PHASE II PROJECT DESCRIPTION • Milling and resurfacing of CR 241 from SR 235 North to CR 236. • Construction of 4’ bike lanes (both directions). Phase II of this project is a milling and resurfacing of CR 241 from CR 236 to SR 235. Construction consists of 2 bike lanes (4 feet wide), striping, turn lane and drainage. Construction is expected to last 90 calendar days and cost $3,300,000. Funding for this project comes from Gas Tax Bond revenues that had been approved by the Board in April 2005.
28
ALACHUA COUNTY PAVEMENT MANAGEMENT PROGRAM UPDATE REPORT
JUNE 24, 2010