July 2013 Biomass Magazine

Page 12

ÂŚCONSTRUCTION UPDATE Biomass Power

Pellets

Biogas

Advanced Biofuel

Green Whey Energy Location

Turtle Lake, Wis.

Biogas production capacity

868 scfm

Engineer/builder

Ecolab & Symbiont/Miron Construction

Biogas end use

Electricity production

Substrate(s)

Waste water

Installed power capacity

3.2 MW

Digester type

Upflow

Groundbreaking date

January 2013

Gas cleaning technology

Unison Gas Conditioning System

Start-up date

July 2013

Concrete work is complete, and piping is nearly complete. Precommissioning work underway.

Location

New Franklin, Ohio

Biogas production capacity

195 scfm

Engineer/builder

Quasar Energy Group

Biogas end use

Electricity, heat

Substrate(s)

Food waste, FOG, biosolids

Installed power capacity

810 kW

Digester type

complete mix

Groundbreaking date

May 2013

Gas cleaning technology

NA

Start-up date

September 2013

On schedule, working towards substantial completion by Sept. 30.

Green Whey Energy, Turtle Lake, Wis.

PHOTO: ENERKEM

Quasar Energy Group - Barberton