April 2014 Biomass Magazine

Page 12

Biomass CONSTRUCTION UPDATE Biomass Power

Pellets

Biogas

Advanced Biofuel

Q1: A Quarter of Progress and Completion by Kolby Hoagland

The Q1 2014 Biomass Construction Update celebrates the start of commercial operation for five bioenergy installations: DTE Stockton LLC, Gainesville Renewable Energy Center, Enviva Pellets Northampton LLC, Hometown Bioenergy LLC and KB Bioenergy. These five plants represent a total of 156.7 MW of biomass power and 500,000 metric tons of pellet capacity. The terms that define a plant's completion and start of “commercial operation” vary greatly among the four sectors covered in the Biomass Construction Update: biomass power, pellets, biogas and advanced biofuels. Multiple and varying factors influence when a project completes construction and begins commercial operation. For biomass power, start up is defined as a multistep process that begins during commissioning, and continues after the plant is supplying electricity to the grid. This is done to ensure that the power plant can dependably supply electricity to the grid. Regulation and the technological intricacies of power generation and supply require a slower start up than other sectors. Commissioning and start up of advanced biofuel plants and biogas facilities require synchronization of microbial communities and industrial processes. Abengoa’s Kansas cellulosic ethanol plant, for example, has a 21-MW biomass power plant installed in line with the pretreatment, fermentation and distillation processes necessary for producing cellulosic ethanol. Naturally, the more complex a project's design and base technology, the

DTE Stockton LLC, DTE Energy Location

Stockton, Calif.

Engineer/builder

Project Complete

Gainesville Renewable Energy Center PHOTO: GREC

more time required to bring the project into commercial operation. Contracts also play a large part in when a plant is considered complete and ready to sell bioenergy products and services into its respective market. Regulators and funders often set financial benchmarks and performance requirements that tie to funding. The capital, time, and coordination needed to bring a project to successful completion is not a feat with a clear finish line, but a period of time during which achieving a number of small goals denotes enormous accomplishments. If you would like your construction accomplishments covered by Biomass Magazine, please send an email to khoagland@bbiinternational.com.

Gainesville Renewable Energy Center, American Renewables LLC Location

Gainesville, Fla.

ESI Inc., DTE Stockton, LLC

Engineer/builder

Fagen Inc.

Primary fuel

Woody biomass

Primary fuel

Woody biomass

Boiler type

Stoker

Boiler type

Bubbling fluidized bed

Nameplate capacity

45 MW

Nameplate capacity

102.5 MW

Combined heat & power

Yes

Combined heat & power

No

Government incentives

NA

Government incentives

Federal 1603 grant

IPP or Utility

IPP

IPP or utility

IPP

Groundbreaking date

September 2011

Groundbreaking date

Q3 2011

Start-up date

December 2013

Start-up date

December 2013

The project is complete and operating commercially.

GREC is now operating commercially.

Atikokan Generating Station, Ontario Power Generation Inc. Location

Atikokan, Ontario, Canada

Engineer/builder

Aecon, Doosan, Nordmin

Primary fuel

Industrial pellets

Boiler type

Suspension fire system

Nameplate capacity

211 MW

Combined heat & power

No

Government incentives

10-year PPA

IPP or Utility

Provincial utility

Groundbreaking date

October 2012

Start-up date

Q2 2014

Boiler controls commissioning is underway. Silo mechanicals are 80 percent complete, and transfer tower electrical and cladding are proceeding.

12 BIOMASS MAGAZINE | APRIL 2014

Atikokan Generating Station PHOTO: ONTARIO POWER GENERATION INC.

Project Complete


Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.