Introduction: We are writing to inform you of the current progress on the project and also advise you of the work being planned over the next two months. We believe communication is key and by you raising any issues with us as soon as possible, we can ensure that any matters are promptly resolved.

Progress on site: Works completed so far: • •

• • • •

Site set up & demolition Sheet piling adjacent to existing aquarena Piled foundations Basement slab construction Temporary dewatering Diving pool structure

Works coming up: The principle activities to take place over the next few months comprise largely of reinforced concrete substructure works to the following elements of the project: • • • • • •

The basement plant room walls The competition pool and leisure pool structures Underground plenums that serve the air handling to the swimming pool halls The suspended ground floor slab above the plant room and plenums External underground drainage around the building External retaining walls


Worthing’s New Pool Newsletter to all Local Residents

Delivering your pool on behalf of

January / February 2012 Worthing Fire and Rescue service plan to undertake a trial rescue plan on the tower crane in the near future. Please do not be alarmed if you do happen to witness this operation as our crane driver will not be injured. If there are any concerns or queries you have on these or any other matters with the construction works then please do not hesitate to contact one of our site team. Inevitably, you will experience some disturbance as a result of this work but our aim is to minimise this as much as we can.

Lawrence Wilson Project Manager

Site team contact details: Generally large deliveries of materials and plant access into and egress from the site are through the vehicle gates off Brighton Road. On a few occasions over the next two months we may also need to use the site entrance on the corner of Merton Road / New Parade for certain works. This will include a few concrete pours to the southern end of the site. We will try to keep these to a minimum and strive not to cause any inconvenience to the residents of these roads. We also apologise to any users of the raised public footpath between our site and the Aquarena that were affected by it’s closure for a number of days during the first week of January. Unfortunately we will need to close off access again for a short period of time whilst we undertake some modifications to the hoarding during the middle part of January.

Lawrence Wilson Project Manager 07812 961883 Lawrence.wilson1@morgansindall.com

Stuart Carruthers Site Manager 07813 056809 stuart.carruthers@morgansindall.com

Worthing Borough Council, Morgan Sindall and the professional team celebrate the start of the construction works. For more information on the Pool visit www.worthing.gov.uk and meanwhile don’t forget it is business as usual at the Aquarena.

www.morgansindall.com

New Pool Newsletter 2012  

Worthing’s New Pool Newsletter to all Local Residents

Read more
Read more
Similar to
Popular now
Just for you