AIT Waste Water Treatment Facility: Activity Attributes
ID: 1033 Activity: Prepare Stakeholder Register Description of Work: Responsible party: TNLS This activity involves the preparation of a comprehensive list of all the stakeholders, and their importance to the project is stated. Also, their expectations for the project are identified
Activity Predecessors:
Lead or Lag:
Activity Successors:
Lead or Lag:
Prepare Project Charter
No lead or lag
Stakeholder Management Strategy Prepare Communication Management Plan
No lead or lag
Activity Cost â‚Ź 142.50
Activity effort: 3.2 Hours
No lead or lag
Activity Resource Requirements
ID: 1034 Activity: Prepare Stakeholder Management Strategy Description of Work: Responsible party: TNLS This activity involves the determination of how groups of stakeholders and/or individual stakeholders incorporated in the project.
Activity Predecessors:
Lead or Lag:
Prepare Stakeholder Register
No lead or lag
Activity Cost â‚Ź 90.00
Activity effort: 2.0 Hours
18
Activity Successors:
Lead or Lag:
Activity Resource Requirements