Contractors State License Board Makes New Mechanics Liens Forms Available Forms (attached) took effect July 1, 2012 SACRAMENTO – The

Contractors State License Board (CSLB) wants to inform licensees of changes in the state’s mechanics lien law effective July 1, 2012. While these changes don’t substantially change the laws, they do change the wording and formats of the notice and lien release forms required to protect contractors’ lien rights. The new law replaces the 20-Day Preliminary Notice with the Preliminary

Notice. Sub-

contractors and materials suppliers should use the newly-worded forms. The Preliminary Notice should be delivered to the homeowner in person or by certified, registered, or first-class mail, with a receipt of the mailing as proof. You may give notice any time before work starts or product is delivered and up to 20 days after. If the Preliminary Notice is given more than 20 days later, you are only able to receive payment for work or products supplied 20 days before notice was given, and anytime thereafter. The Notice of Mechanics

Lien wording is also changed in the new law. This notice must ac-

company the claim of lien and be sent via certified, registered, or first-class mail, with the receipt as proof of mailing. Failure to send the notice with the claim could result in the lien being unenforceable. The conditional and unconditional lien release forms have also changed. Make sure you have subcontractors and suppliers sign the new conditional forms as progress payments are owed and when the project is finished before they are given final

payment. Have them sign the new

unconditional release forms when they receive progress payments and their final payment. The new law gives the homeowner 15 days instead of 10 to file a notice of completion with the county recorder. If notice is filed, the contractor has 60 days and subcontractors 30 to record a lien. If there is no notice filed all parties have 90 days to record a lien.

— REGISTER TODAY! —

Mechanic’s Lien Seminar presented by Construction Attorney, Dan McLennon

Wednesday July 25th, 2012 8:30 AM to 10:30 AM click

here for details


www.marinba.org ◆ mba@marinba.org

Wednesday, July 25 8:30AM – 10:30AM Mechanic’s Lien Law basics and recent changes

Thursday, August 2 Golf Tournament

August 10th

7:30PM

Night at the Ballpark San Rafael Pacifics vs. Sonoma County Grapes

Thursday, August 16 8:00AM – 5:00PM EPA’s new renovation, repair and painting rule (RRP)

Marin Builders Association ◆ Weekly Bulletin ◆ Page 2


www.marinba.org ◆ mba@marinba.org

in this issue

PROJECT OF THE WEEK

New Mechanics Lien Forms ...............1 MBA Calendar ......................................2

Marin County Dept. of Public Works

Directors

Invitation to bid

.............................................4

Golf Tournament ................................6

LUCAS VALLEY ROAD SLIDE REPAIR PLAN 493

Kalb’s Q & A

.................................8

Phil Vermeulen ....................................9 MBA Carwash Fundraiser

Sealed proposals will be received until

...............11

Safety Topic: Material Handling

......12

The Material Difference: HLC

.......15

Permits

.........................................19

Thursday, August 9th @ 3:00PM

Completions & Liens ........................22

at the Clerk of the Board of Supervisors, Room 329 Marin County Civic Center, San Rafael, California 94903

Bid Results ..........................................32

Project Bid Schedule ..........................25

Classifieds ..........................................33

No pre-bid meeting is scheduled and the Engineer’s estimate for this project is $350,000.

Membership Application ...................34

Plans and specifications may also be purchased for $50.00 per set (nonrefundable).

_____________________

Subscribers to the MBA On Line Plan Service can access this project online and it is also available to members in the on-site plan room. Work will involce a Cast-In-Drilled-Holes (CIDH) retaining wall on Lucas Valley Road 300 feet west of MP 4.75. A Class “A” license is required. For questions regarding this project and/or plans and specifications, call (415) 473-7877.

contact MBA 660 Las Gallinas Avenue San Rafael, CA 94903 ◆ Office: 415-462-1220 Fax: 415-462-1225 ◆

www.marinba.org mba@marinba.org

Marin Builders Association ◆ Weekly Bulletin ◆ Page 3


www.marinba.org ◆ mba@marinba.org

Protecting More.

Attaining More.

2012 MBA Directors & Officers President Aimi Dutr a - The Dutr a Group

ConstruCtion & real estate attorneys

Chief Financial Officer jim Schalich - Schalich Brothers Construction

talk to Glenn free telephone Consultations for Marin Builders assoCiation MeMBers

Glenn M. Smith 707.522.1100 www.smithdollar.com ContraCt issues

MeChaniC’s liens

stop notiCes

Vice President Jeff Mertel - Mertel Carpets, Inc.

Secretary Tyler Doherty - Cal West Rentals, Inc. PAST PRESIDENT Dave Tr ahan - Patriot Mechanical Executive Director Klif Knoles

Bond ClaiMs

Herb Moran - MOC Insurance Services John Busick - Bob Kunst Painting Oliver Dibble - Dibble & Company Tom Barr - Ghilotti Bros., Inc. Mark Silvia - Marin Mechanical, Inc. Gary Frugoli - Construction Consultant Rob Scerri - Golden State Lumber Keith Dotto - Dotto Glass, Inc. Dick Ghilotti - Ghilotti Construction Company Dave Garbarino - Marin Sanitary Service, Inc Diane Henderson - DMH Land Use Planning Jeff Grady - Grady Financial, Inc.

MBA MEMBER

STAFF Paula Krause - Office Manager Barbara Jones - Membership Manager Diane Van Renselaar - Plan Room Technician Kellie Buono - Administrative Assistant/Reception Casey Mazzoni - Legislative Analyst/ Consultant The weekly bulletin is owned by MBA and is available at www.marinba.org 660 Las Gallinas Avenue, San Rafael, CA 94903 Publisher: Klif Knoles Publication Editor: And Them Design

Marin Builders Association ◆ Weekly Bulletin ◆ Page 4


www.marinba.org ◆ mba@marinba.org

– Brett Owner, Anytime Fitness Member since 1993

Owning a business can be complicated. We make it simple. Your partner in: Commercial Real Estate Small Business Loans

www.redwoodcu.org/business 1 (877) 545-4100 Marin Builders Association ◆ Weekly Bulletin ◆ Page 5


www.marinba.org ◆ mba@marinba.org

Marin Builders Association Annual Golf Tournament

Thursday ~August 2, 2012 Indian Valley Golf Course 3035 Novato Blvd., Novato, CA

Registration: 11:00 A.M. Lunch: 12:00 Noon Shot-Gun Start: 1:00 P.M. (Scramble Format) Dinner & Awards: 6:00 P.M. Cost: $165.00 per player (Includes lunch, green fees, cart, refreshments, dinner with wine and MARGARITAS on the course)

Dinner and wine only - $40.00 per person

ALL PROCEEDS BENEFIT MARIN BUILDERS ASSOCIATION SCHOLARSHIP FUND

Make your reservations early. Tournament limited to 144 players. Return registration form with payment to Marin Builders Association, 660 Las Gallinas Avenue, San Rafael, CA 94903 or fax to (415) 462-1225. Refund/Cancellation Policy: NO cancellations or refunds after Friday, July 27th. _________________________________________________________________________

Golf Reservation Form

Player ________________________

Company _____________________________

Index or Average Score ______

________________________

_____________________________

______

________________________

_____________________________

______

________________________

_____________________________

______

************************************************************************ *Pay by Visa, MasterCard or pay online www.marinba.org*

Company Name_______________________ Contact Person_____________________ Address ____________________________

Phone_____________________________

Check enclosed made payable to: Marin Builders Association Scholarship Fund □Visa □Master Card #___________________Expiration Date______ 3-digit code _____ Signature___________________________________ Marin Builders Association ◆ Weekly Bulletin ◆ Page 6


www.marinba.org ◆ mba@marinba.org

Annual Golf Tournament August 2, 2012

TEE SIGNS ~ $125 EACH Enclosed is a check for $________ for _____ tee signs.

RAFFLE PRIZE DONATION My company will donate the following raffle prize _________________

I am unable to participate, please accept my contribution to the Scholarship Fund

__$25 __$50 __$75 __$100 __Other ALL PROCEEDS BENEFIT MBA SCHOLARSHIP FUND *Pay by Visa, MasterCard or pay online www.marinba.org*

Company Name_______________________ Contact Person_____________________ Address ____________________________

Phone_____________________________

Check enclosed made payable to: Marin Builders Association Scholarship Fund □Visa □Master Card #___________________Expiration Date______ 3-digit code _____ Signature_____________________________________ The Scholarship Fund is a non-profit 501c(3) organization, Federal ID #94-2540274. All donations made to the Scholarship Fund are tax deductible; however, certain limitations may apply. Please consult with your tax professional regarding deductibility. Marin Builders Association ◆ Weekly Bulletin ◆ Page 7


www.marinba.org ◆ mba@marinba.org

Kalb's Q&A for Contractors

By David Kalb & Shauna Krause, Capitol Services, Inc.

We ‘heat’ up the discussion with contractors as a warning reminder to stay cool on the job this summer. Another contractor is concerned about what happens if his Qualifier gets thrown ‘under the bus’. A general gets advice on ‘covering’ his base, and more on the statewide crackdown on the economic ‘underground’…

the heaviest work first thing in the morning when heat exposure is less. Use mechanical equipment whenever possible to eliminate or reduce manual labor in the heat. Schedule frequent rest breaks in a cool spot or shade; have plenty of drinking water available (i.e. stay hydrated), and stay away from caffeinated drinks and alcohol. Finally, take precautions to protect your skin (hat, long sleeve clothing, etc.), eyes (sunglasses), and use sunscreen.

Q: I am President of this company and as we discussed, we intend on using “Bob” to be our qualifying person for our CA contractor’s license. That being said, what happens if “Bob” gets hit by a bus or leaves the company for any reason? What is the typical protocol for companies in dealing with this issue? Look forward to your response.

Dubbed, “Operation Underground”, investigators from the Contractors State License Board (CSLB), Department of Insurance (CDI), Employment Development Department (EDD) and county District Attorneys’ offices partnered for a series of sweeps at suspected illegal construction sites on June 20 and 21, 2012. Sweeps were conducted in 11 counties, where over 100 enforcement actions were issued for, among other things: failure to carry Worker’s Compensation insurance; under-reporting the number of workers to obtain cheaper insurance premiums; and cash payments to avoid payroll withholding taxes.

A: The State of CA has a procedure in place should your qualifying individual (in this case “Bob”) leave or be unable to continue as your Qualifier for any reason. The Contractors Board will give a company 90 days to replace this individual, during which time the license remains in good standing as if the Qualifier were still there. Q: We are bidding a public works project for new construction. The question came up: Can an “A” License contractor install exterior fire service items or does it require a “C-16” license? What research I found, I don’t see where the “C-16” license is necessary because I hold an “A” general license, but I want to make sure I’m covered. A: Your covered! General Engineering (“A”) contractors can self-perform the installation of exterior fire service items like water mains, fire hydrants, and other related fixed works requiring specialized engineering knowledge and skill. WARNING! It’s the time of year when temperatures can rise to over 100 degrees. The summer sun is more direct and radiant heat from the sun and ground (concrete, asphalt, etc.) can take its toll on construction workers. MOST IMPORTANTLY, know the symptoms of heat stress, heat exhaustion and heat stroke.

“Participants in the state’s underground economy are harmful to everyone,” said CSLB Registrar Steve Sands. “Anyone who neglects their responsibility to comply with state contracting, insurance, and payroll requirements drives up premiums. At the same time, legitimate licensed contractors struggle because illegal operators underbid them.” According to Insurance Commissioner Dave Jones, “Operation Underground is a result of the partnership under the Joint Enforcement Strike Force to aggressively combat the underground economy”. Jones stated, “Legitimate businesses that play by the rules are often forced to close their doors because illegal businesses are cheating the system.” While knowledge is power, knowing where to go for the answers is half the battle. Get expert assistance immediately when you call 866-443-0657, email info@cutredtape.com, or write us at Capitol Services, Inc., 1225 8th St. Ste. 580, Sacramento, CA 95814. Research past columns at www.cutredtape.com.

As most readers know, it’s recommended that you try to perform

Marin Builders Association ◆ Weekly Bulletin ◆ Page 8


www.marinba.org◆ ◆mba@marinba.org mba@marinba.org www.marinba.org

Will The Train Ever Leave the Station?

5 Reasons the California High-Speed Rail Project Shouldn’t get More Money BY Phil Vermeulen, Governmental Relations

Also In This Update • Cal OSHA’s Most Common Citations in 2011 • ARB Off-Road Regulation: Two engine vehicles and labeling updates - Revised

Will The Train Ever Leave the Station? California lawmakers may have given their OK to what would be the nation’s first high-speed rail line, but the project is still a long way from leaving the station (if it ever does in the first place). Among the challenges project supporters must overcome are environmental concerns, clashes with local leaders over land use, a $68 billion price tag with no funding guarantees and an increasingly disenchanted public.

an IIPP, if you have 10 or more employees, it must be in writing. Conversely, if you have less than 10 employees, the IIPP can be verbal, but documenting that you verbally provided your employees with the required information is a questionable solution at best.

Following are the 25 most frequently issued citations:

Supporters applauded Friday when the senate narrowly (it passed with just the required 21 votes) approved billions in funding for an initial train segment in the agricultural Central Valley, enabling the state to tap $3.2 billion in federal bond money. Critics already are redoubling their efforts to defeat the project, which would be central to the legacy of Gov. Jerry Brown. Stay tuned as this story continues to unfold. Cal OSHA’s Most Common Citations in 2011 The new director of CAL OSHA, Ellen Widess (whom we strongly supported in her confirmation hearings before the Legislature several months ago) has released a list of Cal OSHA’s most common citations in 2011 (shown at the end of this story). I provide this to you as a “Take Heed!” Far and away the number one citation filed against businesses was for not having an Injury and Illness Protection Plan [IIPP]. It should be noted that the fine can reach up to $5000 for being cited for this violation. The next largest number of citations were written for the lack of content in the IIPP. While all businesses are required to have

The Injury and Illness Prevention Program (IIPP) is a basic written workplace safety program. Title 8 of the California Code of Regulations (T8CCR) section 3203, requires every employer to develop and implement an effective IIPP. An effective IIPP improves the safety and health in your workplace and reduces

Marin Builders Association ◆ Weekly Bulletin ◆ Page 9


www.marinba.org ◆ mba@marinba.org costs by good management and employee involvement. The 8 required Injury and Illness Prevention Program elements are: 1. Responsibility 2. Compliance 3. Communication 4. Hazard Assessment 5. Accident/Exposure Investigation 6. Hazard Correction 7. Training and Instruction 8. Recordkeeping To be effective your IIPP must: • Fully involve all employees, supervisors, and management • Identify the specific workplace hazards employees are exposed to • Correct identified hazards in an appropriate and timely manner • Provide effective training Need further help in developing an IIPP? Go to Cal OSHA’s website: http://www.dir. ca.gov/DOSH/etools/09-031/index.htm ARB Off-Road Regulation: Two engine vehicles and labeling updates - Revised Many diesel on-road vehicles with twoengines are subject to the Off-Road Regulation and must be reported to the Air Resources Board (ARB), and all vehicles subject to the regulation must be labeled on both sides by January 1, 2013. Amendments to the Off-Road Regulation approved in 2010 make both engines of many on-road two-engine vehicles subject to the regulation. The following two-engine vehicles and their engines are subject to the Off-Road Regulation and should already have been reported to ARB. If not yet reported, they must be reported immediately or face enforcement action: • Not already subject to the Fleet Rule for Public Agencies and Utilities; • Not a two-engine on-road sweeper; • Have a gross vehicular weight > 14,000 pounds; and • Have an auxiliary engine

≥ 50 brake horsepower that is permanently attached and integrated into the design of the vehicle. All two-engine cranes and water well drilling rigs continue to be subject to the regulation. More information on this requirement is available at http://www.arb. ca.gov/msprog/ordiesel/regadv/adv1202b. pdf. Effective January 1, 2013, all vehicles subject to the Off-Road Regulation will be required to have both sides labeled with their Equipment Identification Number (EIN). All vehicles newly reported to ARB must now be labeled on both sides within 30 days of receiving the EIN and all previously reported vehicles must be labeled on both sides by January 1, 2013. For more information about labeling on both sides of a vehicle or the off-road regulation, visit the off-road regulation website at http:// www.arb.ca.gov/msprog/mailouts/msc1208/ msc1208.pdf. Also effective January 1, 2013, Captive Attainment Area Fleets are required to label their vehicles with EINs that have white lettering with a green background (rather than white on red). All Captive Attainment Area Fleets newly reported to ARB must now be labeled on both sides within 30 days of receiving the EIN, and all previously reported vehicles must be labeled on both sides by January 1, 2013. Captive attainment area fleets are treated as small fleets even if their total horsepower (hp) exceeds the small fleet threshold of 2,500 hp. More information about how the labels must appear is available at http:// www.arb.ca.gov/msprog/ ordiesel/faq/faq-labeling.pdf.

The regulation for In-Use Off-Road Diesel Vehicles first became effective under California law on June 15, 2008. This regulation is intended to reduce harmful emissions from diesel powered construction and mining vehicles operating in California and having propulsion engines that are 25 hp or greater. Fleets were required to initially report their off-road diesel vehicles to ARB in 2009 via the Diesel Off-road On-line Reporting System (DOORS). In addition, fleet owners are currently subject to restrictions on unnecessary idling, and will be subject to accelerated replacement/ repower requirements beginning January 1, 2014, If you have any questions regarding offroad reporting, please contact the DOORS hotline at (877) 59-DOORS (877-593-6677) or by email at doors@arb.ca.gov. For further information on ARB’s diesel vehicle and equipment regulations, please call the California Air Resources Board Diesel Hotline at 866-6DIESEL(866-634-3735). For further information about the off-road diesel vehicle regulation, please visit the off-road regulation website at: http://www. arb.ca.gov/ordiesel.

Background

Marin Builders Association ◆ Weekly Bulletin ◆ Page 10


www.marinba.org ◆ mba@marinba.org

SUMMER IS HERE! Marin Builders Association in partnership with Matt & Jeff’s Car Wash is providing an opportunity to get a top quality car wash and support the MBA Scholarship Fund Matt & Jeff’s will donate 50% of car wash price to the Scholarship Fund

Purchase:

Packet of 4 for $100 or Individual car wash for $24.95

How:

MBA Office, 660 Las Gallinas Avenue. San Rafael Reserve tickets by calling Barbara at 462-1220 or send an email to barbara@marinba.org. We can bill your membership account!

You get:

Full service car wash – takes approximately 15 minutes Free shuttle to Costco while you wait – come back to a clean car! Car wash tickets never expire! Offer is available 7 days a week

Marin Builders Association ◆ Weekly Bulletin ◆ Page 11


Safety Matters California Builders Insurance Program: Your construction workplace safety partner

Manual Material Handling For construction workers and contractors, repetitive motions, poor lifting and unsafe handling injuries are some of the most common. Coincidently, they are also usually preventable by practicing safe lifting techniques. Use these helpful ergonomic guidelines to lift any size load without causing injury to yourself or others. Pre-Lifting Techniques Determine whether or not you will need assistance to do the job. Consider the size or shape of the load – bulky or odd-shaped building materials could create additional challenges. Determine if you will have to turn or change direction while carrying the load. Find out if the route you will take with the load is clear of obstructions and slip, trip or fall hazards. Make sure your route is not dangerously close to vehicular traffic, especially if it is traveling at high speeds. Make sure you have a back support belt and are wearing it properly. Determine what kind of personal protective equipment (PPE) you will need to protect your hands and prevent slippage during lifting. Lifting Techniques Get as close as possible to the load and keep it close to your body. Always bend from the knees and not the back, and lift using your legs. Be aware of your balance. Stand on a stable, even surface, and wear proper foot protection to prevent slips and other injuries. Bring the load down to waist level if lifting from above, and wear a hard

hat to prevent head injuries from dropped materials. No matter what you are carrying, always avoid reaching and lifting at the same time. Carrying Techniques Look ahead instead of down to make sure your path is clear. Watch out for terrain changes, and avoid carrying up stairs if possible. Have someone else open doors, gates or other closed entries for you. Keep shoulders, hips and feet aligned – do not twist at the waist or change direction by moving your hips. Set the load down on a firm surface if it becomes too heavy or unstable. Watch for pinch or shear points on carts, dollies and hoists. When you are finished transporting the load, set down the corner or edge of the object closest to you first, keeping your fingers out from underneath.

For construction workers and contractors, repetitive motions, poor lifting and unsafe handling are the cause of some of the most common injuries.

THIS FLYER IS FOR GENERAL INFORMATIONAL PURPOSES ONLY, AND IS NOT INTENDED AS MEDICAL OR LEGAL ADVICE. CONTENT © 2010 ZYWAVE, INC. ALL RIGHTS RESERVED.

For more information, call: (866) 216-5255 or visit our website: http://www.cbeins.com California Builders Insurance Program

Marin Builders Association ◆ Weekly Bulletin ◆ Page 12


California Builders Insurance Program

• Designed Specifically for Contractors • Open to all Licensed Brokers (some conditions and restrictions apply) • Multiple Carrier Participation • Very Competitive Rates (if you are still with the State Fund you can change at any time and save money.) • Low Minimum Premium for many of our Artisan Classes • Flexible Payment Options • On-Line Access to Policy Data, Loss Runs, Claims Status, Account Status, etc. • Free Access to Extensive Safety Library (English and Spanish) • Preferred Provider Network • Nurse Case Management • Accident Investigation Techniques

IMPORTANT ANNOUNCEMENT TO ALL

MARIN BUILDERS ASSOCIATION MEMBERS Your Board of Directors has approved our participation in the California Builders Insurance Program. Program partners include several other builders exchanges and associations. We have all joined forces to deliver competitive insurance programs as well as services designed to meet your specific needs. We have endorsed Jenkins Insurance Group (a Leavitt Group Affiliate) as the managing broker for the California Builders Insurance Program. As your insurance programs approach expiration, please consider participating in this program. If you are with the State Fund, you can change at any time and save 15% to 35% (depending on underwriting guidelines of participating carriers)

• Safety Programs • Uniform Injury & Illness Prevention Program • Strong Return to Work Program

ALSO AVAILABLE • General Liability, Property, Inland Marine, Automobile, Bonding, etc.

Please support your local Builders Exchange Insurance Program! For more information, please contact: clcnbjenkins@leavitt.com or call (866) 216-5255 or visit our website: www.cabuildersinsuranceprogram.com

• Safety Training Classes and Seminars • Human Resource Services • Dedicated website • And Much More!

CA License #0545478

Marin Builders Association ◆ Weekly Bulletin ◆ Page 13


Asuntos de Seguridad California Builders Insurance Program: Su socio de seguridad en el lugar de trabajo de la construcción

Manipulación manual de materiales Para los trabajadores de la construcción y los contratistas, los movimientos repetitivos, el mal levantamiento y las lesiones por manipulación insegura son algunas de las más comunes. Casualmente, también son generalmente prevenibles poniendo en práctica las técnicas seguras de levantamiento. Utilice estas pautas ergonómicas útiles para levantar toda carga sin lesionarse o lesionar a los demás. Técnicas previas al levantamiento Determine si necesitará o no ayuda para realizar el trabajo. Considere el tamaño o la forma de la carga, los materiales de construcción voluminosos o de forma extraña pueden crear desafíos adicionales. Determine si deberá girar o cambiar de dirección mientras lleva la carga. Averigüe si el camino que tomará con la carga está libre de obstrucciones y riesgos de resbalones, tropiezos o caídas. Asegúrese de que su camino no esté peligrosamente cerca del tránsito vehicular, especialmente si está trasladándose a alta velocidad. Asegúrese de tener una faja lumbar de apoyo y de usarla adecuadamente. Determine qué tipo de equipo de protección personal (personal protective equipment, PPE) necesitará para proteger sus manos y evitar resbalarse durante el levantamiento. Técnicas de levantamiento Colóquese lo más cerca posible de la carga y manténgala cerca de su cuerpo. Siempre doble las rodillas y no la espalda, y levántese con las piernas.

Esté atento a su equilibrio. Párese sobre una superficie estable, plana y use la protección adecuada para los pies para evitar tropiezos u otras lesiones. Baje la carga a la altura de la cintura si levanta desde arriba y use un casco para evitar sufrir lesiones en la cabeza con los materiales que caen. No importa qué esté llevando, siempre evite estirarse y levantar al mismo tiempo. Técnicas para llevar cargas Mire adelante en lugar de abajo para asegurarse de que su camino esté despejado. Tenga cuidado con los cambios en el terreno y evite subir escaleras si es posible. Que alguien le abra las puertas, los portones u otras entradas cerradas. Mantenga los hombros, las caderas y los pies alineados, no gire a la altura de la cintura ni cambie de dirección moviendo las caderas. Baje la carga sobre una superficie firme si se torna muy pesada o inestable. Tenga cuidado con los puntos de aplastamiento o de corte en los carros, las plataformas rodantes y las grúas. Cuando termine de transportar la carga, baje el vértice o el borde del objeto lo más cerca suyo posible primero, y mantenga los dedos alejados de la parte de abajo.

Para los trabajadores de la construcción y los contratistas, los movimientos repetitivos, el mal levantamiento y la manipulación insegura son la causa de algunas de las lesiones más comunes.

ESTE FOLLETO TIENE FINES INFORMATIVOS GENERALES EXCLUSIVAMENTE Y NO DEBE CONSIDERARSE COMO UNA RECOMENDACIÓN MÉDICA O LEGAL. © 2010 ZYWAVE, INC. TODOS LOS DERECHOS RESERVADOS.

For more information, call: (866) 216-5255 or visit our website: http://www.cbeins.com California Builders Insurance Program

Marin Builders Association ◆ Weekly Bulletin ◆ Page 14


Marin Builders Association â—† Weekly Bulletin â—† Page 15


Marin Builders Association â—† Weekly Bulletin â—† Page 16


Marin Builders Association â—† Weekly Bulletin â—† Page 17


Marin Builders Association â—† Weekly Bulletin â—† Page 18


www.marinba.org ◆ mba@marinba.org

Permit lists subject to change, please check with Association.

PERMITS

COUNTY OF MARIN PERMITS ISSUED Owner Contractor Address Parcel # Construction Stines La Verne T /Tr/ DE MELLO ROOFING 2569 Las Gallinas Ave San Rafa 164-331-07 (53) Reroof De Losada Florence E /Tr/ ALLY ELECTRIC & SOLAR, IN 8 Carmel Ct San Rafael 179-332-03 (60, 50) Install Sverdlik Alex & CLOUGH, JAMES S ENTERPRIS 10 Wolfe Glen Way Greenbrae 071-181-29 (13) Detached Dec Rotary Valley Assoc L/L LAWSON ROOFING CO INC, TH 10 Jeannette Prandi Way #13 Sa 164-640-02 (53) Reroof Rotary Valley Assoc L/L LAWSON ROOFING CO INC, TH 10 Jeannette Prandi Way #14 Sa 164-640-02 (53) Reroof Rotary Valley Assoc L/L LAWSON ROOFING CO INC, TH 10 Jeannette Prandi Way #15 Sa 164-640-02 (53) Reroof Rotary Valley Assoc L/L LAWSON ROOFING CO INC, TH 10 Jeannette Prandi Way #16 Sa 164-640-02 (53) Reroof Hegel Uli & Kathleen NORTHWEST EXTERIORS INC 170 Wild Horse Valley Dr Novat 146-241-05 (58)Remove And Re Anthony William & Jeann HWAN LEE CHANG 4 Sutton Ln Novato 143-341-50 (58) Repl 11 Wind Chadbourne Barbara MYERS, CURTIS 56 Issaquah Dock Sausalito 901-050-20 (23) Minor Kit Rm Ripley Gregory Wilbur /Tr LANDMARK BLDRS. 3 Luiz Ct San Rafael 164-562-20 (23) Remodel Exis Waldo Pt. Harbor Lt MID-CAL CONSTRUCTION INC 0 Waldo Pt. Harbor Gate 5 Rd S Liberty Dock Quay Waldo Pt. Harbor Lt MID-CAL CONSTRUCTION INC 0 Waldo Pt. Harbor Sausalito Issaquah Dock Qua Doctors Samuel I MCLERAN, INC 1429 Butterfield Rd San Anselm 176-091-16 (53) Reroof Kroeck Constance C /Tr/ JANNEY, STEVE ROOFING 75 Morning Sun Ave Mill Valley 051-051-31 (53) Reroof Jacobs, James ENVIRONMENTAL BIO-SYSTEMS 707 View Point Rd Mill Valley 049-133-02 (22,50,52) Struct Lerman Jeffrey H Tr & TITAN ROOFING AND CONSTRU 57 Bridgegate Dr San Rafael 164-570-13 (53) Reroof Mt Tamalpais Primry Sch ENTERPRISE ROOFING 100 Harvard Ave Mill Valley 051-034-01 (53) Commercial R Mansbach Sarah N DE MELLO ROOFING 50 Wolfe Canyon Rd Greenbrae 071-091-21 (53) Reroof Canton Gayle A /Tr/ HELIO POWER, INC 488 Green Glen Way Mill Valley 049-202-32 (60) Roof-Mounted Patterson Leonard M /Tr/ BY DESIGN 22 Stetson Ave Kentfield 071-144-42 (12) Garage Rebui Bowden Christopher J & ECO-VALLEY CONSTRUCTION 736 SEQuoia Valley Rd Mill Val 046-301-23 (23--0/0) Remodel De Biasio Robert ADVENTURES IN PRODUCTION 263 Crest Rd Novato 143-411-08 (56,58)Repl 4 Sli

Value $10,136 $22,209 $18,000 $18,559 $18,559 $18,559 $18,559 $17,804 $19,741 $20,000 $63,291 $77,448 $86,352 $19,800 $19,872 $10,000 $12,300 $72,318 $15,500 $49,350 $41,000 $16,400 $18,425

COUNTY OF MARIN PERMITS RECEIVED Address Owner 461 W Live Oak Dr Mill Valley 4 Starboard Ct Mill Valley 360 San Geronimo Valley Dr Woodacre 91 Oak Ave Novato 325 Mt Shasta Dr San Rafael 480 Los Cerros Dr Greenbrae 936 Alturas Way Mill Valley 6 Carmel Way San Anselmo 55 Cliff Rd Bolinas 6 Heavenly Way Mill Valley 10 Jeannette Prandi Way #13 San Rafael 10 Jeannette Prandi Way #14 San Rafael 10 Jeannette Prandi Way #15 San Rafael 10 Jeannette Prandi Way #16 San Rafael 170 Wild Horse Valley Dr Novato 442 Laverne Ave Mill Valley

Work Value Kyzysztof Malarecki (20--1/3)(12)(13) New Sfd With Lowry Adam K & (22--1/4) Remodel 2 Baths & Ki Pacific Tel & Tel Co (52)(50) Replace Piping For Ta Gaines Richard N Tr Etal (21) Addition For Elevator And Reizman Victor J Tr & (21,22)Addition & Remodel Carbullido Felix & (20--0/1)(23--0/0) Safavi Nikolai S & (22) Struct Kit RmdlT D 7/26/ Singer Stacey L (60) Roof Mount Solar Electric Gorek Josef & (55) Partial Foundation Repl Mustag Ramona (22--1/3),(12,13) Rmdl Fire Da Rotary Valley Assoc L/L (53) Reroof Rotary Valley Assoc L/L (53) Reroof Rotary Valley Assoc L/L (53) Reroof Rotary Valley Assoc L/L (53) Reroof Hegel Uli & Kathleen (58)Remove And Replace 20 Wind De Benedictis Nancy M & (52) Install Sewage Ejector Pu

$600,000 $100,000 $10,000 $60,000 $100,000 $85,000 $35,000 $24,812 $25,000 $200,000 $18,559 $18,559 $18,559 $18,559 $17,804 $22,000

Marin Builders Association ◆ Weekly Bulletin ◆ Page 19


www.marinba.org ◆ mba@marinba.org

Permit lists subject to change, please check with Association.

PERMITS CITY & TOWN PERMITS ISSUED City/Town

Issue Date

Owner

Contractor

Site Address

Type

Valuation

Novato

7/2

Svanoe Thomas /Tr/ &

Blue Mountain Air, Inc

338 San Marin Dr

Minor Construction

$17,004

Novato

7/2

Brant & Mary Gregory

Save Energy Company (Maap Dba)

8 Oliva Dr A

Construction

$20,000

Novato

7/2

Jenny Rosenberg

Smart Energy Usa

30 Maybeck St

Window

$21,375

Novato

7/3

Polymathic Properties

Lic.Contract.Hired By Owner

1288 Cambridge St

Minor Construction

$18,000

Novato

7/3

Jeff Schlosser

O’Connell Landscape

1046 Valle View Ct

Construction

$70,000

Novato

7/3

Jeff & Susan Schlosser

Basham Douglas /Tr/

1046 Valle View Ct

Construction

$100,000

Novato

7/5

Rebelo Frank Jr &

Lic.Contract.Hired By Owner

750 Grant Ave

Minor Mechanical

$13,727

Novato

7/5

Andrewson Roy &

Sears Home Improvement

27 Oak View Ct

Minor Construction

$16,000

Novato

7/5

Martinez Gonzalo &

West Coast Fiberglass Pools

3 White Oak Way

Solar

$24,000

Novato

7/5

Mike & Deborah Dacquistio

Oasis Pool & Spa Construction

1144 Mirabella Ave

Pool

$34,500

Novato

7/5

Gill Travis /Tr/ &

Design Build Specialists, Inc

246 Club Dr

Pool

$50,000

San Rafael

7/3

Hunter Richard A Tr &

Lamperti Contracting & Desig

140 Riviera Dr

Alter-Sfd

$10,000

San Rafael

7/3

Patel Pervez D /Tr/ &

Barton Michele

112 Surrey Ln

Alter-Condo

$12,000

San Rafael

7/3

Eah Inc

Westower Communica- 1011 Andersen Dr Alter-Commertions cial

$25,000

San Rafael

7/5

Buecker Andrew Willi

Bravo Company Restoration

50 Sandalwood Ct Alter-Sfd

$10,000

San Rafael

7/5

Gallagher Eugene H /T

379 Devon Dr

$12,000

Alter-Sfd

San Rafael

7/5

Carlson Eleanor J Tr

Morris Roofing

325 Clorinda Ave

Alter-Sfd

$13,125

San Rafael

7/5

Golden Gate Bridge Hw

Brocket Construction

32 Meadow Ave

Alter-Sfd

$20,200

San Rafael

7/5

Antonioli Ronald F Tr

G Family Construction

24 Pico Ct

Alter-Sfd

$40,000

San Rafael

7/5

SR CORPORATE CENTER

Rossi Builders Inc

790 Lindaro St 390

Alter-Commercial

$115,000

San Rafael

7/6

Ortez David G &

Crown Ridge Roofing

38 Lucas Park Dr

Alter-Sfd

$12,975

San Rafael

7/6

Roth Nathan G /Tr/ &

All Phase Roofing

215 C St

Alter-Sfd

$15,000

San Rafael

7/6

Sr Corporate Center

Overland Contracting

55 Mitchell Blvd

Alter-Commercial

$45,000

San Rafael

7/9

Hatada Michael T /Tr/

7 Perry Walk

Alter-Sfd

$10,000

San Rafael

7/9

Barton Michele

Sterling Roofing

159 Glen Park Ave

Alter-Sfd

$11,700

San Rafael

7/9

Brocket Construction

Ken Cooper Roofing

191 Riviera Dr

Alter-Sfd

$16,802

Marin Builders Association ◆ Weekly Bulletin ◆ Page 20


www.marinba.org ◆ mba@marinba.org

Permit lists subject to change, please check with Association.

PERMITS

City/Town

Issue Date

Owner

Contractor

Site Address

Type

Valuation

San Rafael

7/10

Lendler Kusum &

PUROFIRST Von Const

7 Mariners Cir

Alter-Sfd

$37,600

Tiburon

7/9

Minah Lee

S & S Builders

40 Geldert Drive

Add Deck, Stairs, Window & Ac

$35,000

Tiburon

7/10

Jay & Marguerite Andrews

Richard Steele Construction Inc.

11 Apollo Road

Solar

$10,000

Tiburon

7/10

Dazy Petri

Solarcraft Services, Inc.

7 Audrey Court

Solar

$12,998

Tiburon

7/10

Vincent Thompson

The Window Specialist

553 Silverado Drive

Replace Windows & Doors

$17,500

Tiburon

7/10

Robert & Ingrid Becker

European Craftsmen & Associates

1907 Straits View Drive

Install Elevator

$20,000

Tiburon

7/11

Scott Dixon

Owner Builder

2441 Spanish Trail Road

Remodel Kitch and 2 Bath

$55,000

Tiburon

7/12

Michael Peters

Forster Pump & Engineering

271 Cecilia Way

New Subdrain

$18,000

Marin Builders Association ◆ Weekly Bulletin ◆ Page 21


www.marinba.org ◆ mba@marinba.org

TAX LIENS & COMPLETIONS COMPLETIONS Recording Date Grantors/Grantees

Grantees/Grantors

Title

07/03/2012

D & D PIPELINES INC (I)

(none)

COMPLE- 2012-0040453 TION

Document Number

07/05/2012

GUERRA CONSTRUCTION GROUP (I)

(none)

COMPLE- 2012-0040635 TION

07/05/2012

MARIN COUNTY OFFICE OF EDUCA- (none) TION (I)

COMPLE- 2012-0040635 TION

07/03/2012

MARIN MUNICIPAL WATER DISTRICT (none) (I)

COMPLE- 2012-0040453 TION

LIENS Recording Date Grantors/Grantees

Grantees/Grantors

Title

Document Number

07/05/2012

AMERICAN DESIGN & BUILD INC (E)

COOMBE TRACY D (O)

LIEN

2012-0040686

07/05/2012

AMERICAN DESIGN & BUILD INC (E)

HORN RANDALL S (O)

LIEN

2012-0040686

07/05/2012

BAHIA HOMEOWNERS ASSOCIATION (E)

ZILBERBERG NOAH (O)

LIEN

2012-0040560

07/03/2012

CHAMPOUX RONALD E (E)

BIEL JO L (O)

LIEN

2012-0040451

07/06/2012

LARKSPUR ISLE CONDOMINIUM HOA (E)

MASOUMI ANOUSHIRAVAN (O)

LIEN

2012-0040839

07/06/2012

LARKSPUR ISLE CONDOMINIUM HOA (E)

TCHEHRAZI SISSI (O)

LIEN

2012-0040839

07/02/2012

PICNIC HILL HOMEOWNERS ASSOCIATION (E)

NIEDDU NICOLA (O)

LIEN

2012-0039738

07/02/2012

RAFAEL BAY TOWNEHOMES HOMEOWNERS ASSOCIATION (E)

EDMONDS DAVID (O)

LIEN

2012-0039737

Document Number

RELEASE OF LIENS Recording Date Grantors/Grantees

Grantees/Grantors

Title

07/02/2012

BENDY JESSICA (E)

ZAPALSKI NATHAN C (O)

RELEASE 2012-0039992 OF LIEN

07/02/2012

BENDY JESSICA (E)

ZAPCON (O)

RELEASE 2012-0039992 OF LIEN

07/05/2012

ECKL JASON (E)

MEADOW PARK HOMEOWNERS ASSOCIATION (O)

RELEASE 2012-0040607 OF LIEN

07/05/2012

FEDERIGHI MICHAEL H (E)

MARIN LAGOON HOMEOWNERS ASSOCIATION (O)

RELEASE 2012-0040561 OF LIEN

07/05/2012

FEDERIGHI SUSAN K (E)

MARIN LAGOON HOMEOWNERS ASSOCIATION (O)

RELEASE 2012-0040561 OF LIEN

07/05/2012

HSBC BANK USA (E)

CARPETERIA (O)

RELEASE 2012-0040504 OF LIEN

07/05/2012

HSBC BANK USA (E)

GULESSERIAN BROS INC (O)

RELEASE 2012-0040504 OF LIEN

07/05/2012

HSBC BANK USA (E)

CARPETERIA (O)

RELEASE 2012-0040505 OF LIEN

07/05/2012

HSBC BANK USA (E)

GULESSERIAN BROS INC (O)

RELEASE 2012-0040505 OF LIEN

Marin Builders Association ◆ Weekly Bulletin ◆ Page 22


www.marinba.org ◆ mba@marinba.org

TAX LIENS & COMPLETIONS RELEASE OF LIENS (continued) Recording Date Grantors/Grantees

Grantees/Grantors

Title

Document Number

07/03/2012

PAUL A TANNER & JANIS TANNER REVOCABLE TRUST (E)

BAHIA HOA (O)

RELEASE 2012-0040228 OF LIEN

07/02/2012

PEDRICK CHRISTOPHER (E)

ZAPALSKI NATHAN C (O)

RELEASE 2012-0039992 OF LIEN

07/02/2012

PEDRICK CHRISTOPHER (E)

ZAPCON (O)

RELEASE 2012-0039992 OF LIEN

07/05/2012

RODAS ANA L (E)

MEADOW PARK HOMEOWNERS ASSOCIATION (O)

RELEASE 2012-0040606 OF LIEN

07/05/2012

RODAS BAYRON B (E)

MEADOW PARK HOMEOWNERS ASSOCIATION (O)

RELEASE 2012-0040606 OF LIEN

07/03/2012

TANNER JANIS L (E)

BAHIA HOA (O)

RELEASE 2012-0040228 OF LIEN

07/03/2012

TANNER PAUL A (E)

BAHIA HOA (O)

RELEASE 2012-0040228 OF LIEN

TAX LIENS Recording Date Grantors/Grantees

Grantees/Grantors

Title

Document Number

07/02/2012

FRANCHISE TAX BOARD (E)

HUGHES JOHNNY A (O)

TAX LIEN

2012-0039969

07/02/2012

FRANCHISE TAX BOARD (E)

CHAMBERLAIN CELIA (O)

TAX LIEN

2012-0039971

07/02/2012

FRANCHISE TAX BOARD (E)

CHAMBERLAIN CLAYTON (O)

TAX LIEN

2012-0039971

07/02/2012

FRANCHISE TAX BOARD (E)

HALLMARK DENTAL LAB INC (O)

TAX LIEN

2012-0039991

07/02/2012

FRANCHISE TAX BOARD (E)

FERN HILL INVESTMENTS L P (O) TAX LIEN

2012-0040036

07/03/2012

FRANCHISE TAX BOARD (E)

COAST PRINTING EQUIPMENT CO INC (O)

TAX LIEN

2012-0040094

07/03/2012

FRANCHISE TAX BOARD (E)

LOTUS CUISINE OF INDIA (O)

TAX LIEN

2012-0040095

07/03/2012

FRANCHISE TAX BOARD (E)

NAVJOTS (O)

TAX LIEN

2012-0040095

07/05/2012

FRANCHISE TAX BOARD (E)

KERNER CAMERA TECHNOLOGIES INC (O)

TAX LIEN

2012-0040628

07/02/2012

INTERNAL REVENUE SERVICE (E)

FRANK JACK (O)

TAX LIEN

2012-0039933

07/02/2012

INTERNAL REVENUE SERVICE (E)

COCO-LUXE CONFECTIONS (O)

TAX LIEN

2012-0039934

07/02/2012

INTERNAL REVENUE SERVICE (E)

MARCON STEPHANIE (O)

TAX LIEN

2012-0039934

07/02/2012

INTERNAL REVENUE SERVICE (E)

MONDOT LINDA J (O)

TAX LIEN

2012-0039935

07/02/2012

INTERNAL REVENUE SERVICE (E)

MONDOT MICHAEL (O)

TAX LIEN

2012-0039935

07/02/2012

INTERNAL REVENUE SERVICE (E)

SF WORKHORSE INC (O)

TAX LIEN

2012-0039936

07/02/2012

INTERNAL REVENUE SERVICE (E)

THORSSON GLEN (O)

TAX LIEN

2012-0039937

07/02/2012

INTERNAL REVENUE SERVICE (E)

THORSSONS AUTO BODY (O)

TAX LIEN

2012-0039937

07/02/2012

INTERNAL REVENUE SERVICE (E)

GODINO ANTHONY (O)

TAX LIEN

2012-0039938

07/02/2012

INTERNAL REVENUE SERVICE (E)

SHAW ROBERT (O)

TAX LIEN

2012-0039939

07/02/2012

INTERNAL REVENUE SERVICE (E)

RACKUSIN BRUCE H (O)

TAX LIEN

2012-0039940

07/02/2012

INTERNAL REVENUE SERVICE (E)

RACKUSIN SUSAN K (O)

TAX LIEN

2012-0039940

07/02/2012

INTERNAL REVENUE SERVICE (E)

AL VILLA BUILDER A CORP (O)

TAX LIEN

2012-0039942

07/02/2012

INTERNAL REVENUE SERVICE (E)

WOLD DAVID (O)

TAX LIEN

2012-0039943

Marin Builders Association ◆ Weekly Bulletin ◆ Page 23


www.marinba.org ◆ mba@marinba.org

TAX LIENS & COMPLETIONS TAX LIENS (continued) Recording Date Grantors/Grantees

Grantees/Grantors

Title

Document Number

07/02/2012

INTERNAL REVENUE SERVICE (E)

WHITCOMB JUDITH L (O)

TAX LIEN

2012-0039944

07/02/2012

INTERNAL REVENUE SERVICE (E)

WHITCOMB STEPHEN J (O)

TAX LIEN

2012-0039944

07/02/2012

INTERNAL REVENUE SERVICE (E)

ESPARZA DAVID (O)

TAX LIEN

2012-0039945

07/02/2012

INTERNAL REVENUE SERVICE (E)

HAZEL CONSTRUCTION INC (O)

TAX LIEN

2012-0039946

07/02/2012

INTERNAL REVENUE SERVICE (E)

STODDARD FREDERICK R (O)

TAX LIEN

2012-0039947

07/02/2012

INTERNAL REVENUE SERVICE (E)

MC KENNA SHARON C (O)

TAX LIEN

2012-0039948

07/02/2012

INTERNAL REVENUE SERVICE (E)

MALONEY CHRISTINE T (O)

TAX LIEN

2012-0039949

07/02/2012

INTERNAL REVENUE SERVICE (E)

MALONEY MICHAEL D (O)

TAX LIEN

2012-0039949

07/02/2012

INTERNAL REVENUE SERVICE (E)

BATLIN GREGORY DAVID (O)

TAX LIEN

2012-0039950

07/02/2012

INTERNAL REVENUE SERVICE (E)

ESPRESSO GREGO (O)

TAX LIEN

2012-0039950

Marin Builders Association ◆ Weekly Bulletin ◆ Page 24


www.marinba.org ◆ mba@marinba.org

Bid list subject to change prior to bid date, please check with Association.

Project Bid Schedule

PROJECT BID SCHEDULE Bid List Subject to Change Prior To Bid Date, Please Check With Association

Friday, July 13, 2012

Tuesday, July 17, 2012

THE PRESERVE AT MARIN APARTMENT RENOVATIONS PROJECT

Plan#: 401CORTE MADERA 12-00401 0NLINE COMPLETE INTERIOR AND EXTERIOR REMODEL OF EXISTING WOOD FRAMED STRUCTURES OVER PARKING GARAGES WITH ASSOCIATED SITE IMPROVEMENTS AND LANDSCAPING FOR 7 RESIDENTIAL BUILDINGS EACH WITH 18 UNITS FOR A TOTAL OF 126 NEW UNITS. SCOPE OF WORK ALSO INCLUDES A NE Project Type: REMODEL Bid Date: 7/13/2012 2:00 PM Addenda: 8 7/12/2012 Prebid Conf: 6/7/12 1:00 PM Contact: TRICORP CONSTRUCTION INC 916-779-8010

CONFIRMED BIDDERS: Name

Phone

Fax

A.E. Nelson Construction 707-636-1750 707-636-1755 Midstate Construction 707-762-3200 707-762-0700 STORMWATER SPECIALISTS 707-280-2510 916-405-4180

REHABILITATION OF LINDA VISTA AVENUE REDWOOD ROAD TO TROWER AVENUE

NAPA 12-00428 Plan#: 428 PAVEMENT EDGE GRINDING, ASPHALT CONCRETE PLUGS, ASPHALT CONCRETE OVERLAY, INSTALLATION OF ASPHALT CONCRETE DIKES, REMOVAL AND REPLACEMENT OF CURB RAMPS, CURB RAMP UPGRADES, SIDEWALK REPAIRS, REMOVAL AND REPLACEMENT OF SIGNS, REPLACEMENT OF PAVEMENT MARKIN Project Type: STREET IMPVS Bid Date: 7/13/2012 3:00 PM Est. Cost: $633000 Addenda: 2 7/9/2012 Ref #: ST11PW03 Prebid Conf: 6/28/12 10:00 AM Contact: NAPA CITY OF, DPW 707-257-9408

CONFIRMED BIDDERS: Name

Phone

Argonaut Constructors 707-542-4862 Ghilotti Brothers Inc 415-454-7011 GHILOTTI CONSTRUCTION 707-585-1221 CO 925-957-9200 MCK Services, Inc. STORMWATER SPECIALISTS 707-280-2510 Suulutaaq, Inc. Unit 2 707-427-3209

Fax

707-542-3210 415-454-8376 707-585-1601 925-957-9292 916-405-4180 707-419-4851

BOLLMAN HIGH LIFT AND NORTHGATE PUMP STATION REHABILITATION Plan#: 434

CONCORD

12-00434

Project Type: PUMP STATION Bid Date: 7/17/2012 10:00 AM Addenda: 1 7/11/2012 Ref #: 112045 Prebid Conf: 6/27/12 10:00 AM Contact: CONTRA COSTA WATER DISTRICT

CONFIRMED BIDDERS: Name

Phone

MAGGIORA & GHILOTTI INC415-459-8640 Mission City Rebar, Inc 925-449-6999 STORMWATER SPECIALISTS 707-280-2510 Valentine Corporation 415-453-3732

Fax

415-459-2065 925-447-8797 916-405-4180 415-457-5820

2012 STREET REHABILITATION PROJECT

FAIRFAX 12-00460 Plan#: 460 RECONSTRUCT BELLE AVENUE, BAYWOOD COURT, PIPER COURT AND PIPER LANE AND PLACE ASPHALT CONCRETE OVERLAY ON ALDER COURT, BELMONT AVENUE, COOLIDGE AVENUE AND WINNIE LANE Project Type: STREET IMPVS Bid Date: 7/17/2012 2:00 PM Addenda: 1 7/3/2012 Ref #: 53-887 Contact: COASTLAND CIVIL ENGINEERING INC 707-571-8005

CONFIRMED BIDDERS: Name

Phone

Argonaut Constructors Ghilotti Brothers Inc

Fax

707-542-4862 707-542-3210 415-454-7011 415-454-8376

RENGSTORFF PARK TENNIS COURTS RESURFACING

Plan#: 462 MOUNTAIN VIEW 12-00462 RESURFACING OF EIGHT TENNIS COURTS AND TWO BACKBOARD COURTS AND RESEALING PATHWAYS AROUND THE COURTS AND PATHWAYS LEADING OUT TO THE PARK AS SHOWN ON THE PROJECT DRAWINGS IN THE APPENDIX SECTION. Project Type: TENNIS COURTS Bid Date: 7/17/2012 2:00 PM RESURFACE Est. Cost: $45000to Addenda: 0 Ref #: 11-20 $55000 Contact: MOUNTAIN VIEW PUB WORKS 650-903-6311

Monday, July 16, 2012 2012 CURED-IN-PLACE PIPE (CIPP) LINING PROJECT

MARIN COUNTY 12-00465 Plan#: 465 EXCAVATION, PIPE LINING, BACKFILL, PAVING Project Type: SEWER/SANITATION Bid Date: 7/16/2012 11:00 AM Addenda: 1 6/29/2012 Contact: NUTE ENGINEERING 415-453-4480

Marin Builders Association ◆ Weekly Bulletin ◆ Page 25


www.marinba.org ◆ mba@marinba.org

Bid list subject to change prior to bid date, please check with Association.

Project Bid Schedule HEADQUARTERS LANDSCAPE-EMPLOYEE ENTRY

Plan#: 466 FREMONT 12-00466 IRRIGATION SYSTEM IMPROVEMENTS, CONCRETE WORK, NEW PLANTINGS AND BOLLARD TYPE LIGHTING Project Type: LANDSCAPE Bid Date: 7/17/2012 2:00 PM Addenda: 0 Ref #: 6544 Prebid Conf: 7/10/12 9:00 AM Contact: ALAMEDA COUNTY WATER DISTRICT 510-668-4484

CONFIRMED BIDDERS: Name

Phone

Fax

CF CONTRACTING 415-721-7160 415-296-6437 GREEN GROWTH INDUSTRIES 916-722-8830 916-722-8840

TENNIS COURT RENOVATIONS AT THE SAN MARIN HIGH SCHOOL

NOVATO 12-00469 Plan#: 469 RESURFACING OF TENNIS COURTE, FENCE REMOVAL, ROOT BARRER INSTALLATION AND STRIPING Project Type: TENNIS COURTS Bid Date: 7/17/2012 2:00 PM RESURFACE Addenda: 0 Ref #: 229-6100-40312 Prebid Conf: 6/26/12 2:00 PM Contact: NOVATO UNIFIED SCHOOL DIST 415-898-2859

CONFIRMED BIDDERS: Name

Phone

A.E. Nelson Construction

GLEN CANYON PARK IMPROVEMENTS

Plan#: 464 SAN FRANCISCO 12-00464 THE WORK IS LOCATED AT GLEN CANYON PARK, NEAR THE INTERSECTION OF CHENERY AND ELK STREETS. THE WORK TO BE DONE INCLUDES DEMOLITION AND HAZMAT WORK: RESTORATION AND IMPROVEMENTS TO ROADS AND PATHWAYS: RENOVATION OF ENTRY PLAZA AND CONSTRUCTION OF DROP OFF Project Type: PUBLIC WORKS Bid Date: 7/18/2012 2:30 PM Addenda: 0 Ref #: 3071V to $3500000 Prebid Conf: JULY 9, 2012 at 10:00am Contact: SAN FRANCISCO, CITY & COUNTY 415-575-5601

MAIN WASTEWATER TREATMENT PLANT PGS1 EXHAUST HEAT RECOVERY SILENCERS REPLACEMENT

OAKLAND 12-00468 Plan#: 468 DEMOLITION AND REMOVAL OF 3 EXISTING EXHAUST HEAT RECOVERY SILENCERS, ASSOCIATED PIPING, INCLUDING TEMPORARY REMOVAL OF APPUTENANT EQUIPMENT AND INSTALLATION OF 3 NEW DISTRICT-FURNISHED EXHAUST HEAT RECOVERY SILENCERS INCLUDING REPLACMENT PIPING AND VALVE Project Type: REPLACEMENT Bid Date: 7/18/2012 1:30 PM Est. Cost: $550000to Addenda: 1 7/11/2012 Ref #: SD-345 $650000 Prebid Conf: 7/ Contact: EBMUD, ENGINEERING SERVICES 510-287-1638

Fax

707-636-1750 707-636-1755

MISSION PEAK MCCLURE RANCH HOUSE FOUNDATION REPAIR

Thursday, July 19, 2012 DRY CREEK ROAD REPAIR

Plan#: 483 FREMONT 12-00483 REMOVE, REPLACE AND REPAIR FOUNDATION AND FOOTINGS AND OTHER RELATED WORK Project Type: FOUNDATION Bid Date: 7/17/2012 2:00 PM Addenda: 0 Ref #: 176M-12-114 Est. Cost: $175000 Prebid Conf: MAND 7/10/12 10:00 AM Contact: EAST BAY REGIONAL PARK DISTRICT 510-544-2562

NAPA 12-00448 Plan#: 448 THE PROJECT WILL TAKE PLACE ON DRY CREEK ROAD NEAR MILE POST MARK 9.75. THIS PROJECT INVOLVES THE CONSTUCTION OF A NEW SOLDIER PILE WOOD LAGGING RETAINING WALL AND BACK DRAIN SYSTEM. THE WORK WILL INCLUDE BUT NOT BE LIMITED TO CONSTRUCTION AREA SIGNING, Project Type: PUBLIC WORKS Bid Date: 7/19/2012 3:30 PM Addenda: 0 Ref #: PW 07-18 to $539000 Prebid Conf: JUNE 28, 2012 at 10:00am Contact: NAPA COUNTY, DPW

CONFIRMED BIDDERS:

CONFIRMED BIDDERS:

Name

Phone

Fax

DVBE Trucking & Construction408-971-4430 408-971-9942 Co., Inc.

Wednesday, July 18, 2012 HEADQUARTERS COMPUTER SERVER ROOM RENOVATION

FREMONT 12-00450 Plan#: 450 REMOVAL OF THE EXISTING HEATING AND VENTILATION COMPONENTS THAT SERVICE THE COMPUTER SERVER ROOM AREA AND REPLACE THEM WITH A VARIABLE FLOW REFRIGERANT COOLING SYSTEM AND OTHER RELATED WORK Project Type: RENOVATION Bid Date: 7/18/2012 2:00 PM Addenda: 1 6/29/2012 Ref #: 6457 Prebid Conf: MAND 6/28/12 10:00 AM Contact: ALAMEDA COUNTY WATER DISTRICT 510-668-4484

CONFIRMED BIDDERS: Name CF CONTRACTING

Phone

Fax

415-721-7160 415-296-6437

Name

Phone

Fax

Ghilotti Construction Co Inc 707-585-1221 707-585-1601 Groeniger & Company 916-455-3333 916-455-3402 Hess Construction Company, 707-552-7931 707-552-3988 Inc.

ROCKY RIDGE ROAD LANDSLIDE REPAIR LAS TRAMPAS REGIONAL WILDERNESS Plan#: 470

CONTRA COSTA 12-00470 COUNTY REPAIR OF LANDSLIDE INCLUDING EARTHWORK, RIPRAP, DRAINAGE, AGGREGATE BASE, ASPHALT PAVING, EROSION CONTROL AND HYDROSEEDING Project Type: LANDSLIDE REPAIR Bid Date: 7/19/2012 2:00 PM Addenda: 0 Ref #: 06-12-170 Est. Cost: $198000 Prebid Conf: 7/9/12 10:00 AM Contact: EAST BAY REG PARK DISTRICT 510-544-2301

CONFIRMED BIDDERS: Name Legg, Inc.

Phone

Fax

925-605-4500 925-605-4510

Marin Builders Association ◆ Weekly Bulletin ◆ Page 26


www.marinba.org ◆ mba@marinba.org

Bid list subject to change prior to bid date, please check with Association.

Project Bid Schedule CITYWIDE SIDEWALK REPAIR PROGRAM

MENLO PARK 12-00477 Plan#: 477 CLASS "A" OR C8 LICENSE REQUIRED Project Type: REPAIR PROJECT Bid Date: 7/19/2012 2:00 PM Addenda: 0 Ref #: 20-2012 Contact: MENLO PARK, CITY OF 650-330-6740

MEADOW DRIVE PIPELINE REPLACEMENT PROJECT

Plan#: 484 MILL VALLEY 12-00484 NEW FURNISH LABOR AND EQUIPMENT FOR THE INSTALLATION OF 1,080 FT OF 6-INCH WELDED STEEL PIPE AITH ASSOCIATED APPERTNANCES Project Type: PIPELINE Bid Date: 7/19/2012 10:00 AM Addenda: 1 7/9/2012 Ref #: 1689 Contact: MARIN MUNICIPAL WATER DISTRICT 415-945-1576

Tuesday, July 24, 2012 SOUTHERN MARIN ROAD RETAINING WALL PROJECT

KENTFIELD 12-00431 Plan#: 431 FURNISH LABOR AND EQUIPMENT FOR EXCAVATION AND PROVIDE 28 24-INCH DIAMETER CAST-IN-PLACE CONCRETE PIERS, 168 FT CAST-IN-PLACE CONCRETE PIER CAPS AND ASSOCIATED APPURTENACES Project Type: CONCRETE WORK Bid Date: 7/24/2012 10:00 AM Est. Cost: $325000 Addenda: 1 7/9/2012 Ref #: 1587 Contact: MARIN MUNICIPAL WATER DISTRICT 415-945-1577

CONFIRMED BIDDERS: Name

Phone

Fax

CF CONTRACTING 415-721-7160 415-296-6437 GHILOTTI CONSTRUCTION 707-585-1221 707-585-1601 CO Valentine Corporation 415-453-3732 415-457-5820

REROOF CHB AND HAYWARD YARD CONTROL CENTER UPPER ROOF

OAKLAND 12-00443 Plan#: 443 REMOVE EXISTING ROOFING AND INSTALL MODIFIED BITUMEN ROOFING USING ONE-PART COLD ADHESIVE ON THE EXISTING ROOF DECK OF CHB IN OAKLAND SHOP AND CONTROL CENTER UPPER ROOF IN HAYWARD YARD Project Type: REROOFING Bid Date: 7/24/2012 2:00 PM Est. Cost: $175000to Addenda: 0 Ref #: 15QJ-120 $225000 Prebid Conf: 7/10/12 11:00 AM Contact: BART 510-287-4717

THE INSTALLATION OF SPEED HUMPS AND SPEED TABLES AT VARIOUS LOCATIONS IN ALAMEDA COUNTY

ALAMEDA COUNTY 12-00463 Plan#: 463 CLASS "A" OR C12 LICENSE REQUIRED.: FOR FURTHER INFORMATION, CONTACT RICK YEUNG Project Type: ROAD WORK Bid Date: 7/24/2012 2:00 PM Addenda: 0 Ref #: 2205 Est. Cost: $90000 Prebid Conf: 7/10/12 1:30 PM Contact: ALAMEDA COUNTY PUBLIC WORKS AGENCY 510-6705450

ELECTRICAL AND MECHANICAL IMPROVEMENT TO HIGH SCHOOL RESERVOIR

Plan#: 473 HAYWARD 12-00473 WORK INCLUDES A PUMPING UNIT, PIPING, VALVES, ELECTRICAL EQUIPMENT, VAULT, DEMOLITION AND SITE WORK, SITE LIGHTING Project Type: ENGINEERING/CIVIL Bid Date: 7/24/2012 2:00 PM Addenda: 0 Ref #: 622-7137 Est. Cost: $330000 Prebid Conf: 7/11/12 2:00 PM Contact: HAYWARD, CITY OF, ENGINEERING 510-583-4734

CONFIRMED BIDDERS: Name

Phone

CF CONTRACTING Mission City Rebar, Inc

Fax

415-721-7160 415-296-6437 925-449-6999 925-447-8797

PROMONTORY PARK AT HUNTERS VIEW

Plan#: 474 SAN FRANCISCO 12-00474 REDEVELOPMENT WORK INCLUDES CONTRUCTION OF RETAINING WALLS, STAIRS, RAMPS, PAVED AREAS AND LAWN FOR USE AS A PARK FACILITY Project Type: PARKS-RECREATION Bid Date: 7/24/2012 2:00 PM Addenda: 0 Prebid Conf: 7/10/12 9:30 AM Contact: CAHILL-NIBBI JV 415-863-1820

GOLDEN GATE TRANSIT SAN FRANCISCO MID-DAY BUS PARKING FACILITY

Plan#: 475 SAN FRANCISCO 12-00475 RELOCATE MID-DAY BUS PARKING LOT TO A NEW LOCATION IN SAN FRANCISCO Project Type: PARKING LOT Bid Date: 7/24/2012 4:00 PM Addenda: 0 Contact: GOLDEN GATE BRIDGE-HIGHWAY & TRANSPORTATION DISTRI 415-923-2223

Wednesday, July 25, 2012 CENTRAL TRANSFER STATION FLOOR AND WALL REPAIR PROJECT

PETALUMA 12-00433 Plan#: 433 REPLACE PORTIONS OF THE CONCRETE SLAB FLOOR AND REPAIR PUSH WALL AND COLUMNS. PROJECT ALSO INCLUDES DEMOLITION, STEEL WOR AND WELDING Project Type: REPAIRS Bid Date: 7/25/2012 2:00 PM Addenda: 0 Ref #: WO7914 Prebid Conf: MAND 7/11/12 10:00 AM Contact: SONOMA COUNTY DEPART OF TRANSPORTATION 707565-2620

CONFIRMED BIDDERS: Name

Phone

CF CONTRACTING Murray Building

Fax

415-721-7160 415-296-6437 707-939-9001 707-939-9048

Marin Builders Association ◆ Weekly Bulletin ◆ Page 27


www.marinba.org ◆ mba@marinba.org

Bid list subject to change prior to bid date, please check with Association.

Project Bid Schedule MENDOCINO COMMUNITY COLLEGE WILLITS CENTER

WILLITS 12-00442 Plan#: 442 NEW 6,762 SF CC CAMPUS: NEW 2-STORY WOOD FRAMED CONSTRUCTION OF ADMINSITRATION/CLASSROOM BUILDING, SHADE STRUCTURES AND ASSOCIATED SITE WORK Project Type: NEW CONSTRUCTION Bid Date: 7/25/2012 1:00 PM Est. Cost: $4000000 Addenda: 1 7/6/2012 Ref #: 11003.00 Prebid Conf: MAND 7/10/12 1:00 PM Contact: TLCD ARCHITECTURE 707-525-5600

AUSTIN PARK CURB, GUTTER, SIDEWALK AND BIKE LANE & OLD HIGHWAY 53 BIKE LANE PROJECT

CLEARLAKE 12-00486 NEW Plan#: 486 QUESTIONS: HEIDE UTTERBACK AT 707-571-8005 Project Type: STREET IMPVS Bid Date: 7/25/2012 3:00 PM Addenda: 0 Ref #: RPSTPLE5427(021) Contact: COASTLAND CIVIL ENGINEERING INC 707-571-8005

CONFIRMED BIDDERS: Name

Phone

A.E. Nelson Construction 707-636-1750 BCM Construction Co. Inc. 530-342-1722 Codding Construction Co 707-795-3550 Danco Builders Northwest 707-822-9000 Donald F. Gallino, Inc. 530-246-7671 DVBE Trucking & Construction408-971-4430 Co., Inc. FORT BRAGG ELECTRIC 707-964-9118 Graham Concrete 530-993-4598 Helmer & Sons, Inc. 707-965-2425 Jeff Luchetti Construction 707-527-5788 PIERSON COMPANY 707-268-1800 R E West Builders Inc 707-576-1224 RE West Builders 707-576-1224 Wright Contracting Inc 707-528-1172

Fax 707-636-1755 530-342-1768 707-665-2883 707-822-9596 530-246-8714 408-971-9942

707-964-1404 530-993-4758 707-965-2982 707-636-5509 707-268-1801 707-541-0117 707-541-0117 707-528-3714

DOT 04-153004 WIDEN RAMPS, CONSTRUCT RETAINING WALLS, AND INSTALL RAMP METERING

ALAMEDA 12-00453 Plan#: 453ONLINE WIDEN RAMPS. CONSTRUCT RETAINING WALLS, AND INSTALL RAMP METERING. IN ALAMEDA COUNTY AT VARIOUS LOCATIONS. THE CONTRACTOR MUST HAVE EITHER A CLASS A LICENSE OR A COMBINATION OF CLASS C LICENSES WHICH CONSTITUES A MAJORITY OF THE WORK. Project Type: PUBLIC IMPVS Bid Date: 7/25/2012 2:00 PM Addenda: 0 to $3741000 Contact: CALTRANS 510-286-5209

CONFIRMED BIDDERS: Name

Phone

Fax

DVBE Trucking & Construction408-971-4430 408-971-9942 Co., Inc. Ghilotti Construction Co Inc 707-585-1221 707-585-1601

SANITARY SEWER CLEANING AND VIDEO INSPECTION BASINS A1, A2, A3, A4

Plan#: 478 SAN MATEO 12-00478 Project Type: SEWER/SANITATION Bid Date: 7/25/2012 2:00 PM Addenda: 0 Ref #: 469925-46000Est. Cost: $500000 9019 Contact: SAN MATEO, CITY OF 650-522-7331

Thursday, July 26, 2012 WILDCAT CREEK RESTORATION TILDEN PARK GOLF COURSE

Plan#: 457 BERKELEY 12-00457 RESTORE STREAM BY CONSTRUCTING ROCK STEP POOLS AND SOIL BIOENGINEERING Project Type: RESTORATION Bid Date: 7/26/2012 2:00 PM Addenda: 0 Ref #: 07-12-105 Est. Cost: $325000 Prebid Conf: MAND 7/10/12 10:00 AM Contact: EAST BAY REG PARK DISTRICT 510-544-2301

CONFIRMED BIDDERS: Name

Phone

CF CONTRACTING

Fax

415-721-7160 415-296-6437

OLD SONOMA RD, SOUTH KELLY RD, AND OAK KNOLL AVE. OVERLAY,

Plan#: 479 NAPA 12-00479 CLASS "A" or "C-12" REQUIRED. WORK WILL INCLUDE AN ASPHALT OVERLAY WITH CONFORM GRINDING AT THE PROJECT LIMITS AND INTERSECTIONS. THE PROJECT WILL ALSO INCLUDE RAISING UTILITY COVERS WITHIN THE ROADWAY TO MATCH NEW ROADWAY ELEVATIONS. Project Type: PUBLIC WORKS Bid Date: 7/26/2012 3:30 PM Addenda: 0 Ref #: RDS 12-19 Contact: NAPA COUNTY DPW 707-257-9305

CONFIRMED BIDDERS: Name

Phone

Argonaut Constructors Ghilotti Brothers Inc OC Jones and Sons

Fax

707-542-4862 707-542-3210 415-454-7011 415-454-8376 510-526-3424 510-526-0990

SAFE ROUTES TO HILLVIEW MIDDLE SCHOOL

MENLO PARK 12-00485 NEW Plan#: 485 INSTALLATION OF THREE LIGHTED CROSSWALK SYSTEMS AND ADA CURB RAMP IMPROVEMENTS AT THE INTERESECTIONS OF SANTA CRUZ AVENUE WITH OLIVE STREET, COTTON STREET AND SAN MATEO DRIVE Project Type: STREET IMPVS Bid Date: 7/26/2012 2:00 PM Addenda: 0 Ref #: 70-065 Prebid Conf: 7/17/12 10:00 AM Contact: MENLO PARK, CITY OF 650-330-6740

CONFIRMED BIDDERS: Name

Phone

RODAN BUILDERS, INC.

Fax

650-508-1700 650-508-1705

Marin Builders Association ◆ Weekly Bulletin ◆ Page 28


www.marinba.org ◆ mba@marinba.org

Bid list subject to change prior to bid date, please check with Association.

Project Bid Schedule SILVERADO TRAIL OVERLAY ZINFANDEL LANE TO SKELLENGER LANE

Plan#: 488 NAPA 12-00488 NEW CLASS "A" or "C-12". WORK WILL INCLUDE AN ASPHALT OVERLAY WITH CONFORM GRINDING AT PROJECT LIMITS AND AT INTERSECTIONS. THE PROJECT WILL ALSO INCLUDE RAISING WATER UTILITY COVERS WITHIN THE ROADWAY TO MATCH NEW ROADWAY ELEVATIONS. NO UTILITY RELOCATI Project Type: PUBLIC WORKS Bid Date: 7/26/2012 3:30 PM Addenda: 0 Ref #: RDS 12-20 Contact: NAPA COUNTY DPW 707-257-9305

Tuesday, July 31, 2012 SANTA ROSA AQUEDUCT SEISMIC HAZARD MITIGATION (RODGERS CREEK FAULT CROSSING)

Plan#: 472 SANTA ROSA 12-00472 INSTALLATION OF APPROXIMATELY 1,900 LF OF 36-INCH STEEL WATER PIPE AND OTHER RELATED WORK Project Type: WATER-POWER Bid Date: 7/31/2012 10:00 AM Addenda: 0 Ref #: 60-64-7 #1 Est. Cost: $2000000to $2600000 Prebid Conf: MAND 7/10/12 10:00 AM AND 7/12/12 2:00 PM Contact: SONOMA COUNTY WATER AGENCY 707-547-1900

Wednesday, August 01, 2012 DOT 04-3A7764 WIDEN RAMPS AND INSTALL RAMP METERING SYSTEM

Plan#: 456ONLINE

ALAMEDA AND 12-00456 CONTRA COSTA COUNTIES WIDEN RAMPS AND INSTALL RAMP METERING SYSTEM. IN ALAMEDA AND CONTRA COSTA COUNTIES AT VARIOUS LOCATIONS FROM POWELL STREET UNDERCROSSING TO 0.1 MILE WEST OF THE CARQUINEZ BRIDGE. THE CONTRACTOR MUST HAVE EITHER A CLASS A LICENSE OR ONE OF THE ONE FOLLOW Project Type: PUBLIC IMPVS 1:00 PM Bid Date: 8/1/2012 to $5600000 Addenda: 0 Contact: CALTRANS 510-286-5209

CONFIRMED BIDDERS: Name

Phone

TERRACE AVENUE WATER MAIN RELOCATION PROJECT

Plan#: 467

MARINWOOD, GREENBRAE, STRAWBERRY AND MARIN CITY IMPROVEMENTS

Plan#: 482 MARIN COUNTY 12-00482 CONSTRUCTION OF NEW SIDEWALK, CURB, GUTTER AND DRAINAGE IMPROVEMENTS ON LUCAS VALLEY ROAD INCLUDING RETAINING WALLS AND CURB RAMPS Project Type: STREET IMPVS Bid Date: 7/31/2012 2:00 PM Addenda: 0 Ref #: 2010-15 Est. Cost: $750000 Contact: MARIN COUNTY DEPT. OF PUB WORKS 415-499-7877

CONFIRMED BIDDERS: Name CF CONTRACTING Ghilotti Brothers Inc

Phone

Fax

415-721-7160 415-296-6437 415-454-7011 415-454-8376

SANITARY SEWER INDUSTRIAL TRUNKLINE REHABILITATION

Plan#: 487 LIVERMORE 12-00487 NEW CLASS "A" LICENSE REQUIRED. Project Type: PIPELINE Bid Date: 7/31/2012 2:30 PM Addenda: 0 Ref #: 1997-57 Contact: LIVERMORE, CITY OF, ENGINEERING 925-960-4540

Fax

DVBE Trucking & Construction408-971-4430 408-971-9942 Co., Inc. Ghilotti Construction Co Inc 707-585-1221 707-585-1601

BOLINAS

12-00467

Project Type: WATER MAIN 12:00 PM Bid Date: 8/1/2012 Addenda: 0 Prebid Conf: MAND 7/18/12 10:00 AM Contact: BOLINAS COMMUNITY PUBLIC UTILITY DISTRICT 415868-1224

Thursday, August 02, 2012 WW-542 OCEANSIDE WATER POLLUTION CONTROL PLANT, DEWATERING FACILITY UPGRADES

Plan#: 480 SAN FRANCISCO 12-00480 PRE-QUALIFICATION BIDDERS ONLY. CLASS "A" LICENSE. THE OBJECTIVE OF THE PROJECT IS TO UPGRADE THE DEWATERING FACILITIES AT THE OCEANSIDE WATER POLLUTION CONTROL PLANT BY: REPLACING EXISTING BELT PRESSES WITH SCREW PRESSES AND FLOCCULATION TANKS: INSTALL Project Type: PUBLIC WORKS 2:00 PM Bid Date: 8/2/2012 Addenda: 0 Ref #: WW-542 to $6300000 Prebid Conf: JULY 10, 2012 at 9:00AM Contact: SAN FRANCISCO, CITY & COUNTY 415-554-3106

AS-NEEDED MAIN SEWER REPLACEMENT

SAN FRANCISCO 12-00481 Plan#: 481 CLASS "A" LICENSE IS REQUIRED. THE OBJECTIVE OF THE PROJECT IS TO PROVIDE CONTINGENCY-BASED MAIN SEWER REPLACEMENT ON SHORT NOTICE AT LOCATIONS TO BE DETERMINED WITHIN CITY AND COUNTY OF SAN FRANCISCO. Project Type: PUBLIC WORKS 2:00 PM Bid Date: 8/2/2012 Addenda: 0 Ref #: WW-553 to $3400000 Prebid Conf: JULY 12, 2012 AT 10:00AM Contact: SAN FRANCISCO CITY & COUNTY 415-551-4335

Marin Builders Association ◆ Weekly Bulletin ◆ Page 29


www.marinba.org ◆ mba@marinba.org

Bid list subject to change prior to bid date, please check with Association.

Project Bid Schedule Tuesday, August 07, 2012

Tuesday, August 14, 2012

DOT 04-153504 INSTALL RAMP METERING, TOS, MBGR, SIGN STRUCTURES, WIDEN RAMP

DOT-04-264074 MODIFY OVERCROSSING

Plan#: 454VALLEJO, FAIRFIELD 12-00454 ONLINE AND VACAVILLE INSTALL RAMP METERING, TOS, MBGR, SIGN STRUCTURES, WIDEN RAMP. IN SOLANO COUNTY IN VALLEJO, FAIRFIELD AND VACAVILLE FROM THE CONTRA COSTA COUNTY LINE TO ROUTE 505. THE CONTRACTOR MUST HAVE A CLASS A LICENSE OR A COMBINATION OF CLASS C LICENSES WHICH CONS Project Type: PUBLIC IMPVS 2:00 PM Bid Date: 8/7/2012 to $12100000 Addenda: 0 Contact: CALTRANS 510-286-5209

Plan#: 438NOVATO 12-00438 ONLINE MODIFY OVERCROSSING IN MARIN COUNTY IN AND NEAR NOVATO FROM 1.0 MILE NORTH OF NORTH NOVATO OVERHEAD TO 0.6 MILE SOUTH OF SONOMA COUNTY LINE. THE CONTRACTOR MUST HAVE EITHER A CLASS A LICENSE OR A COMBINATION OF CLASS C LICENSES WHICH CONSTITUTES A MAJORIT Project Type: ROAD WORK Bid Date: 8/14/2012 2:00 PM to $28000000 Addenda: 0 Ref #: 04-Mrn-101R23.2/27.1 Contact: CALTRANS 510-286-5209

CONFIRMED BIDDERS:

CONFIRMED BIDDERS:

Name

Phone

Fax

DVBE Trucking & Construction408-971-4430 408-971-9942 Co., Inc. 415-454-7011 415-454-8376 Ghilotti Brothers Inc Ghilotti Construction Co Inc 707-585-1221 707-585-1601

Wednesday, August 08, 2012 DOT 04-3A23U4 WIDEN ROADWAYS AND RAMPS, PLACE HMA, CONST SWS, WIDEN AND CONST BRIDGES

Plan#: 458WINDSOR 12-00458 ONLINE WIDEN RDWYS AND RAMPS, PLACE HMA, CONST SWS, WIDEN AND CONST BRIDGES. IN SONOMA COUNTY IN AND NEAR WINDSOR AT VARIOUS LOCATIONS FROM 0.3 MILE SOUTH OF FULTON ROAD OVERCROSSING TO 0.2 MILE SOUTH OF WINDSOR LANE UNDERCROSSING. THE CONTRACTOR MUST HAVE EITH 2:00 PM Project Type: PUBLIC IMPVS Bid Date: 8/8/2012 to $27000000 Addenda: 0 Contact: CALTRANS 510-286-5209

CONFIRMED BIDDERS: Name

Phone

Fax

DVBE Trucking & Construction408-971-4430 408-971-9942 Co., Inc. Ghilotti Brothers Inc 415-454-7011 415-454-8376 GHILOTTI CONSTRUCTION 707-585-1221 707-585-1601 CO

Name

Phone

Fax

DVBE Trucking & Construction408-971-4430 408-971-9942 Co., Inc. 415-454-7011 415-454-8376 Ghilotti Brothers Inc Ghilotti Construction Co Inc 707-585-1221 707-585-1601

Wednesday, August 15, 2012 CITY COLLEGE OF SAN FRANCISCO PERFORMING ARTS CENTER

SAN FRANCISCO 12-00471 Plan#: 471 CONSTRUCTION OF A NEW, TWO-STORY PERFORMING ARTS CENTER BUILDING WITH CLASSROOMS AND PERFORMING ARTS FACILITY Project Type: NEW CONSTRUCTION Bid Date: 8/15/2012 2:00 PM Addenda: 1 7/3/2012 Ref #: 20412.00 Prebid Conf: MAND 7/25/2012 1:00 PM Contact: TOM ELIOT FISCH 415-391-7918

Tuesday, August 21, 2012 DOT 04-2640U4 CONSTRUCT PETALUMA BLVD SOUTH INTERCHANGE, REPLACE PETALUMA RIVER BR

PETALUMA 12-00437 Plan#: 437ONLINE CONSTRUCT PETALUMA BLVD SOUTH INTERCHANGE, REPLACE PETALUMA RIVER BR. IN SONOMA COUNTY IN AND NEAR PETALUMA FROM GUNN DRIVE TO ROUTE 101/116 SEPARATION AND OVERHEAD THE CONTRACTOR MUST HAVE EITHER A CLASS A LICENSE OR A COMBINATION OF CLASS C LICENSES WHI Project Type: PUBLIC WORKS Bid Date: 8/21/2012 2:00 PM to $66000000 Addenda: 0 Ref #: 04-SON-1010.9/3.6 Prebid Conf: MAND JULY 25, 2012 1-3 PM Contact: CALTRANS 510-286-5209

CONFIRMED BIDDERS: Name

Phone

Fax

DVBE Trucking & Construction408-971-4430 408-971-9942 Co., Inc. Ghilotti Brothers Inc 415-454-7011 415-454-8376 GHILOTTI CONSTRUCTION 707-585-1221 707-585-1601 CO

Marin Builders Association ◆ Weekly Bulletin ◆ Page 30


www.marinba.org ◆ mba@marinba.org

Bid list subject to change prior to bid date, please check with Association.

Project Bid Schedule Wednesday, August 22, 2012 DOT 04-3A9214 WIDEN FREEWAY, REPLACE OVERCROSSINGS, AND RECONSTRUCT RAMPS/ROADS

ALAMEDA COUNTY 12-00459 Plan#: 459ONLINE WIDEN FREEWAY, REPLACE OVERCROSSINGS, AND RECONSTRUCT RAMPS/ROADS. IN ALAMEDA COUNTY IN SAN LEANDRO FROM 0.4 MILE SOUTH OF MARINA BLVD OVERCROSSING TO 0.3 MILE NORTH OF ROUTE 112/880 SEPARATION. THE CONTRACTOR MUST HAVE EITHER A CLASS A LICENSE OR ANY COM Project Type: PUBLIC IMPVS Bid Date: 8/22/2012 2:00 PM to $45000000 Addenda: 0 Ref #: 04-Ala-88022.6/24.0 Prebid Conf: MAND JULY 25, 2012 at 1:00pm Contact: CALTRANS 510-286-5209

CONFIRMED BIDDERS: Name

Phone

Ghilotti Construction Co Inc

Fax

707-585-1221 707-585-1601

Tuesday, August 28, 2012 DOT 04-3A9224 WIDEN MAINLINE AND BRIDGE FOR HOV LANE

ALAMEDA COUNTY 12-00489 NEW Plan#: 489 WIDEN MAINLINE AND BRIDGE FOR HOV LANE IN ALAMEDA COUNTY FROM 0.2 MILE NORTH OF ROUTE 112/880 SEPARATION TO HEGENBERGER ROAD OVERCROSSING THE CONTRACTOR MUST HAVE EITHER A CLASS A LICENSE OR A COMBINATION OF CLASS C LICENSES WHICH CONSTITUTES A MAJORITY O Project Type: PUBLIC WORKS Bid Date: 8/28/2012 2:00 PM to $24100000 Addenda: 0 Ref #: 04-Ala-88024.0/25.5 Prebid Conf: JULY 25, 2012 at 1:00pm Contact: CALTRANS 510-286-5209 Contact: Ghilotti Brothers Inc 415-454-7011

-MBA Quote of the day -

People

who say it cannot be done should not interrupt those who are doing it.

- George Bernard Shaw

Marin Builders Association ◆ Weekly Bulletin ◆ Page 31


www.marinba.org ◆ mba@marinba.org

Project Bid RESULTS PROJECT BID RESULTS 7.03.12 - 7.11.12 Date

Job Name

Location

7/3/2012

DOWNTOWN DISTRICT SEWER REPLACEMENT & PAVEMENT RENOVATION WW-499

SAN FRANCISCO

SHAW PIPELINE

$2,206,786

HILL GYMNASIUM ROOF REPLACEMENT

NOVATO

WEDGE ROOFING

$158,600

PETERSON DEAN

170,371

MCM ROOFING

$180,680

HILL GYMNASIUM INTERIOR REPAIRS

WINDSOR

A.E. NELSON

$175,650

ONPOINT CONST.

198,870

TANK RECOATING AND SCCESS IMPROVEMENTS-PHASE 2

WINDSOR

FARR CONST.

$679,870

UTILITY SERVICE CO

$718,000

CORR RAY PAINTING

755,000

LARKSPUR FERRY TERMINAL SERCURITY IMPROVEMENTS

LARKSPUR

KCK BLDG

$275,000

MASSA CONST.

7/3/2012

7/3/2012

7/3/2012

7/5/2012

7/9/2012

7/9/2012

7/10/2012

7/10/2012

DRY CREEK HABITAT ENHANCEMENT DEMONSTRATION

HEALDSBURG

BIOENGINEERING ASSOCIATES, INC

174,737.11

HANFORD APPLIED 191,661.23 RESTORATION & CONSERVATION WYLATTI RESOURCE MANAGEMENT 7/10/2012

237,901.96

NEW GOMPERS & LPS RICHMOND RICHMOND SCHOOL MCCARTHY BROS. CO (SF)

53,365,000.00

LATHROP CONST.

53,887,350.00

ARNTZ BLDG.

54,852,764.00

EL CHARRO SPECIFIC PLAN MITIGATION & MAINTENANCE

LIVERMORE

GREEN VALLEY LANDSCAPE

790,561.23

2012 SIDEWALK ACCESS RAMP ADA UPGRADES

ROHNERT PARK

WILDCAT ENGINEERING

83,253

HEMBREE LANE RESURFACING

WINDSOR

$302,420

GHILOTTI CONST.

421,901

CF CONTRACTING

307,000

ARGONAUT CONST.

451,690

SEISMIC IMPROVEMENTS FOR RENTAL PROPERTY 8231

CONTRA COSTA

GHILOTTI BROS INC (SF)

452,610

CF CONTRACTING

$186,800

WINDSOR

WINDY HOLLOW ROAD REHABILITATION

SANTA ROSA

COMMUNITY CENTER ACCESSIBILITY IMPROVEMENTS A.E. NELSON

29,150

NORTHWEST GENERAL ENG

503,995

CCS- AT DOWNER SCHOOL (RE-BID)

SAN LEANDRO

SAN LEANDRO HIGH SCHOOL SWIM CENTER & FIELDS

SAN LEANDRO

GRAND CONST.

93,200

ERA CONST.

111,294

A & E EMAAR

115,000.00

F & H CONST.

$4,800,000

7/10/2012

7/10/2012

7/10/2012

7/11/2012

7/11/2012

Marin Builders Association ◆ Weekly Bulletin ◆ Page 32


www.marinba.org ◆ mba@marinba.org

Classified ads are provided free to MBA members & staff. Please advise if position is filled or commodity is sold.

Classified ADS

paula@marinba.org

Position: Experienced Power Tool and Hardware Counter Sales

Jackson’s Hardware in San Rafael is currently seeking a Full and Part time Experienced Power Tool and & Hardware Counter Sales. Schedules will vary and can change weekly based upon staffing requirements. Our store hours are Monday thru Friday 6:00am – 6:00pm & Saturday 8:00am – 5:00pm

Field Supervisor and Concrete Foreman

Ghilotti Bros., Inc. is in search of 2 Field Supervisors to join our team. A Field Supervisor with Highway work/ Caltrans background is plus. The Concrete Foreman must specifically have an architectural concrete background. These positions will report to VP of Operations and Concrete Manager respectively.

Position: Part Time Bid Runner

Ghilotti Bros., Inc. is seeking an experienced part–time Bid Runner. Flexible hours range from 5-10 hours per week. Responsible for delivering bid documents. Must be dependable, punctual, and have excellent penmanship. The ability to listen and write quickly and accurately under pressure is crucial. Must have the confidence to meet strict time deadlines. Receives bid pricing and subcontractor information over the telephone. Reliable vehicle necessary and a clean driving record. Mileage reimbursed. Please apply to apply@ghilottibros.com or fax to 415.455.9274.

Please send your resume to jobs@jacksonshardware.com

Position – Experienced Decorative Plumbing and Door Hardware Counter Sales

Jackson’s Hardware in San Rafael is currently seeking a Full and Part time Experienced Decorative Plumbing and Door Hardware Counter Salesperson. Schedules will vary and can change weekly based upon staffing requirements. Our store hours are Monday thru Friday 6:00am – 6:00pm & Saturday 8:00am – 5:00pm Please send your resume to jobs@jacksonshardware.com .

Clean dirt available now! Sausalito Virgin Site 1200 cubic yards of great soil to be removed for new home, permits in place July start email terrykeast@gmail.com

Marin Builders Association ◆ Weekly Bulletin ◆ Page 33


www.marinba.org ◆ mba@marinba.org

Marin Builders Association ◆ Weekly Bulletin ◆ Page 34


www.marinba.org ◆ mba@marinba.org

Marin Builders Association circa 1962 Publication rules for submission of articles to the MBA Weekly Bulletin Members corner Limited to 600 words and edited for length, grammar, spelling, clarity, style, libel and civility. We do not publish form letters, petitions or consumer complaints. Please include writers name, address and phone number. All submissions become the property of Marin Builders Association and cannot be returned. note: We would like a photo (jpeg) head shot and can offer ¼ page ad space to *fill out page for ½ the price. *Ad space only available to fill out page if necessary. Page 34 34 Marin Builders Association ◆ Weekly Bulletin ◆ Page 35


MBA Weekly Bulletin Vol.56 Issue#29