ÂŚCONSTRUCTION UPDATE Biomass Power
Pellets
Biogas
Advanced Biofuel
Green Whey Energy Location
Turtle Lake, Wis.
Biogas production capacity
868 scfm
Engineer/builder
Ecolab & Symbiont/Miron Construction
Biogas end use
Electricity production
Substrate(s)
Waste water
Installed power capacity
3.2 MW
Digester type
Upflow
Groundbreaking date
January 2013
Gas cleaning technology
Unison Gas Conditioning System
Start-up date
July 2013
Concrete work is complete, and piping is nearly complete. Precommissioning work underway.
Location
New Franklin, Ohio
Biogas production capacity
195 scfm
Engineer/builder
Quasar Energy Group
Biogas end use
Electricity, heat
Substrate(s)
Food waste, FOG, biosolids
Installed power capacity
810 kW
Digester type
complete mix
Groundbreaking date
May 2013
Gas cleaning technology
NA
Start-up date
September 2013
On schedule, working towards substantial completion by Sept. 30.
Green Whey Energy, Turtle Lake, Wis.
PHOTO: ENERKEM
Quasar Energy Group - Barberton