Page 1

GPS Project Timeline complete

Phase I Implementation

Mar-12

Appoint and form the implementati on teams

Apr-12

May-12

Jun-12

Jul-12

by 5/18/12 Develop Transition Plan

Set up team meetings/ launch meeting

Aug-12

ongoing

Sep-12

Oct-12

iterative

Nov-12

unplanned

Dec-12

June - Iterative Process Improvement – Map current process->Develop future state->Implement improved process

End of May - OngoingProcess Mapping Applied Training End of January - Ongoing Change Management - ADKAR training, coaching, assessment, etc.

Phase II Design Mar-12 Form PhaseII project team

GPS PhaseII kick-off meeting

Prepare and approve the project and change management plan BPD, LLC and CPA team meet with Executive sponsor

Apr-12

May-12

End of April Future vision/ relationship between BPD& CPD

Jun-12

Jul-12

End of June Process Inventory (SIPOC, RACI, Function areas)

Aug-12

End of July Articulate criteria and create the potential structure

Bi-monthly ADKAR

Sep-12

Oct-12

End of September Decision Validation

Bi-monthly ADKAR

Mid February - Ongoing Determine/Obtain additional information and data – survey, consultation, CAUCE, external scan, etc.

End of February - Ongoing Communication Plan – audience, method, time, key message, etc. End of February - Ongoing Change Management - ADKAR training, coaching, assessment, etc. Page 1

Nov-12

Dec-12

unplanned

in progress

GPS Timeline  

This is the timeline for the GPS project