out research, consultation, and pilot testing of a range of projects that would eventually lead to new partnerships and new types of ADB transport sector operations. The Plan readily recognizes that the “emerging urban transport problem will be the biggest transport challenge for developing Asia and the Pacific in the coming years”. 5. In order to contribute to the outcome of ADB’s STI, and to align ADB’s lending to Lao PDR in the transport sector with the delivery of clean and energy efficient transport infrastructure and services, this TA will be the initial step in identification and prioritization of SUT pipeline projects for Lao PDR. It will develop demonstration/pilot cases for low carbon urban transport solutions and act as a catalyst for further SUT work in Vientiane, and ultimately throughout the country. 6. The Government has prepared a (draft) Seventh National Plan for submission to the next National Assembly8. The four targets of the Seventh National Plan are: (i) ensured national economic growth, at a minimum of 8% of GDP per year; (ii) achievement of Millennium Development Goals by 2015, and graduating from LDC status by 2020; (iii) achievement of sustainable economic development by preserving national resources and protecting the environment; and (iv) ensured political stability, peace and an orderly society. The VSUTP is consistent with these targets, in particular target (iii) the achievement of sustainable economic development and the protection of the environment 9. 7. Lao PDR, through the Ministry of Works and Transport (MPWT) has prepared a draft national environmentally sustainable transport (EST) strategy 10. The final draft of this EST strategy has been prepared. I t is currently undergoing “final screening” by the Lao PDR, National Environment Committee (NEC), chaired by the Deputy Prime Minister. NEC approval is expected in early 2011. Once it has been finalized and officially issued, the EST strategy will become the overarching EST policy and implementation guideline for the country 11. The 6

ADB. 2010. Sustainable Transport Initiative Operational Plan. Manila. ADB. 2008. Strategy 2020: The Long-Term Strategic Framework of the Asian Development Bank 2008–2020. Manila. 8 Government of Lao PDR 2010. “Draft” Executive Summary: The Seventh National Socio-Economic Development Plan (2011-2015). Vientiane, Capital. The next National Assembly is scheduled to meet in early 2011. 9 Within this target, the Seventh Plan has a s ub-target: “To set up m odels for managing green environments, particularly in the for cities along the Mekong River: Vientiane Capital, Luang Prabang, Kaysone Phomvihane and Pakse. Establish clean development and carbon credit mechanisms in maximize the benefits for the country”. 10 Ministry of Public Works and T ransport. 2010. The National Strategy and Action Plan on Environmental Sustainable Transport, Lao PDR (DRAFT). Vientiane. 11 The strategy is divided into three phases: short term (up to 2010); medium term (2011-2015); long term (20162020). 7

6


Government envisions that this EST strategy will be used: ( i) as a tool for management, monitoring, and evaluation of land transport on a n ationwide basis; (ii) as a guideline for policy decision makers on transport sector in the whole country; (iii) as a national guideline for planning and investment in the transport sector; and (iv) for identifying and prioritizing activities of the national action plan for the transport sector. The EST strategy will establish action plans for nine areas 12 Two of the action plans: Transport Planning and Travel Demand Management; and Environmentally and People Friendly Urban Transport Infrastructure Development are directly in line with the scope of the VSUTP. 8. JICA Japan International Cooperation Agency (JICA) is an active donor partner in providing development technical assistance in the transport sector to the city of Vientiane. Among recent studies undertaken by JICA are (i) the 2008 Vientiane urban transport master plan 13 (VUTMP), including the on-going follow up study to improve the public bus capacity in Vientiane 14 (TCPB); and (ii) the Vientiane urban master plan 15 (VUDMP), which is presently under preparation. T he VUTMP is the most comprehensive transport study of its kind yet undertaken for Vientiane 9. Historically the World Bank has also been a m ajor donor partner in the transport sector in Lao PDR. Presently the World Bank only has one active project: the Road Sector Project 16. The objectives are (a) to improve road services on two main national corridors and the provincial road network; (b) to rehabilitate roads damaged by Typhoon Ketsana in the five affected southern provinces (Attapeu, Sekong, Saravanh, Champasack, and Savannakhet); and (c) to establish and support an emergency contingency fund that will disburse quickly for emergency civil works and construction materials needed to ensure safe operations of affected national and provincial road links during periods of emergency. There are no other World Bank transport projects in the pipeline for Lao PDR. 10. Vientiane Capital City is composed of nine Districts17 encompassing almost 4,000 square km and a present day estimated population of about 750,00018. The urbanized areas are primarily concentrated in only four of the Districts: Chanthabouly, Xaysettha, Sisattanak, Sikhottabong, with an estimated population of about 500,000. [See Figure 1 at the beginning of this report.] The focus of this TA is the city central core area, entirely located in Chanthabouly District. T his core area 19 is relatively small, and only totals about 1.6 square km 20. I t is a 12

EMT has developed Action Plans for (i) Affect on H ealth (Road Safety); (ii) Ambient Air Quality Monitoring and Management; (iii) Vehicle Emission Contract; (iv) Inspection and Maintenance (I/M) of Vehicles; Regulation of Fuel Quality of Standard; (v) Transport Planning and T ravel Demand Management; (vi) Environmentally and P eople Friendly Urban Transport Infrastructure Development; (vii) Traffic Noise Monitoring; (viii) Information and P ublic Awareness; and (ix) Gender Issues. 13 JICA. 2008. The Study of Master Plan on Comprehensive Urban Transport in Vientiane in Lao PDR. Prepared by Katahira & Engineers International. Final Report, September 2008, Vientiane, Lao PDR. 14 JICA. 2010 (on-going). The Project for Improvement of Transportation Capacity of Public Bus in Vientiane Capital of Lao P eople’s Democratic Republic. The Outline Design Report has been prepared by Katahira & Engineers International., December 2010. Vientiane, Lao PDR. 15 JICA 2010. The Project for Urban Development Master Plan Study in Vientiane Capital. U nder preparation by Nippon Koei Co., Ltd., International Development Center of Japan, Pacet Corp., and Oriental Consultants Co., Ltd. Progress Report<Summary>, June 2010. Vientiane, Lao PDR. 16 The Road Sector Project was approved on 25 M arch 2010 (closing date 30 September 2014) with a total project cost of $43.18 million; and with three themes: regional integration, natural disaster management, and infrastructure services for private sector development. The implementing agency is the Ministry of Public Works and Transport. 17 The nine districts are Chanthabouly, Xaysettha, Sisattanak, Sikhottabong, Xaythani, Haythani, Pak-Ngum, Naxaithong and Sangthong. 18 Ministry of Planning and Investment, Lao Department of Statistics. Statistical Yearbook 2009. Vientiane. 19 Refer to Figure A6.1 in Appendix 6. 20 The influence area for use of public transport services is about 2.5 square km.

7


relatively narrow area about 2.5 km in length lying along the northerly banks of the Mekong River. The central core area is a rich mixture of governmental, educational, religious, commercial, financial and residential development. An important feature of the central part of Vientiane is the Conservation Zone 21, or sometimes referred to as the historical zone or the heritage zone. Almost all of the study core area study lies within the Conservation Zone 22. This area is also the tourist center of the city, containing many of the hotels, restaurants, and tourist areas, including five historical Buddhist temples. B.

Project Components 1.

Introduction

11. The terms of reference of the TA identifies three components or packages of the Project: institutional strengthening and capacity development; a p ilot public transport service and facilities; and a demonstration traffic management scheme. These three divisions of project implementation have generally been followed in the report. As the project preparation process moves forward it might be more appropriate to consider dividing the Project into four components/packages: (i) institutional development and capacity development; (ii) a pilot public transport service and facilities; (iii) parking structure and facilities; and (iv) demonstration traffic management scheme. 2.

Potential Institutional, Funding, Capacity Building and other Supporting Framework

12. Based on assessments of current awareness, capacity and needs in the provision, use, management and regulation of the urban transport system in Vientiane, an institutional framework, funding mechanism and capacity building component of the VSUT pilot project has been identified in concept. A proposed pilot EST Agency (PEA) under agreement among, and joint oversight of, all stakeholder agencies will implement, manage the operation and maintenance, and finally extend the solution beyond the pilot project. The pilot entity’s work will be funded through a fiscal measure designed to ensure financial sustainability, and supported by a capability building program that includes strengthening of its management through specialized consulting services commencing at the beginning of implementation and retained through the start-up phase of operations, and an awareness and community participation program to promote public ownership of the VSUTP. 3.

Public Transport Improvements and Pilot Route Development

13. The concept of an inclusive EST public transport system, propelled by clean/efficient energy does not yet exist in Vientiane. Even the basic acceptance that reliability, efficiency, and safety should be integral parts of any public transport system is not practiced. I n order for the city to move in the direction of EST it will require a major shift not only in operational business plans, but also in the basic thinking of public transport carriers. The most effective short term means for Vientiane to begin to move toward sustainable transport will be the implementation of a small, pilot public bus system. P resently there is no public bus service that directly services the Vientiane core area. Based on reviews of recent transport studies, the feedback from focus 21

Refer to Figure A6.5 in Appendix 6. The National Historical and Cultural Heritages Preservation Law declares that five temples (Inpeang, Onteu, Sisaket, Ho Pakeo, Si Muang), one monument, That Luang, and the surrounding areas are protected areas. 22

8


groups and individual interviews with stakeholders, there is pent up demand for dependable, clean and affordable public bus transport services in the core area of the city. 14. Based on a study of existing traffic and the basic internal street layout of the core area, two closed loop routes have been defined that will provide public transport bus coverage to essentially the entire city core area. These routes are depicted graphically in Figure A5.1. The operational model for the proposed development of these two pilot bus shuttle routes is to be based on the following guidelines: (i) maximum convenience to passengers; (ii) dependable and punctual time schedules; (iii) air conditioned, with a c lean, comfortable environment within the bus; (iv) relatively low, fixed bus fares, with free (no cost) transferring from one shuttle loop to the other to complete a trip; and (v) utilization of smart card technology for all fare collections, operating under a policy of “no cash transactions” throughout the system. Appendix 5, Public Transport Improvements and Pilot Route Development provided additional details on this component. 4.

Traffic Management

15. The management of traffic in Vientiane faces many obstacles – physical, attitudinal and institutional. These include poor infrastructure, lack of parking management, entrenched bad driving habits, a sub-optimal pedestrian environment, and poorly coordinated development administration. These are exacerbated by low public awareness of regulations, low levels of parking and traffic enforcement, poor perceptions of road safety, lack of equipment maintenance, and low operating budgets. At the same time the amount of traffic is increasing dramatically. The total number of vehicles registered in Vientiane Capital has doubled over the last five years. 16. Whilst the volumes of traffic in Vientiane are not high by international standards, the streets are mostly narrow, particularly in the historic central area, and uncontrolled parking reduces road space. Uncoordinated developments also contribute to traffic problems, and there are many more in the pipeline. The center of Vientiane has an attractive environment comprising a mixture of colonial French architecture, low-rise shop houses, temples and shady streets. Traffic management can play an important role in preserving this character. 17. The improvements needed to the road, traffic and pedestrian infrastructure are relatively straightforward to identify, and the costs of doing so are moderate compared to major civil works projects23. However, these will have minimal impact on traffic movement and road safety if they are not accompanied by institutional change. The effectiveness of any traffic management strategy in Vientiane will therefore depend to a large extent on the presence of enabling conditions. These will involve changes in institutional structure, education and enforcement. These include:   

The introduction of effective traffic and parking enforcement The education of drivers, other road users, and the regulators Improved coordination and control of new development schemes

23

Refer to Appendix 6, Traffic Management, which describes the analysis undertaken under the traffic management component of the TA, and includes an assessment of the existing situation, key issues, strategy and identification of potential sub-projects. Reference should also be made to associated appendices on the parking survey, walkability survey, and traffic count, (Appendices 7, 8 and 9 respectively).

9


Details of the traffic management assessment are provided in Appendix 6, Traffic Management. C.

Impact, Outcome, and Outputs

18. A design and monitoring framework (DMF) will need to be prepared as part of the Concept Paper during the initial phase of project preparation. In order to give some early input to this future exercise, a “proto” design and monitoring framework has been p repared as part of this TA. Refer to Appendix 3. The impact of the Project as it is now envisioned is summarized as: Improved urban transport operations and systems in the Vientiane City core area that contributes to reduced congestion, GHG emissions and traffic accidents, all as part of a SUT program that supports the National EST Strategy. 19. To focus on a single outcome at this stage will, to a large extent depend on progress during the first half of 2011 in trying to come to a joint vision between the Government and the ADB as to the institutional framework for the implementation and O & M of the Project. The target outcome is expected to be: a functioning successful pilot EST agency mandated to operate and maintain traffic management, parking and a pilot public transport system for the Vientiane City core area. D.

“Indicative” Investment and Financing Plans

20. An “indicative” investment plan, Table 1, has been prepared. The purpose is to provide ADB with an approximation of the level of costs that can reasonably be expected for the various Project components at this early stage of the Project. Table 1: “Indicative” Investment Plan ($ million) Item A.

B. C.

Totala

%

Base Costb 1. Civil Works 2. Vehicles and Equipment 3. Land Acquisition 4. Resettlement 5. Implementation and Monitoring Consultants 6. Institutional Capacity Building Consultants 7. Project Administration Subtotal (A) Contingenciesc Financing During Constructiond Total (A+B+C)

a

9.7 3.7 4.2 0.3 2.2

34.8 13.3 15.0 1.1 7.9

2.6

9.3

0.2 22.9 5.0 0.0 27.9

0.7 82.1 17.9 0.0 100.00

Includes taxes and duties of $ 1.7 million based on a tax rate of 10% on civil works, vehicles and equipment and 1% on consulting services contracts, as applied to base costs and contingencies. b Based on February 2011 prices. c Physical contingencies computed at 10% of base costs. Price contingencies computed at 12% of base costs. d Assumes that all funding will be on a grant basis, i.e. no financing during construction.

10


21. An “indicative” financing plan, Table 2 below, has been prepared in order to provide the ADB with an approximation as to the overall level of financing that might reasonably be expected in order to implement the Project. More specifically it is intended to provide early guidance to ADB of the approximate amount of co-financing that will need to be obtained. Table 2: “Indicative” Financing Plan Amount ($ million)

Source Asian Development Bank Cofinanciersa Government Total a

Share of Total (%)

10.0 13.2 4.7c

b

35.8 47.3 16.9

27.9

100.0

Potential cofinanciers include the NDF, AusAid and others yet to be identified. b Amount indicated for ADB financing based on the 4 July 2010, Indicative Assistance Pipeline, Table A1 of LRM. c Amount indicated for Government financing is based on indicative costs for land acquisition, resettlement and project administration.

E.

Economic and Financial Assessments

22. Based on this TA’s prefeasibility assessment, the VSUT project’s economic internal rate of return (EIRR) is 15.3%. A prefeasibility financial assessment conducted on the bus service sub-project shows a financial internal rate of return (FIRR) significantly above the weighted average cost of capital (WACC) of 3%, indicating strong contribution to project financial viability. Finally, a financial statements analysis was conducted for the PEA as the prospective responsible agency for the project. The results support a positive expectation that the PEA will be able to recover its capital and recurrent operating costs in the project’s urban transport infrastructure and services, which is a positive outlook for the PEA’s sustainability. F.

Safeguard Issues

No major safeguard issues were identified at this prefeasibility stage. Resettlement, gender and other social safeguard issues are summarized in Appendix 11. Environmental safeguard issues, including a rapid environmental assessment is included in Appendix 12. G.

Expected Implementation Arrangements

23. The expected Executing Agency (EA) will be the Ministry of Public Works and Transport. The targeted Implementing Agency (IA) will be the pilot EST unit to be created as a result of this Project, referred to in Appendix 4 as the Pilot EST Agency (PEA) III.

TECHNICAL ASSISTANCE

24. A consultancy for implementation and monitoring will also be r equired. T he interim estimate is that about 42 person-months of international consultants and about 120 personmonths of national consultants will be required. Expertise will be required in project 11


management, civil works design and preparation of civil works procurement documents, preparation of specifications and procurement documents for vehicles and other equipment, construction supervision, and training in operations and maintenance of vehicles and equipment. 25. Capacity development technical assistance will be a key component of the Project. The assistance would be designed to commence about 1 year before completion of the implementation phase of the Project, and continue for total estimated period of about 6 years. It is contemplated that the assistance would be divided into three subprojects: ( i) a community awareness raising and participation program; (ii) an awareness raising and training program for Pilot EST Supervisory Board members and PEA staff; and (iii) the provision of a Chief Technical Advisor (CTA). The consulting services for the CTA would best be rendered full-time, under a separate contract, by an individual with transport management experience acquired in a successful international integrated urban transport agency, such as Singapore Land Transport Authority, Transport for London, or similar. The interim estimate is that about 81 personmonths of international consultants and 18 months of national consultants would be required for the three subprojects 24. IV.

PROJECT PREPARATORY TECHNICAL ASSISTANCE

26. A project preparatory technical assistance (PPTA) will be necessary in order to carry out studies/surveys, investigations and preliminary designs required to adequately prepare the required documentation for ADB project approval. The expected “ Targeting Classification” for the Project is “Targeted Intervention” (TI); and the expected Thematic Priority is Economic Sustainability (ECO). It is estimated that the TA would take about 6 to 8 months to prepare. I t will require a wide range of expertise, including project management; land-use planning; financial and economic analysis; traffic and traffic management engineering; public transport services; architecture and landscape architecture; civil/structural, mechanical and electrical engineering; procurement; training; legal; and institutional capacity development. V.

1

PROCUREMENT, RISKS AND NEXT STEPS

Procurement

27. The initial Procurement Plan for the Project will be prepared as part of the PPTA. In general the procurement will be divided into three categories: (i) civil works and vehicle/equipment procurements required to repair, upgrade and construct new improvements, including a new multi-story car park, and including procurements to provide vehicles and equipment for project operations; (ii) operations and maintenance procurements to select an entity (or entities) to staff, operate and maintain the newly organized PEA; and (iii) consultant procurements. All procurements will be carried in accordance with ADB guidelines and requirements.

24

The international consultant services would include about 4.5 person-months each, for (i) a community awareness and participation specialist, and (ii) for a knowledge management specialist; and about 72 person-months for the international CTA. T he national consultants would include about 9 per son-months each for (i) a community awareness and par ticipation specialist, with a background in public relations and multi-media; and (ii) a knowledge management specialist with a background in training.

12


2

Consideration of the Risk Categorization

28. The Project is considered to be Complex, primarily because the Project will be “breaking new ground” in the methodology to be employed in the implementing, operating, and financing of urban transport in Lao PDR. There will be a number of critical risks involved for the Project to be successful. The primary ones are (i) that the National Assembly will approve a new tax or other mechanism to provide sustainable funding for the pilot EST agency (PEA); (ii) that the Government will approve and commit to the policies and action plan of the National EST Strategy; and (iii) that there will be effective cooperation and coordination among national and local governmental units, donors and private sector entities. 3

Next Steps

29. In general the “next steps” will consist of achieving typical ADB project preparation milestones required for any civil works type of project: preparation and approval of the project concept paper; recruitment of the PPTA consultant and preparation of the PPTA report; and preparation and approval of the Report and Recommendation to the President. Based on discussions with ADB project preparation staff at the Transport and Communications Division, Southeast Asia Department, it is anticipated that his process with take approximately 18 to 20 months to complete. T able 3 established indicative dates for achieving the various key milestones in processing the Project. Appendix 13 presents an overall Indicative Implementation Schedule; a detailed implementation schedule will need to be prepared by the PPTA consultant. Table 3: Next Steps Key Milestones Approve Project Concept Paper a/ Recruitment of PPTA Consultant(s) PPTA Implementation Grant Fact-Finding Mission Board Approval Finalize Approval of RRP Commence Implementation

Assumed Date

2nd Quarter 2011 3rd Quarter 2011 4th Quarter 2011 and 1st Quarter 2012 2nd Quarter 2012 3rd Quarter 2012 4th Quarter 2012 4th Quarter 2012

a/ Including preparation and approval of the Terms of Reference for the PPTA consultants

13


VI.

KEY PROJECT ISSUES TO BE ADDRESSED

30. Certain key issues will need to be addressed during 2011. These issues are discussed and eluded to throughout this report. Some issues are summarized in Table 4. Table 4: Key Issues to be Addressed Issue

Description

Required Clarity and/or Action to be Taken

Integrated approach to project implementation and operations

Responsibility for traffic management, public transport and parking in core area to be integrated under one unique entity, the pilot EST agency (PEA).

Preliminary confirmation from a representative cross section of governmental decision makers in support of an integrated and coordinated approach using the PEA concept.

Financial sustainability

This issue is discussed in detail in Appendix 4, i.e. the institutionalization of a specific fiscal measure designed to ensure financial sustainability

MOF will need to move forward with establishing an EST tax (or similar fiscal measure) for presentation to the National Assembly

Operational sustainability

This issue is discussed in detail in Appendix 4, i.e. the creation of a PEA within the governmental organizational structure

MPWT or other entity will need to move forward with the establishment of a PEA, including drafting of pilot EST MOU among stakeholder entities

Bus maintenance facility site

A definite site for the bus maintenance facility was not able to be identified during this prefeasibility study.

Government to provide a short list of possible sites for the bus maintenance facility

Traffic demand management (TDM)

Utilization of traffic demand management (TDM) approaches in core, particularly regarding parking, i.e. the requirement that users of parking pay the costs directly

Government to confirm that it supports TDM approaches in the core area of Vientiane

Car park facility site(s)

Determine availability of the existing waterslide site for the car park; and/or availability of other sites.

Government to determine if the existing waterslide site is available for the car park, and/or provide a short list of other sites that can be made available for the car park facility

Parking rule enforcement

The PEA will employ traffic wardens to enforce parking rules

The EST MOU to acknowledge the utilization of traffic wardens and their responsibilities.

Resettlement

The implementation of the project will need to take resettlement issues into account in an adequate and transparent manner.

Government will confirm that resettlement issues will be addressed in accordance with ADB guidelines

14


Appendix 1 LIST OF PEOPLE MET Ministry of Public Works and Transport (MPWT) H.E. Mr. Sommad Pholsena

Minister

Department of Transport (DOT) Mr. Viengsavath Siphandone Dr. Bounta Onnavong Mr.Anousone Chanthaphonh

Director General R&D and International Cooperation Director, Vehicle Management Division

Department of Roads (DOR) Mr.Pothong Ngonphachan

Deputy Director General

National Road Safety Committee Mr.Somnuk Mektakul

Head of Secretariat Office

Department of Housing and Urban Planning (DHUP) Mr.Khanthavy Thaiphachanh Acting Director General Dr. Aphisayadeth Insisiengmay Director of Urban Planning Division Department of Transport Mr. Thongvanh Phethaviseng Mr. Phanthaphab Phounsavanh

Deputy General Director

Vientiane Urban Development Administration Authority (VUDAA) Dr. Ketkeo Sihalath Mr.Duangchan Vilachit Mr. Panya Manivong

Vice President Deputy of Traffic management unit Administration Div., Databank Unit

Department of Public Works and Transport of Vientiane Capital (DPWT) Mr.Keophilavanh Aphaylath Mr Somsanith Hodthongkham Mr.Phoutthaphone Khotpanya Mr Khamphay Souvathdy Mr. Bounchanh Keosithamma

Director General Director Development of Transport Division Head of Housing and Town Planning Division Transport Division National Project Manager, Mekong River Integrated Management Project (MRIMP)

Urban Research Institute Mr. Chanthasack Bottaphanith

Urban Planner & Environmental Management Specialist

Dr. Thongdam Saypakassa

Former Director General

Public Works and Transport Institute (PTI) Mr.Thenekham Thongbonh Ms. Pho Ngeun Souvannavong, Mr.Phaknakhone Rattana

Acting Director General Director of Environmental and Social Div. Chief of Environmental Section

15


Appendix 1 Ministry of Finance Mr. Sila Viengkeo

Permanent Secretary, Chief of Cabinet

Ministry of Planning and Investment Department of International Cooperation Mr. Somchith Inthamith Mr. Douangmala Chanthalangsy

Director General of DIC Director of International Financial Institution Div.

Ministry of Public Security, Department of Traffic Police Mr.Khamthavay Phetouthai

Deputy Director General of Traffic Department

Japan International Cooperation Agency (JICA) Ms. Yoko Hattori Representative, Infrastructure Sector NIPPON KOEI, Consulting Engineers Mr. Kuniomi Hirano

The Project for Urban Development Master Plan Study in Vientiane Capital

Embassy of Japan in Lao PDR Mr. Masahiko Mitsumoto

Second Secretary

Project Development Department (Tokyo) Mr. Toshinori Toda

Managing Director

World Bank Office Mr. Sombath Southivong Ms. Khamla Phonsavath

Sr. Infrastructure Specialist Climate Change Analyst

Vientiane State Bus Company Mr. Khamphoune Temerath Mr. Bouapha Phetvixay

Director Deputy Director of Planning

Lao Hotel and Restaurant Association Mr. Oudet Souvannavong

President

Tuk-Tuk Association of Vientiane Mr.Bouaxeng Phissalath

Vice President

Kingkham Transportation Co. Ltd Mr. Khamsay Vongxay

Director

Lao Resident Mission (ADB) Dr.Chong Chi Nai Mr. A. Barend Frielink Mr. Phomma Chanthirath

Country Director Principal Country Economist Project Implementation Officer (Transport)

16


17 Insufficient OffStreet Parking

Basic Driving Laws not Followed or Enforced Frequent Pedestrian Vehicular Conflict

Poorly Enforced On-Street Parking

Inadequate Traffic Control Devices

Road and Traffic Infrastructure in Poor Condition

Narrow Road Rights of Way

Poorly Conceived, Operated and Enforced Traffic Management Systems

Public Buses do not Adequately Service City Core Area

Poor Quality and Coverage of Public Bus Transport and Para-Transport Services Concept of Inclusive and of Clean/ Efficient Energy Public Transport System Does Not Exist

VSBC Uses NonQuality Based Operation Model

Inadequate Development and Poor Delivery of Public Transport Services

Lack of Capacity Development in Planning, Finance, Engineering, and Operations

Inadequate Institutional Coordination and Cooperation

Lack of Institutional Commitment to Enforce Traffic and Zoning Laws and Regulations

Institutional Responsibilities and Authority between Entities Unclear

Inadequate and Weak Urban Transport Institutions

Rapidly Increasing Traffic Congestion in City Core Area

C

Lack of Hierarchy of Urban Road System

PROBLEM TREE ISSUES

Appendix 2


Appendix 3 PROTO - DESIGN AND MONITORING FRAMEWORK Data Sources and/or Reporting Mechanisms

Assumptions and Risks Assumptions

(i) Increase modal share of public transport and non-motorized transport to at least 30% each, and (ii) decrease motorcycle transport only 30% of total urban trips within Vientiane City core area, all by 2020

Government statistics and project developed monitoring mechanisms

• Government approves and is committed to the National Strategy and Action Plan on EST

Reduction by 15% in emissions of GHG [CO2, methane (CH4), nitrous oxide (N2O) and certain halocarbons] by 2020

Government accident data records

Reduction of 25% in vehicle and pedestrian traffic accidents within Vientiane City core area by 2020. (accidents: fatalities, serious and minor)

Reports and records of the new pilot EST agency

Design Summary

Performance Targets/Indicators

Impact Improved urban transport operations and systems in the Vientiane City core area, that contributes to reduced congestion, GHG emissions and traffic accidents, as part of a SUT program that supports the National EST Strategy

Air quality data of WREA monitoring stations

Government budget records

• Government establishes a monitoring system of transport related emissions and accidents in support of the National EST Strategy Risks • Government fails to approve and/or commit to the policies and action plan of the National EST Strategy

Establishment of financial mechanism to insure continuing operation and expansion of the pilot EST agency Outcome A functioning successful pilot EST agency mandated to operate and maintain traffic management, parking and a pilot public transport system for the Vientiane City core area.

Government agreement to develop sustainable urban transport projects and policies in Vientiane Capital City with ADB support

ADB project monitoring documents, mid-term reviews, and project completion report(s) Reports and records of the new pilot EST agency

Assumptions • National Assembly will approve a new tax on turnover for Vientiane to provide sustainable funding of pilot EST agency • Effective cooperation and coordination among national and local governmental units, donors and private sector entities Risks • Government fails to approve and/or commit to the policies and action plan of the National EST Strategy

Outputs Part 1: PPTA 1.

Comprehensive institutional implementation framework that adequately addresses organizational, funding and capacity development requirements for a pilot EST agency, and pilot

Early indications and actions on part of Government of acceptance of establishing a pilot EST agency and the drafting of a pilot EST MOU among stakeholder agencies

18

Final Report for TA 7243: Implementation of Asian City Transport Vientiane Sustainable Urban Transport Project

Assumptions • Government approves and remains committed to the National EST Strategy

ADB Project monitoring

• ADB approves the PPTA


Appendix 3

Design Summary

Performance Targets/Indicators

EST MOU among stakeholder agencies including a draft Business Operating Plan

Other ADB sustainable transport reports and the ADB STI

TOR for Institutional Capacity Development Consultants 3. Draft outline for tax legislation for a new EST Tax 4. Technical, economic and financial feasibility study of a pilot public transport improvements. 5. Detailed economic and financial analyses for VSUTP public transport and traffic management programs 6. Specifications and procurement documents for buses and related equipment 7. Preliminary designs for: multi-story car park, improvements to central bus station, and for traffic management improvements 8. Project Improvement Plan and Financial Plan (per ADB format) 9. TOR for Implementation and Monitoring Consultants Outputs Part 2: Implementation

2.

Assumptions and Risks

reports

2.

1.

Data Sources and/or Reporting Mechanisms

A sustainable Vientiane core urban transport implementation program managed by a functioning pilot EST agency backed by adequate institutional capacity and financial resources to support the delivery of priority urban transport systems improvements that are socially, environmentally, economically and financially sustainable.

Delivery modalities and prioritization for sustainable urban transport are clearly defined and a suitable enabling environment is created with sufficient capacity to establish a pilot EST agency, and to deliver the pilot public transport and traffic management projects.

Final PPTA Report and Final Report for TA 7243: Implementation of Asian City Transport Vientiane Sustainable Urban Transport Project

Assumptions • Government approval and commitment to deliver and support EST for urban transport in Vientiane

ADB Project monitoring reports

Risks • Government will fail to support establishment of pilot EST agency and/or pass tax legislation to fund pilot EST agency

An operating pilot public transport service for the Vientiane core area consisting of 2 shuttle bus loops, 5.2 km and 4.9 km

Pilot public transport service system developed in accordance with the agreed priorities of Government and ADB

Final PPTA Report and Final Report for TA 7243: Implementation of Asian City Transport Vientiane Sustainable

Assumptions • Government and existing public transport entities will support pilot public transport project

19


Appendix 3

Design Summary

Performance Targets/Indicators

Data Sources and/or Reporting Mechanisms

in length operating along Urban Transport Project the four major east-west Technical, economic and roads in the city center, financial feasibility study of pilot ADB Project monitoring including bus operations public transport shuttle buses for reports and maintenance facilities; Vientiane core area the construction of 21 bus stops; and improvements to the existing Central Bus Station. 3. Implementation of various Select and develop traffic Final PPTA Report and traffic management submanagement improvements Final Report for TA projects including multiwithin the Vientiane core area 7243: Implementation of story car park, traffic Asian City Transport management improveVientiane Sustainable ments near Nong Chanh, Urban Transport Project improvements in on-street parking, pedestrian ADB Project monitoring facilities, traffic lights, road reports markings, and support for the traffic control center. Activities with Milestones – PPTA 1. Develop a pilot EST agency framework. 2. Prepare a draft MOU among EST stakeholders 3. Develop TOR for Capacity Development Consultants 4. Draft outline legislation for new EST tax 5. Formulate and finalize details and requirements of pilot public transport bus shuttle loops in city core, including central bus station and bus stop improvements 6. Formulate and finalize details for traffic management improvements and initiatives 7. Prepare preliminary designs of multi-story car park, improvements to central bus station, and for traffic management improvements. 8. Prepare feasibility study for pilot public transport and traffic management improvements 9. Prepare financial analyses for pilot EST agency, and prepare draft Business Plan 10. Prepare TOR Implementation and Monitoring Consultants Activities with Milestones – Implementation 1. Develop a sustinable implementation program for priotization and delivery of key urban transport improvements. 1.1. Develop an insitutional stucture, with capacity development requirements to enable the delivery of priority urban transport system improvements and support the delivery of the National EST strategy and Vientiane urban transport masterplan. 1.2. Assess the option for development of a sustainable urban transport fund, such as an Environmental Transport Fund, to support the Environmental Protection Fund and provide continued development of sustainable urban transport 2.

Assumptions and Risks Risks • Objections to new public transport services from VSBC or other entities

Assumptions • Government commitment to support and implement traffic management improvements in Vientiane core area

Inputs ADB $ 600,000 Government $ 100,000

Inputs ADB: $ 10,000,000 Cofinanciers: $ 13,200,000 Government: $ 4,700,000

Public transport service and operation improvements 2.1. Develop an outline plan for improvements to public transport services, franchising arrangement, coverage area, service integration, and operational efficiencies 2.2. Undertake a feasibility study of a pilot public transport route to demonstrate the proposed service and operational improvements.

3.

Traffic management 3.1 Prepare a demonstration study to improve traffic demand management in the central area including parking control, vehicle restraint, pedestrian facilities, signal improvements and street lighting ADB = Asian Development Bank, EST = environmentally sustainable transport, GHG = greenhouse gases, MOU = memorandum of understandings, PPTA = project preparatory technical assistant, STI = sustainable transport initiative, SUT = sustainable urban transport, TA = technical assistance, TOR = terms of reference, VSBC = Vientiane State Bus Company, WREA = Water Resources and Environmental Agency

20


Appendix 4 POTENTIAL INSTITUTIONAL, FUNDING, CAPACITY BUILDING AND OTHER SUPPORTING FRAMEWORK 1. This appendix describes the analysis conducted for a potential institutional, funding, and capability raising component of the VSUT pilot project; the project location is the City Core as shown in Figure A6.1 (Appendix 6). The analysis, based on assessment of the current practices, identifies key issues and institutional capacity constraints in A, and proposes solution strategy in B. A.

Assessment of the Current Situation 1. Interdependencies in City Core Transport Issues

2. City Core transport issues are interdependent. Figure A4.1 illustrates how problems of traffic congestion, insufficient parking space and lack of reliable and user-friendly public transport in the project area are interdependent. Figure A4.1 Interdependency of Core Area Transport Issues Traffic System

Illegally parked vehicles cause slow and unpredictable traffic flow

Parking System

Congestion prevents accurate bus scheduling, reduces reliability of bus service and attraction of public transport for travelers

With poor public transport, more private vehicle use and worse congestion

Congestion prevents reliable and efficient public transport , encourages more private vehicles and need for more parking space

Without well-conceived parking facilities, a city core bus service lacks a key support

Public Transport

Without quality public transport, there are more private vehicles and illegal parking in the city core

Source: TA Consultants

3. City Core transport and land use issues are interdependent. Figure A4.2 illustrates this second set of interdependencies. A focal point for the hospitality, travel and financial services industries, Pangkham Road is an example of how land use issues affect the traffic and parking system in the City Core. Conversely, for an example of how transport issues can reduce the effectiveness and/or efficiency of the core area land resource, Nokeokhoummane Road, attractively laid out with restaurants and cafes with street-side patios, has high potential as urban recreational space; but illegal parking and congestion spoil the effect. Parking in temple grounds, which detracts from the tranquil atmosphere of the cultural heritage sites, again illustrates the interdependency of transport and land use problems in the core area. 21


Appendix 4 Figure A4.2 Interdependent Core Area Transport and Land Use Issues Urban Transport System Intensifying land use – due to growth of service industries (eg hospitality, banking) – and failed parking regulation are forcing vehicle and pedestrian movements into an unsafe mixed traffic on Pangkham Road

With rising income and financial market development, a growing access to private motor vehicles will support a tendency towards a purchased home in suburbs (cheaper land ) and commuting to work in the city center

Pressure of economic growth on the demand for urban space for living, work, school, recreation etc promotes a rising demand for trips, and greater challenge for the urban transport system

An urban transport system based on highercapacity vehicles will support and promote greater economic activity and more effective land use, avoiding eg the present state of Nokeokhoummane Road (see main text)

Land Use Source: TA Consultants

4. The Government’s two roles as national land asset manager and land use regulator. By law, land in the Lao PDR belongs in common to the country’s nationals, and is managed centrally by the state; that management role includes granting land use concessions 1. On current land concession practices, and recalling the state control of land attached to the numerous public sector premises in the core area, any attempt to resolve the area’s transport and land use issues is likely to come up against an extra complication. To illustrate, offer of a lease or grant of land concession is a common feature of the Government’s investment promotion strategy. Without the combination of awareness and a robust mechanism to coordinate land concessioning with planning and regulation, potential land use and transport problems can easily be passed over in an investment promotion drive. Like a hypothetical giant shopping mall in the core area, the result could mean a grossly unbalanced land use pattern and a disrupted transport system. 2. Institutional Capacity Constraints 5. Figure A4.3 depicts the current organization of the management, provision and regulation of urban transport infrastructure and services in Vientiane 2. The capital’s urban transport is the responsibility of Vientiane Capital Administration. V CA’s Department of Public Works and Transport combines transport and urban planning responsibilities in one unit. DPWT also has a direct reporting responsibility to MPWT on centrally-administered matters, including budgeting. 6. Details of a proposed strategy for sustainable, dynamic mitigation of the urban transport problems in the core area are set out elsewhere in this report. O ne aspect of that solution strategy is relevant to the present discussion; it is the well-coordinated bus public transport 1

Land Law 2003, Article 3. Three Laws – on Land Transport (1997), Public Roads (1999), and Land Traffic (2000) – together describe the legal framework for the state’s role in urban transport. The state is the main provider of urban public transport services through the state owned enterprise Vientiane State Bus Company. 2

22


Appendix 4 service, parking and traffic sub-systems that make up the total urban transport system proposed for the core area. A ssessed in terms of capacity to (i) support, and (ii) promote the required coordination, there are limitations in the current task organization and underlying approach. The major bottlenecks are summarized in paragraphs 7-10. Figure A4.3 Organization of Vientiane Urban Transport Prime Minister

MPWT VCA

Other Ministries

Reporting on technical matters, budget preparation, internationally financed projects and national roads

DPWT

Divisions

Transport

Roads and Bridges

Waterways and Riverbank

Personnel and Administration Planning and Finance Urban Planning and Housing

DPWT= Department of Public Works and Transport; MPWT= Ministry of Public Works and Transport; VCA = Vientiane Capital Administration Source: interviewed VCA official

7. Accountability stops at outputs of activities, and does not extend to their purpose, or larger impact; so the required coordination is not supported. For example, while providing running buses (outputs), VSBC is not made to ensure that drivers follow the regular schedule of a reliable passenger service, even though public transport needs to provide a strong alternative to private vehicles (purpose) to relieve the traffic congestion (impact). 8. When accountability stops at outputs, performance evaluation tends to be limited to outputs. With weak motivation to look beyond outputs, and ever-present risk in acting outside the limits of what is required, to work in coordination from awareness of a larger outcome is therefore not second nature within the organization. Organized according to specialized outputs, without top-down instruction DPWT’s transport and urban planning divisions are likely to be seriously challenged to coordinate interdivisional action and plans. But a departmental head with all the responsibilities in the larger organization would find it impossible to undertake a daily coordinating role for the department’s own divisions. 9. An inter-agency committee can serve to coordinate action in special, but not everyday circumstances. E ach agency on the committee is accountable for its own decreed tasks; a responsibility assigned under a committee resolution assumes a lower ranking. 10. Above all, by not looking beyond outputs, public agencies easily become isolated from the community that depends on their work. This serves to explain the gap between their internal performance evaluation and the users’ poor perception of public service quality. 23


Appendix 4 B.

Solution Strategy Figure A4.4 Pilot VSUTP Institution: Role and Structure

Pilot EST MOU among stakeholder agencies

Supervisory Board

Pilot EST Agency

Traffic

Parking

Bus

Traffic

Parking

Bus

Traffic

Parking

Bus

Stage 1 Pilot project implementation

Stage 2 Pilot project O&M

Stage 3 Extension of solution Beyond pilot project

EST=Environmentally Sustainable Transport; MOU=memorandum of understanding; O&M=operation and maintenance Source: TA Consultants

11. Drawing upon the assessment in section A, a “Pilot EST Agency� (PEA) is proposed for carrying out the pilot VSUTP. 12. PEA role and institutional structure. Formed as a new agency through a memorandum of understanding among stakeholder agencies including those, at all levels of government, with an interest in the urban transport system in the City Core, PEA is under the direct oversight of a supervisory board including representatives of the stakeholder agencies and invited participants. A feasibility study for the VSUTP should include examination of the need and scope for a formal declaration of state policy commitment, perhaps in the form of an EST Law. 13. Figure A4.4 illustrates the responsibility of PEA for taking the pilot project through three stages of implementation, operation and maintenance, and preparing an extension of the solution beyond the pilot project. The principal work of PEA will be management in nature, including planning and managing contracts for delivery of infrastructure, operation and maintenance and other services required under sub-projects. 14. Funding mechanism. To ensure sustained funding of PEA capital and recurrent costs, a new tax (EST Tax) is introduced, calculated on the same base as the present Turnover Tax, and of the order of 1-2% expressed as a percentage of turnover. This indicative range is based on an analysis of government report of the 2008-2009 fiscal year implementation of the state budget. The indicative VSUTP investment and financing plan is described elsewhere in this report. 24


Appendix 4 15. Capacity development. The program of capacity development in support PEA’s responsibility for carrying out the VSUTP is summarized in Table A4.1. Table A4.1 Pilot VUSTP Capacity Development Item 1. Community awareness raising and participation program

Coverage To include use of traffic system, new parking arrangements, public transport

When During implementation

2. Awareness raising program for PEA Supervisory Board Members

To include issues and proposed solution described in this report, and introduction to results chain planning, implementation and monitoring, or similar analytical tool (eg ADB’s design and monitoring framework)

During implementation

3. PEA staff training programs

To be elaborated during VSUTP project preparation, and to include the material for 2

Ongoing from PEA becoming staffed and operational

4. Service of a Chief Technical Officer

Consulting services for capacity building of the PEA management to be provided under contract by an individual advisor with transport management experience acquired in a successful international integrated urban transport agency.

For six years or more starting in the final year of implementation

PEA= Pilot Environmentally Sustainable Transport Agency; VSUTP=Vientiane Sustainable Transport Project. Source: TA Consultants

Separately, technical assistance for pilot VSUTP project implementation support is also proposed; it is detailed elsewhere in this report.

25


Appendix 5

PUBLIC TRANSPORT IMPROVMENTS AND PILOT ROUTE DEVELOPOMENT

I.

INTRODUCTION AND BACKGROUND

1. The primary output from this TA is the identification of potential energy-efficient, clean energy, and inclusive urban transport projects for the city of Vientiane. The objective of the Package 2 component of the TA is to identify public transport projects that also meet these overall “clean” and “inclusive” parameters. As summarized in ADB’s operational plan for STI 1, these types of public transport projects are needed to provide urban populations with safe, secure, accessible, rapid, efficient, and user-friendly transport. In parallel, these projects will serve to reduce urban pollution, congestion, and traffic accidents. 2. More precisely the output for this component will be to identify and develop a conceptual pilot public transport service, that when implemented will provide effective and efficient public transport services. T he TA TOR indicated that the new public transport services should focus on the city core of Vientiane 2, or possibly along a key city transport corridor. Improvements should demonstrate service rationalization that should consider possible franchising and/or related implementation and O and M arrangements, operational efficiencies, service integration if applicable, related civil works requirements and the identification of a transport fleet program. 3. The central core area of Vientiane is rich mixture of Lao traditional, French and contemporary development, with a wide cross section of governmental, educational, religious, commercial, financial and residential structures scattered throughout the core area. An important feature of the central part of Vientiane is the Conservation Zone3, sometimes referred to as the historical zone or the heritage zone. Almost all of the core area of this TA study lies within the Conservation Zone 4. This area is also the tourist center of the city, containing many of the hotels, restaurants, and tourist areas, including five historical Buddhist temples. 4. The Japan International Cooperation Agency (JICA) is a most active donor partner in providing development technical assistance in the transport sector to the city of Vientiane. Among recent studies undertaken by JICA are (i) the 2008 Vientiane urban transport master plan 5 (VUTMP), including the on-going follow up study to improve the public bus capacity in Vientiane 6 (TCPB); and (ii) the Vientiane urban master plan 7 (VUDMP), which is presently under preparation. The VUTMP is the most comprehensive transport study of its kind yet undertaken for Vientiane. It dealt with (i) detailed surveys and analyses of the existing conditions, regarding 1

ADB 2010. Sustainable Transport Initiative, Operational Plan. Manila. The city core area is shown in Appendix 6, Figure A6.1;, which area also incorporates much of the widely recognized Vientiane historical temples and monuments. 3 Refer to Figure A6.5 in Appendix 6. 4 The National Historical and Cultural Heritages Preservation Law declares that five temples (Inpeang, Onteu, Sisaket, Ho Pakeo, Si Muang), one monument, That Luang, and the surrounding areas are protected areas. 5 JICA. 2008. The Study of Master Plan on Comprehensive Urban Transport in Vientiane in Lao PDR. Prepared by Katahira & Engineers International. Final Report, September 2008, Vientiane, Lao PDR. 6 JICA. 2010 (on-going). The Project for Improvement of Transportation Capacity of Public Bus in Vientiane Capital of Lao People’s Democratic Republic. Under preparation by Katahira & Engineers International. Vientiane, Lao PDR. 7 JICA. 2010. The Project for Urban Development Master Plan Study in Vientiane Capital. U nder preparation by Nippon Koei Co., Ltd., International Development Center of Japan, Pacet Corp., and Oriental Consultants Co., Ltd. Progress Report<Summary>, June 2010. Vientiane, Lao PDR. 2

26


Appendix 5

traffic, safety, public transport, environmental and social considerations, and with existing institutional, legal and budget considerations; (ii) preparation of an urban development scenario and traffic demand forecast; and (iii) preparation of an urban transport development plan. From these study components and analyses the following, specific, but rather limited final recommendations were developed: that the Government: (i) approve the Vientiane urban transport master plan, and incorporate it into the national environmental and development policy; (ii) adopt a t arget of “shifting” 40% of trips using motorcycle and private cars to public transport; (iii) seek urgent action to secure right of way for future widening of roads/streets; (iv) prepare a future business plan for the VSBC; (v) establish a committee to discuss urban transport problems; and (vi) implement the pilot public transport project 8 studied in the urban transport master plan. 5. Based on the primary “pilot project” developed by the VUTMP, the Governments of Japan and Lao PDR in 2010 agreed to proceed with a detailed study (the TCPB) to improve the capacity of bus public transit in Vientiane 9. The TCPB inception report identified three components to be studied for eventual implementation with the assistance of Japan Grant Aid. The components identified were: (i) bus procurement (40 units); (ii) a university bus terminal at Dongdok; and (iii) O & M training and capacity building. As originally conceived all the buses were to be used on one route, providing shuttle bus service between downtown Vientiane and the National University of Laos (NUOL) campus at Dongdok. In December 2010, the TCPB outline design report revised the project scope to exclude capacity building, to increase the number of buses to be procured to 42 units 10, and to increase the utilization from the previously identified 1 route to eight VSBC bus routes 11. 6. Lao PDR has prepared a draft national environmental sustainable transport (EST) strategy 12. The final draft of EST strategy is presently under Government review, and is expected to be approved in 2011. Once it has been approved and officially issued it will become the over-arching EST policy and implementation guideline for the country13. The EST strategy will establish specific actions plans for nine areas 14. Two of these areas: (i) Transport Planning and Travel Demand Management; and (ii) Environmentally and People Friendly Urban Transport Infrastructure Development, are in direct concert with the scope of the VSUTP. Specific initiatives mentioned in the EST action plan include a study of the public transport system in Vientiane, a series of parking studies in Vientiane, Luang Prabang and other major

8

The project is to provide shuttle bus service between the central bus station and the Dongdok campus of the National University of Laos (NUOL). 9 5 See footnote herein. 10 Although the VUTMP recommended “electric engine” as the engine type, specified engines for the 42 units to be procured are 6-cylinder, water cooled diesel engines, meeting Euro 1-4 equivalent emission control standards. 11 Of the 8 routes, 6 are existing: (i) Central Bus Terminal – Dongdok [the original pilot route recommended by the VUTMP] ; (ii) Central Bus Terminal - Phontong - Dongdok; (iii) Central Bus Terminal - Friendship Bridge - Thadeua; (iv) Central Bus Terminal - Thangon; (v) Central Bus Terminal –-Nongteng; and (viii) Central Bus Terminal Dongkhamxay. One is an old route that is to be reactivated: Central Bus Terminal - Nongtha - Dongdok; and one is a new route: Central Bus Terminal - Hongseng - Dongdok; 12 Ministry of Public Works and Transport, Lao PDR. 2010. The National Strategy and Action Plan on Environmental Sustainable Transport, Lao PDR (DRAFT). Vientiane. 13 The strategy is divided into three phases: short term (up to 2010); medium term (2011-2015); long term (20162020). 14 The Lao P DR EMT has developed Action Plans for (i) Affect on H ealth (Road Safety); (ii) Ambient Air Quality Monitoring and Management; (iii) Vehicle Emission Contract; (iv) Inspection and Maintenance (I/M) of Vehicles; Regulation of Fuel Quality of Standard; (v) Transport Planning and Travel Demand Management; (vi) Environmentally and People Friendly Urban Transport Infrastructure Development; (vii) Traffic Noise Monitoring; (viii) Information and Public Awareness; and (ix) Gender Issues.

27


Appendix 5

cities, the promotion of non-motorized vehicles, and the promotion of NGV/battery powered motorcycles. II.

EXISTING CONDITIONS AND PROJECT ALTERNATIVES

7. The EST concept of an inclusive public transport system, propelled by clean/efficient energy does not yet exist in Vientiane. Even basic concepts that reliability, efficiency, and safety should be integral parts of any public transport system are still in their infancy, and not widely practiced, if at all. The primary entity providing public transport services in the city is the Vientiane State Bus Company 15 (VSBC), a state-owned enterprise that was formed in 199116. Its present fleet comprises 128 bus es, varying in capacity from 45-seat buses, to small 8 and 10-seat battery operated buses, imported from China in 2009. The VSBC maintains approximately 35 routes, of which 4 are international servicing a few major cities in neighboring Northeastern provinces of Thailand. T here are 15 national routes servicing major cities in Lao PDR; and the remaining 16 routes service the Vientiane Capital Region 17. There are three bus terminals in the city. T he primary terminal is the Central Bus Terminal (also referred to as Khuadin Bus Terminal) located in the center of town. It is owned and operated by the VSBC. The other two are the Northern and Southern Bus Terminal, which are privately owned, and primarily cater to inter-provincial and international bus passengers. 8. The bus operation model that is used by VSBC, although relatively simple, is not one that is designed to provide quality service. The VSBC pays its bus crews minimal salaries to operate buses and collect passenger fares. The crew keeps any fare revenue above a p reset fixed sum per bus trip, and crews must makes up, out of its own pocket, for any shortfall. This type of incentive scheme severely reduces the ability of VSBC management to control service quality features such as bus frequency, punctuality and reliability, or even to insure that buses ply the correct route, or keep to planned stops for passenger pick-up and drop-off. In addition to the overall poor service and lack of reliability factors, the other most frequent complain of passengers is very poor air quality in buses 18. The net outcome of this poor quality of service is a reduction of the competitiveness of this public bus transport relative to private modes. 9. Other types of public transport service in Vientiane are limited. T hey are comprised of taxis (98 units); vehicles operating as hired cars/private taxis (32 units); sonteos 19 (289 units);

15

Administratively the VSBC comes under the supervision of the Vientiane Department of Public Works and Transport (VDPWT), but in reality it receives directions from both the VDPWT and t he Office of the Mayor of Vientiane. 16 JICA was very instrumental in the establishment and initial funding of the VSBC. In 1989/90 the Project for the Improvement of Urban Transport in Vientiane provided $10 million for the initial purchase of 50 bu ses, and the construction of the Central Bus Station and a w orkshop. S ubsequently in 2000 unde r a s econd program the Government of Japan donated an additional 56 buses and spare parts. 17 There is also a small, Chinese owned, private Vientiane bus firm, the Kingkham Transportation Company (sometimes referred to as the yellow bus company). It has been operating around Vientiane since early 2008, along six routes, mostly in the suburbs of the city. It has a small 36 unit fleet, consisting of poor quality, 16-seat Chinese made buses. Its quality of service is very poor and present daily ridership is estimated to be only in the range of 500 to 700 passengers. Although they have a “fleet� of 36 buses, on any given day it is doubtful that 50% of the fleet is serviceable, primarily due to the lack of budget for maintenance and the lack of drivers. 18 VSBC buses plying routes in Vientiane Capital City are not air conditioned; some of the national routes and all of the international routes have air conditioned service. 19 Sonteos are typically converted trucks or pick-ups with wooden benches along the sides used to convey passengers. They generally operate between city market areas and outlying areas of greater Vientiane. There is an association of sonteos drivers.

28


Appendix 5 tuk-tuks/ jumbos20 of various sizes (1,750 units) 21; and about 300 individually owned vans that appear to operate on an ad hoc, part-time basis around the greater Vientiane Capital City22. 10. The most effective means for Vientiane to make significant advancement in support of sustainable transport will be the implementation of programs and systems that promote the management and redistribution of (trip) modal splits. Specifically, this would mean programs that promote the use of public and non-motorized transport; as well as programs that discourage the use of private cars and motorcycles. Table 5.1 provides an indication of the present distribution of modal splits; and target, future modal splits suggested by the Government and JICA. Suggested target modal splits for use as Impact “performance targets/indicators” in any future ADB design monitoring frameworks (DMF) are also indicated. Table 5.1: Modal Splits (% of Trips) Katahira* (2007 baseline)

National Strategy and EST** (2010 baseline)

Non-Motorized*** Motorcycle Public Transport

25

21

60

60

4

3

Private Car Truck/Commercial

11 100

Mode of Travel

Totals

Katahira Target for 2013

Strategy and EST Target for 2015

Strategy and EST Target for 2020

Suggested ADB (Impact) Targets for 2020

25

30

30 (minimum)

50

30

30 (maximum)

15

30

30 (minimum)

10

10

10

-

6 100

100

100

n/a

15

* JICA. 2008. The Study of Master Plan on Comprehensive Urban Transport in Vientiane in Lao PDR. Prepared by Katahira & Engineers International. Final Report, September 2008, Vientiane, Lao PDR. ** Ministry of Public Works and Transport. 2010. The National Strategy and Action Plan on Environmental Sustainable Transport, Lao PDR (DRAFT). Vientiane. *** Primarily walking and bicycle

11. The conceptual idea of this TA as outlined in the aide-memoire for the 9 April 2010 reconnaissance mission, was an integrated approach encompassing three major components: institutional/capacity development, a n ew pilot public transport service, and a demonstration traffic management scheme, but with all initiatives focusing in “the central part of the city”, so that each component would reinforce and be supportive of the other. 12. The only practical, short term solution that would have any significant impact on increasing the use of public transport in the Vientiane core area, would involve providing dependable, clean and affordable public bus transport services 23. Such quality based public transport service is lacking in Vientiane. Based on the feedback from focus groups, individual interviews with stakeholders, and surveys carried out under this TA, it is clear that there is pent up demand for such services, particularly in the core area of the city. Presently there is no 20

Tuk tuks are three-wheel vehicles typically make in Thailand; jumbos are converted motor bikes made in Lao PDR. There is a private association of tuk tuk and jumbo drivers that represents about 1,350 of the 1,750 drivers that operate these para- transport vehicles. These 1,350 drivers essentially service hotels, restaurants, and other tourist areas. T he remaining 400 p ara-transit vehicles in general provide service to local Lao and other permanent residents, and are based near markets and other commercial areas around the city. 22 Data provided by Transport Division, Department of Public Works and Transport (DPWT) of Vientiane; October 2010. 23 In the mid to long term, other solutions such as BMT or urban light rail might eventually be considered, but at this time the technical and economic viability of such solutions appear problematical. 21

29


Appendix 5

public bus service that directly services the Vientiane core area. A ll existing routes emanate from the Central Bus Station and essentially radiate outwards to areas 5, 10 and 20 km distant. There are no shuttle routes that circulate within the city center and around the Vientiane Master Plan Conservation Zone24. There are no public transport services that would complement a park and ride concept, which is discussed in Appendix 6. T here is no dependable public transport in the core area for students, shoppers or tourists. 13. As a d irect result of the studies, surveys and analyses carried out under the Project, a review of the VUTMP, and discussions with officials of MPWT, the significant gap in public transport service for the core area became obvious. The consensus being a need for: a dependable, clean and affordable shuttle type bus system that would, continually circulate throughout the core area. From this determination, together with the basic internal street layout, and specific site investigations, two closed loop routes have been defined that will provide public transport bus coverage to essentially the entire city core area. These routes are depicted graphically in Figure A5.1. III.

RED AND BLUD SHUTTLE BUS LOOPS

14. For this report the bus shuttle routes are descripted as the red loop and the blue loop. Both loops are about 5 km in length, with bus stops spaced at an average distance of about 0.7 km. T he proposed shuttle buses will service the four primary east-west arterial streets of the core area: Khoun Boulom, Samsenthai存 Setthathirath and Fa Ngum Roads; and will intersect the primary north-south arterial Lane Xang Avenue at three locations. T he proposed red loop will provide three bus stops along Fa Ngum Road to provide public transport service to the new riverside recreational, scenic and cultural development 25. The initial estimate is that a fleet about 16 buses will be required to service the two bus shuttle loops. Table 5.2: Proposed Urban Core Bus Shuttle Routes

24 25

Loop

Length (km)

Stops

Major Roads Serviced along Loop

Approximate Round-trip (min) Peak OffHours Peak Hours

Red

5.3

14

Samsenthai, Fa Ngum, Sakkarine, Khouvieng

33

30

Morning Market, Electricite de Laos, Thadam, National Culture Hall, Centre Point, Sihom, Lao-Viet School, SCC, Pakpasak School, Watchanh, Watxiang-Gnun, Mahosot Hospital, Phiawat School,

Blue

5.0

11

Khoun Boulom, Setthathirath, Khouvieng

32

29

Morning Market, Three Junction Saylom, National Stadium, Centre Point, Wat Ong Teu, Namphue, Wat Ho Phakeo, Mahosot Hospital, Wat Simuang, Talat Khuadin

See Appendix 6, Figure A6.5. Refer to Appendix 6, paragraph 58.

30

Bus Shuttle Loop Service Areas/Destinations


Appendix 5

Figure A5.1 City Center Bus Loops

31


Appendix 5

15. For the proposed shuttle bus services to succeed, it cannot be operated in the same manner as other public transport bus services in the city. If the operation model presently used by VSBC is followed, the traveling public will not give up their present mode of travel to wait for bus transport that is not punctual, and does not maintain a high quality of service. The operational model for the proposed bus shuttle should to be based on the following guidelines: (i) maximum convenience to passengers; (ii) dependable and punctual time schedules; (iii) air conditioned, with a clean, comfortable environment within the bus; (iv) relatively low, fixed bus fares, with free (no cost) transferring from one shuttle loop to the other to complete a trip; and (v) utilization of smart card technology 26 for all fare collections, operating under a policy of “no cash transactions” throughout the system. Appendix 4 discusses institutional, financing and capacity development issues, including franchising arrangements and fleet sustainability issues.

IV.

IDENTIFIED SUB-PROJECTS

16. In addition to the bus shuttle loops, other supporting public transport subprojects have been identified for inclusion in the Project. The two sub-projects identified are: (i) bus maintenance yard; and (ii) improvements to the Central Bus Terminal. 17. The site for the bus maintenance sub-project should be located not more than 5 kilometers from the city core area. The primary usage of the site would be for: (i) a service garage for routine bus maintenance27, with two offices in the garage structure set aside for bus shuttle administration and operations; and with an adjoining fuel dispensing facility; (ii) an area for bus washing and cleaning; and (iii) an area for bus parking. It is assumed that the Government would be responsible for land acquisition for the site. Detailed site investigations will be carried out by the PPTA consultant to determine likely sites for these facilities; and then discuss the provision of land for bus maintenance facility with the Government 28. Present thinking, as indicated in Table 2: “Indicative” Financing Plan is that the Government will be responsible for provision of the land for this site29. 18. A site visit was made to the Central Bus Station. In general the site and the facilities are not well maintained, and operations are not functioning efficiently. In order to implement the Project, operational and civil works improvements to the Central Bus Terminal will be required in order to integrate the shuttle bus stops, and bus waiting area, into the overall scheme of the terminal. T he Vientiane DPWT has two conceptual ideas for improving the terminal. N either DPWT option would significantly affect the operations or efficiency of the terminal, as both ideas only appear to include the construction of a new two-story structure on the site. It is not entirely clear whether this new building would be entirely allocated for VSBC operations, or whether all 26

The smart card technology to be utilized on the shuttle bus system may be integrated with the technology to be used for parking (as described in Paragraph 93, Appendix 6). T he degree of integration will greatly depend on institutional considerations and the degree to which the private sector may or may not be involved, in parking and/or bus operations. 27 Only routine maintenance would be performed on-site; major maintenance or bus overhauls would be contracted out to the private sector. 28 Two possible sites north of the core area were investigated during this TA: (i) the existing site of the Vientiane Capital Road Maintenance Unit; and (ii) at the site of the existing Construction and Installation Public Company, near the Dong Chong oil storage area 29 Discussion was had between the TA Consultant and the JICA consultant for the TCPB in order to determine if there would be a pos sibility to have site that could accommodate both the new 42 buses to be procured under the JICA program and the buses to be procured under the VSUTP. It was determined that, in general, this is a possibility but that to date no bus maintenance and bus parking site has been identified for the new JICA buses. This is an issue that will need to be further addressed by the PPTA consultant.

32


Appendix 5

or part of the structure would be utilized for commercial activities. I t is recommended that in addition to integrating the shuttle bus stops into the terminal operations, additional civil works improvements for site paving, drainage, and improved toilet facilities be included in the Project 30. V.

FUTURE EXPANSION OF URBAN BUS ROUTES

19. If the Project is successfully implemented, both institutionally and operationally, then it would be relatively easy to extend the pilot bus services to other neighboring sections of central Vientiane, areas beyond the core area as defined by this TA. Future expansions to be considered by Government (and the ADB and other donors), once the pilot program has been successfully implemented include: 1. Airport Shuttle Bus System 20. Airport Shuttle Bus System . A public transport bus link connecting Wattay International Airport with the core area of Vientiane should be considered in the near future. It could even be considered by the PPTA consultant for possible inclusion in the initial Vientiane Sustainable Urban Transport, possibly providing service to and from but more likely in a following phase of Phase 2 of the, including a small bus facility at the airport. 21. Other Shuttle Bus Loops. Four primary adjacent neighbor shuttle bus loops have been identified totaling about 27.3 km. These bus shuttle routes are depicted on Figure A5.2

30

A number of attempts were made by the TA consultant to engage the DPWT and VSBC in discussions about the scope and level of improvements that they would should be included in the Project. These attempts were to no avail. For the sake of this TA an a mount of $500,000 has been included in the budget estimate for general civil works upgrading of the site, and the inclusion of the new red/blue shuttle bus stops into the existing facility.

33


Appendix 5

Figure A 5.2 Possible Additional City Bus Loops

34


Appendix 6

TRAFFIC MANAGEMENT I.

INTRODUCTION

1. This Appendix describes the analysis undertaken under the traffic management component of the study for VSUTP. It includes assessment of the existing situation, key issues, strategy and identification of potential sub-projects. Reference should also be made to associated appendices on the parking survey, walkability survey, and traffic count, (Appendices 7, 8 and 9 respectively). The study area for traffic management is the Core Area as shown in Figure A6.1. II.

TRAFFIC MANAGEMENT ASSESSMENT

2. The management of traffic in Vientiane faces many obstacles – physical, attitudinal and institutional. These include poor infrastructure, lack of parking management, entrenched bad driving habits, a sub-optimal pedestrian environment, and poorly coordinated development administration. These are exacerbated by low public awareness of regulations, low levels of parking and traffic enforcement, poor perceptions of road safety, lack of equipment maintenance, and low operating budgets. At the same time the amount of traffic is increasing dramatically. The total number of vehicles registered in Vientiane Capital has doubled over the last five years. 1 A.

Infrastructure

3. Infrastructure deficiencies include poor road conditions, limited control equipment, and equipment failures. Road surface conditions have improved in recent years following investments supported by ADB, AFD and JICA. However there are still several sections of road in the central area that are in bad condition with potholes and broken surfaces. 1.

Road Condition

4. Under the previous ADB Vientiane Urban Infrastructure and Services Project (VUISP) many roads were improved in the central area between 2002 to 2008. These included several of the smaller streets in the main tourist zone (with attractive brick footpaths). The main roads of Samsenthai and Sethathirath were resurfaced at a similar time under JICA funding. Whilst most of these road structure improvements remain in good condition, there are problems with the junction equipment and with road markings that were parts of these projects. 2.

Junction Equipment

5. There are thirteen light-controlled junctions in the core area. Four of these have CCTV and five have traffic sensors (under the road surface). However none of these CCTV systems was operational at the time of study. A transformer blowout adjacent to the VUDAA control centre in August 2010 burned out the computer control circuits for 6 of the CCTV units including all of the ones in the core area. The traffic lights themselves are mostly functioning, but the phasing appears to be at fault on some, with the green phase on the minor road longer than the phase for the major road.

1

Source: Department of Transport, MPWT

35


Appendix 6

36


Appendix 6

3.

Road Markings

6. Road markings are often confusing and impractical. Lane purposes (sometimes reflected in their widths) are in many places ambiguous. The reason for having a central wide lane and two narrow side lanes, for instance in Settathirath Road, is unclear and leads to confusion. In parts the narrow lanes are used for parking, in parts as a right or left turning lane, in other parts they operate as unofficial motorcycle lanes. They do not operate in the same way as the clearly defined motorcycle lanes seen in Vietnam. 7. There are also instances where lane markings should be reviewed to reflect common practice rather than trying to impose a particular regime that does not work. An example of this is along Fa Ngum Road where a narrow parking lane is provided on the Mekong side of the road. In practice most people park on the other side, adjacent to the shops, guesthouses and restaurants. In consequence the lane for moving traffic on the shop side is impeded and vehicles have no option but to encroach beyond the centre line of the road. 8. Existing lane markings do not maximize efficiency of road space usage. For instance, in Lane Xang Avenue there are three traffic lanes on each side of the central reservation. Typically at the junctions, these are indicated for right turns, straight ahead and left turns. However at busy times cars frequently double up in the centre creating two straight-on queues. This can cause conflicts with some vehicles perceived as ‘pushing in’. There is adequate road space for this, and it would be better therefore to revise the markings to accommodate the extra lane. 9. Away from the main roads road markings are very poor – faint or non-existent lane curb markings making it difficult to see the edge of the road in low light conditions. 4.

Street Lights

10. The quality of street lighting in the core area is reasonable, and significantly better than other parts of the urban area. Nevertheless the quality of light is not consistent. Changing light levels, coupled with the absence of or faint road markings creates hazardous conditions, particularly when visibility is impaired by rain. 5.

Road Dividers

11. In an attempt to improve traffic flows and limit directional conflicts central reservations have been included during the improvement of several roads in Vientiane. This works effectively on roads where there is adequate width to provide two lanes in each direction plus shoulders for stopping and/or parking. However, where this width is not available the design actually impairs traffic flows. When cars stop or park in the right hand lane the traffic is reduced to one lane. The system works only if there is strict control over parking and stopping. This is currently an issue more common outside the core area (e.g. on Thadeua Road) but needs to be borne in mind in future plans. 6.

Parking Provision

12. Previous data on parking provision (and demand) is patchy. For the 2008 Transport Master Plan the Katahira team reviewed the work undertaken on parking by the BCEOM team under VUISP. The latter concluded that, in 2004, there was adequate parking capacity in the city centre area to accommodate traffic demands up to 2010. It seems that, on this basis, the 2008 study determined that there was sufficient parking provision at that time also. 37


Appendix 6

13. However, examination of the BCEOM figures reported by Katahira raises questions. The derivation of the data is unclear. The conclusions are based on the assertion that there was roadside parking space for over 4,400 vehicles in an area slightly smaller than the core area identified for this project. On-road parking for 4,400 vehicles would require 30km of roadside. This length of parking area could only be provided if both sides of every stretch of every road in the area were allocated for parking. Clearly this was not the reality and is impractical and nonsensical. The analysis in the Katahira report is founded on the BCEOM data and cannot therefore be used as a starting point for parking assessments under VSUTP. A parking survey was therefore undertaken for VSUTP and the results are reported in Appendix 7. 14. The parking survey revealed that there were just over 5,200 cars parked in the core area on a typical working day. Of these about 2,400 were on the street and 2,800 were off-road, including designated roadside right angle and echelon parking areas, and public and private car parks. Of those on the streets, about 130 were parked fully off the road in property frontages, whilst over 400 were on the footpath. Of the cars on-road over 700 were illegally parked in restricted areas - waiting only, no parking, on the wrong side of odd and even date zones, or on the footpath. 15. Illegal and inappropriate parking is not just something that occurs sporadically and it appears to have become an accepted norm. There are instances of institutionalized illegal parking as described in Box 1 below. Box 1: Footpath Parking The common use of the footpath for parking vehicles in Vientiane is exemplified by the case of a newly-opened medium-high-end hotel within the study area. The hotel’s printed and website information says that the hotel has a car park. In fact the ‘car park’ is simply the footpath across the road from the hotel, alongside the wall of a temple. In this location the footpath is wide enough to accommodate the parking of small to medium-sized cars at right angles to the road. The footpath here is one those that were improved under VUISP and is paved with brick. Continued parking here will damage both the bricks and the curb (which is normal height and not lowered for vehicular access as none was intended). In addition, the parked cars are a pedestrian hazard as they force people to walk in the roadway.

16.     

The key issues for parking in the core area are: Unclear and confusing parking restrictions Lack of parking enforcement Poor and inefficient management of existing parking areas Discrepancy in parking charges – no charge for on-road parking Drivers’ and passengers’ reluctance to walk any distance from their cars to their destinations

17.

These and other parking issues are discussed in Appendix 7.

B.

Pedestrian Environment

18. Compared to many capital cities, the environment of the central area of Vientiane is relatively pleasant for the pedestrian. Low-rise buildings, relatively narrow roads, moderate traffic volumes, and trees providing shade (on some streets), all contribute to a generally comfortable feeling. However, pedestrians are actually not well provided for. Many footpaths are cluttered and obstructed, and pedestrian road crossings are not effective. Added to these, the 38


Appendix 6

volume of road traffic in Vientiane has perceptibly increased in recent years resulting inevitably in a higher incidence of pedestrian-vehicular conflicts. 19. Pedestrian crossings are a particular concern. Although there are a number of these in the core area, the road markings on most are wearing out and hardly visible. 2 There is no current acceptance by drivers that they should stop when pedestrians are waiting to cross or have even started to cross at a designated crossing. Whilst local residents are used to the attitude of car drivers, it is potentially very dangerous for tourists who assume that they have some priority at these crossings. 20. Some of the existing crossings are at light-controlled junctions but generally there is no specific pedestrian phase. At the few that do have a pedestrian phase, such as the junction between Lane Xang Avenue and Samsenthai the phase is sufficient only to reach the central reservation and there is no button there to active the pedestrian lights to cross the other carriageway. It is understood that VUDAA plan to install some new light-controlled pedestrian crossings, but none of these are within the core area. 21. A ‘walkability’ survey was undertaken in the core area using methodology developed by the World Bank and ADB 3. The survey and results are described in Appendix 8. The score achieved puts Vientiane somewhere in the middle of the range of Asian cities measured thus far. Whilst ostensibly a r easonable result, it masks the fact that a relatively low-density, low-rise urban environment should really have a higher score. It reflects a h igh level of automobile dependence amongst the middle and upper classes in Lao society. 22. Community consultations have suggested that there are some locations where pedestrian bridges might be needed. Two of these are adjacent to schools and one between the morning market and the bus-station. The two school locations are reportedly well known for the number of accidents but this has not been separately corroborated by official data. C.

Driver Behavior

23. Driving standards and discipline are generally very low in Lao PDR. It is relatively easy to obtain a d riving license without taking any official tests. Many drivers therefore have had no proper training. Even those that do go through the official procedures receive training primarily in handling a vehicle in a special off-street training area, with little or no practice on the actual streets. In common with other developing countries many new drivers are first generation car owners and have not had the road experience gained from growing up with parents who drive cars. Added to this, many of today’s car drivers previously drove motorbikes and have carried on driving their cars in the same way they drove their bikes. Entrenched bad habits that had minor impacts on other road users when undertaken on a motorbike have potentially dangerous results when carried out on four wheels. 24. The provisions of the Lao Highway Code are consistent with international traffic rules. However many of the rules are consistently ignored, and are not enforced by the police. Common practices that can be observed every day on Vientiane streets are summarized in Box 2.

2 3

At the time of completing this report some crossings were being repainted in the core area http://cleanairinitiative.org/portal/whatwedo/projects/Walkability

39


Appendix 6

25. Clearly, as well as interrupting the flow of traffic, bad driving habits have significant road safety implications. Traffic management and road safety issues are interrelated and many issues need a coordinated response. 26. Despite the array of poor driving habits shown in Box 2, it should be stressed that the situation on the roads is not as chaotic in Vientiane as in some other Asian cities. It is still relatively early in the life of Vientiane as a heavily trafficked city, and presently the poor driving does not generally take place at high speeds in the urban area. There is time to address these issues before the situation does become critical. Box 2: Every Day Poor Driving Habits in Vientiane Junction behavior. Many motorists take the shortest route through a junction, cutting the corner into oncoming traffic, sometimes around blind corners. When an unc ontrolled junction is busy drivers will often take several routes either side of opposing vehicles. Incorrect lane use at signalized junctions. It is relatively common practice for motorists to occupy left and right turning lanes when they actually intend to go straight on. Running red lights. Cars generally do not stop on amber. Running red lights happens at every junction every day. It is a serious issue that is not currently being dealt with. Jumping out before green light phase after being stationary is also common. Roundabout priority. The prevailing system in Lao PDR is to give priority to vehicles entering roundabouts. This goes against the advice in the Lao Highway Code (There are ‘Give Way’ signs clearly situated on t he entrance to most roundabouts). It frequently results in roundabouts becoming ‘locked up’, with the roundabout full of stationary vehicles. This is also potentially dangerous as it goes against international practice and will confuse overseas drivers. Motorbikes travelling against traffic. Motorcycle riders frequently ignore the direction of traffic, particularly on sections of road with a central reservation. This happens even at night causing significant hazard for car drivers. Pedestrian crossings ignored. As a general rule motorists do not stop if they see pedestrians waiting to cross the road at a zebra crossing. This is particularly dangerous for tourists who expect vehicles to stop. Poor use of indicators. Drivers generally use indicators less than they should. They are frequently used too late to alert drivers behind that they intend to turn, and are mostly not used when changing lanes. A particular bad habit that has become prevalent in Asia is the use of hazard lights to indicate an intention to go straight on at a junction. This is not a signal endorsed by the Lao Highway Code, and can cause confusion as those drivers to the sides can see only one set of indicators working. Wandering between traffic lanes. Moving from one lane to another mostly occurs without any warning to other motorists, and frequently without checking for adjacent vehicles. Big cars bullying others. There is a noticeable tendency for large cars to bully their way through traffic. Their drivers expect smaller cars to make way irrespective of the correct priority. Generally the drivers of the smaller vehicles oblige – but not always. Pulling out into traffic without looking. A common trait amongst motorcycle riders is to pull out into traffic from being stationary on the side of the road without looking behind them. Also common is for motorcyclists to turn right to join a road from a side road without stopping or looking. Swerving to avoid holes in the road. As mentioned above, there are numerous locations in Vientiane where the road surface is not good. Deep potholes, ruts, and other deformities are quite common. Motorists frequently swerve to avoid these hazards rather than slowing down and checking what vehicles are around them before making the maneuver.

40


Appendix 6

D.

Problem Spots and Black Spots

27. As well as the area-wide issues outlined above, there are a number of location-specific problems – ‘problem spots’. These are summarized in Table A6.1, and shown in Figure A6.2. Table A6.1 Traffic and Parking Problem Spots in the Core Area No.

Road*

Location

Problem

1

Nongbone

2

Nokeokhoumane

Adjacent to Talat Sao and bus station, and side road to Khoudien Market From Fa Ngum to Setthathirath

3 4 5

Francois Ngin Manthatourath Chou Anou

As above As above As above

6

Fa Ngum

7

Samsenthai

8

Khouvieng

From Khoun Boulum to Chanthakhoumane Nokeokhoumane to Chao Anou Vietnamese market

9

Khouvieng

Junction with Phainam

10

Khouvieng

11

Nam Phou

12

Pangkham

13

Khouvieng

14

Sakkarine

15

Sakkarine

16

Hatsady

17

Samsenthai, Sethathirath and Fa Ngum

Junction with Khoun Boulum Approach to and round fountain Fa Ngum to Setthathirath In front of shopping mall and Post Office In front of Mother and Baby Hospital Junctions with Samsenthai and Sethathirath Khou Vieng to Lane Xang Several locations, but particularly on Pangkham/Nam Phou axis

Chaotic parking and double (sometimes treble) parking with small pick-ups, tuk-tuks, and barrows delivering and collecting from the markets and shops. One-way street with odd and even date parking restriction, but not being enforced. Much parking on footpaths forcing pedestrians onto roadway. The street appears completely full of cars. As above As above As above (although slightly wider street than the others) Busy riverfront road. Confusing lane and parking markings. Parking in red zone, parking on footpath, bottleneck in busy periods Small pick-ups, tuk-tuks, and barrows delivering and collecting from the market interfere with through traffic – particularly at peak times. Poor junction geometry and confusing road markings Poor junction geometry and confusing road markings Conflict for road space between cars and pedestrians Chaotic parking and stopping for short periods for the BCEL Bank, Lao Aviation and other offices. Parking for PO and tuk-tuks, dropping off point for shopping mall, interferes with very busy road. Chaotic car parking, poor road surface and shoulders Busy junctions with no traffic lights. Double and triple parking by visitors to banks and other offices. Very poor road surface. Inadequate pedestrian crossing facilities within main tourist area.

*Note: For the sake of brevity prefixes and suffixes such as Rue, Road etc. have been omitted from the names in this table

41


Appendix 6

42


Appendix 6 28. Two recent studies 4 identified ‘black spots’ in Vientiane based on accident data. However the two reports present different black spot locations, and only those in the 2007 study included a location in the core area - Fa Ngum road. In both studies the black spots were based on the number of accidents resulting in serious injuries and fatalities. It is likely that traffic congestion in the central part of the city induces slower speeds resulting in lower fatality rates than roads elsewhere in the urban area. Nevertheless feedback from community consultations has indicated that there have been fatalities within the core area, many involving young people. 5 E.

Traffic Management and Control 1.

Responsibilities

29. Currently VUDAA is responsible for traffic management in the central part of Vientiane. At the same time the police have the role of controlling traffic on the ground. The two roles overlap and coordination between the two agencies is not always effective. 30. At busy times the police often override traffic lights by manually directing traffic. They do not have access to the light switches so are not able to disable the lights. This can cause significant confusion. Anecdotal evidence suggests that police intervention rarely improves traffic flows in the system overall, and sometimes not even at the junctions they are controlling. 2.

Traffic Control Systems

31. A traffic management section was set up with assistance from AFD under VUISP. This includes a c omputer control centre tasked with monitoring and controlling 26 l ight-controlled intersections (see Figure A6.3 and Table A6.2). Due a power transformer blow-out during an electrical storm in August 2010 most of the control circuits were burnt out. As a result, of seven CCTV units only one is now operational. Even when fully operational the control centre does not have the means to monitor most of the intersections. Only nine have sensor strips in the roadways, some, but not all, of which are the same junctions as have CCTV. In total just twelve intersections have cameras and/or sensors with which the control centre can monitor them remotely. 32. There are a further nine light-controlled intersections for which VUDAA has responsibility, but are not connected to the central control. There are also three traffic light junctions on the Dongdok Road under DPWT’s responsibility. In addition, there are four recent traffic light installations in VUDAA’s area that are still under the contractor’s guarantee. 33. The control centre appears to be under-resourced. There has been little or no investment since it was established under VUISP. To be effective the control centre needs connection to all light-controlled junctions along with monitoring devices such as sensor strips and/or CCTV at all key junctions. 34. The Police also have 100 CCTV cameras – but these are designed to monitor key locations for security purposes. 4 5

‘Road Accident Black Spots in Vientiane and Recommended Countermeasures’, ICT, SweRoad, and Burapha, 2007, and ‘The Study of Master Plan on Comprehensive Urban Transport in Vientiane Capital’, Katahira, 2008 Note: The VSUTP team has attempted to obtain details of accidents by specific location but no dat a has been forthcoming. This is despite the fact that the Road Safety Committee has reported that a R oad Accident Information System (RAIS) has been set up.

43


Appendix 6

CCTV

Sensor

Central control

Table A6.2 Existing Light-controlled Junctions

VUDAA

AFD

VUDAA

AFD

Khounboulom Road

VUDAA

AFD

Saylom Road

VUDAA

AFD

VUDAA

AFD

VUDAA

AFD

VUDAA

AFD

VUDAA

AFD

VUDAA

AFD

VUDAA

AFD

VUDAA

AFD

VUDAA

AFD

VUDAA

AFD

VUDAA

AFD

Fa Ngum Road

VUDAA

AFD

Mahosot Road

Setthathirath Road

VUDAA

AFD

Samsenthai Road

Thatdam Road

VUDAA

AFD

18

Suphanouvo ng Avenue

T2 Road

VUDAA

AFD

19

Asian Road (T2)

Dongnasok Road

VUDAA

AFD

20

Asian Road (T2)

Hongkha Road

VUDAA

AFD

21

Asian Road (T2)

Sisavath Road

VUDAA

AFD

22

Asian Road (T2)

Thongsangnang Road

VUDAA

AFD

23

Asian Road (T2)

Sibounheuang Road

VUDAA

AFD

24

Kaysone Phomvihane Road

T2 Road

VUDAA

AFD

25

Kaysone Phomvihane Road

3A Road

VUDAA

AFD

26

Saylom Road

Khounboulom Road

VUDAA

AFD

27

Thadeua Road

T4 Khamphengmouang Road

VUDAA

China

28

Phonthan Road

T4 Khamphengmouang Road

VUDAA

Vietnam

29

Thatluang Road

T4 Khamphengmouang Road

VUDAA

Vietnam

30

Thatluang Road

3A Obee Road

VUDAA

France

31

Kaysone Phomvihane Road

T4 Khamphengmouang Road

VUDAA

China

32

Kaysone Phomvihane Road

Nongnieng Road

VUDAA

China

33

Dongdok Road

Kayson Phomvihane Road

VUDAA

China

34

Nongdouang Road

Dongnasok Road

VUDAA

Vietnam

35

Dongdok Road

National University Road

No work

DPWT

Vietnam

36

Dongdok Road

Dondeng Road

Removed

DPWT

Vietnam

37

Dongdok Road

Nonthane Road

Hongkayasin

Chao Anouvo ng Road

39

Phonphanao

P3 Road

40

Road 13S Km 16

National Stadium

41

Road 13S Km 21

National Stadium

DPWT Under Contractor Under Contractor Under Contractor Under Contractor

Vietnam

38

Damaged Newly installed Newly installed Newly installed Newly installed

1

Lane Xang Avenue

Setthathirath Road

2

Lane Xang Avenue

Samsenthai Road

3

Lane Xang Avenue

4

Lane Xang Avenue

5

Setthathirath Road

Khounboulom Road

6

Thadeua Road

Phaxay Road

7

Samsenthai Road

Khounboulom Road

8

Khouvieng Road

Mahosot Road

9

Nongbone Road

Dongpalane Road

10

Nongbone Road

T2-4 Road

11

Khounboulom Road

Chao Anouvo ng Road

12

Thongkhankham Road

T2 Road

13

Lane Xang Avenue

Patuxay Road

14

Kaysone Phomvihane Road

Patuxay Road

15

Suphanouvo ng Avenue

16 17

  

Notes

Working

  

Removed

44

Agency responsible

Funded by

China China China China


Appendix 6

45


Appendix 6

3.

Enforcement

35. As mentioned above, there is little enforcement of traffic rules. Although police are positioned at many intersections, and infringements constantly take place by vehicles of all types, they rarely take action other than pulling over motorcycle riders (for not wearing helmets or just to check their papers). Car drivers, of big cars in particular, know they can get away with going through red lights etc. and will continue to do so until the police take action to curb these practices. 36. It is a s imilar situation with parking. There is minimal enforcement of parking rules. Occasional clamping takes place but this appears to be arbitrary. It is mostly carried out only on highly visible main roads where the impact of a single parked car is minor, rather than on the smaller roads where improperly parked vehicles create major disturbance to the traffic. The district police are responsible for clamping and there is no apparent consistency in clamping policy across the six districts in the main urban area. There is only one tow-truck available in Vientiane and this is used mostly for moving vehicles involved in accidents. 37. There is no system of ‘parking tickets’ in Vientiane whereby illegally parked cars can be issued with fines. The police therefore have limited powers to get drivers to obey parking restrictions on a wider scale. It is common to see scores of cars parked in yellow ‘waiting only’ areas, and on the wrong side of odd and even date parking zones. Double parking is commonplace and triple parking is not rare. 38. From discussions with the Department of Traffic Police in the Ministry of Security the indications are that there would be support from the traffic police to divest themselves of the responsibility for parking enforcement. This has happened in many other countries and allows the police to concentrate on the control and enforcement of moving traffic. F.

Urban Planning Context 1.

Planning and Development Control System

39. Urban planning in Lao PDR struggles to cope with the pace and scale of development in the country’s towns and cities, particularly Vientiane. The current master planning system is not well suited to managing growth in a market economy, and the enforcement of zoning and development controls is weak. In addition to this the spatial planning process does not have the central strategic role that it needs in order to coordinate developments across all sectors. Consequently the master plans that are prepared are viewed by other ministries as simply the outputs of one sector. Even within MPWT there is only limited coordination between the Department of Urban Planning and Housing (DHUP) who prepare the plans and other departments. 40. As well as the limitations of poor horizontal coordination within government, the vertical linkages are also largely ineffective in urban planning. Plans are produced centrally (by DHUP and the Planning and Public Works Institute – PTI). This results in a lack of ownership of the plans by the authorities tasked to implement them. In Vientiane this is particularly acute. The Vientiane Capital authority has a record of paying little heed to the approved master plan. An example of this is the construction of the Don Chanh Palace Hotel, built in 2005 in an area designated as a natural conservation zone. Vientiane has also witnessed a c ontinual encroachment into wetland areas in and around the city despite them being earmarked for 46


Appendix 6

protection as important flood retention basins. This latter issue is largely a result of the district authorities issuing development permits without reference to the master plan zoning. 41. This uncoordinated and ad-hoc planning system means that it is difficult to plan effectively for traffic management. In particular many major developments schemes are discussed and agreed with minimal or no cooperation with traffic planners. A case in point is the clutch of proposals for the Nong Chanh area in the north eastern part of the core area. Here there are plans being proposed on three adjacent sites by several investors all of which include large shopping centers. There is no overall plan for the area, other than demarcation of the sites, and there is no coordinated access, traffic management or parking plans. 2.

Urban Character

42. The historic part of the city centre is typified by a c ombination of two-storey shophouses, French colonial villas and townhouses, and ancient wats (temples). This is all interspersed with more recent architecture, much of which makes little attempt to blend or complement the older buildings, and some of which detracts from the character of the area. Nevertheless the overall urban form and character is attractive and remains the focus for tourists. Previous and existing Government master plans for Vientiane identify this area as a zone for protection (see sub-section 3 below). 43. Land use within the core area is mixed. Shops, restaurants, hotels, guest houses and other businesses predominate with residential space above or behind the commercial premises. There are also a large number of government buildings (see Figure A6.4), occupying large sites in the eastern part of the core area. 44. The core area is also characterized by its river frontage, which is a particular focal point for tourists. The frontage is about to change significantly with the imminent completion of Phase 1 of the riverside development project – see below. 3.

Current Plans

45. The Government’s current Urban Master Plan for Vientiane was approved by Prime Minister’s decree in 2002. 6 The master plan is based on a system of zoning introduced by French consultants in a 1994 m aster plan study funded by UN. The system includes 17 z one types. A review of the plan was undertaken by DHUP in 2007 and revisions drafted. However the revised version has never been approved. The DHUP work has effectively been superseded by the JICA-funded review of the master plan that commenced in January 2010. 7 46. The core area falls almost entirely within one zone in the approved master plan– Zpp-Ua (see Figure A6.5). This is designated as ‘Preservation zone - old city’. The zoning provisions include a height limit for new buildings of 12m (see Table A6.3). (However, there are recent examples of new construction in excess of this e.g. the new bank building in Rue Pangkham which is around 20m high). The core area also includes small sections of three other zone types, UAa – Administration and Commerce, UC – Mekong riverbank, and NE – Public open space.

6 7

PM Decree 216, 10 December 2002 The Project for Urban Development Master Plan Study in Vientiane Capital, Nippon Koei Co., Ltd. International Development Center of Japan, Pacet Corp., Oriental Consultants Co., Ltd., JICA

47


Appendix 6

48


Appendix 6

49


Appendix 6

47. In the draft Interim Report of the master plan study the consultants recommend the introduction of six broad planning zones to guide the development of Vientiane. These are not intended to replace the existing 17 z one types, but to overlay them. The core area would fall within a p roposed ‘Zone 1 - Historic Conservation Zone’ which is similar in area to the existing Zpp-Ua zone. The key planning policies proposed for this zone are:    

Preservation of historic buildings (Enforcement of “Building Construction Permit” System) Enhancement of the attractiveness in the urban center as tourist resources (Landscape/ Urban Design, Pedestrian-friendly roads, etc) Relocation of national public offices toward the Suburbs Control of building design and use to create visually attractive central urban spaces

48. The suggested strict enforcement of building code in this zone is a good recommendation. Preservation of the character of this area is important for the city, and controlling the intensity of development will play a key role in limiting the growth of traffic. The study points to the tight controls in force in the Luang Prabang heritage area as an example. Whilst the Luang Prabang regulations are probably overly restrictive for application in Vientiane, there are some provisions worth considering. These include, for example, the prohibition of the parking of vehicles on the frontage area of shops and restaurants, and the delivery by goods vehicles only at certain times. 49. A problem with trying to impose stricter controls is that even existing standards are not enforced. In fact there is some ambiguity in the status of master plan zoning and building regulations. It is not entirely clear that the recommended building parameters (site coverage, plot ratio, height) contained in the master plan have any weight in the law. In practice most authorities largely ignore these provisions. 50. At a m ore strategic level the JICA master plan study suggests the relocation of government offices and colleges away from the historic core. This should be supported as it is likely to reduce peak hour trips into and out of the core area. 51. The recommendations in the master plan study also include some adjustments to the site coverage and plot ratios in different zones. Those for the zones within the core area are shown in Table A6.3. Table A6.3 Existing Development Density Provisions in Core Area and Urban Master Plan Study Recommendations Zone ZPP-Ua Historic town centre conservation UAa Administration and commercial UC Mekong riverbank NE Public open space preservation

Existing Site coverage Height Plot ratio Site coverage Height Plot ratio Site coverage Height Plot ratio Site coverage Height Plot ratio

75% 12m 2.5 75% 26m 2.5 50% 10m 1.0 -

50

Proposed

(by Urban Master Plan Study)

75% 12m 2.0 60% 26m 4.0 50% 10m 1.0 -


Appendix 6

52. The master plan study puts forward proposals for a BRT scheme that would include a route passing along Sethathirath. This would entail changes to the one-way system currently in place and would significantly affect the character of the historic area. This proposal is discussed in more detail in Appendix 5, Public Transport. 53. It should be noted here that the Urban Transport Plan prepared by Katahira does not relate to the existing master plan. Instead the proposals therein are based on the study team’s own assumptions about future urban form and growth. 4.

Current Parking Standards

54. Parking standards stipulated in the approved master plan for zones in the core area are shown in Table A6.4. Table A6.4 Parking Standards Stipulated in Approved Master Plan for ZPP-Ua, UAa and UC zones Land Use/Building Type Residential Hotel School, Office, Bank Restaurant, Club Market, Shopping Mall, Supermarket

Parking Requirement 1 lot per 2 families 1 lot per 3 rooms 2 1 lot per 20m floor space 2 1 lot per 4m floor space 2 1lot per 10m floor space

55. The requirements shown in Table A6.4 are clearly out of step with the growth of car ownership in Laos, and are in any case not enforced. 5.

Developments in the Pipeline a.

Commercial Development Sites

56. There are a number of development projects at various stages of design and approval for sites in the core area. These are summarized in Table A6.5 and their locations shown in Figure A6.6. From the table it can be seen that the majority of buildings proposed are 5 storey and over. Assuming an average floor height of 3m, the height of these developments will therefore contravene the existing building regulations (12m), and the total floor space created will be in excess of the scale anticipated for the historic core. The combined effect of these will put significant excess pressure on the traffic and transport facilities in the core area, and will also have a potentially detrimental effect on the visual character of the historic centre of Vientiane.

51


Appendix 6

52


Appendix 6

Table A6.5 Ongoing and Planned Development Sites Name of Building Department of Public Security Namphou Building Kanlaya Building Alisara Building Chanthapanya Hotel ST Hotel Boun Eiang Building Lao - Viet Building Lao Telecommunication Building

1 2 3 4 5 6 7 8 9

Location

Proposed Used

No. of Floors

Total m2

Samsenthai Road

Police office

5

7,500

Namphou Xiengnhun Village Setthathirath Road Hengboun Road Hanoi Road Samsenthai Road Saylom Road

Offices Apartment Apartment Hotel Hotel Offices Offices

7 5 6 5 6 4 5

3,760 5,178 2,135 2,654 1,283 880 9,685

Saylom Road

Office

9

10 5 Star Hotel

Samsenthai Road

11 12 13 14 15

Pakpasak Nongchanh wetland Nongchanh wetland Nongchanh wetland Nongchanh wetland

Angyalay (Vietnamese) Vietnam Market North Nong Chanh Khouadin market South Nong Chanh

b.

Hotel, Office, Serviced apartments Hotel Super Market Supermarkets Supermarket ??

Car Status spaces 50

Under construction

8 12 25

Under construction Under construction Under construction Under construction Under construction Under construction Under construction

12,672

113

Under construction

12

80,000

800

Proposed

5

4,730

223

5,730

138

18 5

In design In design In design Planned Planned

Nong Chanh Developments Proposals

57. The development sites described above are distributed throughout the core area. However, notable amongst these are the three major sites grouped together in the Nong Chanh area mentioned above. Details are not finalized but the likely scale of developments here are as shown in Table A6.6 below: Table A6.6 Proposals for Nong Chanh Development Sites Site A

Scale of Proposed Development 2 3 buildings totaling 5,730m , 138 car spaces, possibly Big C supermarket?

B C

5-storey supermarket building, 4,730m , 223 car spaces Tesco Lotus supermarket and Home Pro DIY supermarket

2

Source of information Vientiane Times and DPWT DPWT DPWT

58. Clearly these are individually significant schemes and when combined together constitute a major development project in the heart of the city. Yet there is no clear comprehensive plan for the area and this has huge implications for traffic management. In fact the types of shops being proposed are normally located on edge of city sites, and are not really appropriate in this location. It is understood that there are also plans being prepared for the remaining portion of the Nong Chanh wetland area, Site D. Whilst the original plan for this area was to retain it as predominantly open space, proposals could include up to 40% of the area given over to buildings.

53


Appendix 6

c.

Riverside Development

59. The riverside development now under way comprises 12.6 km of riverbank protection and a public park of 14.5 ha (see Figure A6.7). The scheme incorporates a 6 km riverfront road running from Packpasack to the Watnak area with other connections to the existing road network at Mahosot Road, That Khao Road, and the Lao-Thai Road. It is not clear at this stage how the junction between the riverside road and Fa Ngum will function, and what impact if any the development will have on traffic patterns. This will need to be reviewed once the scheme is complete. G.

Previous and Pending Traffic Management Recommendations

60. Traffic management in Vientiane has been addressed by three projects/studies in the last decade. The outputs from these are summarized in Table A6.7. Thus far, only one of these has led to implementation. This was the ADB’s VUISP undertaken between 2002 and 2007. The main project included the improvement of a number of city centre streets whilst the traffic management component came under parallel funding from AFD. 61. The AFD grant supported the establishment of a traffic operation center at the new VUDAA office building, along with the installation of traffic lights at 26 programmed intersections (of which 6 are in the core area). Operators were trained to handle the equipment and software. In addition, a training course for all stakeholders, including the Vientiane traffic police, was held in 2006. VUDAA later requested ADB to provide and install 116 streetlights under an amendment to the VUISP contract. 62. In addition to the works carried out, the AFD consultants, BCEOM, recommended several other interventions that were not implemented. One of these was tried but lasted only a few days, namely the closure of streets to non-essential traffic in the evenings. Gates were erected at the entrances to three streets (Nokeokhoummane, Manthathourath and Francois Ngin). However it is understood that the lack of any parking management in the areas adjacent to these streets resulted in some chaotic knock-on effects of the closures, and the gates were removed. This serves to demonstrate that any one traffic management or traffic calming measure needs to be undertaken with complementary actions in a comprehensive approach. 63. The Urban Transport Master Plan Study carried out by Katahira (2008) proposed a number of traffic management measures, some strategic, some very detailed. To date however none of these has been taken forward into implementation (although the recommended enhancements to bus services is in the pipeline). The Katahira study reports that many of its recommended actions were being undertaken by the Government through its Road Safety Action Plan. The reality is that only some of these have happened and those that have commenced are of limited scope. 64. The ongoing Urban Master Plan Study, by Nippon Koei, has also identified potential traffic management measures. These include a bus rapid transit (BRT) system that would pass through the heart of the historic centre, the need for traffic demand management, and the creation of ‘community roads’ in some of the small streets in the tourist area. The last of these has been developed further under this VSUTP. The need for TDM is also supported by this project, but the BRT scheme as proposed is not (alternative public transport proposals are described in Appendix 5). A concern here is that the Nippon Koei team has developed transport proposals that are not consistent with the Urban Transport study, and are based on their own independent traffic surveys. 54


Appendix 6

55


Appendix 6

Table A6.7 Summary of Previous Traffic Management Proposals Project/Proposals

Notes

BCEOM Upgrade street lighting – 140 units for city centre – mostly in streets at right angles to Fa Ngum road Traffic lights – 6 intersections Thermoplastic road markings

Not implemented

Pedestrian safety barriers – 600m

Not implemented

Installation/reorganization of regulatory road signs Gates and signs for 3 pedestrian streets (night time closures) – Francois Ngin, Nokeokhoummane, Manthathourat

Not implemented – tried for 3 days but knock-on effect of parking in adjacent streets was seen to be unacceptable

Raised platforms - 6 no. - (wide speed bumps) on Fa Ngum Road

Not implemented

Speed ramps on side streets (at each end) – 10 no. – Chou Anou, Francois Ngin, Nokeokhoumane, Manthaturat, Pangkham

Not implemented

Parking control signs near intersections – 40 no. Tuk-tuk parking bays – 8 no. – improvement of areas where tuk-tuks and other vehicles regularly park already

Not implemented

Mid-block motorcycle parking bays – 5 no.

Not implemented

Shared pay-parking and tuk-tuk waiting areas – 3 no.

Not implemented

Speed limit signs – 21 no. Pedestrian gates at Nam Phou Fountain

Not implemented

Regulatory signs for deliveries

Not implemented

Bus shelters – 8 no. Katahira Traffic management facilities – road markings, safety islands, road signs – at nonsignalized junctions

Not implemented

Traffic markings along roadways

Not implemented

Signalization needed but being covered under other projects and by VUDAA’ Traffic accident data system and management needed but being addressed by Government under Road Safety Action Plan

System still in development and not in operation

Writing tests for motorcycle license applicants – but being dealt with by MPWT Training for motorcyclists – driving schools and training centers – being addressed by Road Safety Action Plan Comprehensive traffic enforcement manual and training to traffic enforcement officers – but being implemented under Road Safety Action Plan Improvements to seven black-spot junctions Nippon Koei Creation of ‘woonerf’ streets (where pedestrians and cyclists have legal priority over vehicles). Pilot roads suggested as Rue Nokeokhoumane and Rue Hengboun

Seems unlikely that JICA will fund it?

Bus rapid transit through core area along Sethathirath road. TDM needed – but no specific proposals Key to projects: BCEOM - ADF/ADB 2003, Vientiane Urban Infrastructure and Services Project, City Centre Conservation Zone, Street Management Plan Katahira - JICA 2008, Comprehensive Urban Transport Master Plan Study Nippon Koei - JICA 2010, Urban Master Plan

56


Appendix 6

65. The government’s Road Safety Action Plan program also addresses traffic management issues. Relevant proposals are shown in Table A6.8. Table A6.8 Summary of Government Proposals for Road Safety Selected items with implications for traffic management (Based on Road Safety Action Plan presentation Sept 9th 2010)

Proposals

Notes (e.g. implemented or not, issues arising)

Develop Road Accident Data Information System (RAIS)

Process initiated but the system is not active

Collect at least 5% of RTF for road safety

Decree enacted (but funds not yet flowing?)

Traffic signals improved in 4 hazardous locations in Vientiane

Completed

Driver training handbook

Developed and distributed nationwide

New theory and practical test for motorcycle drivers

Introduced

Computer system for vehicle registration and driving license control

Electronic chip cards in use

New traffic regulations

Drafted

New road signs and traffic marking standards

Drafted

Traffic police training in traffic surveillance

Ongoing

57


Appendix 6

III. A.

PROPOSED TRAFFIC MANAGEMENT STRATEGY

Principles of the Strategy

66. The proposed traffic management strategy is based on the assessments described above. These in turn are founded on the findings from surveys, meetings with stakeholders, focus group discussions and interviews. The key elements of the proposed traffic management strategy are as follows:     

Protect and enhance the environment and character of the historic core Improve the pedestrian environment, particularly the ease (and safety) of access from the city centre to the riverfront Employ TDM measures to limit the number of individual car trips into the core area Encourage public transport usage through convenient linkage of car parking and bus routes Revise parking arrangements (including fees) throughout the core area

67.

The proposed strategy is illustrated in Figure A6.8.

B.

Enabling Conditions

68. The effectiveness of any traffic management strategy in Vientiane will depend to a large extent on the presence of enabling conditions. These include institutional changes that are discussed in Appendix 4. They also include education and enforcement. Without these the improvement of infrastructure and systems to control traffic will have minimal impact on actual traffic movement and road safety. Extensive institutional strengthening and capacity building will be required to achieve these objectives. 69. The strategy proposed here is therefore based on the assumption that institutional strengthening and capacity building will happen. Key amongst these are:    C.

The introduction of effective traffic and parking enforcement The education of drivers, other road users, and the regulators Improve coordination and control of new development schemes Holistic Approach

70. It is also important to point out that an holistic approach is required. Many different types of action will be required to address the wide range of issues that impact traffic and road users. A summary of the traffic and road characteristics and the potential measures to address them is shown in Table A6.9.

58


Appendix 6

59


Appendix 6

Table A6.9 Traffic and Road Characteristics and Measures to Address them

Improved street lighting

Enforcement of parking restrictions

Parking provision

Training of police

Better enforcement of traffic regulations

Improved centralized traffic control

Parking in restricted zones

More controlled junctions

Double parking

Better junction equipment

Driver training – existing drivers

Better road markings

Driver training – new drivers

Better road surfaces

Can be Addressed by:

Education in schools

Traffic and Road Characteristics

Congestion

Lack of junction discipline Driver Behavior Poor junction behavior – especially diagonal crossing

Incorrect lane use at signalized junctions

Rushing red lights

Roundabout behavior – priority mistakenly given to vehicles entering roundabout

Motorbikes travelling against traffic

Zebra crossings completely ignored

Poor use of indicators (e.g. hazard lights for straight on) Wandering between traffic lanes Big cars bullying others Reluctance to park any distance from destination

Pulling out into traffic without looking

Swerving to avoid potholes etc. Other Safety Issues

Faint or non-existent white lines

Restricted visibility

 

Parking and other structures on the footways Policing

Police targeting motorcycles and small trucks, not large cars Police overriding traffic lights

 

60

 


Appendix 6

D.

Parking Strategy

71. On-street parking is one of the pressing issues in Vientiane. Many stakeholders, both in government and in the community, pointed to this issue as a priority. Although there is no magic bullet to solve traffic management problems in Vientiane, better organization and enforcement of parking could make a major contribution to improving the situation. 72. Many stakeholders called for the provision of additional parking. However this is not necessarily the best way to proceed. Increasing parking provision in the core area will inevitably attract more cars and would not be conducive to protecting the character and amenity of the area. As shown in the parking survey (see Appendix 7) there are already around 5,000 car parking spaces in the core area. The provision of additional car parks within the area will not solve the problem in the long-term. 73. The options and approaches to car parking in Asia have been explored extensively by others. A comprehensive analysis of the current situation and latest thinking on the subject are well presented in a recent report prepared for ADB - Parking Policy in Asian Cities. 8 The key findings and recommendations of that study are relevant to the problems faced in Vientiane and are summarized in Box 2. 74.    

The proposed parking strategy is based on the following elements: Provision of new car parks only on the outer edges of the core area A complete review and overhaul of core area parking based on multiple objectives Introduction of payment for on-street parking Encouragement of ‘park once’ by provision of convenient and efficient bus services

75. The strategy therefore is a m ixture of carrot and stick measures. Parking constraints will work effectively only where there is perceived to be good public transport. This should be achievable first in the downtown area, and can then be replicated elsewhere in the city. 76. Although it is not proposed to construct new car-parks within the core area itself, the establishment of park and ride facilities on the edge of the area should go a l ong way towards relieving parking pressure and smoothing traffic flows. 77. A change in attitudes will be required. Not all residents and businesses will be able to park their vehicles in front of their properties, and those that will be able will have to start paying for the privilege. It is inevitable that some people will be adversely affected in terms of their parking convenience. This might result in some moving out of the area, but this a common and ‘natural’ phenomenon in city centers worldwide, and will follow a pattern seen in other countries that have moved towards more open socialist market economies.

8

Parking Policy in Asian Cities, Paul Barter, ADB 2010

61


Appendix 6

Box 2: Summary of Findings and Recommendations from Parking Policy in Asian Cities, Paul Barter, ADB, 2010 Solving on-street parking problems requires on-street parking management, not necessarily off-street supply expansion. Progress on parking policy is difficult without efficient on-street parking management. There is no way to achieve orderly and efficient on-street parking except via effective on-street parking management. Creating off-street parking does not magically suck cars away from streets. Motorists will park in the most convenient spaces, in the streets, so long as the consequences or costs are minimal. Most Asian cities are concerned about a parking shortage. But chaotic on-street parking is not necessarily a signal of shortage. It is a sign of poorly managed on-street parking. Claims that parking is lacking need t o be examined carefully. The opportunity cost of parking is a problem if not reflected in prices. All parking, even if it is on municipal land, has a high spatial opportunity cost especially in high-density urban contexts. Government-subsidized parking is a poor use of taxpayers’ money. Charging market prices in city-owned facilities, as some cities in the study do, would make government-supplied parking less problematic and somewhat easier to fund. Including significant parking requirements in building permissions seems an obvious and easy option but are problematic. This approach is under widespread attack internationally. It risks feeding a ‘predict and provide’ spiral of ever higher parking supply. It is an audacious assumption to think that we can predict parking demand associated with specific buildings even before they are built, regardless of their changing context, and s till be accurate for decades into the future. Price controls on private-sector parking are extremely unwise. Price regulations applying to private sector parking are unusual internationally, but some cities in Asia do t his. Price regulation undermines useful market mechanisms. Constraint-focused parking policy has niches but faces barriers. Around the world, some cities with effective public transport systems use parking constraint policies and ot her TDM measures to get more value from their public transport investments. This also provides congestion relief which does not flow automatically from public transport investments alone. It is difficult to actively and e xplicitly constrain parking in localities that are not perceived to have excellent public transport access. Multi-objective parking management has much to offer, but is not yet being adopted widely in Asia. ‘Multiobjective parking management’ approaches are likely to offer solutions for many parking problems in the region. ‘Park-once’ neighborhoods are suitable for many mixed-use areas in SE Asian cities. In dense, mixed-use areas it makes sense to think of parking demand and supply as neighborhood-wide phenomena. Unfortunately, in many areas, the efficiency and r esponsiveness of parking systems is undermined by poorly managed on-street parking, by too much private parking, or by price controls.

62


Appendix 6

IV.

PROPOSED TRAFFIC MANAGEMENT COMPONENT

78. The proposed traffic management project component is comprised of a number of subprojects. Whilst these sub-projects are put forward as separate discrete items, many can and should be assembled into project packages. A.

Sub-project Selection Criteria

79. The selection of sub-projects has been guided by a range of criteria aimed at maximizing the achievability and sustainability of the interventions. The criteria are:            

Achievable results – not just more recommendations that will remain only in a report Minimize dependency on other things happening as pre-conditions Build on previous ADB investments Pick up previous proposals that were not implemented due to lack of funding Linkage to other ongoing or planned projects High traffic management impact potential High potential for improving road safety High priority for tourism Ongoing support for facilities provided by previous projects (e.g. traffic management centre) Support to existing infrastructure that will improve its sustainability Consistency with National Road Safety Action Plan Potential poverty reduction impact

B.

Summary of the Sub-projects

80.

The proposed sub-projects are summarized in Table A6.10.

C.

Description of the Sub-projects

81. For many components of the proposed project the situation will need to be reviewed and updated prior to determining the actual works to be undertaken. The condition of road and traffic infrastructure and equipment at the time of undertaking the current assessment is likely to have changed by the time the project starts. For this reason specific detailed locations have not been put forward for every sub-project. 82. The full-page plans and maps associated with the various sub-projects are grouped together after the text at the end of this section.

63


Appendix 6

Table A6.10 Summary of Possible Traffic Management Sub-projects Sub-project

Description

1.

Multi-storey car park for ‘park and ride’ on east and west edges of core area.

2.

Traffic management action area plan for market/Nong Chanh zone

3.

Review and rationalization of parking restriction areas

4.

‘Woonerf’ street improvements in Nokeokhoumane, Francois Ngin, Mathathourath, Chou Anou, Ong Teu

5. 6.

‘Woonerf’ street improvements near Nam Phou fountain Street improvements - various

7.

Pedestrian crossing facilities

Construction of parking facility near to bus station and market areas. Possible sites include existing water slides property (closed), or in association with other proposed commercial developments. Construction of parking facility in vicinity of Chao Fa Ngum park. Possible site behind Novotel Hotel. Review and design for traffic management in area including Talat Sao, bus station and proposed new developments on Nong Chanh sites (possibly including new car park). Re organization of red and yellow zones with clearer signage, and enforcement. Introduction of parking control officers. Tow away areas. Payment through electronic vehicle registration cards Adjustment/narrowing of carriageway, landscaping, designated parking areas. Residents parking scheme. (Suggested by JICA study as ‘community roads’). Adjustment/narrowing of carriageway, landscaping, designated parking areas. Carriageway repairs, footway repairs, surfacing and organization of parking areas, street lighting, road markings Installation of light-controlled pedestrian crossing facilities – at existing crossings (and new locations if identified) Pedestrian bridges Upgrading traffic lights, CCTV, sensor strips New traffic lights at two junctions Improvements to junction geometry, road markings (possibly including islands) and signage at two junctions on Khouvieng Road Identification of obstacles and dangers on all footpaths in core area and proposals for removal/relocation (includes vendors, encroachment by cafes etc, motorbike parking) Review and revision of road markings. Replacement of confusing lane markings, introduction of clear motorcycle only lanes, use of permanent …… paint. Lane marking changes on Lane Xang Avenue and Fa Ngum road. Computer and communication equipment, training Study traffic conditions between Patonxay and the New Roundabout to determine viability of converting to one-way street traffic flow pattern

8. Improvements at light-controlled junctions 9. Additional light-controlled junctions 10. Improvements at non-light-controlled junctions 11. Walkability improvements on footpaths

12. Road markings

13. Support to traffic control centre 14. One-way street improvement study

64


Appendix 6

1.

Multi-storey car parks for ‘park and ride’

83. Two general locations have been identified for the provision of car parks on the eastern and western edges of the core area. It is envisaged that these will be multi-storey structures. They will serve as the main car parking for the proposed ‘park and ride’ system for the core area. The park and ride service is described in more detail in Appendix 5. 84. At the western end of the core area no specific site has been found for a c ar park. However, land behind the Novotel has potential and is well located. The government is urged to undertake investigations to see if this site might be feasible. At the eastern end there are a number of possible sites, which are described below, and again the government should take early action to explore the possibilities. The mechanism for acquisition and development of these sites has not been determined at this stage. However it is felt that these could be suitable projects for private sector involvement. This option will need further examination. 85. The eastern location is in the vicinity of Nong Chanh, along Khou Vieng road. This area is in the process of development with several pending schemes as described in Section II. The locality also includes a defunct waterslide complex, abandoned by its Malaysian owner. This would be an ideal site for the car park. It is understood that the government has approached the Malaysian Embassy with a v iew to contacting the owner. It is strongly recommended that the possibility of incorporating a multi-storey car park is put forward once negotiations commence regarding the future of the site. 86. The other development sites at Nong Chanh offer possible alternate sites for the proposed car park, either as a stand-alone facility or incorporated into another element of one of the developments. Discussions on proposals for two of these sites are still at an early stage and the developers could be encouraged to consider this. 87. Another option would be t o consider incorporating the car park in a new bus station development on the existing bus station site. This would be a multi-storey building with the busstation on the ground floor and parking and office space above. 88. The optimal locations of the car parks on the edge of the Core Area are shown in the strategy plan (Figure A6.8). Other possible sites that have been identified are shown in Figure A6.16 and are as follows: 1) South of the proposed car park site within the Nong Chanh southern section. 2) Private land near the junction of Khou Vieng Road and Sokpaluang Road. 3) Private land just north of the junction in 2) above. 4) Adjacent to the new riverside road where it joins Thadeua Road at the junction with the Lao-Thai Road. 5) Near Don Chanh Palace Hotel adjacent to the new link road between the riverside road and the southern end of Fa Ngum Road. 89. All of the above options will require early and decisive action. The government is urged to consider these possibilities and meanwhile put a hold on any approvals for developments in these critical parts of Vientiane city centre. Action now will greatly improve the chances of creating an efficient and attractive centre for commercial activity and a transport hub.

65


Appendix 6

2.

Traffic management action area plan for market/Nong Chanh zone

90. As described above and in Section II the Nong Chanh area will see many new developments in the near future. These need to be coordinated within a c lear and comprehensive plan including access, traffic management and parking. This will also demonstrate how the park and ride facility can be included within the scheme. See Figure A6.9. Figure A6.9 Nong Chanh Development Sites and Potential Car Park Locations

3.

Parking Review, Reorganization, and Enforcement

91. This involves a complete overhaul of the parking regime in Vientiane. The reorganization and the proper enforcement of parking in the core area will improve traffic flows, and have a beneficial impact on the environment generally. 92. The existing restricted areas will be reviewed and rationalized. For instance there are many sections of yellow ‘waiting only’ where cars are habitually parked and cause no particular obstruction. These can become parking permitted zones. There are some areas where the restrictions need to be modified in order to be better coordinated (e.g. Fa Ngum road – see

66


Appendix 6

under road markings sub-project). The odd and even date scheme in Dong Palane road should be scrapped as it is not necessary. There is adequate carriageway width with cars parked on both sides. The odd and even date schemes in Nokeokhoummane and other small streets will be removed under the sub-project for those streets. 93. The system of identifying restricted areas will be improved. The current system relies mostly on being able to see the curb markings. Existing signs are not clear and need to be reviewed, redesigned, and located more clearly. 94. The parking system will also include the introduction of time restrictions. These should include provisions to ensure little or limited parking along the proposed bus routes during peak times. Consideration should also be given to the use of restricted periods for delivery vehicles, for instance to avoid peak times, and evenings in tourist zones. These time limits will be a measure not seen before in Laos and will need to be designed to be both practical and enforceable. 95. The sub-project will include the introduction of a payment scheme for on-road parking. There are several options for the payment and collection of parking fees that can be explored. The existing use of cards with encoded chips for vehicle registration and driver licenses offers an opportunity to introduce an electronic parking fee system. Fee collection could be via on-thespot electronic meters or attendants with hand-held card readers, or through a method of prepayment. Residents and businesses will also have to pay for parking on the street in front of their houses and premises. The payment system for them could be through pre-payment on a monthly or annual basis. The pricing scheme for on and off-road parking will need careful consideration (see Box 2). The aim should probably be to make off-road parking marginally more attractive than on-road, (in terms of security and pricing) and parking outside the historic area a lot more attractive. 96. The revised parking system will work only if properly enforced. It is recommended that the responsibility for enforcement be assigned to a team of Parking Control Officers (PCOs). (The traffic police have indicated that they would be happy to relinquish this task). The institutional responsibility for this team is discussed in Appendix 5. The PCOs would have the power to issue fines and to authorize the clamping and towing away of vehicles. An additional tow truck (or trucks) will be purchased to facilitate this. Tow-away zone signs will be erected in key locations where illegal parking will not be tolerated. These, and a higher frequency of vehicle removals should establish the fact that the tow-away threat is a real one. 4.

‘Woonerf’ street improvements – Nokeokhoumane and others

97. Woonerf streets were pioneered in the Netherlands. They are streets where pedestrians and other non-motorized traffic have priority over motorized vehicles. The design of these streets is aimed at making it clear to users that these are places for pedestrians with access for cars and motorbikes rather than the other way around. This is achieved with a c ombination of width constrictions, surface treatments and landscaping. 98. Four streets are proposed as the pilot area for the woonerf scheme. These are Manthathourath, Nokekhoummane, Francois Ngin, and Ong Teu (see Figure A6.10). The scheme will physically reduce the area available on the roadside for the parking of cars. Although the area will be similar to the existing permitted area, it will be significantly less than used in practice as the odd and even restrictions are ignored in these streets. The scheme will

67


Appendix 6

therefore require some changes of attitude amongst residents and businesses. No longer will everyone will be able to park their car in front or their property. 99. An example of how the woonerf approach might be applied to Rue Nokeokhoumane is shown in Figure A6.11. The sketch design has been based on minimum disruption to the existing roadway and footway fabric as these were constructed to a high quality only a few years ago under the VUISP ADB funding. A more comprehensive woonerf scheme might be considered that would entail major change to the existing road and footway structure. At the same time it should be recognized that these are primarily commercial streets and the appropriate balance of pedestrian/vehicular priority will be different from the original residential woonerf concept. 100. The full pedestrianization of some streets was considered. However, in commercial areas this can happen only if rear access for servicing is provided. In Vientiane this would require extensive clearance of backland properties. It is a possible long-term comprehensive planning option, but has been discounted in the medium-term. 5.

‘Woonerf’ street improvements - leading to and around Nam Phou fountain

101. The woonerf principle can also be applied to Rue Pangkham where it links Samsenthai road to Nam Phou fountain (see Figure A6.10). This is one of the primary routes for tourists who are currently forced to walk in the road due to excessive clutter on the footpaths. 6.

Street Improvements – various

102. There are various locations throughout the core area where minor improvements to the road and footway conditions will contribute to a more convenient and safer environment for drivers and pedestrians. These include broken road surfaces, unsurfaced and ill-maintained parking areas, poor street lighting etc. Some of these locations can be i dentified today, for instance Rue Sakkarine in front of the Mother and Child Hospital, and the parking area in Rue Hatsady. However, the conditions at these and other places may change between now and the start of project implementation, and it is recommended that the situation is reviewed at that time in order to specify the works involved. It is anticipated that this will include:    

Carriageway repairs Surfacing and organization of parking areas Street lighting Road markings 7.

Pedestrian Crossing Facilities

103. The walkability survey (see Appendix 8), along with other site visits and anecdotal evidence, revealed that pedestrian crossing facilities are substandard and unsafe. It is proposed to introduce light-controlled pedestrian crossings at key locations as shown in Figure A6.12. 104. In certain locations there may be justification for grade separation of pedestrians and traffic. The need for pedestrian bridges was raised in some village focus group meetings, particularly near schools and colleges. Possible locations for bridges are shown in Figure A6.12. Busy commercial areas are also potential locations, although bridges in these areas would probably need to be accompanied by pedestrian barriers to ensure their usage. All locations are

68


Appendix 6

based on initial observations and comments, and will need more detailed analysis of pedestrian and traffic volumes, and accident rates. 8. 105.    

Improvements at light-controlled junctions

Investment is needed to improve existing traffic lights in the core area. This will include:

CCTV Under-surface sensor strips Review and adjustment of phasing Improved light technology (LED)

106. The sub-project will include replacement of existing equipment and provision of new equipment where required. Junctions requiring CCTV and sensor strips are shown in Figure A6.13. 9.

Additional light-controlled junctions

107. Two junctions that would benefit from traffic lights have been identified in the core area. These are busy intersections on the main one-way streets that run through the centre, namely Samsenthai and Sethathirath. Including motorbikes these have peak flows of 2,300 and 2,500 vehicles per hour respectively. 108.

The location of these two junctions is shown in Figure A6.13. 10.

Improvements at non-light-controlled junctions

109. The geometry at two junctions on the section of Khou Vieng road just west of Lane Xang Avenue will be improved. The improvements will provide clearer and more controlled channeling of traffic. The locations of the two junctions are shown in Figure A6.10. 11.

Walkability improvements

110. The Identification of obstacles and dangers on all footpaths in core area and proposals for removal/relocation (includes vendors, encroachment by cafes etc, motorbike parking). The principal criteria for clearing the route for pedestrians will be that they can pass along footpaths without being forced into the road. Certain routes will be identified for improvements that will enable their use by the disabled. 111. This will also include repairs to footways, attention to tree roots affecting pavements, and measures to control footway encroachment by building sites. 12.

Road markings

112. Road markings throughout the core area will be reviewed and improved under the Street Improvement sub-project described above (No.6). However, two particular sections of road have been picked out for revision of the lane markings. 113. On Lane Xang Avenue the three existing lanes will be replaced with four (see Figure A6.14). This will provide two lanes for straight on traffic queuing at lights, something that already happens regularly by cars squeezing across from the right turn and left turn lanes. This will 69


Appendix 6

reduce the width of the lanes to 3.0m, which is less than recommended in the MPWT’s Lao road design manual. However, it is a width that is common elsewhere in the core area, and should be considered acceptable. In addition, narrower lanes will serve as a traffic calming measure. 114. On Fa Ngum Road the lanes will be changed to accommodate a parking strip adjacent to the buildings and no parking on the river side of the street. This will eliminate the current occurrences of northbound traffic being forced across the centre line (see Figure A6.15). 13.

Support to traffic control centre

115. The existing traffic control centre requires further investment to enable it to function effectively. This will include replacement of damaged computer equipment, enhanced software, and training of staff. 116. Also included will be the infrastructure required to provide full monitoring and control of all light-controlled junctions in the core area. 14.

One-Way Street Improvement Study

117. In recent years during periods of heavy traffic during festival periods, and also during the 2009 ASEAN games, approximately 1.5 km of Kaisone Phomvihane Road and approximately 1.1 km of 23 S ingha Road, between Patonxay and the New Roundabout, were temporarily converted to one-way operation in order to improve traffic flow characteristics. This subproject will undertake a study of traffic conditions along these two road corridors and adjacent areas to determine the technical viability of permanently converting these two sections of road to oneway operation.

70


Appendix 6

71


Appendix 6

72


Appendix 6

73


Appendix 6

74


Appendix 6

75


Appendix 6

76


Appendix 6

77


Appendix 7

PARKING SURVEY AND ANALYSIS I.

INTRODUCTION

1. This Appendix describes the results of the parking survey carried out for VSUTP. It explains the current system of parking restrictions, and the findings of surveys undertaken to ascertain the numbers of parking spaces and parked vehicles in different types of parking area in the core area. II.

PARKING CONTROLS

2. There are four types of parking restriction used in the core area. These are shown in Table A7.1 and in Figure A7.1. Table A7.1 Types of Parking Restriction Type of Zone Red and white curb markings Yellow and white curb markings Black and white curb markings Odd and even date signs

Parking Restriction No stopping or parking Stopping and waiting only Parking permitted in direction of traffic No parking on alternate dates

Note: Red and white zones, yellow and white zones etc are referred to elsewhere in this and other VSUTP documents as ‘red zone’ or ‘red parking area’ etc

3. The red no-stopping or parking areas are also indicated by the international sign for clearway. However these signs are not always prominent and are accompanied by small signs underneath indicating the distance beyond the sign to which the restriction applies – e.g. ‘50m’. It is unclear how drivers are supposed to know exactly where the 50m ends. 4. The odd and even date parking is indicated only by sign. In Nokeokhoummane and adjacent streets there are signs placed at the entrance to the road and near the far end. There are no ‘reminders’ half way down the (one way) streets. This type of restriction is not commonly used in Vientiane (Dong Palane the only other road known to the VSUTP team) and may be the reason why it is flouted daily by dozens of drivers. III.

PARKING PROVISION

5. Parking surveys were undertaken to ascertain the numbers of vehicles within the core area on a typical weekday. Vehicle numbers were counted in three types of parking area public parking areas, within large Government and commercial premises, and on-street. An initial survey was undertaken on 19th October and the detailed results of this are shown in Tables A7.3, A7.4 and A7.5. A summary is shown in Table A7.2. A second survey was carried out on November 16 to verify that the data from the first was ‘typical’. Summary figures for the second survey are shown in Table A7.2 also.

78


Appendix 7

Table A7.2 Summary of Parking Survey Results Type of Parking Area

Oct 502 2293 1668 742 5205

Public parking areas Car parks in Government and private premises On-street parking - legal On-street parking – illegal* Total

Cars

Nov 695 2518 1990 653 5856

Motorbikes Oct Nov 36 187 5866 5285 1880 3076 144 88 7926 8636

*In red and yellow zones, on the wrong side in odd and even date zones, and on the footpath

6. The survey also estimated the numbers of public spaces available for parking. This showed that about 720 s paces are available in public parking zones and 300 i n designated roadside echelon and right angle parking. The total length of black zone permitted parking areas in the core area is around 5,500 m. That is adequate for approximately 780 vehicles (at 7m per space for parallel parking). In total therefore there are around 1,800 spaces provided by the government for public parking in the core area. From this it can be seen that the bulk of parking provision is within the compounds of ministries and other public and private establishments.

79


Appendix 7

80


Appendix 7

81


Appendix 7

82


Appendix 7

Table A7.3 Public Parking Areas

No.

Road and

Capacity

Parking name 1

Watchan Car parking

2

Lanexang Hotel car parking

3

Mahosot Hospital car parking

4

National Culture Hall car parking

5

Vientiane 450 Market Section 1 Section 2

6

Hatsady Village Car parking

7

Gallieni Road Car parking TOTAL

Vehicles

Motorcycles

Side (No.) North Center South North Center South North Center South

North South North South North South North South

(No.) 28

(No.)

41 44 19 29 100

9 -

35 35 100 100 50 45 75 18

26 23 6 18 35 42 62 20

20 7 -

502

36

719

83

Notes

(Kips/car)

11 6 41 45 44 18 15 20 70

-

Parking Fee 3,000

VUDAA Responsible

3,000

4,000 kip/8 hour for Lao Commercial Bank Staff

3,000

VUDAA Responsible

free

Bank of Lao PDR/Pizza Restaurant customer

For LTC rental 12,000,000 kip/month Market (in front of market building) free 4,000

Private sector responsible Tuk-tuk station (Near Kouadin Market)


Appendix 7

Table A7.4 Parking in Government and Private Premises No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35

Location

Vehicles (No.)

LTC( Lao Telecommunication Main office Sailom) ETL Sailom Mintharadeth Building Tigo - Daoheuang Group - imobile Shop Lao Joint Development Bank Lao - Viet Bank Lao National Tourism Setthi Market (Mini mark) Vientiane Commercial Building Morning Market (Shopping mor) Post office Ministry of Education Ministry of Information & Culture ElectricitĂŠ du Laos (Sisaket office) Ministry of Public Security Kuadin Market Vietnam Market Kouadin Bus Station University of Sciences of health Mahosot Hospital International Clinic National Mother & Child Hospital Vientiane Capital (DPWT & VUDAA) Lao Aviation Faculty of Sciences of Infirmaries Lao Plaza Hotel Ministry of Labour & Social welfare Department of Forestry Chaleunxay Hotel Chao Anouvong Stadium Lao Women Union Lao Red Cross ADB Office Wat Thatfoul Pakpasak Technical College TOTAL

84

Motorcycle (No.)

56 83 7 24 40 17 32 11 69 296 148 94 44 59 174 135 96 18 87 105 16 20 88 22 12 58 37 64 6 36 13 24 13 237 52

124 157 12 46 56 18 58 13 117 148 698 56 37 62 516 781 273 24 348 746 53 76 122 22 263 21 53 27 5 53 28 35 10 131 677

2,293

5,866


Appendix 7

Table A7.5 On-street Parking Section location No. Road and Section From

1

To

Number of Cars Parking Length of Vehicles Illegally Black/White Vehicles Parked Motorcycle in Yellow Red Wrong in Side Road Footpath Property Roadside Marking Marking Side Road Footpath Property Marking Area (No.) (No.) (No.) (No.) (No.) (No.) (No.) (No.) (No.) (No.) (m)

Khounboulom Rd

1.1 - Section 1.2 - Section

Fa Ngum Rd Setthathirath Rd

East

8

2

1

1

0

0

11

0

220

West

3

0

0

5

0

0

7

0

212

East

7

4

0

3

0

4

39

0

85

West

11

2

1

2

0

0

12

0

45

Chao Anouvong Rd East

8

2

3

0

2

1

3

0

97

Setthathirath Rd Samsenthai Rd

1.3 - Section

Samsenthai Rd

West

2

3

2

0

2

0

6

0

130

1.4 - Section

Chao Anouvo ng Rd Saylom Rd

South

7

8

5

1

0

5

15

15

355

North

4

0

0

0

0

0

0

0

411

2

Saylom Road

Khounboulom Rd

South

24

3

2

4

4

0

89

9

285

North

29

0

1

9

2

0

30

6

120

3

Dongpalane Rd South

0

1

0

0

0

0

0

0

105

North

0

5

2

0

0

0

0

2

30

East

15

6

12

21

0

0

46

18

0

West

2

11

10

2

0

0

42

0

0

Chao Anouvong Rd North

4

0

0

0

0

0

10

0

68

South

0

4

2

0

0

0

18

0

0

North

27

4

2

8

0

0

36

35

174

South

1

21

2

0

1

0

36

0

0

North

4

7

0

2

0

0

0

0

0

South

1

4

8

0

1

0

35

0

0

Chanthakhoummane Rd North

13

2

0

0

0

5

29

0

155

South

0

4

0

2

0

1

26

0

0

North

0

2

0

0

0

0

0

0

South

0

2

0

0

0

0

7

0

3.1 - Section 3.2 - Section 4

Remarks

Lanexang Avenue Nongbone Rd

Lanexang Avenue

Nongbone Rd Hong Ke (Channel)

2

Samsenthai Rd

4.1 - Section

4.2 - Section

4.3 - Section

Khounboulom Rd

Nokeokhoummane Chao Anouvo ng Rd Rd Nokeokhoummane Rd

Pangkham Rd

4.4 - Section

Pangkham Rd

4.5 - Section

Chanthakhoummane Lanexang Avenue Rd

85

4

Kualao 130 Restaurant 0


Appendix 7

Section location No. Road and Section From

4.6 - Section 4.7 - Section

Lanexang Avenue Mahosot Rd

To

Mahosot Rd Gallieni Rd

Number of Cars Parking Length of Vehicles Illegally Black/White Vehicles Parked Motorcycle in Yellow Red Wrong in Side Road Footpath Property Roadside Marking Marking Side Road Footpath Property Marking Area (No.) (No.) (No.) (No.) (No.) (No.) (No.) (m) (No.) (No.) (No.) East

7

4

0

West

0

0

0

East

8

0

West

0

0

2

0

Remarks

4

0

0

18

0

0

0

0

0

0

0 Electricite du Lao

0

8

0

0

5

0

0

0

0

0

0

5

0

0

0

0

1

0

0

0

116

6

112

4.8 - Section

Gallieni Rd

Sakarine Rd

East West

1

7

0

0

1

0

0

0

0

4.9 - Section

Khouboulom Rd

Sihom Rd

North

5

1

2

21

1

0

2

0

0

300

South

5

3

3

21

2

3

9

0

8

0

4.10 - Section

Sihom Rd

Sithan Rd

North

2

0

1

0

0

0

0

3

65

South

0

0

3

0

0

0

0

0

0

Chao Anouvong Rd North

0

0

0

0

0

South

11

4

0

0

2

0

6

0

North

0

0

0

0

0

0

36

0

0

South

31

5

0

0

4

0

2

0

220

North

0

0

0

0

0

0

30

0

0

South

31

4

1

3

2

0

37

3

142

Chanthakhoummane Rd North

0

4

0

0

0

0

3

0

South

13

1

0

2

0

0

0

0

130

North

0

0

0

0

0

0

0

0

0

South

0

0

0

0

0

0

0

0

0

East

0

0

0

0

0

0

0

0

Wat 0 Sisaket/Hophakeo

West

0

0

0

0

0

0

0

0

0

East

0

1

0

0

1

0

0

0

0 DPWT

West

0

3

0

3

0

0

0

0

0

Chao Anouvong Rd North

3

1

0

1

0

5

34

0

0

South

0

0

0

0

0

0

0

0

0 Pakpasak

5

Setthathirath Rd

5.1 - Section

Khounboulom Rd

5.2 - Section

Nokeokhoummane Chao Anouvo ng Rd Rd

5.3 - Section

5.4 - Section

5.5 - Section

Nokeokhoummane Rd

Pangkham Rd

Pangkham Rd

Chanthakhoummane Lanexang Avenue Rd

5.6 - Section

Lanexang Avenue

Mahosot Rd

5.7 - Section

Mahosot Rd

Sakarine Rd

6

16

3 16

0 113

0 Water fountain

Fa Ngum Rd

6.1 - Section

Khounboulom Rd

86

13


Appendix 7

Section location No. Road and Section From

6.2 - Section

To

Nokeokhoummane Chao Anouvo ng Rd Rd

Number of Cars Parking Length of Vehicles Illegally Black/White Vehicles Parked Motorcycle in Yellow Red Wrong in Side Road Footpath Property Roadside Marking Marking Side Road Footpath Property Marking Area (No.) (No.) (No.) (No.) (No.) (No.) (No.) (m) (No.) (No.) (No.) North

2

0

0

2

0

0

23

0

98

South

1

0

0

0

0

0

12

0

164

North

1

1

0

0

0

1

15

0

40

South

6.3 - Section

Nokeokhoummane Rd

Manthathourath Rd

2

0

0

0

0

1

5

0

50

6.4 - Section

Manthathourath Rd

Pangkham Rd

North

3

1

0

0

0

0

10

0

115

2

0

0

0

0

1

0

0

145

Pangkham Rd

South Chanthakhoummane Rd North

0

0

0

0

0

0

0

23

0

South

0

0

0

0

0

5

1

0

0

6.5 - Section

6.6 - Section

Chanthakhoummane Mahosot Rd Rd

North

0

1

0

0

1

0

0

0

0

South

0

0

0

0

0

0

0

0

0

5 7

0 1

0 1

3 9

0 0

0 0

Remarks

6.7 - Section

Mahosot Rd

Sakarine Rd

East West

5 8

0 0

0 0

6.8 - Section

Khouboulom Rd

Sithan Rd

North

1

0

0

0

1

5

12

0

0

South

0

0

0

0

0

0

0

0

0

North

4

0

0

4

0

0

0

0

0

South

0

1

0

0

0

0

0

0

0

North

0

0

0

5

0

5

0

0

0

0 Morning market

South

0

0

0

16

0

0

0

0

0

North

5

0

0

5

0

0

4

0

80

South

4

1

1

0

0

3

13

9

243

North

11

0

3

2

3

0

180

South

14

5

0

0

17

0

152 Saisana Hotel

0

0

0

11

0

7

Khouvieng Rd

7.1 - Section 7.2 - Section 7.3 - Section 8

2

Khounboulom Rd Lanexang Avenue Nongbone Rd

Lanexang Avenue Nongbone Rd Sakarine Rd

0 Morning market

Chao Anouvo ng Rd

8.1 - Section

Fa Ngum Rd

Setthathirath Rd

7

8.2 - Section

Setthathirath Rd

Hengboun Rd

North

1

South

10

0

0

8

6

0

0

8.3 - Section

Hengboun Rd

Samsenthai Rd

North

6

3

0

0

13

0

0

South

5

0

0

35

16

0

0

8.4 - Section

Samsenthai Rd

Khounboulom Rd

North

0

13

12

0

3

0

0

87

0


Appendix 7

Section location No. Road and Section From

9

Fancois Ngin Rd

10

Nokeokhoummane Rd

10

- Section

10

- Section

10

- Section

11

Manthathourath Rd

11

- Section

11

- Section

12

Pangkham Rd

12

- Section

Fa Ngum Rd

Fa Ngum Rd Setthathirath Rd Samsenthai Rd

Fa Ngum Rd Setthathirath Rd

Fa Ngum Rd

To

Number of Cars Parking Length of Vehicles Illegally Black/White Vehicles Parked Motorcycle in Yellow Red Wrong in Side Road Footpath Property Roadside Marking Marking Side Road Footpath Property Marking Area (No.) (No.) (No.) (No.) (No.) (No.) (No.) (m) (No.) (No.) (No.) 0

0

0

0

0

0

45

5

0

6

0

29

0

0

7

5

0

5

0

0

19

8

0

0

1

1

6

0

0

6

0

0

9

0

0

9

0

0

0

11

0

0

South

14

0

0

0

0

0

0

North

23

3

0

0

27

20

0

South

21

2

0

0

0

0

0

National culture hall North

10

0

0

0

8

0

0

South

11

0

0

0

10

4

0

Setthathirath Rd

Setthathirath Rd Samsenthai Rd Rue de Puit

Setthathirath Rd

Setthathirath Rd

South

12

0

0

North South

14

0

2

0

0

2

13

0

0

1

North

2

7

0

0

2

South

19

8

2

2

0

North

4

0

South

10

North

0

3 4

19

North

0

15

0

0

0

0

0

0

0

South

31

22

0

0

2

0

0

0

0

10

0

0

0

0

0

64

0

0

0

2

12

- Section

Setthathirath Rd

Samsenthai Rd

North South

8

3

0

0

17

0

0

12

- Section

Samsenthai Rd

Phaynam Rd

North

0

10

0

0

0

0

0

South

6

3

0

0

0

0

0

12

- Section

Phaynam Rd

Khounboulom Rd

North

4

6

0

0

0

0

0

South

1

1

0

0

7

0

0

North

11

0

0

0

0

0

0

South

1

0

0

0

0

0

0

North

0

0

0

18

0

0

0

0 LTC Banch Office

South

5

3

0

10

0

5

4

0 In front of Lido

13

Chanthakhoummane Rd

13

- Section

Fa Ngum Rd

Setthathirath Rd

13

- Section

Setthathirath Rd

Samsenthai Rd

88

7

Remarks


Appendix 7

Section location No. Road and Section From

13

- Section

14

Mahosot Rd

14

- Section

14 14

- Section - Section

15

Sakkarine Rd

15

- Section

Samsenthai Rd

Fa Ngum Rd

Setthathirath Rd Samsenthai Rd

Fa Ngum Rd

To

Phaynam Rd

Setthathirath Rd

Samsenthai Rd Khouvieng Rd

Setthathirath Rd

15

- Section

Setthathirath Rd

Samsenthai Rd

15

- Section

Samsenthai Rd

Khouvieng Rd

16

Galleini Rd

16

- Section

16

- Section

17

De la mission Rd

17

- Section

17

- Section

18

Lanexang Avenue

18

- Section

18

- Section

Setthathirath Rd Samsenthai Rd

Mahosot Rd Gallieni Rd

Setthathirath Rd Samsenthai Rd

Samsenthai Rd Khouvieng Rd

Gallieni Rd Sakarine Rd

Samsenthai Rd Khouvieng Rd

Number of Cars Parking Length of Vehicles Illegally Black/White Vehicles Parked Motorcycle in Yellow Red Wrong in Side Road Footpath Property Roadside Marking Marking Side Road Footpath Property Marking Area (No.) (No.) (No.) (No.) (No.) (No.) (No.) (m) (No.) (No.) (No.)

Remarks

North

14

5

9

1

2

0

0

South

14

11

0

0

0

0

0

North

3

0

0

0

South

0

0

0

North

0

0

0

0

0

0

0

0

0

South

0

0

0

0

0

0

0

0

0

North

15

4

5

2

0

0

0

0

0

South

5

0

0

5

0

0

0

0

0

North

23

0

0

11

0

0

0

South

28

0

0

5

0

0

0

North

8

0

0

0

0

0

0 Piawat School

South

1

2

0

0

5

20

0

North

0

4

0

4

2

7

0

South

1

0

0

0

7

0

0

North

1

0

0

0

0

0

0

South

3

0

0

0

0

0

0

North

0

14

0

0

0

0

0

South

0

10

0

0

0

0

0

East

8

0

0

0

0

0

0

West

12

0

0

0

0

0

0

East

0

0

0

0

0

0

0

West

0

8

0

5

0

0

0

North

0

0

0

0

0

0

0

0

0

South

7

0

0

7

0

0

0

0

0

North

0

3

0

0

0

0

0

0

0

89

16

0

3

0

0

0

0

0

0

0

5

2

Emergency 0 Building


Appendix 7

Section location No. Road and Section From

18

- Section

19

Hengboun Rd

19

- Section

19

- Section

20

Hengboun noy Rd

21

Phainam Rd

21

- Section

Khouvieng Rd

Khounboulom Rd

Anou Rd Setthathirath Rd

To

Saylom Rd

Anou Rd Nokeokhoummane Rd Hengboun Rd

Chao Anouvo ng Rd Stadium

21

- Section

Le Ky Houng Rd

Pangkham Rd

21

- Section

Pangkham Rd

Khouvieng Rd

22

Le ky houng Rd

Samsenthai Rd

Khounboulom Rd

Number of Cars Parking Length of Vehicles Illegally Black/White Vehicles Parked Motorcycle in Yellow Red Wrong in Side Road Footpath Property Roadside Marking Marking Side Road Footpath Property Marking Area (No.) (No.) (No.) (No.) (No.) (No.) (No.) (m) (No.) (No.) (No.) South

1

0

0

1

0

0

0

0

0

North

1

0

0

1

0

0

0

0

0

South

5

4

0

5

0

0

4

0

0

North

23

0

0

0

0

7

25

0

0

South

6

0

0

0

5

0

0

North

70

0

0

0

20

0

0

South

16

3

3

0

14

0

0

North

8

0

0

1

11

0

0

South

0

0

0

0

2

0

0

North

2

0

0

0

0

0

0

South

4

0

0

0

0

0

0

North

9

6

0

0

0

0

0

South

10

1

0

0

0

0

0

North

9

0

0

0

11

0

0

South

7

6

0

0

10

0

0

North

5

1

0

1

3

0

0

South

0

0

0

22

32

0

0 Lao Plaza Hotel

5

23

Hanoi Road

23

- Section

Hengboun Rd

Samsenthai Rd

North

23

- Section

Samsenthai Rd

Phanompenh Rd

North

7

0

0

0

0

0

0

South

8

0

1

0

0

0

0

23

- Section

Phanompenh Rd

Rue du Puit

North

0

0

0

0

4

0

0

South

3

0

0

0

2

0

0

North

1

0

0

0

0

0

0

South

1

0

0

0

0

0

0

Under 0 construction

South

23 24

- Section

Rue du Puit

Phaynam Rd

Remarks

0

Toulan Road

90


Appendix 7

Section location No. Road and Section From

24 24 24

- Section - Section - Section

24

- Section

25

Haiphong Road

25

- Section

Hengboun Rd Samsenthai Rd Phanompenh Rd Rue du Puit

Hengboun Rd

To

Samsenthai Rd Phanompenh Rd Rue du Puit Phaynam Rd

Samsenthai Rd

25

- Section

Samsenthai Rd

Phanompenh Rd

25

- Section

Phanompenh Rd

Rue du Puit

25

- Section

26

Sai Ngon Road

26

- Section

26 26 26

27

28

- Section - Section - Section

Du Puit Rd

Phanompenh Rd

Rue du Puit

Hengboun Rd Samsenthai Rd Phanompenh Rd Rue du Puit

Anou Rd

Anou Rd

Phaynam Rd

Samsenthai Rd Phanompenh Rd Rue du Puit Phaynam Rd Nokeokhoummane Rd Nokeokhoummane Rd

Number of Cars Parking Length of Vehicles Illegally Black/White Vehicles Parked Motorcycle in Yellow Red Wrong in Side Road Footpath Property Roadside Marking Marking Side Road Footpath Property Marking Area (No.) (No.) (No.) (No.) (No.) (No.) (No.) (m) (No.) (No.) (No.) North

4

0

0

5

0

0

0

South

0

0

0

0

4

0

0

North

1

0

0

0

1

0

0

South

5

0

0

0

0

0

0

North

6

0

0

0

0

0

0

South

4

0

1

0

0

0

0

North

0

0

0

0

0

0

0

South

0

0

0

0

1

0

0

North

0

0

0

35

0

0

0

South

2

0

0

18

0

0

0

North

1

7

0

0

0

0

0

South

1

5

0

0

0

0

0

North

0

2

0

0

0

0

0

South

0

2

0

0

0

0

0

North

0

0

0

0

0

0

0

South

0

0

0

0

0

0

0

North

2

0

0

6

0

0

0

South

0

5

0

0

0

0

0

North

4

0

0

0

0

0

0

South

3

2

0

0

0

0

0

North

2

0

0

0

0

0

0

South

1

2

0

0

2

0

0

North

0

0

0

0

0

0

0

South

0

0

0

0

0

0

0

North

7

0

1

2

0

3

0

South

11

0

0

1

2

2

0

North

22

0

0

0

0

0

0

91

Remarks


Appendix 7

Section location No. Road and Section From

29 30 31

Inpeng Road Oongtou Road

Khounboulom Rd Anou Rd

To

20

2

1

0

15

0

0

North

5

0

0

11

7

0

0

South

1

3

0

0

3

0

0

North

9

0

0

5

0

0

0

South

0

2

0

0

19

0

0

North

9

0

0

5

0

0

0

South

0

2

0

0

19

0

0

North

0

0

0

0

0

0

0

South

0

0

0

0

0

0

0

North

0

0

0

42

0

0

0

37

0

0

South

0

0

38

0

0

0

0

0

0

North

3

0

0

10

2

1

1

0

0

0

South

12

0

0

67

0

0

0

35

0

50

North

16

3

1

16

0

0

0

23

0

South

32

12

11

32

0

0

1

60

0

Souphanouvong Rd North

18

0

0

18

0

0

8

0

0

South

11

5

7

1

0

1

4

0

170

North

8

3

0

8

3

0

0

0

0

South

9

1

0

3

0

0

0

0

200

9

2

0

0

0

11

20

Road in Sihom 0 Village

0

Fancois Ngin Rd

Fa Ngum Rd

32

Yonnet Rd

Nokeokhoummane Rd

Pangkham Rd

33

Hatsady Rd

Khouvieng Rd

Lanexang Avenue

Oongtou Rd

34

Nongbone Rd

Khouvieng Rd

Dongpalane Rd

35

Suphanouvo ng Rd

Sithan Rd

Khounboulom Rd

Sithan Rd

36

- Section

36

- Section

Samsenthai Rd

Remarks

South Anou Rd

Wat Chan Rd

36

Number of Cars Parking Length of Vehicles Illegally Black/White Vehicles Parked Motorcycle in Yellow Red Wrong in Side Road Footpath Property Roadside Marking Marking Side Road Footpath Property Marking Area (No.) (No.) (No.) (No.) (No.) (No.) (No.) (m) (No.) (No.) (No.)

Souphanouvong Rd Fa Ngum Rd

18

37

Sihom Rd

Samsenthai Rd

Souphanouvong Rd East

12

West

10

1

6

0

0

0

13

10

38

Pakpasak Rd

Khounboulom Rd

Souphanouvong Rd East

0

0

0

0

0

0

0

0

West

11

0

0

0

0

0

0

3

413

132

210

55

266

1,436

322

TOTAL 1,203

92

333

64

0 Maintenance road for drainage 0 channel 5,507


Appendix 8

WALKABILITY SURVEY I. A.

WALKABILITY ANALYSIS

Introduction

1. The concept of measuring ‘walkability’ was developed by the World Bank, and more recently applied and further refined under the Clean Air Initiative for Asian Cities (CAI-Asia funded jointly by ADB, World Bank and USAID)1. According to CAI-Asia ‘The "walkability index" can help raise awareness and generate interest among policy makers and city officials and help them improve walking in their cities. In addition, it will highlight how ADB can provide support to DMCs in the improvement of pedestrian facilities and policies in urban areas’. 2 2. Based on this methodology a walkability survey was undertaken in Vientiane for VSUTP. The approach used was not exactly the same as used in other Asian cities in the CAI study. In those cities the surveys were city-wide in several different types of neighborhood. The VSUTP focus for traffic management is the core area in central Vientiane which is only one type of neighborhood, namely commercial. T he route and findings are described below along with a photographic record of the route. B.

Route of Survey

3. The survey followed a route from the vicinity of the central bus station and markets, through the central retail and tourist area, to the Mekong riverside. The route is shown in Figure A8.1. C.

Survey results

4. The final walkability score of 61 puts the central area of Vientiane in the middle of the range of scores derived for other Asian cities, and in the ‘somewhat walkable’ category. The Asian cities rated thus far range from ‘very walkable’ (scores of 70-89) to ‘car-dependent’ (scores of 0-24). Whilst ostensibly a reasonable result, it masks the fact that in a relatively lowdensity, low-rise urban environment the score should really have been higher. It reflects a high level of automobile dependence amongst the middle and upper classes in Lao society. The analysis shows that Vientiane scored low in terms of pedestrian amenities, obstructions, and disability infrastructure. 5. The field survey highlighted a number of issues for pedestrians in Vientiane, many of which can be seen in the photos in this Appendix. These are cluttered and obstructed footways, inconsiderate and illegal parking, and poor quality and unsafe road crossing facilities.

1 2

http://cleanairinitiative.org/portal/whatwedo/projects/Walkability Ibid.

93


Appendix 8

94


Appendix 8

D.

Detailed Survey Analysis

Field Survey Rating

Section 1 4 2 4 2 3 2 2 2 5 36 0.3

Section 2 5 4 4 3 3 4 2 4 5 45 0.15

Section 3 3 3 4 2 3 2 1 2 5 12 0.37

Section 4 4 3 5 4 3 2 1 2 5 36 0.23

Section 5 2 4 4 2 2 2 2 2 5 90 0.21

Section 6 3 2 5 4 3 2 1 2 5 15 0.25

1. Walking Path Modal Conflict 2. Availability Of Walking Paths 3. Availability Of Crossings

1 12 6 12

2 7.5 6 6

3 11.1 11.1 14.8

4 9.2 6.9 11.5

5 4.2 8.4 8.4

6 7.5 5 12.5

4. 5. 6. 7. 8. 9.

6 9 6 6 6 15

4.5 4.5 6 3 6 7.5

7.4 11.1 7.4 3.7 7.4 18.5

9.2 6.9 4.6 2.3 4.6 11.5

4.2 4.2 4.2 4.2 4.2 10.5

10 7.5 5 2.5 5 12.5

1 43.2 21.6 43.2 21.6 32.4 21.6 21.6 21.6 54

2 33.75 27 27 20.25 20.25 27 13.5 27 33.75

3 13.32 13.32 17.76 8.88 13.32 8.88 4.44 8.88 22.2

4 33.12 24.84 41.4 33.12 24.84 16.56 8.28 16.56 41.4

5 37.8 75.6 75.6 37.8 37.8 37.8 37.8 37.8 94.5

6 11.25 7.5 18.75 15 11.25 7.5 3.75 7.5 18.75

1. Walking Path Modal Conflict 2. Availability Of Walking Paths 3. Availability Of Crossings 4. Grade Crossing Safety 5. Motorist Behavior 6. Amenities 7. Disability Infrastructure 8. Obstructions 9. Security from Crime 10. Pedestrian count 11. Length of Surveyed Stretch (km) Rating + Length

Grade Crossing Safety Motorist Behavior Amenities Disability Infrastructure Obstructions Security from Crime

Original Global Walkability Index 1. 2. 3. 4. 5. 6. 7. 8. 9.

Walking Path Modal Conflict Availability Of Walking Paths Availability Of Crossings Grade Crossing Safety Motorist Behavior Amenities Disability Infrastructure Obstructions Security from Crime

95


Appendix 8

Final Walkability Rating

1. Walking Path Modal Conflict 2. Availability Of Walking Paths 3. Availability Of Crossings 4. Grade Crossing Safety 5. Motorist Behavior 6. Amenities 7. Disability Infrastructure 8. Obstructions 9. Security from Crime Walkability Score

70 60 87 57 57 47 30 47 100 61

96


Appendix 8

Photos of Walkability Survey Route Khou Vieng Road Vendors, motorbikes, and other clutter seriously impede the footway in the area in front of the Post Office

Khou Vieng Road Large tree root takes up whole footway. (Pavement needs to be extended around the tree at the cost of a car space).

Lane Xang Avenue Very clear and wellmaintained footways in the street blocks near the Presidential Palace

97


Appendix 8

Lane Xang Avenue Lane Xang Avenue junction with Samsenthai Road. The lights have a pedestrian phase with a flashing green man, but the phase is not long enough to cross both carriageways

Samsenthai Road Pedestrian crossing provided with pedestrian lights. However the pedestrian button does not work.

Samsenthai Road Good quality footway surface but cluttered with motorbikes.

98


Appendix 8

Samsenthai Road Pavement parking in a red no parking zone. Pedestrians forced to walk in street.

Samsenthai Road Pavement parking plus on-road parking in red zone. Tourists forced into middle of road.

Pangkham Road A combination of utilities, shop-front clutter and inconsiderate parking completely block the footway.

99


Appendix 8

Pangkham Road As above, with plants and motorcycles adding to the obstruction.

Pangkham Road Unregulated parking in front of building project at Nam Phou fountain. Will require strict enforcement once building is open.

Sethathirath Road Pedestrian crossing – but no lights. Cars rarely stop.

100


Appendix 8

Sethathirath Road Footway parking and forecourt grabbing (property line coincides with building line) create obstacle course for pedestrians

Sethathirath Road Good shady footways. Ad-hoc frontage parking can create vehicular-pedestrian conflict.

Nokeokhoummane Road Food stall blocking footway and occupying road space

101


Appendix 8

Nokeokhoummane Road Vehicles on footway – on the wrong side in odd and even date parking zone.

Nokeokhoummane Road Vehicles park both sides every day despite odd and even date parking zone – forces pedestrians onto the road surface.

102


Appendix 9

TRAFFIC SURVEY

I.

INTRODUCTION

1. This Appendix describes the results of a traffic survey carried out for the VSUTP. The results of the survey will be utilized to assist in the estimate of future traffic demand required for the pilot public transport shuttle bus loops for Package 2 of the Project. II.

METHODOLOGY

2. Traffic count survey were conducted along 6 road sections in the study area in order to determine indicative daily traffic flows into and out of the core city area, and along two of the side streets where traffic management improvements are contemplated. The locations of the surveys are indicated on Figure A9.1. During the PPTA more detailed traffic surveys will need to be carried out, probably a 3 or 7 day count, and probably covering about 10 locations. 3. Traffic volume by direction and each type of vehicle was manually and separately counted, then recorded for every 15 m inute interval for 12 h ours from 06:00 to 18:00. Counts were made simultaneously at all six locations on 28 October 2010. Vehicle classifications were as follows: bicycle, motorcycle/motorbike, tuk-tuk, sonteo, car/taxi, pick-up, bus, light truck (twoaxle), heavy truck (>two axle), truck-trailer, and other.

Figure A9.1. Traffic Survey Locations

103


Appendix 9

III.

TRAFFIC RESULTS

4. Traffic count stations at locations 1 to 4 were along major arterial streets leading into and out of the core area of the city. A s expected, counts along these major streets showed high traffic volumes. The highest traffic volume was at location 1, along Khounboulom road, totaling about 36,000 vehicles for the 12-hour count. The volumes for all locations are listed in Table A 9.1: Table A9.1 Summary of Traffic Survey Results Daily Traffic Volume(veh/day) – 12 hour count Road Name Including motorcycle

Excluding motorcycle

36,017 18,537 20,306 19,830 1,207 1,719

15,663 9,543 10,762 8,680 589 881

1. Khounboulom 2. Samsenthai 3. Setthathirath 4. Fa Ngum 5. Nokeokhoummane 6. Fancois Ngin

IV.

TRAFFIC ANALYSIS

5. The analysis of the traffic survey on the study areas indicates that trips by motorcycle had the highest share of 53 %, while private car trips (car/taxi and pick-up) were 30%. Trips by public transport (tuk-tuk, sonteo, Starex and bus) were 11%; trips by trucks and other commercial vehicles were 5%; and trips by non-motorized transport only accounted for about 1% of the total. Modal share are shown in Figure A9.2. 6. Figure A9.3. shows the total traffic for all six locations, on an hour by hour basis. The figure shows that there is very high peak in the morning in the traffic flow direction towards the center core area (7:30 to 8:30), and in the opposite direction in the evening peak hour (16:30 to 17:30). The two peak flow periods are relatively short, as compared with larger Asian capital cities.

104


Appendix 9

Figure A9.2. Mode Share

5%

1%

Non-Motorized Vehicle Motorcycle

30%

Public Transport Private Car Truck/Commercial 53% 11%

Vehicles/15 min

Figure A9.3. 15min. Traffic Volume (total traffic at all 6 survey locations)

2000 1800

To city center

1600

From city center

1400 1200 1000 800 600 400 200 0 6:00

6:30

7:00

7:30

8:00

8:30

9:00

9:30

10:00 10:30 11:00 11:30 12:00 12:30 13:00 13:30 14:00 14:30 15:00 15:30 16:00 16:30 17:00 17:30 18:00

105

Tim e


Appendix 9

Table A9.2 Summary of Traffic Results Survey Location Vehicle Types 2.Samsenthai

3.Setthathirath

4.Fa Ngum

5.Nokeokhoummane

6.Fancois Ngin

Total

1.Khounboulom 207

103

93

137

34

113

687

Motorcycle

20,354

8,994

9,544

11,150

618

838

51,498

Tuk-Tuk

1,992

114

253

1,169

47

75

3,650

Sonteo

194

3

226

118

19

23

583

Car/Taxi

4,906

2,868

3,926

2,391

219

275

14,585

Pick Up

4,706

3,903

3,798

2,241

155

207

15,010

Medium Bus

1,944

1,430

1,615

1,106

72

118

6,285

52

50

71

4

0

2

179

1,590

1,033

727

1,215

18

39

4,622

Bicycle

Large Bus Light Truck (2-Axle Truck) Heavy Truck (>2Axle Truck)

54

31

44

254

1

0

384

Trailer

1

0

0

42

0

0

43

Other

17

8

9

3

24

29

90

Total

36,017

18,537

20,306

19,830

1,207

1,719

97,616

106


Appendix 10 ECONOMIC AND FINANCIAL ASSESSMENTS 1. A prefeasibility assessment was made of the potential economic viability of the VSUT pilot project, described elsewhere in this report. Financial viability was assessed for the bus public transport subproject 1. Economic values used in the assessment are at border equivalent prices for tradable goods, and for non-tradable goods at domestic prices after removing the effects of taxes and subsidies. Economic benefits were quantified by comparison of project area conditions with and without the project; financial benefits were measured by estimating revenues. The main viability indicators estimated for the present assessments are economic and financial internal rates of returns (EIRR and FIRR). All values in the viability assessments are expressed in 2010 constant prices. In addition, an initial assessment of financial sustainability of the Pilot EST Agency (PEA) was made by conducting a financial statements analysis of the pilot entity based on pre-feasibility projections. A.

Project Cost

2. The project cost is based on prefeasibility engineering estimates and exclude financial charges during construction. Project economic costs were derived from financial construction, equipment, administration and other, and land and resettlement costs for capital cost, and recurrent financial operation and maintenance cost for recurrent O&M cost. The capital costs include replacement of all equipment including buses after an assumed 10 year life cycle plus additions to the bus fleet to serve an expanded patronage. Economic costs exclude taxes, duties, price contingencies, but include physical contingencies. Administration and other cost covers consultancy services and related expenses for implementation support, awareness and community participation and institutional capacity development. Table A10.1 summarizes the project economic capital costs. Table A10.1 Project Economic Capital Cost ($ million) Year

Construction

Equipment

2012 2013 2014 2015-25

0.000 2.938 5.876 0.000

0.000 1.421 2.842 8.437

Source: TA Consultants

Administration and other 0.456 1.824 1.824 0.000

Land and resettlement 0.000 1.640 3.279 0.000

Total 0.456 7.823 13.821 8.437

3. The O&M cost includes an allowance for recurrent spending on awareness and community participation during the VSUT project operation. B.

Economic and Financial Benefits 1. Transport Demand Assessment

4. Traffic and parking surveys were conducted to establish baseline transport demand conditions the project area. This information provided a base for quantifying the expected project area vehicle and passenger demand for motorized trips, with total and average trip times 1

A financial viability assessment was not attempted for parking, the second potential revenue earning subproject, but was left to a future feasibility study project preparation. A clear determination of the parking charge policy involves complex considerations linked to the traffic management and public transport subcomponents of VSUTP. T he necessary policy analysis could not be attempted at this pre-feasibility stage.

107


Appendix 10 and distances by transport mode, under two scenarios: (i) with the project implemented, and (ii) if the present trends are allowed to persist (‘without the project’)2. The estimates for the scenario without the project drew on the JICA Transport Masterplan study3. T able A10.2 summarizes the estimated demand for passenger trips. Table A10.2 Daily Passenger Trips (2015-2025) Scenario WO W

Year 2015 2025 2015 2025

W=with project; WO=without project Source: TA Consultants

Car 51,250 96,051 44,405 66,127

(Unit: Trip) Motorcycle 64,777 85,311 51,430 65,176

Bus 0 0 19,883 34,463

Total 116,027 181,362 115,718 165,765

2. Economic Benefits 5. For an analysis of the economic return on investment, using the transport demand assessment of the average daily passenger trip time and distance, the project benefits were identified with cost savings in relation to the travel time and vehicle operating cost (VOC) that travelers demonstrate a willingness to incur without the project. These user benefits were valued at a derived unit value of travel time and a unit VOC. 6. The unit value of travel time was based on survey data from a r egional urban transport study, after adjusting for per capita GDP differential. Details appear in Table A10.3. The unit Table A10.3 Value of Passenger Time per Hour ($) Household Category Car-owning Motorcycle-owning

2015 1.40 0.88

2025 1.97 1.29

Source: based on TA 7443 VIE: Ho Chi Minh City MRT Line 2 Project, 2010, consultants report

VOC was based on a standard model in current use at an international transport authority for project economic cost-benefit appraisals 4. Fuel prices were independently estimated. The estimate of the economic price of fuel is based on applying standard refining margins to the economic price of crude oil to obtain petrol and diesel prices. T he price assumed for the analysis is $90 p er barrel in constant 2007 prices. Table A10.4 summarizes the derived travel costs with and without the project.

Table A10.4 User Cost per Passenger Trip (2015-2025) ($) 2

The transport demand assessment is a supplementary appendix available on request. JICA. 2008. Masterplan on Comprehensive Urban Transport in Vientiane. 4 California Transport Department. See Booze Allen Hamilton, Hagler Bailly, Parsons Brinkerhoff, 1999, California Life-Cycle Benefit/Cost Analysis Model, Technical Supplement to Users Guide. 3

108


Appendix 10 Description 2015 WO Time cost VOC Total 2015 W Time cost VOC Total 2025 WO Time cost VOC Total 2025 W Time cost VOC Total

Car 0.259 0.391 0.650 0.222 0.338 0.561 0.550 0.545 1.095 0.372 0.424 0.796

Motorcycle 0.128 0.201 0.329 0.104 0.174 0.278 0.303 0.280 0.582 0.186 0.217 0.404

VO=vehicle operating cost; W=with project; WO=without project Source: TA Consultants

Bus 0.000 0.000 0.000 0.189 0.093 0.282 0.000 0.000 0.000 0.322 0.086 0.408

All Modes 0.186 0.288 0.474 0.164 0.223 0.387 0.434 0.420 0.854 0.289 0.272 0.561

3. Financial Benefits 7. Revenues of the bus loops service were estimated using bus patronage forecast prepared under the transport demand assessment. At KN2,500 per trip the selected average fare is consistent with the stated preference in a willingness to pay survey conducted under this TA. C.

Economic and Financial Analysis 1. Economic Analysis

8. The benefits included in the economic analysis comprise the user benefits described in paragraph 5. The costs are those described in paragraphs 2-3. At 15.3%, the EIRR obtained in the analysis is above the 12% minimum acceptable economic yield for an ADB project. Details of the EIRR calculation appear as Annex A to this appendix. 2. Financial Analysis Table A10.6 Project Weighted Average Cost of Capital (WACC) ADB Grant Principal amount ($ million) Weight Nominal cost (relending rate) Tax rate Tax adjusted nominal rate Inflation rate Real cost Weighted component of WACC 3.

Source: TA Consultants

10.000 38% 1.5% 40% 0.9% 1.5% 0.9% 0.3%

Co-financiers 12.200 46% 6.7% 40% 4.0% 1.5% 4.1% 1.9%

Government Funds 4.300 16% 8.0% 40% 4.8% 5.5% 5.1% 0.8%

Total 26.500 100%

3.0%

9. Financial analysis was conducted for the bus public transport subproject. Based on the KN2,500 average fare, the subproject is likely to: (i) have little difficulty recovering its cost; (ii) yield and FIRR of slightly above 8.5% if 50% of the traffic management capital cost is added to the bus subproject costs; and (iii) still yield an FIRR of 3.5% if all of the traffic management capital cost is added. Details of the FIRR analysis appear in Annex B to this appendix. The 109


Appendix 10 3.5% FIRR is above the expected average weighted cost of capital (WACC) of 3% for the whole project, calculated on the likely financing costs, confirming a positive contribution to overall project financial viability. Table A10.6 shows details of the WACC. D.

Financial Sustainability of the Pilot EST Agency 1. Assumptions for Financial Projections

10. Financial projections were prepared for the PEA as the responsible agency for implementation and operation and maintenance of the pilot VSUT project. The projections cover a total period of 20 years (2012-2031). Table A10.7 summarizes the proposed financial arrangements for PEA’s implementation and operation of the pilot VSUT project. Table A10.7 Proposed PEA Project Financial Arrangements Item 1. Revenue

Arrangement EST Tax, as described in Appendix 4

2. Financing

PEA’s implementation of the project is financed by Government onlending of the total amount of the grant (ADB), loans (co-financiers), and counterpart funds on the following principal terms: (i) to be repaid in 18 years with a 6-year grace period; (ii) at interest rates based on 0%(ADB grant), 5.2% (co-financiers loans) and 6.5% (counterpart funds) after applying a 1.5% administration charge. Other project capital costs are PEA equity funded.

3.Government subsidy

The bus subproject fare collection is paid into a reserve account to be used by the Government for providing a subsidy to PEA as needed.

Source: TA Consultants

11. The Government subsidy centralizes the use of the bus farebox proceeds to supplement the PEA’s funding of the project, and serves to support an integrated management of the project while promoting an efficient use of the funds. In particular, it prevents capture of the bus service collection for a purpose not subject to PEA prioritization and expenditure planning. 2. Financial Statements Analysis Results 12. Analysis of PEA’s projected financial statements indicates positive prospects of cost recovery. Specifically, it supports a reasonable expectation that PEA will be able to recover its capital and recurrent costs through the EST tax revenue supplemented by the proceeds of the bus service fare collection proceeds. The Government’s subloan to finance the initial project investment remains at an acceptable risk through the loan repayment cycle, with a minimum debt service coverage of 1.2 times, a debt-equity ratio not exceeding 2.5 times, and full repayment of the loan as scheduled. The analysis also indicates that the capital cost in particular to renew equipment including buses can be managed within the proposed financial arrangements. The project financial statements of PEA appear in Annex C to this appendix.

110


Appendix 10 Annex A Analysis of Economic Return on Investment ($ million) Year

2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025

Investment cost 0.46 7.82 13.82 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Costs Other capital cost 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.28 0.00 0.00 0.00 4.56 1.60

O&M=operation and maintenance Source: TA Consultants

O&M cost

Total costs

0.00 0.00 0.00 1.78 1.78 1.78 1.78 1.78 2.17 2.17 2.17 2.17 2.17 2.44

0.46 7.82 13.82 1.78 1.78 1.78 1.78 1.78 4.45 2.17 2.17 2.17 6.73 4.04

111

Benefits User 0.00 0.00 0.00 3.48 4.07 4.77 5.58 6.53 7.63 8.93 10.45 12.23 14.31 16.74

Total benefits

0.00 0.00 0.00 3.48 4.07 4.77 5.58 6.53 7.63 8.93 10.45 12.23 14.31 16.74 EIRR

Net benefits stream -0.46 -7.82 -13.82 1.70 2.29 2.99 3.80 4.74 3.18 6.76 8.28 10.06 7.58 12.70 15.3%


Appendix 10 Annex B Analysis of Financial Internal Rate of Return for Bus Loops Subproject with 0%, 50% and 100% of Traffic Management Capital Cost 0% Year 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031

50%

Project Cost O&M Cost Revenues 0.000 2.158 4.317 0.000 0.000 0.000 0.000 0.000 2.281 0.000 0.000 0.000 3.650 1.597 0.000 0.000 0.000 0.000 2.281 0.000

0.000 0.000 0.000 0.621 0.621 0.621 0.621 0.621 1.010 1.010 1.010 1.010 1.010 1.282 1.282 1.282 1.282 1.282 1.282 1.282

0.000 0.000 0.000 1.450 1.639 1.846 2.435 2.570 2.713 2.864 3.022 3.190 3.367 3.554 3.751 3.959 4.179 4.411 4.656 4.914

Net Inflow s 0.000 (2.158) (4.317) 0.828 1.018 1.224 1.814 1.949 (0.578) 1.854 2.013 2.180 (1.293) 0.676 2.470 2.678 2.897 3.129 1.093 3.632

Year 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031

100%

Project Cost O&M Cost Revenues 0.000 4.155 7.756 0.000 0.000 0.000 0.000 0.000 2.281 0.000 0.000 0.000 4.105 1.597 0.000 0.000 0.000 0.000 2.281 0.000

0.000 0.000 0.000 0.621 0.621 0.621 0.621 0.621 1.010 1.010 1.010 1.010 1.010 1.282 1.282 1.282 1.282 1.282 1.282 1.282

0.000 0.000 0.000 1.450 1.639 1.846 2.435 2.570 2.713 2.864 3.022 3.190 3.367 3.554 3.751 3.959 4.179 4.411 4.656 4.914

FIRR 17.6% FIRR NPV at 3% discount rate 12.53 NPV at 3% discount rate FIRR = financial internal rate of return; NPV = net present value;O&M = Operation and Maintenance

Source: TA Consultants

112

Net Inflow s 0.000 (4.155) (7.756) 0.828 1.018 1.224 1.814 1.949 (0.578) 1.854 2.013 2.180 (1.747) 0.676 2.470 2.678 2.897 3.129 1.093 3.632 8.6% 7.20

Year 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031

Project Cost O&M Cost Revenues

Net Inflow s

0.000 6.152 12.305 0.000 0.000 0.000 0.000 0.000 2.281 0.000 0.000 0.000 4.559 1.597 0.000 0.000 0.000 0.000 2.281 0.000

0.000 (6.152) (12.305) 0.828 1.018 1.224 1.814 1.949 (0.578) 1.854 2.013 2.180 (2.202) 0.676 2.470 2.678 2.897 3.129 1.093 3.632

0.000 0.000 0.000 0.621 0.621 0.621 0.621 0.621 1.010 1.010 1.010 1.010 1.010 1.282 1.282 1.282 1.282 1.282 1.282 1.282

0.000 0.000 0.000 1.450 1.639 1.846 2.435 2.570 2.713 2.864 3.022 3.190 3.367 3.554 3.751 3.959 4.179 4.411 4.656 4.914

FIRR NPV at 3% discount rate

3.5% 0.85


Appendix 10 Annex B PEA Projected Financial Statements (2012 – 2021) ($ million at current prices) ITEM A. Income Statement Revenue (from EST tax) O&M costs Traffic management O&M cost Parking O&M cost Bus O&M cost PEA administrative overheads Operating profit Depreciation Interest (sub-loan) Net operating profit / (loss) Central governmental subsidy B. Cashflow Statement initial Operating income Depreciation Movement in working capital Net cashflow from operation Equity 0 Central government grant 0 Central government sub-loan 27.2 Investment cost 27.2 A. VSUT infrastructure and services Traffic management 2.0 Parking 12.3 Bus loops 7.7 B. Implementation support and capacity building Sub-loan principal repayment Central governmental subsidy Net Cashflow Accumulated cashflow

31.3 Total

0 0 27.2 49.4 3.5 12.6 28.1 27.2 31.3

2012

2013

2014

2015

2016

2017

2018

2019

2020

2021

0.000

0.000

0.000

0.000 0.000 0.000 0.000 0.000

4.345 2.273 0.122 0.757 0.793 0.601 2.072 1.432 1.348 (0.708) 1.004

4.562 2.387 0.128 0.795 0.833 0.631 2.175 1.432 1.348 (0.605) 1.004

4.790 2.506 0.135 0.835 0.874 0.662 2.284 1.432 1.348 (0.496) 1.004

5.030 2.631 0.141 0.876 0.918 0.695 2.398 1.432 1.348 (0.382) 2.284

5.281 2.763 0.149 0.920 0.964 0.730 2.518 1.432 1.263 (0.177) 2.164

5.545 3.534 0.156 0.966 1.645 0.767 2.012 1.432 1.174 (0.594) 2.670

5.767 3.710 0.164 1.015 1.727 0.805 2.057 2.062 1.081 (1.086) 2.625

0.000 0.000 0.000 0.000 0.000

0.000 0.000 0.000 0.000 0.000

0.000 0.000 0.000 0.000 0.000 0.000 0.538 0.538 0.000 0.000 0.000 0.000 0.538 0.000 0.000 0.000 0.000

0.000 0.000 0.000 0.000 0.000 0.000 9.381 9.381 7.122 0.643 3.981 2.499 2.259 0.000 0.000 0.000 0.000

0.000 0.000 0.000 0.000 0.000 0.000 17.328 17.328 14.957 1.350 8.360 5.247 2.372 0.000 0.000 0.000 0.000

(0.708) 1.432 0.000 0.723 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 1.004 1.727 1.727

(0.605) 1.432 0.000 0.827

(0.496) 1.432 0.000 0.936

(0.382) 1.432 0.000 1.050

(0.177) 1.432 0.000 1.255

(0.594) 1.432 0.000 0.837

(1.086) 2.062 0.000 0.976

0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 1.004 1.831 3.558

0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 1.004 1.940 5.498

0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 1.717 2.284 1.617 7.115

0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 1.802 2.164 1.617 8.731

0.000 0.000 3.716 3.716 0.000 0.000 3.716 0.000 1.891 2.670 (2.099) 6.632

0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 1.985 2.625 1.617 8.249

113


Appendix 10 Annex B PEA Projected Financial Statements Cont’d (2012 – 2021) ($ million at current prices) ITEM C. Balance Sheet Cash and short-term investments Fixed assets Accumulated depreciation Net fixed assets Total Assets Central government sub-loan Central government grant Equity Total Liabilities and Equity

2012

2013

2014

2015

2016

2017

2018

2019

2020

2021

0.000 0.538 0.000 0.538 0.538 0.538 0.000 0.000 0.538 0.0

0.000 9.919 0.000 9.919 9.919 9.919 0.000 0.000 9.919 0.0

0.000 27.247 0.000 27.247 27.247 27.247 0.000 0.000 27.247 0.0

1.727 27.247 1.432 25.815 27.542 27.247 0.000 0.296 27.542 0.0 2.28 92.2 0.5 1.004 1.450 1.348

3.558 27.247 2.863 24.383 27.941 27.247 0.000 0.695 27.941 0.0 2.36 39.2 0.5 1.004 1.639 1.348

5.498 27.247 4.295 22.952 28.449 27.247 0.000 1.203 28.449 0.0 2.44 22.7 0.5 1.004 1.846 1.348

7.115 27.247 5.727 21.520 28.635 25.530 0.000 3.105 28.635 0.0 1.53 8.2 0.5 2.284 2.435 3.065

8.731 27.247 7.159 20.088 28.820 23.728 0.000 5.092 28.820 0.0 1.53 4.7 0.5 2.164 2.570 3.065

6.632 30.963 8.590 22.372 29.005 21.837 0.000 7.168 29.005 0.0 1.53 3.0 0.6 2.670 2.713 3.065

8.249 30.963 10.653 20.310 28.559 19.852 0.000 8.707 28.559 0.0 1.53 2.3 0.6 2.625 2.864 3.065

DSCR (Debt Service Coverage Ratio)1 2 DER (Debt to Equity ratio) 3 Working ratio Required subsidy 31.3 0.000 0.000 Bus fare revenue 0.000 0.000 Debt service amount 0.000 0.000 Source: Asian Development Bank estimates. 1 DSCR: Debt Service Coverage Ratio = (operating profit + subsidy) / debt service 2 DER: Debt to Equity ratio = Debt / Equity (equity includes central governmental grant) 3 Working ratio = O&M cost / Revenue (revenue not include subsidy)

Source: TA Consultants

114

0.000 0.000 0.000


Appendix 10 Annex C PEA Projected Financial Statements Cont’d (2022 – 2031) ($ million at current prices) ITEM A. Income Statement Revenue (from EST tax) O&M costs Traffic management O&M cost Parking O&M cost Bus O&M cost PEA administrative overheads Operating profit Depreciation Interest (sub-loan) Net operating profit / (loss) Central governmental subsidy B. Cashflow Statement Operating income Depreciation Movement in working capital Net cashflow from operation Equity Central government grant Central government sub-loan Investment cost A. VSUT infrastructure and services Traffic management Parking Bus loops B. Implementation support and capacity building Sub-loan principal repayment Central governmental subsidy Net Cashflow Accumulated cashflow

2022

2023

2024

2025

2026

2027

2028

2029

2030

2031

5.998 3.896 0.172 1.065 1.813 0.845 2.102 2.062 0.982 (0.943) 2.580

6.238 4.091 0.181 1.119 1.904 0.888 2.147 2.062 0.879 (0.795) 2.535

6.487 4.295 0.190 1.175 1.999 0.932 2.192 2.062 0.771 (0.642) 2.490

6.747 5.075 0.199 1.233 2.664 0.979 1.672 1.851 0.658 (0.837) 3.010

7.017 5.329 0.209 1.295 2.797 1.027 1.688 2.262 0.539 (1.112) 1.991

7.297 5.595 0.220 1.360 2.937 1.079 1.702 2.262 0.413 (0.973) 1.976

7.589 5.875 0.230 1.428 3.084 1.133 1.714 2.262 0.282 (0.830) 1.964

7.893 6.169 0.242 1.499 3.238 1.189 1.724 2.262 0.145 (0.682) 1.954

8.208 6.477 0.254 1.574 3.400 1.249 1.731 2.262 0.000 (0.530) 0.000

8.537 6.801 0.267 1.653 3.570 1.311 1.736 2.718 0.000 (0.982) 0.000

(0.943) 2.062 0.000 1.120

(0.795) 2.062 0.000 1.268

(0.642) 2.062 0.000 1.421

(0.837) 1.851 0.000 1.014

(1.112) 2.262 0.000 1.149

(0.973) 2.262 0.000 1.289

(0.830) 2.262 0.000 1.432

(0.682) 2.262 0.000 1.579

(0.530) 2.262 0.000 1.731

(0.982) 2.718 0.000 1.736

0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 2.083 2.580 1.617 9.866

0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 2.186 2.535 1.617 11.483

0.000 0.000 9.027 9.027 1.523 0.277 7.227 0.000 2.294 2.490 (7.410) 4.073

0.000 0.000 3.320 3.320 0.000 0.000 3.320 0.000 2.408 3.010 (1.703) 2.370

0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 2.527 1.991 0.613 2.983

0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 2.652 1.976 0.613 3.596

0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 2.783 1.964 0.613 4.209

0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 2.921 1.954 0.613 4.823

0.000 0.000 6.053 6.053 0.000 0.000 6.053 0.000 0.000 0.000 (4.322) 0.501

0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 1.736 2.237

115


Appendix 10 Annex C PEA Projected Financial Statements Cont’d (2022 – 2031) ($ million at current prices) C. Balance Sheet Cash and short-term investments Fixed assets Accumulated depreciation Net fixed assets Total Assets Central government sub-loan Central government grant Equity Total Liabilities and Equity

2022

2023

2024

2025

2026

2027

2028

2029

2030

2031

9.866 30.963 12.715 18.247 28.114 17.770 0.000 10.344 28.114 0.0 1.53 1.7 0.6 2.580 3.022 3.065

11.483 30.963 14.778 16.185 27.668 15.584 0.000 12.084 27.668 0.0 1.53 1.3 0.7 2.535 3.190 3.065

4.073 39.989 16.840 23.149 27.222 13.290 0.000 13.933 27.222 0.0 1.53 1.0 0.7 2.490 3.367 3.065

2.370 43.309 18.691 24.618 26.988 10.882 0.000 16.106 26.988 0.0 1.53 0.7 0.8 3.010 3.554 3.065

2.983 43.309 20.953 22.356 25.340 8.355 0.000 16.984 25.340 0.0 1.20 0.5 0.8 1.991 3.751 3.065

3.596 43.309 23.214 20.095 23.691 5.704 0.000 17.988 23.691 0.0 1.20 0.3 0.8 1.976 3.959 3.065

4.209 43.309 25.476 17.833 22.043 2.921 0.000 19.122 22.043 0.0 1.20 0.2 0.8 1.964 4.179 3.065

4.823 43.309 27.737 15.572 20.394 0.000 0.000 20.394 20.394 0.0 1.20 0.0 0.8 1.954 4.411 3.065

0.501 49.362 29.999 19.363 19.864 0.000 0.000 19.864 19.864 0.0

2.237 49.362 32.716 16.645 18.882 0.000 0.000 18.882 18.882 0.0

0.0 0.8 0.000 4.656 0.000

0.0 0.8 0.000 4.914 0.000

DSCR (Debt Service Coverage Ratio)1 DER (Debt to Equity ratio)2 Working ratio 3 Required subsidy 31.3 Bus fare revenue Debt service amount Source: Asian Development Bank estimates. 1 DSCR: Debt Service Coverage Ratio = (operating profit + subsidy) / debt service 2 DER: Debt to Equity ratio = Debt / Equity (equity includes central governmental grant) 3 Working ratio = O&M cost / Revenue (revenue not include subsidy)

Source: TA Consultants

116


Appendix 11

RESETTLEMENT, GENDER AND OTHER SAFEGUARDS ISSUES

I.

INTRODUCTION

1. In accordance with ADB’s guidelines for integration of social analysis in the pre-design and design phases of project implementation a s ocial analysis was carried out to identify opportunities, constraints, and risks for poor and marginalized groups related to the project; to establish a participatory process for the design of the project; and to prepare design measures to achieve social development outcomes and avoid or mitigate any social risks during implementation. 2. This report is a preliminary assessment of potential benefits and adverse impacts of various project components on women, the poor, elderly, disable and other socially vulnerable groups undertaken as part of the Vientiane Sustainable Urban Transport Project under the Asian City Transport – Promoting Sustainable Urban Transport in Asia Project. The overall aim of this assessment is to assess the potential impacts of the proposed sub-projects and to propose interventions for next steps. This assessment is intended to establish a base of information on social conditions and resettlement issues that will help ensure that future interventions respond more effectively to the needs of the local people particularly the poor and marginalized groups. 3. This report is structured into four main sections with the introduction in Section I; Section II presents a brief summary of preliminary findings; Section III describes problems identified during the field surveys with regard to traffic, parking and public transport issues, and their suggested improvements; and Section IV addresses gender and resettlement issues of the proposed subprojects. Additional survey and other supporting information are contained in the annexes at the end of this appendix. II. SUMMARY OF PRELIMINARY FINDINGS

4. The major transport issues raised by both women and men are road congestion, rulesbehavior, accidents and disputes amongst road users. The women are more concerned about the lack of parking area while the men prioritize traffic jam as their first concern. The primary suggestion to improve public transport in the core area is to provide better public bus service. Bus transport services should include: (i) new buses, with air conditioning; (ii) drivers should be experienced and well trained; (iii) service should be regular, with a maximum service interval of 15 minutes; (iv) bus timetable should be posed at each bus stop, both Lao and English; and (iv) bus tickets should be available at shops and mini-marts around town. The majority of male and female roads users are willing to use such improved bus services at a fare rate of between 3,000 to 5,000 kips per trip. 5. The Project can be classified as a project with some gender benefits amongst the 4 ADB’s gender mainstreaming categories since it is unlikely to provide direct and substantial benefits to women. Based on ADB’s categories on resettlement Sub-project 1 on construction of parking lots can be classified as category A because it may have significant resettlement impact if the proposed construction of parking lots will be built in the water park compound or private lands so a full resettlement plan is required. Resettlement impact of sub-projects 4, 5, 6 and 11 is non-significant and can be in category B, thus a short resettlement plan is required. Sub-projects 2, 3, 7, 8, 9, 10 and 12 have no resettlement impact so no resettlement report is required. 117


Appendix 11 6. During the PPTA a gender action plan and resettlement framework should be developed to provide guidelines for the development of an (implementation phase) resettlement plan for subproject 1 a nd sub-projects 4, 5, 6 and 11. Attention to women will need to be included in the resettlement plan such as compensation payments to both men and women, joint-ownership of replacement land/housing, and restoration of livelihoods initiatives for women.

III. URBAN TRANSPORT ISSUES AND PUBLIC SUGGESTIONS FOR IMPROVEMET 7 ADB’s Staff Guide on Consultation and Participation (2006) recommends the preparation of a Consultation and Participation Plan (C&P Plan) for most projects. Different stakeholders consulted during the social impacts assessment included villages authorities, male and female residents, business operators, street vendors and other road users including pedestrians, motorbikes and cars users. Consultation methods used were 6 group discussions with the total participants of 92 of whom 47 were the women, and 120 individual interviews of which 65 interviews were carried out with the women. Selected villages and streets where consultations were undertaken are summarized in the Table A12.1. Guiding questions group discussions and questionnaires for individual interviews are in Annexes 1 and 2 of this appendix. Table A12.1: List of Surveyed Villages and Streets No.

Village

Street

Participants in Group Discussions

District

Total

Women

1. Watchanh

14

7

2. Xiengngun

15

8

3. Haysok

19

9

Chanthabouly

4. Anou

16

12

Chanthabouly

5. Simuang

10

5

Sisattanak

6. Kaongot

18

6

Sisattanak

Chanthabouly Nokeokhouman: 5 interviews of whom 3 were women

Chanthabouly

7. The three most frequently mentioned urban transport issues expressed by the different focus groups were related to (i) traffic congestion; (ii) rules-behavior of drivers and pedestrians, and; (iii) accidents and disputes amongst road users. 8. The number of vehicles has increased significantly in Vientiane capital but the road networks as well as public transport services have not been improved to cope with the traffic growth in 118


Appendix 11 Vientiane Capital and as a result it has created road congestions particularly during rush hours along the roads to business centers, schools and government offices. 9. Individual interviews with road users in downtown mentioned that there is insufficient parking space for road users so they are force to park in other available (illegal) spots that can block the entrance to private businesses and residence. Figure A12.1 shows that 83% of car drivers and motorbike riders do not have parking area at their work places. Figure A12.1: Availability of Parking Space in Downtown Vientiane

A.

Specific Traffic Congestion and Parking Problems

10. Residents living downtown often cannot park their own cars in front of their houses; and even those residents who have their own off-street parking spaces are often prevented from entering or leaving these spaces because of illegally parked vehicles blocking the driveway/entrance. Tuk-Tuks are permitted to park around the fountain (Namphou) in Xiengngun Village; and they have created line of sight problems for drivers making turns from the side streets. Big trucks of wholesale businesses often deliver the merchandise during day time and block the road. The residents complained that employees of private companies and government workers park their cars along Samsenthai Road for extended periods (often the entire day) in front of private residences in Anou village. 11. Road users’ lack of respect of traffic rules as well as road signs are also one of the main issues expressed during group discussions and individual interviews. Alternate odd and even parking-date signs are not working well, and there is still regular parallel parking on both sides of the roads regardless of the signs or date. Sometimes the cars are double and triple parked and block the entire roadway. The main reason mentioned for ignoring the rules are poor (or complete lack) of law enforcement. Sometimes traffic rule breakers are foreigners who cannot read the road signs which are written only in Lao; very little signage is in English. 12. The lack of respect to traffic rules, lack of parking spaces and unregulated parking have cause many disputes amongst the road users as well as between roads users and residents living along the road. It has also increased traffic accidents in town. Lack of law enforcement on Tuk-Tuk drivers often creates social problems like fighting with the foreigners (passengers) and also fighting among Tuk-Tuk drivers themselves.

B.

Suggested Solutions from Consultations with Different Road Users

119


Appendix 11 13. Both consultations from focus group discussions and individual interviews have suggested the need for (i) improvement of parking in town, (ii) the improvement of bus management services and (iii) better law enforcement are required to solve the growing transport problems in Vientiane Capital. In addition, the group discussions also suggested the improvement of the environment along the road site such as maintenance of side drains and solving problem of pollutions along the roads. Figure A12.2 reveals that the majority of both male and female road users prioritize improvement of parking lots, followed by bus service management and law enforcement. Figure A12.2: Suggested Solutions from Individual Interviews

14. The suggestions of the residents for solving the problems of parking along the roads in town are: (i) the construction of public parking lots, and the need to promote, build and operate private parking lots (which could be underground or multi storage buildings), (ii) use temple grounds for parking, (iii) the requirement that each office must have the own parking lot, (iv) the need to find more suitable places for Tuk-Tuk parking, (v) the suggestion to move offices particularly government offices from the downtown area, and (vi) a restriction on allowing employees to drive their private cars into the downtown area. 15. Suggested improvement of transport services includes increase public transport, buses must be new with air condition and good driver, the service must be regular with at least 15 minutes interval, bus timetable must be put at the bus stop and the signed board must be in both Lao and English, and the bus tickets must be available at the shops in town. Figures 3 and 4 below show that the majority male and female roads users are willing to use the improved bus services and most of them stated that they can afford the fees of between 3,000 to 5,000 Kip per trip. Figure A12.3: Willingness to use improved bus service in town

120


Appendix 11 Figure A12.4: Affordability for improved bus service in town

16. Equal law enforcement must be applied to all offenders of traffic rules and regulations; and traffic police should make more effort to control the rules and regulations. Many suggested that more one way streets should be established, and the time for the delivery of good to the shops in downtown should be regulated. 17. The foreign tourists have made additional suggestions related to safety and public awareness that include policemen in intersections to manage the traffic; and that policemen should help visitors, and that Tuk-Tuk drivers and motorbike riders be trained in road safety.

IV. GENDER AND RESETTLEMENT ISSUES OF THE PROJECT 18. The Project can be classified as Category 3, with some gender benefits amongst the four ADB’s gender mainstreaming categories since it is unlikely to provide direct and substantial benefits to women, but significant efforts has been made during this study to identify potential positive and negative impacts on women. In addition where resettlement is involved, attention to women will be included in the resettlement plan such as compensation payments to men and women, jointownership of replacement land/housing, restoration of livelihoods initiatives for women. 19. This gender impact analysis is based on village consultations and the individual interviews with women that represent 51% and 54% respectively of the total participants. Figures 5 a nd 6 show the concerns identified by male and female road users during the individual interviews.

121


Appendix 11

Figure A12.5: Urban Transport Problems as Stated by Men

Figure A12.6: Urban Transport Problems as Stated by Women

A.

Urban Transport Issues and Concerns

20. Most men use cars while most women ride motorbikes or bicycles thus the men are more affected by road congestion than the women who are more concerned about the lack of parking lots as shown in Figures A12.5 and A12.6. 21. Most shop owners and restaurant operators are the women so they are more concerned about lack of parking lots that their businesses. In addition, cars parked in front of their shops also hide their shops from attracting customers and sometimes it has created disputes between shop owners and road users who park the cars in front of the shops or residential houses. 22. Men are more concerned about security along the road at night than the women, it may indicate that more men use the road at night than the women, than the fact the men are actually more concerned about safety than women. 122


Appendix 11 23. Most street vendors are the women who carry fruits or vegetable to sell to residents or office workers. Some women also set up stalls to sell cooked food for office workers.

Table A12.2: Potential Benefits and Adverse Impacts Sub-project

Benefits

Sub-project 1

Sub-projects 2, 3, 12,

Sub-projects 4, 5

Sub-projects 6 & 11

Sub-projects 7,8,9 &b 10

Adverse Impacts

Reduces road congestion in town and thus save time for both men and women that can be spent on increased productivity and income

Reduce emission of carbon dioxide

Reduces disputes related to parking

Improve parking problems and thus reduce road congestion and blocking of access to houses and shops

Improve walking path

Reduce emission of carbon dioxide

Provide convenience for pedestrians to walk along the roads

Revive businesses along the road and thus creates more income

Resolve disputes in connection with parking

Maintenance of streets will reduce vehicle operation costs

Improve walking path and thus reduce risk of accident for pedestrians whom presently are force to walk on the road

Increase road safety and thus reduce traffic accidents, save human as well as financial resources for care of injured persons that are mainly the responsibility of the women.

123

May involve involuntary resettlement

Creates additional expenses for parking and bus tickets

Residents along the road will have additional expenses for parking

Residents along the roads may not agree to park their cars elsewhere.

Width constrictions, surface treatments and landscaping along the proposed streets will lead to disruption of existing residents and businesses.

Residents along the road will have additional expenses for parking

During the construction some shop owners and street vendors may lose their income

None


Appendix 11 24. ADB’s Screening questions for resettlement categorization have been applied to categorize each sub-project and the resettlement planning requirements. Table 2 reveals that sub-project 1 on construction of parking lots can be classified as category A because it may have significant resettlement impact so a full resettlement plan is required; resettlement impact of sub-projects 4, 5, 6 and 11 is non-significant and can be in category B thus a short resettlement plan is required; subprojects 2, 3, 7, 8, 9, 10 and 12 have no resettlement impact so no resettlement report is required. Annex 3 provides a sample of resettlement framework for sub-project 4. Annexes 4, 5 and 6 provide an outline for the development of resettlement plan, a guideline for census, socio-economic, and replacement cost survey, and voluntary contribution consent form. 25. During the PPTA a resettlement framework will need to should be developed to provide guidelines for the development of full and short resettlement plan for sub-project 1 and sub-projects 4, 5, 6 and 11 for the subsequent phase after PPTA.

124


Appendix 11 Table A12.3: Screening Questions for Resettlement Categorization Country Project Title: Vientiane Sustainable Urban Transport Project. TA 7243-REG Probable Involuntary Resettlement Effects 1.

Will the project include any physical construction work?

Preliminary findings

Remark

Yes, for Sub-projects: 1, 4, 5, 6 & 11.

2.

Does the project include upgrading or rehabilitation

Yes, for Sub-projects: 3, 6, 7, 11, 12

If the proposed construction of parking lots will be built in the water park compound or private lands will be classified as category A. Width co nstrictions, surface treatments and landscaping along the proposed “Woonerf” streets will lead to disruption of existing residents and businesses. Resettlement framework will be required.

Recommendations for PPTA Preparation of initial resettlement plan for Sub-project 1as well as four subprojects 4, 5, 6 & 11.

of existing physical facilities? 3.

Are any project effects likely to lead to loss of

Possible, for Sub-project 1

Possible, for Sub-projects: 1

Not known, for Sub-projects: 1

Not known, for Sub-projects: 1

housing, other assets, resource use, or incomes/livelihood? 4.

Is land acquisition likely to be necessary?

5.

Is the site for land acquisition known?

6.

Is the ownership status and current usage of the land known?

7.

Will easements be utilized within an existing right of

The proposed location on the east edge is adjacent to Khuadin market and city bus station. For the west edge is surrounded by residential, commercial and government building. If the proposed construction will be built in the water park compound or private lands. At this stage the sites for parking lot have not been decided yet. Proposed construction will be built in the water park compound or private lands At this stage the sites for parking lot have not been decided yet

Resettlement plan is required for subproject 1

Resettlement plan is required for subproject 1 Site for land acquisition need to be identified for development of entitlement schemes for AP of sub-project 1 Ownership status and current usage of land need to be identified for development of entitlement scheme for the AP of sub-project 1

No, for all Sub-projects

way? 8.

Are any non-titled people living or earning their

Possible, for Sub-project 1

If the proposed construction will be built in the water park compound or private lands.

All APs need to be identified for development of entitlement scheme for sub-project 1

Possible, for Sub-project 1

Possible, for Sub-project 1

If the proposed construction will be built in the water park compound or private lands. If the proposed construction will be built in the water park compound or private lands.

All APs need to development of sub-project 1 All APs need to development of sub-project 1

livelihood at the site or within the right-of-way? 9.

Will there be loss of housing?

10. Will there be loss of crops, trees and fixed assets?

125

be identified for entitlement scheme for be identified for entitlement scheme for


Appendix 11 11. Will there be loss of businesses and enterprises? 12. Will there be loss of income and livelihoods? 13. Will people lose access to facilities, services, or

No, for all Sub-projects Yes, for Sub-projects 4,5,6 & 11 No, for all sub-projects

During the construction shop owners and street vendors are going to temporary lose their income.

Entitlement scheme need to be developed and consulted with the APs.

natural resources? 14. Will land use related changes affect any social or

No, for all sub-projects

economic activities? 15. If involuntary resettlement impacts are expected: •

Yes

In general, the main principles of the government policies on land acquisition,

Are local laws and regulations compatible with

compensation, assistance and

ADB’s policy on involuntary resettlement?

resettlement reflect those reflected in ADB’s SPS (2009).

1.

Will coordination between government agencies be

Stakeholder analysis need to be carried out

Yes

required to deal with land acquisition? 2.

Is sufficient skilled staff available in the executing

Not known

Some staff members of VUDAA have

agency for resettlement planning and implementation?

gained this experience from Vientiane

Training need assessment needs to be carried out

Urban Infrastructure and Service Project 3.

Are training and capacity building interventions

Not known

High turnover of VUDAA staff those who

required prior to resettlement planning and

have gained experience from Vientiane

implementation?

Urban Infrastructure and Service Project may not be available for the proposed project.

126

As above


Appendix 11 Annex 1

Question for Interview Public (Road Users)

1.1 1.2 1.3

1) About yourself: gender occupation your working place

2.1 2.2 2.3 2.4 2.5 2.6 2.7

2) Transport use to go to town/work What type of transport do you use to go to town/work? time spent from home to your work place Are there enough parking lots at your working place? Enough for all staff and workers? If not have enough, how you solve it? Where do you park your car/motorbike? Do you see any traffic problems? Any suggestion for solving these problems?

• 3.1 3.2 3.3 3.4 3.5 3.6 3.7

3) Alternatives If there is a public parking lot (nearby the water park) and Lao will have public transport from this public parking lot to the town core area. Are you going to use this public parking lot? Are you going to use the new bus line? How much do you think about the reasonable parking fee? How much do you think about the reasonable bus ticket’s price? (for the one who already paid the parking fee) How much do you think about the reasonable bus ticket’s price? (for public) If provide these services (parking lots and new bus line), do you think that will help to diminish the traffic jam and the crowded town? In case there is an office bus, are you going to use it?

127


Appendix 11 Annex 2 Questions’ Check List for Tourists 1.1 1.2 1.3 1.4 1.5

1) About yourself: Gender……………………. Age …………………… From (which country)………………… Occupation…………………………….. First time visit Laos…………………….

2.1 2.2 2.3 2.4 2.5 2.6

2) About the trip: How long have you been in Vientiane ……………………………………. What type of transport do you usually use during your stay in Vientiane…………… Comfortable enough……………………………………………………….. Reasonable cost……………………………………………………………. Do you see any specific traffic problems here?............................................. Do you have any suggestions for improvement (to provide better service to tourists)?

............................................................................................................................................................... ............................................................................................................................................................... ................... 3) Other choice: In case Lao will have public transport (new, clean, reliable bus service) to service the town core area 3.1 Are you going to use it?............................................................................. 3.2 How much do you think about the reasonable bus ticket’s price?.................................................. 3.3 Any suggestions for further better managing the bus service especially for the foreign tourists? …………………………………………………………………………………………………………………… …………………………………………………………………………………………………………………… ……………………………………………………………………………

128


Appendix 11 Annex 3 Preliminary Resettlement Framework and a Sample Resettlement Plan for Sub-Project 4: ‘Woonerf’ Street Improvements – Nokeokhoumane. A.

Introduction

1. The Vientiane Sustainable Urban Transport Project (VSUTP) is part of phase 1 (2010_2011): “ studies on pilot testing of new types of sustainable transport operations”. The proposed Project will be implemented in the core areas of Vientiane Capital and comprises three components or packages: (i) institutional strengthening and capacity development; (ii) a pilot public transport service and facilities; and (iii) a demonstration traffic management scheme. 2. Under Component 2, 12 sub-projects have proposed: (1) construction of multi-story car park; (2) traffic management action area plan market/Nongchan z one; (3) Review and rationalization of parking restriction areas; (4) Woonerf’ street improvements – Nokeokhoumane, Francois Ngin, Manthathourath, Chao Anou, OngTeu; (5) street improvement near Nam Phou fountain; (6) Various streets improvement; (7) Improvement of pedestrian light crossing facilities; (8) Improvement of light control junction; (9) Set up additional light-controlled junctions; (10) Improvement at non-lightcontrol junctions; (11) Walkability improvement; (12) Road marking. Of the 12 sub-projects, those with potential implications for resettlement will be sub-projects 1, 4, 5, 6 and 11. This RF will also provide a sample of resettlement plan for Nokeokhouman road of sub-project 4. 3. Sub-project 4 will involve width constrictions, surface treatments and landscaping along the proposed streets will lead to temporary loss or disruption of the use of land or other assets caused by construction works and the movement of construction plant and materials to and from work sites. B.

Objective of Preliminary Resettlement Framework (RF)

4. The RF presents the specific policies and guidelines to guide the process for land acquisition and resettlement. RPs will be prepared for each of the subprojects after feasibility studies have been conducted, and where there are potential resettlement implications. 5. The RF shall be built upon the laws of the Government of Lao PDR in particular, the Draft National Resettlement Policy Degree No 192/PM dated 7 July, 2005 and Degree No 699/PMO WREA dated 12 March 2010 on Compensation and Resettlement of the Development Project (Improved), as well as ADB’s Policy on Involuntary Resettlement (1995) and its SPS (2009). It will be applied to all subprojects where there will be land acquisition and/or resettlement 6. The legal and policy framework addressing the resettlement impacts of sub-project 4 is provided by relevant policies and laws of the Lao PDR and the ADB’s Involuntary Resettlement Policy, June 2009 ( as articulated under its SPS 2009). The following section outlines the relevant policies and laws, and highlights where differences exist, and the specific policies and principles adopted for the proposed Project. C.

Legal Foundation and Entitlement Policies 1.

Asian Development Bank Policies

7. The objectives of the ADB social safeguards policy are to avoid involuntary resettlement whenever possible; to minimize involuntary resettlement by exploring project and design alternatives; and to enhance, or at least restore, the livelihoods of all displaced and vulnerable persons in real terms relative to pre-project levels; and to improve the standards of living of the 129


Appendix 11 Annex 3 displaced poor and other vulnerable groups. The policy indicates four important elements in involuntary resettlement:    

Mitigate the need for resettlement and compensation as much as possible; Compensate for lost assets and loss of livelihood and income; Assist in relocation including provision of relocation sites with appropriate facilities and services, and, Assist with rehabilitation so as to achieve at least the same level of well-being with the Project as before.

8. The policy further stipulates that the absence of legal title to land cannot be considered an obstacle to compensation and rehabilitation privileges. All persons affected by the Project, especially the poor, landless, and semi-landless persons should be included in the compensation, resettlement, and rehabilitation package. The Safeguard Policy Statement stipulates that those APs who are unable to demonstrate a legalizable or recognizable claim to the land being acquired will be eligible for compensation with respect to non-land assets only, and not the land itself. They will however be provided with other benefits and allowances as provided other APs. 2.

Laws and Polices of Lao PDR Regarding Resettlement

9. In the Lao PDR, compensation principles and policy framework for land acquisition and resettlement are governed by the following laws, decrees and regulations: the Constitution (1991), the Land Law (2003), the Road Law (1999), Regulations for Implementing the Decree of the Prime Minister on Compensation and Resettlement of People Affected by Development Projects (No.2432/STEA, dated 11 November 2005), and • The new improved decree 699/PMO-Water Resources and Environmental Agency (WREA) dated 12 March 2010 on Compensation and Resettlement of the Development Projects. In general, the main principles of the government policies on land acquisition, compensation, assistance and resettlement reflect those reflected in ADB’s SPS (2009).

• • • •

3.

Reconciliation of Government and ADB Policies

10. Both Lao PDR law and ADB policies entitle APs to compensation for affected land and nonland assets at replacement cost. However, Government and ADB policy differ in the definition of severely affected APs. The ADB (Operational Manual Section F2 para. 5) set a threshold of 10% or more of productive assets to define severely affected APs, while the Government Decree 192/PM (Article 8) adopts a t hreshold of 20% of income generating assets. Using a 10% threshold is, however, in accordance with Decree 192/PM (Article 6) which entitles all APs to economic rehabilitation assistance to ensure they are not worse off due to the proposed Project. 11. Both Lao PDR law and ADB policies entitle APs to compensation for affected assets at replacement cost and other assistance so that they are not made worse off due to the proposed Project. Decree 192/PM goes beyond ADB’s policy and provides APs living in rural or remote areas, or APs in urban areas who do not have proof of land-use rights and who have no other land in other places, compensation for loss of land-use rights at replacement cost, in addition to compensation for their other assets and other assistance. Should APs be found to be non-titled and required to relocate, the proposed Project will ensure they are provided replacement land at no cost to the APs, or cash sufficient to purchase replacement land. 130


Appendix 11 Annex 3 Table A12.4: Comparative Compensation Approaches Key Item Scope of impact

Internationally Applied Best Practice

Lao PDR Legislation All

Include all affected areas including construction and operational sites/facilities

Listed Key

Definition of assets

All fixed and movable assets

Items Are Mandatory

Compensation to formal owners / users of assets

Compensation legally required

Compensation to informal / unregistered owners / users of assets

Compensation to be provide to users of assets and resources based on traditional rights

Special support to vulnerable groups

Special mitigation measures throughout the project cycle

Livelihood restoration

Compensation to be provided in addition to loss of assets, etc.

Relocation

Sub-projects Shall include all residential, agricultural and commercial areas: (i) Permanently /temporarily acquired, (ii) Construction and O&M related, (iii) Private and/or public areas Shall define all assets: (i) Legally acknowledged, and (ii) Socio-economically surveyed as used by households Shall be offered and provided to: (i)

Private users (shop owners, restaurant operators, etc.) (ii) Public users (street vendors) Shall be applied to households or individuals: (i)

Whose user rights are proven by tax or other formal payments (ii) Socio-economically surveyed as users of affected assets Shall be for households or individuals: (i)

Formally known or acknowledged at community level as related to one of these groups (ii) During pre-construction, construction and post-construction phases Shall include, among others: (i) (ii)

Avoiding displacement

Income rehabilitation measures Others to be defined

Shall be applied and shown through: (i) Technical optimized design of proposed infrastructure (ii) If not avoidable, relocated households shall receive (for no costs or payments) issued land titles for their new compounds Before start of construction:

Timing of compensation and support measures

(i) Funds made available and proven to be accessible conditional to release of construction funds (ii) Paid and/or provided to affected individuals/ households Notes: (i) Best international practices as applied by ADB, the World Bank, others; and (ii) final resettlement planning shall provide details of these and other items.

131


Appendix 11 Annex 3 4.

Anticipated Involuntary Resettlement Under Sub-project 4

12. Five streets: Nokeokhoumane, Francois Ngin, Manthathourath, Chao Anou, and OngTeu are covered by sub-project 4. Rapid social assessment was conducted along Nokeokhoumane Street in Xiengngun village, Chanthabouli district, which resulted that resettlement impact may occur when land is required for storing construction materials or other impacts cause by construction activities such as temporary loss of income for hotel, restaurants operators and other businesses operators that rely on walk in customers. The construction activities will also prevent street vendors with pushed cart for selling food, vegetable and fruits along the roads. In addition there is also possible loss of parking of residents along the road. List of affected households and businesses is summarized in the table below. Table A12.5: Preliminary List of Businesses and Residential Houses along Nokeokhoumane Road. Category

Number

Impacts during the construction

Average estimation of lost per day per business (in USD)

Hotel

1

Number of walk in guest will reduce

300.00

Guest house

3

As above

150.00

Restaurant

7

Number of clients may reduce due to access constraint and disruption

200.00

Handicraft /souvenir shop

5

As above

300.00

Motorbikes and lending operators

5

Number of clients may reduce due to access constraint

150.00

Boutiques

3

As above

100.00

Laundry shop

2

As above

50.00

Book store

2

As above

50.00

bikes

Street vendor

3 (Fruit, vegetable and pancake vendors with pushed cart)

Cannot access to the street

20.00

Travel agency

1

Number of walk in guest may reduce

200.00

Government flat houses (11 blocks)

Serve as residence for 20 families of officers working for Ministry of Education

Cannot park their cars on the street additional expense to park their car at the new parking lot along Mekong River

1.00

Residential houses

3 Lao style houses

As above

1.00

132


Appendix 11 Annex 3 5.

Entitlement Eligibility and Compensation

13. Eligibility will be determined with regards to the cut-off date, which is taken to be the date of completing the consultation and field survey for which land and/or assets affected by the sub-project are measured. The APs will be informed of the cut-off date for each subproject component, and any people who settle in the sub-project area after the cut-off date will not be entitled to compensation and assistance under the sub-project. 14. Cash Assistance for loss of income: Since resettlement impact of sub-project 4 will be minor and related only to the construction activities thus APs are entitled to compensation of loss of income from business during the construction phase. Estimation of net income of shops should be carried out during the resettlement plan preparation. It will then be used for calculation of cash compensation. 15. Voluntary Donation: Since sub-project 4 will positively impact on the income and well-being of local people and impacts are determined to be minor and the affected households do not want to receive compensation for the impacts, the voluntary contribution on sub-project 4 can be applied using the Voluntary Contribution Form (See Annex 6 for a sample form) must be attached to the subproject RP. D.

Implementation Issues 1.

Information Disclosure, Consultation and Participation

16. According to the ADB SPS, the following documents are submitted to the ADB for Disclosure on the ADB website: o o o o

Draft RP or RF endorsed by the Client before project appraisal Final RP endorsed by Client after the Census of APs Updated RP following any changes from the Census of APs or other changes introduced (if any) Resettlement monitoring reports

17. In the RP preparation following the Census of APs and formulation of the Inventory of Losses (IOL) the implementing agency will coordinate with the local authorities to provide information for local people on: o o o o o

Description of the subproject; Potential resettlement impacts by the subproject; Project Resettlement Policy Framework (concentrate on the entitlements); Implementation schedule; and, Grievance redress mechanism.

18. The local people and affected households and other stakeholders will continue to be consulted during RP updating and implementation, following a two-way process – information dissemination and gathering of feedback and suggestions. 19. Public Consultations: A first public consultation with local people and the affected households and other stakeholders will be held prior to the start of the inventory of losses (IOL), as a way of introducing the subproject and the resettlement policy to the local population. Focus groups are to be held with all households/businesses affected by the sub-project. During the focus groups participants can express their concerns that should be addressed in the resettlement process and on their preferences for compensation.

133


Appendix 11 Annex 3 20. A second Public Consultation will take place to share the results of the IOL, the entitlements and the resettlement plan. This public consultation will include discussing the results of the impacts survey with the affected households and getting feedbacks and suggestions on their compensation and entitlements. 21. Further public consultations will continue during implementation. These consultations should take place (i) following completion review and updating of unit costs for affected assets or businesses, where the resettlement committees consult with the affected households individually and/or in group in connection with the updating of compensation and entitlements and, (ii) following approval of the updated RP, to present to the affected households in the village (i.e., also referred to as “final disclosure meeting�) the validated/updated list of affected people, compensation and entitlements due to them, and schedule of delivery of compensation and entitlements. 22. Disclosure of RP: The draft RP will be uploaded on the ADB website. Following approval of the draft RP by the authority of Vientiane Capital and ADB, the final RP will again be disclosed to the affected households and uploaded on the ADB website. 23. o o

o

o

o

o

o

The contents of the public meetings will cover the following: Subproject information. This includes the places where stakeholders can obtain more detailed information about the project. Subproject impacts. Anticipated impacts on the people living and working, making livings in the affected areas of the project including explanations about the need for land acquisition for the subproject components. APs rights and entitlements. The rights and entitlements for different categories of APs, including the entitlements for those losing businesses, jobs and income. Options for compensation or voluntary donation. Grievance mechanism and the appeal process. All APs are to be informed that project policies and procedures are intended to ensure their pre-project living standards are at least restored if not improved. All APs must also be informed that if there is any confusion or misunderstanding about any aspect of the project, the village or district resettlement committee can help resolve problems. If they have complaints about any aspect of the land acquisition, compensation, resettlement, and rehabilitation process, including the compensation rates being offered for their losses, they have the right to make complaints and to have their complaints heard. APs will also receive an explanation about how to access grievance redress procedures, according to Project’s mechanisms. Resettlement activities. All APs are to be given an explanation regarding compensation calculations and compensation payments, monitoring procedures (which will include interviews with a s ample of APs), reorganization, relocation to an individual location/selfrelocation, and preliminary information about physical works procedures. Organizational responsibilities. All APs are to be informed about the organizations and levels of Government involved in resettlement and the responsibilities of each, as well as the names and positions of the Government officials with phone numbers, office locations, and office hours if available; Implementation schedule. All APs should receive the proposed schedule for the main resettlement activities and informed that physical works would start only after the completion of all resettlement activities and clearance from the project area. It should be clarified that APs would be expected to move only after full payment of compensation for their lost assets. Implementation schedules and charts will be provided to resettlement committees at all levels.

24. Following all public meetings with APs and stakeholders the District Resettlement Committee must complete the following activities: 134


Appendix 11 Annex 3 o o o

Make a list of all APs who joined the meeting; Make a complete record of all questions, comments, opinions, problems and decisions that arose during the information and consultation meetings. Deliver leaflets and project announcements to the APs.

25. Grievance Redress Procedure: In order to ensure that all APs’ grievances and complaints on any aspect of land acquisition, compensation and resettlement are addressed in a timely and satisfactory manner, and that all possible avenues are available to APs to air their grievances, a well-defined grievance redress mechanism needs to be established. All APs can send any questions to implementation agencies about their rights in relation with entitlement of compensation, compensation policy, rates, land acquisition, resettlement, allowance and income restoration. Otherwise, all APs are not ordered to pay any fee during the grievance and complaints at any level of trial and court. 26. In terms of grievance redresses, the APs will be made fully aware of their rights to grievance and the procedures by doing so verbally and in writing during consultation, survey and time of compensation. The APs may present their complaints to the concerned local administrative officials and resettlement committees. The complaint can be filed first at the village level and can be elevated to the highest or provincial level if the APs are not satisfied with the decisions made by the village and district levels/committees. APs will be exempted from all taxes, administrative and legal fees associated with their claims and grievance redress. 27. Attempts should be made to settle the issues at the village level through the village mediation committee. This shall be supported through involvement of social and resettlement experts as required. 28. In general, the following main steps shall be applied and serve as an orientation for the grievance main approach which shall be defined during the preparation of the detailed resettlement (action) plan. For each step details shall be described, agreed and explained to both resettlement responsible committees and the residents of affected villages. Additional steps can be incorporated as appropriate. Subproject APs shall understand the complaints and grievance mechanisms concerning related compensation and mitigation measures. Step 1: In each village existing mediation committees would be the first contact for APs to address their concerns. It is recommended that in agreement with villages either this committee would be responsible for resettlement issues or the village would establish a project related resettlement committee. The village shall decide about its community internal approach. Step 2: APs would address their complaints to these committee/s that would have to react within a defined time (5 days to be defined by village) after submission of the complaint. Step 3: In case provided responses are not satisfying to affected people the grievance applications would be forwarded to the district council for resolution within a defined time (5 days) from the date of filing the complaint with this court. Step 4: In case APs are still not satisfied next steps could involve concerned authorities at Vientiane Capital level that would have to issue a final decision within a defined time (10 days). Before applying step 4, the involved district staff shall undertake a f inal effort for an amicable solution at village level to avoid next legal steps. Step 5: If subproject APs are still not satisfied with the response given or decisions made, the complaint can be elevated at national level either to the national court, if legal decision at the Capital level will require this. 135


Appendix 11 Annex 3 29. All complaints and resolutions will be properly documented by the concerned resettlement committee and be available for (i) the public and (ii) review for monitoring purposes. E.

Institutional Arrangement and Implementation

30. Resettlement committees at Vientiane Capital and district levels will be established to review and approve the sub-project RPs submitted by the implementing agency (VUDAA/DPWT). The resettlement committees will also act as an advisor and will assess and monitor the RP activities. They will also act as grievance officers. 31. Vientiane Capital Resettlement Committee will be established and will be h eaded by the Governor or Vice Governor. Members of this are, but not limited to the following: concerned district governors, Department of Finance (Land Property Office), VUDAA, the Department of Planning and Investment, and concerned DPWT heads. 32. The District Resettlement Committee will be headed by the district governor and will be composed of representatives from PWT of district, APs, Lao Women’s Union of district, heads of affected villages. 33. There is a n eed for capacity building in resettlement planning for the above mentioned implementing stakeholders expected to be involved and responsible for the final preparation and implementation of resettlement plans. Costs for the capacity building in respect of resettlement must be incorporated into the project budget. It is recommended to organize resettlement related training sessions prior to the start of resettlement activities, where the following topics have to be introduced: • Latest policies, decrees and technical guidelines. • Basic principles of resettlement planning and the conceptual approach on entitlements for losses. • Institutional requirements. • Staff and training requirements. • Others.

F.

Implementation Schedule

34. The RP for each subproject will be prepared following the completion of concept design for that subproject (i.e. feasibility study stage). A detailed implementation schedule of the various activities to be undertaken will be included in each RP. The schedule for all resettlement activities must be agreed and settled by all stakeholders before resettlement activities begin. Satisfactory payment of compensation and provision of other rehabilitation entitlements and relocation, if that be the case, will be completed before a ‘no objection’ for ADB can be provided for award of civil works contract under each subproject. G.

Resettlement/Compensation Budget

35. Sub-project 4 will minor resettlement impact on temporary loss of income of businesses during the construction but it is expected that sub-project 1 will involve resettlement if private land is going to be acquired. Thus the major cost for compensation will be related to sub-project 1. It was 136


Appendix 11 Annex 3 beyond the scope of this TA to calculate a b udget for resettlement, but based on judgment a lump sum amount 300,000 will be utilized.

137


Appendix 11 Annex 3 H.

Preliminary Staffing Requirements and Budget

36. Resettlement is unlikely to be a significant issue in the implementation of the proposed Project in view of the identification criteria and the pre-screening activities already undertaken during the preparation phase. In order to address the national specialists will be engaged to assist the implementing ensure that resettlement procedures are followed in accordance with laws of Lao PDR and policies of ADB. It is estimated that one national resettlement specialist will be required with inputs of 6pm . Timing of input and budget are outlined in Table 12.6.

Table12.6: Resettlement Staffing Budget Budget Item

Unit Cost ($)

Units

Domestic Specialist

3,800

6p.m

38,000

Census survey of APs and community consultation

10,000

Lump sum

10,000

Capacity building of government partners

10,000

Lump sum

10,000

Total

Total ($)

58,000

37. The specialists will assume responsibility for development of resettlement plan for the subprojects, for the training of government staff at t he project, provincial and district level in resettlement issues and procedures. S/he will also be responsible for establishing procedures in respect of resettlement and assist in the identification of procedures to resolve any resettlement that might be needed associated with rural infrastructure rehabilitation. The national specialist will be an experienced specialist with a minimum of 10 years practical experience with appropriate tertiary qualifications. The national specialist will be conversant with the resettlement laws of Lao PDR and will also have considerable experience in internationally financed development projects where resettlement was an issue.

I.

Monitoring and Reporting Arrangement

38. Internal Monitoring. VUDAA, in collaboration with DPWT and resettlement committees, are responsible for internal monitoring of RP implementation. VUDAA with DPWT assistance, will supervise the resettlement activities and provide quarterly reports to the national project manager for inclusion in the Quarterly Progress Report, which is circulated to ADB and members of the Project Steering Committee. The national project manager will ensure that the grant implementation consultants include in their progress reports the status of the RPs, and information on location and numbers of people relocated, compensation amounts paid by item, and assistance provided to APs. All reports will be submitted in English. ADB will also monitor these activities in its regular supervision missions during the period of project implementation. 39. External Monitoring. Independent monitoring will take place by external organization for post-resettlement impact evaluation to assess whether impacts of the proposed sub-projects have 138


Appendix 11 Annex 3 been mitigated adequately and the pre-project standard of living of APs have been restored as a result of resettlement and project activities.

139


Appendix 11 Annex 4 Outline of a Resettlement Plan for sub-project 1 1. This outline is part of the Safeguard Requirements 2. A resettlement plan is required for all projects with involuntary resettlement impacts. Its level of detail and comprehensiveness is commensurate with the significance of potential involuntary resettlement impacts and risks. The substantive aspects of the outline will guide the preparation of the resettlement plans, although not necessarily in the order shown.

A.

Executive Summary

2. This section provides a concise statement of project scope, key survey findings, entitlements and recommended actions. B.

Project Description

3. This section provides a general description of the project, discusses project components that result in land acquisition, involuntary resettlement, or both and identify the project area. It also describes the alternatives considered to avoid or minimize resettlement. Include a t able with quantified data and provide a rationale for the final decision.

C.

Scope of Land Acquisition and Resettlement

4. This section: (i) discusses the project’s potential impacts, and includes maps of the areas or zone of impact of project components or activities; (ii) describes the scope of land acquisition (provide maps) and explains why it is necessary for the main investment project; (iii) summarizes the key effects in terms of assets acquired and displaced persons; and (iv) provides details of any common property resources that will be acquired.

D.

Socioeconomic Information and Profile

5. This section outlines the results of the social impact assessment, the census survey, and other studies, with information and/or data disaggregated by gender, vulnerability, and other social groupings, including: (i) define, identify, and enumerate the people and communities to be affected; (ii) describe the likely impacts of land and asset acquisition on the people and communities affected taking social, cultural, and economic parameters into account; (iii) discuss the project’s impacts on the poor, and other vulnerable groups; and (iv) identify gender and resettlement impacts, and the socioeconomic situation, impacts, needs, and priorities of women.

E.

Information Disclosure, Consultation, and Participation

6. This section: (i) identifies project stakeholders, especially primary stakeholders; (ii) describes the consultation and participation mechanisms to be used during the different stages of the project cycle; (iii) describes the activities undertaken to disseminate project and resettlement information during project design and preparation for engaging stakeholders; (iv) summarizes the 140


Appendix 11 Annex 4 results of consultations with affected persons (including host communities), and discusses how concerns raised and recommendations made were addressed in the resettlement plan; (v) confirms disclosure of the draft resettlement plan to affected persons and includes arrangements to disclose any subsequent plans; and (vi) describes the planned information disclosure measures (including the type of information to be disseminated and the method of dissemination) and the process for consultation with affected persons during project implementation.

F.

Grievance Redress Mechanisms

7. This section describes mechanisms to receive and facilitate the resolution of affected persons’ concerns and grievances. It explains how the procedures are accessible to affected persons and gender sensitive.

G.

Legal Framework

8. This section: (i) describes national and local laws and regulations that apply to the project and identify gaps between local laws and ADB's policy requirements; and discuss how any gaps will be addressed. (ii) describes the legal and policy commitments from the executing agency for all types of displaced persons; (iii) outlines the principles and methodologies used for determining valuations and compensation rates at replacement cost for assets, incomes, and livelihoods; and set out the compensation and assistance eligibility criteria and how and when compensation and assistance will be provided. (iv) describes the land acquisition process and prepare a s chedule for meeting key procedural requirements.

H.

Entitlements, Assistance and Benefits

9. This section: (i) Defines displaced persons’ entitlements and eligibility, and describes all resettlement assistance measures (includes an entitlement matrix); ( ii) Specifies all assistance to vulnerable groups, including women, and other special groups; and, (iii) Outlines opportunities for affected persons to derive appropriate development benefits from the project.

I.

Relocation of Housing and Settlements

10. This section: (i) describes options for relocating housing and other structures, including replacement housing, replacement cash compensation, and/or self-selection (ensure that gender concerns and support to vulnerable groups are identified); (ii) describes alternative relocation sites considered; community consultations conducted; and justification for selected sites, including details about location, environmental assessment of sites, and development needs; (iii) provides timetables for site preparation and transfer; (iv) describes the legal arrangements to regularize tenure and transfer titles to resettled persons; (v) outlines measures to assist displaced persons with their transfer and establishment at new sites; (vi) describes plans to provide civic infrastructure; and (vii) explains how integration with host populations will be carried out.

141


Appendix 11 Annex 4

J.

Income Restoration and Rehabilitation

11. This section: (i) identifies livelihood risks and prepare disaggregated tables based on demographic data and livelihood sources; (ii) describes income restoration programs, including multiple options for restoring all types of livelihoods (examples include project benefit sharing, revenue sharing arrangements, joint stock for equity contributions such as land, discuss sustainability and safety nets); (iii) outlines measures to provide social safety net through social insurance and/or project special funds; (iv) describes special measures to support vulnerable groups; (v) explains gender considerations; and (vi) describes training programs.

K.

Resettlement Budget and Financing Plan

12. This section: (i) provides an itemized budget for all resettlement activities, including for the resettlement unit, staff training, monitoring and evaluation, and preparation of resettlement plans during loan implementation. (ii) describes the flow of funds (the annual resettlement budget should show the budget-scheduled expenditure for key items). (iii) includes a j ustification for all assumptions made in calculating compensation rates and other cost estimates (taking into account both physical and cost contingencies), plus replacement costs. (iv) includes information about the source of funding for the resettlement plan budget.

L.

Institutional Arrangements

13. This section: (i) describes institutional arrangement responsibilities and mechanisms for carrying out the measures of the resettlement plan; (ii) includes institutional capacity building program, including technical assistance, if required; (iii) describes role of NGOs, if involved, and organizations of affected persons in resettlement planning and management; and (iv) describes how women’s groups will be involved in resettlement planning and management,

M.

Implementation Schedule

14. This section includes a detailed, time bound, implementation schedule for all key resettlement and rehabilitation activities. The implementation schedule should cover all aspects of resettlement activities synchronized with the project schedule of civil works construction, and provide land acquisition process and timeline.

N.

Monitoring and Reporting

15. This section describes the mechanisms and benchmarks appropriate to the project for monitoring and evaluating the implementation of the resettlement plan. It specifies arrangements for participation of affected persons in the monitoring process. This section will also describe reporting procedures.

142


Appendix 11 Annex 5 Guideline for Census, Socioeconomic Survey and Replacement Cost Survey

A.

Census of APs and Inventory of Affected Assets

1. A census of APs and their households and the inventory of assets to be acquired serve two vital functions. The primary function is to identify APs eligible for resettlement entitlements, which is especially important if disclosure of subproject plans is likely to encourage land invasion and fraudulent claims for compensation. The census and inventory also supply an important part of the resettlement database to be used for project monitoring and supervision. The census and the inventory of assets can be done separately. As each requires visits to all affected households, however, doing them together is generally more efficient. Where establishing ownership or length of residency is difficult, the census should be conducted as soon as possible, to determine a cut-off date for eligibility for entitlements. In such situations an immediate partial inventory, sufficient to establish the number and general size of structures and other assets to be taken, may be advisable to supplement the census. The precise attributes of structures and an inventory of remaining fixed assets (such as boreholes) acquired or affected can be determined later. The census needs to be undertaken as soon as possible to ensure accurate determination of eligibility for entitlement. The formats for the census and the asset inventory must be adapted to the specific context and informational requirements of the subproject. In any case, the format needs to be field-tested, to ensure that the questions and the phrasing of them elicit the required information. The usual practice is for enumerators to code information while the teams are in the field. This way, incomplete or obviously incorrect information can be corrected on repeat visits. The information is then sent to the project office for data entry and filing. 2. Once the final technical design of the subproject is available, the Detailed Measurement Survey (DMS) needs to be carried-out, and the DMS results are used for the RP updating.

B.

Socioeconomic Survey (SES)

3. The census and inventory are supplemented with data from socioeconomic surveys. The SES data and information are used to establish baseline information on household income, livelihood patterns, standards of living, and productive capacity. For the significant involuntary resettlement subproject 1, AP population can be sampled for the socioeconomic surveys. The sample should provide a sufficient number of cases for statistical analysis.

C.

Replacement Costs Survey (RCS)

4. Compensation is based on the principle of replacement cost. Replacement cost is the amount calculated before displacement which is needed to replace an affected asset without deduction for taxes and/or costs of transaction as follows: -

Productive Land (agriculture, aquaculture, garden...) based on market prices that reflect recent land sales, and in the absence of such recent sales, based on productive value; Residential land based on market prices that reflect recent land sales, and in the absence of such recent land sales, based on similar location attributes; Houses and other related structures based on current market prices of materials and labor without depreciation nor deductions for salvaged building materials; Annual crops equivalent to current market value of crops at the time of compensation; 143


Appendix 11 Annex 5 -

For perennial crops and trees, cash compensation at replacement cost is equivalent to current market value given the type, age and productive value (future production) at the time of compensation. Timber trees based on diameter at breast height at current market value.

5. The evaluation of replacement costs will be carried out based on information collected from both research and field work including surveys and data collection from people in the affected and adjacent areas, both those affected and those not affected. 6. Desk research will focus on relevant publications, decisions of Government authorities at national, city and district levels. However, these materials will play the supporting role only. As the work is aimed at obtaining reasonable replacement costs for different types of affected assets, market evidences are the factors which most strongly base the formulation of these costs. Surveys with people in the affected area, both those, whose assets are affected by the project, and those whose assets are not, will produce reliable data for evaluation. 7. For land, the objective of evaluation is to determine the prices or rates that will enable APs to purchase the same type and quantity of land. The evaluation of compensation for the loss of land is based on its market value. Direct interviews with land-owners in the subproject area, including those whose land is affected and those whose land is not; and consultation with the land and realestate agency service staff, the District Site Clearance and Resettlement committee officer, etc. are required. The information to collect include the recent land use rights transfers (buying/selling transactions) in the area; the price, at which owners are willing to sell their land; or/and price of the recent transaction; type of land (Non – Agriculture land, Agriculture land with different categories); and the government established rates for land. 8. For perennial trees, the information about production and benefit of their fruit tree during last 3 years and the market price of the trees are needed. 9. For structures, the survey is to determine whether the government regulated prices enable APs to rebuild their affected structures. The evaluation of compensation for affected structures is based on the principle of replacement cost. The information to base the evaluation will mainly be collected from direct interviews with parties involved, including owners of structures in the subproject site and the owner of similar structures in the region whose are not affected, local construction contractors specialized in residential building; owner of newly built houses.

144


Appendix 11 Annex 6 Typical Voluntary Contribution Consent Form [INSERT NAME] Province [INSERT NAME] District [INSERT NAME] Village CERTIFICATE OF CONTRIBUTION I, [INSERT NAME, AGE, NATIONALITY, OCCUPATION], with residence located in [INSERT NAME] village, [INSERT NAME] district, [INSERT NAME] province, Certify that I have been previously informed by local authority of my right to entitle compensation for any loss of property (house, land and trees) that might be caused by the construction of [INSERT ACTIVITY]in [INSERT NAME] village, ([INSERT NAME]) district. I confirm that I voluntarily accept the land of [INSERT AMOUNT LOSS] square meters located in [INSERT NAME] village ([INSERT NAME] district) to be provided by the local authority for compensation (If any). I also confirm that I do not request any compensation of loss of [INSERT OTHER LOSSES SUCH AS INCOME FROM BUSINESS, TREES STRUCTURES] and would request the local authority to consider this as my contribution to the Project. Type of Loss

Unit

Quantity

Unit Rates

Total

Comment

Land Trees Income from business Total

Therefore, I prepare and sign this certificate for the proof of my decision. [INSERT NAME] district [INSERT DATE] The owner of the land [INSERT NAME AND SIGN] Witnesses: 1. [INSERT NAME] 2. [INSERT NAME] 3. [INSERT NAME] 145


Appendix 11 Annex 6 Certified by the Chief of the Village [INSERT NAME AND SIGN]

The Chief of [INSERT NAME] district [INSERT NAME AND SIGN]

146


Appendix 12

RAPID ENVIRONMENTAL AND IEE ASSESSMENTS I.

INTRODUCTION

1. Management of urbanization and population growth in big cities in a manner of sustainable and environmental way becomes a significant challenge for both develop and developing countries. In particular, sustainable urban transport seems to be one of the most concerned issues relating to urbanization. 2. Sustainable land transportation tends to be significantly important to Lao PDR as the country does not have an access to the sea transport. Though, transport system in Lao PDR comprises of land, water and air transport but economy of the country tends to be heavily relied much on land transport. It is anticipated both goods and passenger land transport have been increased of around 169% and 161% from 2000-2005 respectively 1. In particular, rapid increase in numbers of private vehicles in the capital, Vientiane, leaded to serious traffic congestions and road accidents due to there was a lack of investment on public transport improvement, poor enforcement of laws relating to traffic laws and poor urban planning in the past. 3. Vientiane Sustainable Urban Transport Project (VSUTP) is proposed with the financial assistance from ADB TA early this year to improve urban environment, minimize air pollutions associated with car emissions by developing sustainable urban transport systems that encourage the use of non-motorized and public transport while still managing the use of private vehicles traffic 2. A.

Description of the Project

4. Proposed activities of package 2&3 will take place in the city core area covering of 12 villages (Nongdouang Tai, Anou, Haysok, Watchanh, Mixai, Xiangnheun, Hatsadi Neua, Hatsadi Tai, Nongchan, Simeung, Sisaket, Kaogot and Phiawat) from 3 Districts: Chanthabouly, Sikhottabong and Sisattanak. The area is considerably regarded as having most significant economic importance to Vientiane, is enclosed by dense population, businesses, offices and hotels. Figure 13.1 indicates proposed activities and bus loops for VSUTP.

1 2

This result states in the draft report of The National Strategy and Action Plan on Environmental Sustainable Transport 2010. Ministry of Public Works and Transport, Department of Transport. Stated in Inception report of TA 7243: Implementation of Asia City Transport Vientiane Sustainable Transport Project, September 2010.

147


Appendix 12

Figure 13.1: Proposed activities and bus loops for VSUTP Nongdouang Tai

Anou Haysok Hatsadi Neua

Hatsadi Tai

Watchanh

Mixay

Xiangnhun

Nongchanh

Kaogot

Phiawat

Simuang

Source: VSUTP Team

5. There are 3 major packages in the VSUTP namely 1: Urban Transport Implementation Program; 2: Public Transport Improvement and Pilot Route Development; and 3: Traffic Improvement Demonstration Project. Based on proposed sub-project components activities only package 2&3 are required to do REA. 6. Package 2 of the VSUTP comprises three primary public transport sub-projects (i) procurement and operation buses for two new shuttle bus loops within the core areas of the city; (ii) the construction of appropriate 25 bus stops (see Annex 1: photos of proposed locations); and (iii) the implementation of various bus maintenance and administration facilities. 7. Package 3 of the VSUTP comprises of 14 traffic management sub-project components aiming to improve/expand existing traffic management facilities, to provide a new multi-story car park facility, other related improvements to improve traffic operation within the city core area. Description of each sub-project is mentioned in Appendix 6, Table A6.10. 8. As stated in the ADB Environmental Assessment Guidelines, all projects financed by ADB have to conduct environmental assessment to assess potential impacts. Such assessments are needed in order to determine whether, based on an assigned environmental impact category 3, an Initial Environmental Examination (IEE) or an Environmental Impact Assessment (EIA) needs to be carried out for a specific project. 3

Category A-significant severe environmental impacts, needs EIA; B-some severe environmental impacts but lesser than category A, need IEE; and C- unlikely to have adverse environmental impacts, no need IEE.

148


Appendix 12

9. The Rapid Environmental Assessment (REA) standard form had been prepared to use for assessing potential environmental impacts for all sub-projects of the Vientiane Sustainable Urban Transport Project (VSUTP). The form has been developed from REA for Urban Development of ADB. 10. Based on this methodology, surveys were carried out for all proposed sub-project components for VSUTP to assess potential environmental impacts that will occur during the project implementation stage. Surveys were based on proposed implementation activities and actual site conditions of each location. 11. In support of these surveys, interviews were carried with a n umber of boards of schools, located within/nearby proposed (Package 2) bus loops. These interviews were primarily concerned with current environmental issues relating to urban transportation in Vientiane, and in particular to highlight typical problems that are regularly encountered by students that relate to the existing urban transport system. 12. The VSUPT aims to promote sustainable urban transport, urban economic development, and minimize local pollution and greenhouse gas emissions by upgrading existing urban transport system such as buses and its facilities to make the system becomes more reliable and environmentally. I would help to reduce numbers of private vehicles out from key business areas which in turn would contribute a major part into minimization of traffic congestion in the city. B.

Existing Conditions Related to Urban Transport in Vientiane Capital 1.

Land Use

12. Within the proposed areas of the sub-project components, majority of land use types were residential land with medium to dense dwellings. Many people who located along main roads usually transformed their residences to be as a shop, office or for other commercial purposes due to lands in the city core are very expensive and there are very high demands for land. Thus, it is very rarely to see empty lands being left without building structures on the lands. 13. Other land use types in the area were also mixed up with schools, government offices, temples, markets, wetlands and banks. In particular the banks which significantly play key roles onto transformation of its neighboring areas as commercial hubs of the capital, resulted in there were rapid constructions of new business buildings, located adjacent to the banks (see Annex 2). 14. It is noticed that no agricultural lands were found in the study area as lands have highly economic importance thus the lands or houses were commonly sold out to business people. Local residents who cannot afford to stay in the city or cannot resist to high demand of the land by outsiders later then shifted their houses to outskirt of the capital where the lands were cheaper. 15. Currently, the ongoing construction project of the Mekong river bank protection in the capital that reclaims the land from the river, will provide additional useful rest area for public after its completion due to there were only few parks available in the city that local people can benefit from. Though, the government has plans to create more public parks in the near future but these projects may face challenges especially from uncertainty of financial restrictions. 2.

Insufficient Parking

149


Appendix 12

15. Lack of parking spaces can be observed throughout working hours in many places along main roads in the city core areas. In places such as bank, government office, shopping and business areas many people parked their cars in prohibited locations such as at junctions, near traffic lights, on footpath or carriageway without having a thought of consequences chaos they created to other road users. 16. Available parking spaces cannot be matched with rapid increase in numbers of traffic volume especially private cars. Most roads in the study area as well as in the capital are relatively narrow (limited to around 2 to 4 carriageways per lane) due to its previous urban design constraints in the past which could not be enlargeable. It is very usual that one carriageway and both sides of the footpath were commonly used as the parking lanes. 3.

Lack of Investment on Public Transport Improvement

17. Currently it is estimated around 5% of the total land travelers in the capital were dependent on public transport as their main transport tools for daily travel 4. Majority of travelers preferred to use their own cars as the key traveling mode. Key reasons may be associated with a lack of investment on public transport. This could be indicated in no new buses have been replaced the existing buses which most of them are in very poor conditions. 18. The improvement of this sector tends to heavily rely on international aid reflecting in most buses that owned by the VSBC, the main bus service provider, mainly provided by Japan and Korea. Though, many new roads had been built and existing roads in the capital have been fairly maintained but budgets to improve bus facilities are limited. 4.

Substandard Vehicles

19. Rapid increase in uncontrolled numbers of used vehicles in the capital that is older than 4 years counting from its manufactured date 5, especially minivans and trucks from Korea. This led to increase of substandard vehicles in the capital due to they are relatively very old and need intensive maintenance in order to make them in good and safe conditions for driving. 20. Though vehicles with age older than four years old mentioned above have been banned but it is very common to see them in big cities. Importers normally disassemble these vehicles and then import to Laos as spare parts to avoid the regulations and then reassemble them again. These vehicles are considerably cheap thus it could be seen many of these cars being displayed for sale along main roads in Vientiane capital. 21. Another key reason contributing to the rapid of substandard vehicles in particular Chinese motorcycles which are relatively very cheap and sold nationwide, compared to Japanese one such as HONDA or YAMAHA. After being used for one or two years most Chinese motorcycles are vulnerable to cause accidents as their head and turning lights tend to be broken down. Thus, riding these motorcycles in the dark conditions could post a severe risk to both riders and other road users. 5.

Increase of Vehicular Traffic and Road Accidents

22. Department of Transport, Ministry of Public Works and Transport data indicates there were around 836,000 registered units of automobile vehicles throughout the country and

4 5

Verbal discussion with General director of Vientiane State Bus Company on 11 October 2010. According to a recent agreement of MPWT on Import Vehicles; Vehicles are older than 4 years from the date they were built will not be allowed to import to Lao PDR.

150


Appendix 12 about 80% of these figures were motorbikes 6. In the capital there were more than 365,000 units of vehicles with half of that figure drivers did not have proper driving licenses and more than 70% of the figures are motorbikes. Vehicle ownership rate for the capital is estimated at two persons per one vehicle (Vientiane population data in 2009 = 754,384)7. 23. Each year in the capital had the highest numbers of the road accidents in the country, compared to other provinces. A high percentage of the accidents involved motorcycles, with students playing a major part of such motorbike accidents. The accidents mostly occurred between 4pm and 11pm 8 especially in locations where visual ability is poor and lack of safety facilities such as sufficient road lights, road marking and warning signs. 24. From 2005-2009 there were around 3,500 cases of the accidents taking place in the capital. More than a hundred of people were killed and more than 2,000 were injured (see Figure 13.2). There is no trend indicating that the number of accident will decline, in contrast, with the number of vehicles in the country continuing to increase rapidly, it can be predicted with some assurance the trend of increasing road accidents will continue nationwide. 25. Statistics of road accidents in the country from 2009-2010 reported by the Traffic Police Department pointed out approximately 2 to 3 people were got kill daily in road accidents. The two primary causes of accidents have been related to driving vehicles without proper license (62%) and drunk-drive (32%)9. 26. The situation of Vientiane urban transport, hence, is in urgent need for road safety measures including public campaigns and enforcement of traffic regulations in order to prevent loss of lives and reduce numbers of the accidents on the roads in the capital. Figure 13.2: Statistics of Road Accidents from 2005-2009 in Vientiane Capital

Statistics of Road Accident in Vientiane from 2005-2009 Accident

Injured 4,199

3,179

3,572 2,295

2,091

1,838

119 2005

3,852

2,015

171

119 2006

Fatality

2007

3,468 1,857

165 2008

203 2009

Source: Vientiane capital Traffic Police Department

6.

City Bus Transport Company

27. There are 2 bus es companies who provide alternative urban public transport for Vientiane residents, Vientiane State Bus Company and the Chinese bus company, Khingkham. The majority of buses provided by both companies especially the VSBC, the main bus provider, are old and in poor condition. 6

The data of vehicles in 2010 obtained from Traffic Management Division, DoT MPWT. Reported in the Lao PDR Statistical Year Book 2009, National Statistics Center. 8 th Reported in Vientianetimes on dated 30 July 2010. 9 Discussion with Police Major : Keomala Sengthong, Director of Traffic Accident Prevention Division 7

151


Appendix 12

28. During the interview with affected villagers there were repeated references to unreliable of public transport in the capital. It had been reported by the villagers that main reasons affecting the reliability of the buses were poor bus drivers and the poor condition of buses that were being put into service. 29. Normally the city bus drivers will not receive a salary from the bus company for their service but they will make money from the net money remaining after they paid fees for the buses to the company for each month. Thus, the buses will not depart from bus stations unless numbers of passenger are full. As a r esult, this significantly affects the reliability of the service for public transport in Vientiane10. The net result being that commuters cannot depend on the existing public transport system as a means of urban transport. 7.

Industrial Development Plan in the Nong Chanh Wetland

30. Discussion with responsible authorities for urban planning and development revealed there are serious proposals to develop whole area of the remaining Nong Chanh wetland for commercial/industrial buildings which will include the construction of Home Pro, Big C; and Tesco Lotus. Currently Vietnamese Shopping Center is under the construction (see Figure 13.3). Figure 13.3: Under consideration development projects in Nong Chanh Wetland boundary

Current Land Use at Nong Chanh Wetland (source: Google)

Proposed development projects Source: VUDAA

31. It is not known yet whether, or what number of parking spaces these proposed projects will be included in the developments. The ongoing construction of the Vietnamese shopping center will have about 220 parking spaces 11 but the numbers may be relatively small and not be able to match with actual demand for parking spaces in the surrounding areas as already evidenced in the New Morning Market Shopping Mall. In less than few years after its completion the parking spaces with the capacity of around 300 cars are full of cars and not to be able to provide sufficient parking spaces for their customers. 32. Although there are plans be studied to build the proposed buildings on Nong Chanh wetland but there is no plan (or study) to enlarge or improve the road/street network in the adjacent areas. Such improvements would be critical to reduce traffic congestion as a result 10 11

rd

Discussion with village authority of Ban Watchanh on 3 November 2010 Numbers of parking space counted by VSUTP Team from final drawing of the market provided by VUDAA

152


Appendix 12 the large influx of vehicles that would be attracted into this area12. Traffic jams in this area is already in a serious condition, thus any plans/studies to develop this area should be reconsidered, and other alternative locations outside of the city center should be considered. C.

Discussion of Key Survey Results

33. REA results indicated that most sub-projects of the VSUTP would not generate severe environmental impacts to surrounding areas as most of them will not require significant changes of physical landscape. Sub-project component improvements will be carried out within the limits of existing sidewalks, i.e. not beyond existing street rights-of-way. Thus, environmental impacts will be minor as no additional land acquisitions or resettlement works will be required for the proposed (see Annex 3 for the rapid environmental assessment checklist). 34. Sub-project 1 of package 3 is the only one that tends to cause environmental concerns, as location of the proposed car park will be near wetlands (Nong Chanh and Nong Douang Wetland). In particular the car park proposed to be constructed at the site of the existing (abandoned) water slide property, may need to have compensation to owner of the property as the proposed land was granted land concession to the current owner of the slide. In addition to the construction of the new car park the demolition of the existing water slide structure will cause a great of noise, dust and silt runoff. An IEE will be required at this location to deal with demolition, runoff and construction activities. 35. Current city buses of the Vientiane State Bus Company have been in service for a long time. Although they have been regularly repaired by the VSBC, it is still quite common to see the buses broken down on roads throughout the city. 36. The ongoing increase of both traffic vehicles and road accidents in the city which claimed lives daily (mostly from riding motorcycles) could explain how the public transport system need to be improved urgently. Major part of the accident is related to the use of private vehicles in particular motorbikes for the transportation as travelers cannot rely on the public transport. Motorbike is an option to get through the traffic congestion in the city quickly. 37. The capital recorded highest cases of road accident in the country 13. Most accident cases occurred due to drivers did not have proper licenses and were underage. As most accidents took place from evening to midnight when visual ability is weak hence installation of street lights and necessary signs can help to prevent risk of accidents. 38. Air emissions from vehicle exhausts particularly from private cars are becoming a major threat to ambient air quality in the core area of Vientiane. There have been recent rapid increases of car ownership rates in Vientiane, especially of import of used cars from Japan and Korea. These used cars tend to disproportionally cause the deterioration of air quality; which problem is acerbated by the lack of proper vehicle inspection or regular maintenance. It is estimated that only a very small percentage of such vehicles have been properly maintained inspected. 39. Air pollution associated with emission gases releasing from exhausted pipes of the vehicle traffics could become a major problem for the city as currently there are no established stations to monitor ambient air quality regularly in the capital. Most updated air quality survey was implemented by ADB in 2006. The results of the survey suggested the city had 12 13

Verbal discussion with concerned parties VUDAA and DPWT and VSUTP team th Road accident statistics published in Vientianetimes dated 5 October 2010.

153


Appendix 12

excessive ambient concentration of SO2, CO2 and Particulate Matter (PM), a small particle, were above the limit set by World Health Organization 14. Thus, it could lead to an increase of respiratory diseases. Hence, it would be very helpful to set up ambient air quality monitoring stations to monitor air quality in the city as the capital lacks of useful air quality database. 40. The parking issue within the VSUTP core boundary is of major concern for all road users. S ince there are not enough parking spaces, many drivers illegally park their cars in prohibited areas such as on roadside and walkway. This caused traffic congestion, blocking pedestrians and may lead to road accidents. This is especially a problem near banks and government offices where severe traffic congestion usually takes place. 41. Indigenous people would not have a significant impact from the project as no resettlement works are needed. Most impacts will only be a temporary during the construction such as an inconvenience to enter to their residences/shops particularly residences/shops located adjacent to the Mekong River such as Pangkham, Khoun Boulom, Fa Ngum and Samsenthai road. Many residents in these areas either already sold or rent their houses to outsiders as the areas were regarded as one of main business areas in the capital. By contrast, local people will have great benefits from a b etter traffic flow in the areas and better public transport. 42. Discussions were had with boards of a number of schools located within the service areas of the proposed bus loops. These discussions revealed a real concern regarding road accidents in the core urban area of Vientiane. F or instance, it was reported by Pakpasack College that every year there is a record of at least 30 severe cases of road accidents affecting their students, with 1 or 2 fatal student accidents a year. The vast majority of the fatalities are related to motorbike accidents; with the apparent cause of most accidents being drinking (alcohol) after evening classes. The school boards of all schools contacted were of the opinion that providing reliable public transport, as an alternative to motorbike usage, would significantly help to reduce the accident rate. 43. The other issue that most concerned the boards of schools are pedestrian accidents for students (and others) while crossing roads near the schools. This issue particularly concerned students from Phiawat School when trying to cross the street near the Kaongot Junction (on Samsenthai road). The junction is especially dangerous during commute rush hours in the morning and in the evening. Cars refuse to stop or even slow down for students. It has been reported that accidents often take place at this location, and it causes a significant loss to property and severe injuries to pedestrians (and students). Building a pedestrian bridge near the junction will greatly benefit all pedestrians. D.

Anticipated Environmental Issues Anticipated During Construction 1

Drainage System Blockage

44. One of major potential concerned issues associated with the proposed activities during its construction phase may lead to blockage of drainage system resulting from construction wastes. In general, Vientiane was built on low land areas of the Mekong floodplain with low filtration but high ground water. Most urban drainage channels in the capital had rarely been maintained after completion of construction. Uncontrolled dispersal garbage coming along with surface runoff is likely to end up in the drainage systems. This factor plays a major part to stagnant water on roads during storms events as it always blocks channel waterways. 14

Ambient air quality of Vientiane capital stated in Country Synthesis Report on Urban Air Quality Management Lao PDR 2006, conducted by ADB.

154


Appendix 12

45. Construction activities proposed in the sub-projects of the VSUTP such as new bus stops and other physical change requirement works may potentially cause negative impacts upon the existing drainage systems that are already in poor condition. All proposed activities will be located in the city core with highly populated areas and commercial buildings. Therefore, attentions have to be made by the contractors to minimize the impacts relating to the construction. Construction wastes have to be properly discarded in designated or provided areas. 2

Inconvenience to Local Residents and Road Users

46. It is inevitable that access to vehicles in some proposed areas during the construction will be closed in order to maximize safety environment of the sites and to allow proposed works continuing as planned. This temporary impact will affect local residents and others businesses as they may not be able to enter or run their businesses as normal condition before the construction started. Thus, accessibility to the sites has to be enterable by foot all the times. Necessary mitigations have to be implemented to assure the safety of road users. 3

Increased Traffic Congestion and Road Accidents

47. Traffic congestion and road accident are of main concerns for the Vientiane city. Uncontrolled parking with limitation of the parking spaces and lacking of strong traffic laws enforcement altogether already worsened urban transport. Especially on some economically important roads located along the Mekong river bank such as Pangkham, Khoun Boulom, Fa Ngum and Samsenthai road. Uncontrolled parking is going to be the most difficult problem to be sorted by the government. 48. Proposed sub-projects activities would have added more adverse impacts to the urban transport of the city if without having good plan during the construction. Transportation of construction materials and equipments to the sites may worsen road accident records which the city was already ranged as having the highest accident records in the country. Thus, attention must be made on road safety programs during the construction to reduce the risks. II. 1.

SUMMARY OF FINDINGS

General

49. The sub-projects in the Packages 2 and 3 will not create a significant environmental concern upon degradation of existing infrastructures, natural water resources, cultural and/or heritage values. No major physical changes of landscape and land acquisition are required, except the proposed construction of multi-story car park. The demolition of the existing water slide park and the construction of a new car park will need an IEE. It can be expected that this project will be designated as environmental category B. 50. Road accidents, particularly those associated with the use of motorbikes (no proper driving licenses and drunk-drive), is the major traffic safety concern in the city. Within the core area of the study, a significant number of students are killed each year as a result of motorbike accidents. Additionally, students are also a risk when trying to cross busy streets when traveling to and from school. Therefore, (i) providing reliable public transport, as an alternative to motorbike usage, would significantly help to reduce the student accident rate; and (ii) the provision of pedestrian bridges at key junctions near schools would reduce pedestrian related accidents and benefit all road users. 155


Appendix 12

2. 

   

  

Obtaining concession of lands to construct the proposed car park buildings is significant as land for the proposed car par on the east edge is still under contract of another project. While land for the west edge car park construction may not owned by the government. The construction of multi-story car parks has to be carefully planned as it would be located adjacent to wetlands. Noise and dust relating to construction activities may become a p roblem as there is no responsible agency in Vientiane to monitor the problem. Silt runoff during the construction also needs to be addressed. Traffic flow and road safety management during construction of proposed sub-projects have to be carefully addressed in order to not add further congestion to the streets of the city due to Vientiane already recorded the highest number of road accidents in the country. The reliability and affordability of the proposed shuttle bus service will be the key factors with regard to the overall success of the VSUTP. Funds for public campaigns and educational programs relating to urban transport and raising awareness of public/drivers concerning traffic regulations in general, and to raise awareness of the VSUTP in particular should be made available. Street lighting needs to be improved in locations where accidents often take place to reduce the risk of having accidents. 3.

Sample Red Flag Issues that could Pose Problems during Project Implementation

Other Issues to be Addressed under the PPTA

The operation and maintaining of bus facilities is not well-defined at this stage of the Project. This will need to be well defined during the PPTA stage, to determine the level of environmental assessment that will need to be carried out. The need for an IEE can be expected. Vientiane urban planning guidelines are not well defined, and even when defined, regulations are not enforced. This needs to be carefully addressed between the Government and the ADB during the PPTA. It would be important that current ambient air quality in key locations of Vientiane have to be addressed during the PPTA. This data would be used as a baseline data to monitor the air quality in the future as there is a lack of this data available. Effective mitigations and enforcement to control underage driving, drunk-drive and substandard vehicles while also encouraging them to use the public transport as an alternative for the transportation/travel have to be considers.

156


Appendix 12 Annex 1 Proposed Locations of Bus Stops Photo 1: New proposed bus stop of blue loop B1N on Khounboulom, in front of Chalernxay Hotel and opposite of Department of Forestry.

Photo 2: New proposed bus stop of blue loop B2N, near Vang Thong Market.

Photo 3: Proposed bus stop for B3E, near Anou National Stadium.

Photo 4: Proposed bus stop for B4E on Khounboulom road, in front of KP fashion shop where road is narrow and parking along this area is very difficult

Photo 5: Proposed bus stop for B5N near Lao Development Bank.

Photo 6: Proposed bus stop for B6N near Kop Chai Der restaurant.

157


Appendix 12 Annex 1

Photo 7: Proposed bus stop for B7N adjacent to the back of Mother and Child Hospital.

Photo 8: Proposed bus stop for B8N in front of Simeung Temple

Photo 9: Proposed bus stop for B9N at Ban Kaongot village

Photo 10: Proposed bus stop for B10N on Khouvieng road, near entry gate of Khuadin market.

Photo 11: Actual location for bus stop of B11N and R14N will use the same bus stop. It is not yet known about the location due to there is no response from the State Bus Company about where the bus stop can be built on the existing compound of the bus station, but preferably near the exit gate of the station.

Photo 12:

158


Appendix 12 Annex 1

Photo 13: Proposed bus stop for R1N, the red loop, in front of Vientiane Electric Company. Parking issue is also critical during the working days.

Photo 14: Proposed bus stop for R2N opposite to Lao Wine Shop. Traffic moment is very poor during the rush hours on this road. Finding a parking is very difficult.

Photo 15: Proposed bus stop for R3E in front of National Cultural Hall

Photo 16: Proposed bus stop for R4N opposite to Lane Xang Jewelry Shop.

Photo 17: Proposed bus stop for R5E opposite to Lao Air Booking

Photo 18: Proposed bus stop for R6N adjacent to the back gate of Sikhottabong Secondary School.

159


Appendix 12 Annex 1

Photo 19: Proposed bus stop for R7N in front of Jotun Paint Shop

Photo 20: Proposed bus stop for R8N adjacent to dormitory of Pakpasack College

Photo 21: Proposed bus stop for R9N in front of Watchanh temple

Photo 22: Proposed bus stop for R10E in front of Xieng Gnhun temple

Photo 23: Proposed bus stop for R11N near the corner of the parking of Mahosot hospital

Photo 24: Proposed bus stop R12N opposite to Phiawat secondary school

160


Appendix 12 Annex 2 Current Land Use Situation near the Mekong River Bank

Photo 25: A new hotel recently completed on Fancois Ngin road, near the Mekong river bank and Lao Development Bank with no car parks provided inside the hotel.

Photo 26: Disordered parking in front of Lao Development Bank on Fancois Ngin road where customers of the bank park their cars blocking the walkway

Photo 27: The new building under construction (right corner) on Norkeokummane.

Photo 28: Illegal parking on Norkeokummane. People always park their cars just right to the prohibited sign for even date but no one seems to obey the traffic sign

Photo 28: Situation of insufficient parking during daytime along Setthathilath road where many commercial buildings located

Photo 29: Triple parking on Pangkham road where most of the cars are BCEL Bank’s clients and their staffs, causing severe traffic congestion in this area

161


Appendix 12 Annex 3 Rapid Environmental Assessment Checklist for VSUTP Sub-projects SCREENING QUESTIONS

SUB-PROJECTS 1. Multi-story car park for park and ride on east and west edges of core area

A. Project Sitting Is the Project area adjacent to or within any of the following envi ronmentally sensitive areas? 1. Densely populated?

2. Traffic management action area plan for market/Nong Chan Zone

REMARKS

3&12. Review and rationalisation of parking restriction areas and Road markings

REMARKS

Yes. Depending on selected locations

Yes. But, depending on selected locations.

Yes. The proposed route surrounded by shops, hotels and banks.

Yes. Depending on selected locations

No

No. But, some industrial projects near Nong Chanh wetland compound are under consideration of the government.

Yes. Watchanh, Mixai and Ong Teu temple. Full description of the development proposal (IEE with EMP) will be required. No No

No

No

No

No No

No No

No No

Yes. The proposed routes are surrounded by shopping malls, banks, offices, restaurants and tourist companies located along the areas. No

No

3.

Cultural heritage/Historical site

No

No

4. 5.

Protected Area Wetland

No Yes. The east edge car park is adjacent to Nong Chan wetland which its area has been rapidly declined as a result from ongoing urban development, in particular the construction of Vientiane Water Park in this wetland. The west edge car park is adjacent to Nong Douang

No Yes. It is in Nong Chanh zone. If the new car park will be built, full description of the development proposal (IEE with EMP) will be required.

No No

162

REMARKS

10. Improvements at non-light-controlled junctions

Yes. These areas are famous for tourist attraction with shops and restaurants surrounded. Full description of the development proposal (IEE with EMP) will be required. Yes. Description of the development proposal (IEE with EMP) will be required.

Yes. Mostly are commercial and office buildings

No. But, proposed locations are potential prime land for commercial development. Proposed parking construction will require an IEE.

7. Pedestrian light crossings facilities

REMARKS

No

Heavy with development activities?

6. Street improvementvarious

REMARKS

Yes. The proposed location on the east edge is adjacent to Khuadin market and city bus station. For the west edge is surrounded by residential, commercial and government buildings.

2.

4&5. Woonerf street improvements in 5 streets and near Nam Phou fountain.

REMARKS

REMARKS


Appendix 12 Annex 3 SCREENING QUESTIONS

SUB-PROJECTS 1. Multi-story car park for park and ride on east and west edges of core area

2. Traffic management action area plan for market/Nong Chan Zone

3&12. Review and rationalisation of parking restriction areas and Road markings

4&5. Woonerf street improvements in 5 streets and near Nam Phou fountain.

6. Street improvementvarious

7. Pedestrian light crossings facilities

10. Improvements at non-light-controlled junctions

No No No

No No No

No No No

No No No

No No No

No No No

No No No

No

No

No

No

No

No

No

No

No

No

wetland. Quality of Nong Douang wetland has been severely affected as a result from urban wastewater discharge and converting land for commercial building construction. Full description of the development proposal (IEE with EMP) will be required. 6. Mangrove 7. Estuarine 8. Buffer zone of protected area 9. Special area for protecting biodiversity 10. Bay B. Potential Environmental Impacts 11. Deterioration of surrounding environmental conditions due to rapid urban population growth, commercial and industrial activity, and increased waste generation to the point that both manmade and natural systems are overloaded and the capacities to manage these systems are overwhelmed? 12. Degradation of land and ecosystems (e.g. loss of wet-

No

No

No

No

No

No

No

No

No. But, necessary preventive measures will be addressed in EMP.

No

No

No. Positively, it will enhance green environment and less traffic congestion

No. The proposed project will significantly improve the surrounding environment, particularly facilitating traffic flow and road safety.

No

No

No. But, description of the development proposal (with EMP) will be required.

No. If new car park will be built, full description of the development pro-

No. The proposed project does not require a physical change of

No

No. No land acquisition required for the proposed project.

No

No

163


Appendix 12 Annex 3 SCREENING QUESTIONS

SUB-PROJECTS 1. Multi-story car park for park and ride on east and west edges of core area

lands and wild lands, coastal zones, watersheds and forests)? 13. Dislocation or involuntary resettlement of people

14. Degradation of cultural property, and loss of cultural heritage and tourism revenues?

15. Occupation of lowlying lands, flood plains and steep hillsides by squatters and low-income groups and their exposure to increased health hazards and risks due to pollutive industries? 16. Water resource problems (e.g. depletion/degradation of available water supply, deterioration for surface and ground water quality, and pollution of receiving waters?

2. Traffic management action area plan for market/Nong Chan Zone posal (IEE with EMP) will be required.

3&12. Review and rationalisation of parking restriction areas and Road markings landscape.

4&5. Woonerf street improvements in 5 streets and near Nam Phou fountain.

6. Street improvementvarious

7. Pedestrian light crossings facilities

10. Improvements at non-light-controlled junctions

Yes. If the proposed construction will be built in the water park compound or private lands. Compensation/resettlement plan will be required for Affected Persons No

No

No. No land acquisition work required.

No. But, necessary mitigations to assist shop owners along the proposed routes during the construction needs to be addressed in EMP.

No

No. No land acquisition work required.

No. But, description of the development proposal (IEE with EMP) will be required.

No

No. Some shops may lose revenues from selling goods to customers as their customers may not be allowed to park cars in front of their shops if it is in the red zone. However, this will be a minor impact.

No

No

No

No

No

No

Yes. Loss of tourism revenues will be temporary and minor impact for shops located along the proposed routes during the co nstruction. Appropriate mitigations to assist shop owners will be addressed in EMP. No

No

No

No

No. But, necessary preventive measures will be addressed in EMP to prevent runoff water from the parking not to be di rectly discharged into the wetland.

No

No. But, ensure that proper mitigations monitoring programme will be fully addressed in EMP.

No

No

No

No

164


Appendix 12 Annex 3 SCREENING QUESTIONS

SUB-PROJECTS 3&12. Review and rationalisation of parking restriction areas and Road markings No

4&5. Woonerf street improvements in 5 streets and near Nam Phou fountain. No

6. Street improvementvarious

7. Pedestrian light crossings facilities

10. Improvements at non-light-controlled junctions

No

No

No

No. But, description of the development proposal (IEE with EMP) will be required

No

No

No

No

No

Yes. Possible, ensure that proper mitigations monitoring programme will be fully addressed in EMP.

No. But, description of the development proposal (IEE with EMP) will be required

No

No

No

20. Traffic disturbances due to construction material transport and wastes?

Yes. Possible, ensure that proper mitigations monitoring programme will be fully addressed in EMP.

No

No. The proposed project will facilitate a better flow of urban transport.

21. Temporary silt runoff due to construction?

Yes. Possible, ensure that proper mitigations monitoring programme will be fully addressed in EMP.

No

No. But, ensure that during the construction proper mitigations monitoring programme will be fully addressed in EMP. No

Yes. Possible, ensure that proper mitigations monitoring programme will be fully addressed in EMP. No. But, description of the development proposal (IEE with EMP) will be required.

22. Hazards to public health due to ambient, household and water depletion and/or degradation?

No

Yes. Possible, ensure that proper mitigations monitoring programme will be fully addressed in EMP. No

Yes. Possible, ensure that proper mitigations monitoring programme will be fully addressed in EMP. Yes. Possible, ensure that proper mitigations monitoring programme will be fully addressed in EMP. No. But, description of the development proposal (IEE with EMP) will be required.

No

No

23. Overpaying of ground water, leading to land subsidence, lowered ground water table, and salinization? 24. Contamination of surface and ground waters due to improper waste disposal?

No

No

No. But, description of the development proposal (with EMP) will be required.

No. But, description of the development proposal (IEE with EMP) will be required.

17. Air pollution due to urban emissions? 18. Road blocking and temporary flooding due to land excavation during rainy season? 19. Noise and dust from construction activities?

1. Multi-story car park for park and ride on east and west edges of core area

2. Traffic management action area plan for market/Nong Chan Zone

No. But it will become a problem for the city in the future. The iss ue will be addressed in the EMP. No

No

No. But, ensure that proper mitigations monitoring programme relating to road marking works will be fully addressed in EMP. No

No

Yes. Possible, ensure that proper mitigations monitoring programme will be fully addressed in EMP. Yes. Possible, ensure that proper mitigations monitoring programme will be fully addressed in EMP. Yes. Possible, ensure that proper mitigations monitoring programme will be fully addressed in EMP. No

No

No

No

No

No

No. But, description of the development proposal (IEE with EMP) will be required.

No. But, description of the development proposal (IEE with EMP) will be required.

No

No. But, description of the development proposal (IEE with EMP) will be required.

165


Appendix 12 Annex 3 SCREENING QUESTIONS

25. Pollution of receiving waters resulting in amenity losses, fisheries resource depletion, and health problems? 26. Social conflicts between co nstruction workers from other areas and local workers? 27. Large population influx during project construction and operation that causes increased burden on social infrastructure and services (such as water supply and sanitation systems)? 28. Risks to community health and safety due to the transport, storage, and use and/or disposal of materials during operation and construction?

SUB-PROJECTS 1. Multi-story car park for park and ride on east and west edges of core area

2. Traffic management action area plan for market/Nong Chan Zone

4&5. Woonerf street improvements in 5 streets and near Nam Phou fountain. No

6. Street improvementvarious

7. Pedestrian light crossings facilities

10. Improvements at non-light-controlled junctions

No

3&12. Review and rationalisation of parking restriction areas and Road markings No

No

No

No

No

No. But, description of the development proposal (with EMP) will be required.

No

No

No

No

No

No. But, description of the development proposal (with EMP) will be required.

No

No

No

No

No. Construction activities will be small sca le. Workers from the outside the area may not be necessary. No

No. But, description of the development proposal (with EMP) will be required.

No. But, description of the development proposal (IEE with EMP) will be required

No. But, ensure that proper mitigations monitoring programme relating to road safety works will be fully addressed in EMP.

No. But, description of the development proposal (IEE with EMP) will be required.

No. But, description of the development proposal (IEE with EMP) will be required.

No. Positively, it will enhance safety of pedestrians when crossing roads

No. But, description of the development proposal (IEE with EMP) will be required.

166

No


Appendix 13 INDICATIVE IMPLEMENTATION PLAN Year Items

Phase

2010 I

I. 1 2 3 4 5 6 7 8 9 II.

II

III

2011 IV

I

II

III

2012 IV

I

II

III

2013 IV

I

II

Project Preparation Reconnaissance Mission TA Report Preparation Prepare TOR for PPTA Consultant Prepare and Approve Concept Paper Recruitment of PPTA Consultant(s) Implementation of PPTA Grant Fact-Finding Mission Finalize Approval of RRP ADB Board Approval

Implementation 10 Recruitment of Implementation and Monitoring Consultant 11 Commence Implementation and Monitoring Consultant Services 12 Finalize Civil Works Designs, Advertise, Tender and Award Package(s) 13 Finalize Vehicle and Equipment Procurement Documents, Advertise and Award Packages 14 Construct Civil Works Improvements 15 Deliver, Test and Commission Vehicles and Equipment Procurements 16 Equipment and Vehicle O & M Training & Preparation Final Report 17 Completion Implementation and Monitoring Consultant Services

III.

Operation and Maintenance 18 Recruitment of Capacity Development Consultants & Chief Technical Advisor (CTA) 19 Deliver Capacity Development Consultant Services: - Design & Carry Out Awareness Raising and Participation Program - Design & Carry Out Awareness Raising & Training of Pilot EST Supervisory Board Members & PEA Staff - Chief Technical Advisor for PEA

167

III

2014 IV

I

II

III

2015 IV

I

II

III

2016 IV

I

II

III

2017 IV

I

II

III

2018 IV

I

II

III

2019 IV

I

II

III

IV


Appendix 14

STAKEHOLDER WORKSHOP 1 COMMENTS AND PROJECT RESPONSE P0F

Workshop Discussion Group 2

Category

1

1

Policy

2

1, 2

Policy

No.

P

Description of Comment/Issue

Project Response

Vehicle Growth. The majority thought private vehicle growth should be controlled: the means could be a quota system or fiscal measures (e.g. a tax or import duty). One minority opinion considered this would only yield a short-term solution: quotas would not be tolerated for long without an acceptable alternative mode of travel; an import duty would be unfavorable to Lao PDR’s application to join World Trade Organization, and under the terms of the ASEAN Free Trade Agreement might need to be removed in 2015.

Ownership and use of private motor vehicles need to be distinguished. The pilot VSUTP aims at reducing the vehicles use in the core area by a combination of parking policy and public transport (bus loops). The parking policy targets a substantially higher cost of parking in the core area to reflect its scarcity; linked external parking and bus service will be made a more cost effective and convenient mode of access to the core area; and combined pedestrianism and bus loops will be promoted as a key strategy for improved attractiveness and livability of the city core. Controlling the growth of private vehicle ownership should be the subject of a careful policy appraisal, more appropriately as a separate exercise to the project, before being undertaken. All of the coordination policy issues are central to the success of the VSUTP. All

P1F

U

U

Coordination. (i) need to reinforce coordination policy among transport, road U

U

1

Work shop was held on 25 January 2011 Discussion Group 1 primarily consisted of the more senior workshop participants, and dealt with PEA institutional, funding and capacity development issues; Discussion Group 2 dealt primarily with the affectivity and efficiency of the identified Public Transport Service (Red and Blue Shuttle Bus Loops in Core City Area); and Discussion Group 3 dealt with the appropriateness, affectivity and efficiency of Identified Traffic Management Sub-projects (as per Report, Table A6.10).

2

168


Appendix 14

No.

Workshop Discussion Group 2

Category

Description of Comment/Issue

Project Response

and traffic/enforcement agencies; (ii) the Director General, DOT at MPWT proposed making better use of the three existing high-level committees dealing with transport-related issues can serve to strengthen coordination: the National Road Safety Council (chaired by a Deputy PM), the National Transport Committee (chaired by a Deputy Minister of MPWT) and the National Committee for Cross-border Trade and Transport (chaired by a Deputy PM); and (iii) coordinated policy between urban planning and urban transport agencies needs to be improved; particularly since the agencies are in the same ministry (MPWT).

such coordination issues need to be clearly addressed in the Memorandum of Understanding to be drafted for the establishment of the PEA.

Transport/Social Policy. Government policy with regard to urban public transportation, towards subsidies and related issues should be designed to promote the social welfare and to solve social problems. Traffic Management. Traffic management policy should be adjusted to include consideration of the following: (i) the use of pedestrian underpasses in lieu of pedestrian overpasses in order to maintain historical environment, and also consider the use of additional “underpasses� to improve road safety; (ii) to upgrade and improve additional intersections, not just those proposed in the TA report; (iii) to consider additional parking areas along Fa Ngun Street by expanding the size of the 3 existing parking areas; and (iv) consider parking areas designated for tour buses.

This is taken up in the project design.

One-Way Streets The present one-way street policy should be studied in order to determine if the present utilization of one-way street pattern should be revised. This would have to be coordinated with planned implementation of the public transport and traffic management components of the VSUTP

This is a well-considered comment that should be followed up during the PPTA phase of the project, in conjunction with additional traffic volume surveys and origin and destination surveys.

P1F

3

2

Policy

4

3

Policy

5

2

Policy

U

U

U

U

169

(i) This comment is noted for consideration of the PPTA, including developing feedback from focus groups as to the social acceptability/safety of underpasses particularly at night. (ii) Upgrading of additional intersections is noted for consideration of the PPTA. (iii) and (iv) should be studied and appraised in the PPTA.


Appendix 14 Workshop Discussion Group 2

Category

6

2

Policy

7

1, 2, 3

Institutional

8

1

Financial

9

2

Financial

No.

Description of Comment/Issue

Project Response

Future Bus Shuttle Loops A Government policy should be adopted as soon as possible to encourage not only implementation of the Red and Blue bus loops, but also future loops as indicated in the TA report.

Planning of future loops should be considered as part of the PPTA. Such future loops would be phased in after implementation of the Red and Blue loops.

Pilot EST Agency. (i) All groups understood the purpose and need for a Pilot EST Agency’s (PEA) to act as a pilot integrated urban transport agency responsible for traffic, parking and public transport in the pilot core area; (ii) All groups agreed with its establishment under a (transparent) memorandum of understanding among stakeholders and a supervisory board manned by the stakeholders’ representatives; (iii) use of traffic control officers by the PEA should follow an agreement with the police, with regard to the responsibility and limits of authority of traffic control officers; and (iv) the PEA must report to the Government

This is taken up in the project design.

Lao PDR Budget Law. Agreed with the proposal for a special levy such as an EST Tax to fund the PEA capital and operation and maintenance, but the group noted that the funding mechanism will have to comply with the Lao PDR state budget law

The draft of the EST Tax Law to be carried out by the PPTA consultant will take into consideration state budget law, and other pertinent laws and regulations.

Operations and Business Plan. Agreed with the concept of a PEA, but that the operation of the PEA should be based on a clear operations and business plan, and if subsidies from government are to be utilized (fuel tax, exemption from import tax on parts for bus maintenance, etc.), such subsidies should be clearly indicated in the business plan.

A fundamental principle governing the PEA will be that operations are based on a clear and transparent business plan, developed in the public interest and professionally implemented. The draft PEA MOU will include a clear statement of this principle. Details of the fare are still to be finalized. The suggestion will be considered in project preparation.

P1F

10

Financial

U

U

U

U

U

U

Shuttle Loop Bus Fare. The suggested Kip 2,500 fare for the shuttle bus system should be rounded to the nearest thousand Kip, i.e. use Kip 3,000 U

U

170


Appendix 14 Workshop Discussion Group 2

Category

11

2

Regulatory

12

1

Regulatory

13

3

Regulatory

14

1

Regulatory

15

3

Regulatory

16

2

Regulatory

No.

Description of Comment/Issue

Project Response

P1F

Public Transport Law. The is a need for a Public Transport Law for the country EST Law. The need for an EST Law was supported, with the understanding that it should be a clear and transparent statement of state policy, and as a tool for implementing the same (state) policy

Noted for consideration in the PPTA.

Transparency. Any new laws, regulations, etc. to be implemented under this new PEA program must be transparent,, including public participation, adequate publication and dissemination of new laws/regulations, and additional street side signing as necessary. Existing regulations on parking, traffic management and public transport are adequate. Experience during the 25th SEA Games in Vientiane shows that, given the right motivation, the capital’s transport system can function well. To achieve the same result every day however means overcoming challenges that will require a permanent commitment to traffic management and enforcement of existing traffic and parking regulations.

The principle is assumed in the project design.

New Major Commercial Developments. New major retail and other commercial developments (Big C, etc.) should not be permitted in the core area, and wherever they are located they should follow zoning and urban master plan provisions. Integration with Existing Urban Planning Regulations. Implementation of bus loop shuttles must be integrated with existing urban planning parking space regulations, i.e. 1366/MPWT: hotels must provide 1 off-street parking space for each 3 hotel rooms, and restaurants must provide 1 off-street parking space for each 3 square meters of restaurant space.

The project design assumes that the authorities will implement approved and published urban plans in land use permitting.

U

U

U

U

U

U

U

U

171

The principle is assumed in the project design.

This is taken up in the project design.

Parking is a key part of the integrated urban transport solution of the pilot VSUTP, which will incorporate an appropriate parking policy.


Appendix 14 Workshop Discussion Group 2

Category

Description of Comment/Issue

Project Response

17

3

Regulatory

New regulations should be considered/established to promote use of public transport by students, not only to reduce the number of trips into the core area, but also to improve traffic safety (presently student driven motorcycles have a high accident rate).

The principle is taken up in the project design; details will be studied in the PPTA.

18

2

Regulatory

Revision of regulation of “Time Release” for vehicles involved in road accidents, as required to satisfy certain vehicular insurance regulations pertaining to accident investigations, should be part of integrated traffic management (reform).

This is a constructive comment for the improvement traffic management. The legality and the practicality of this issue needs to be studied during the PPTA.

19

1

Other

This suggestion will be taken up in the PPTA.

20

2

Other

Selection of Core Area. The choice of the city core for the pilot project needs to be better explained in terms of the capital’s urban transport master planning. Extension of Red Bus Loop The Red Bus shuttle loop should be extended to the west to provide service to existing developments (Parkview Hotel, Novotel, Mekong Hotel, schools, etc.)

No.

P1F

U

U

U

This extension was considered during this TA; but the existing geometry with regard inadequate weaving and merging distances and the location of the bus stops for the 180o left turn west of the Parkview Hotel made such an extension unsafe. It should be further studies during the PPTA. P

21

2

Other

22

2

Other

Awareness and Promotion Campaigns. The implementation of the program must include well designed awareness and advertisement campaigns to promote the pilot bus shuttles. Red and Blue Bus Shuttles. Also introduce school buses to reduce trips into the core area; bus frequency as indicated in the TA report is sufficient; but strict enforcement of parking will be required to make it successful. U

U

U

172

P

This is included in the project design.

The suggestion is aligned with the project design objectives.


Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.