Floor Details

Floor Details

Typical Floor System See Red-I™ Joist Installation Guide (Available online at www.RedBuilt.com) for additional installation guidelines

Header and Red-I™ Joist Refer to detail 7 on page 11 A 250 lb maximum load can be ­supported on each side of the bottom flange of the Red-I™ joist at 5' o.c.

2 Hanger on Stud Wall

Download AutoCAD .dwg file

.pdf file

3 Hanger on Ledger

Download AutoCAD .dwg file

If seismic tension ties are required, see page 18

Web stiffener each side of joist (if required)

Backer blocks

Web stiffener each side of joist (if required)

Filler blocks between multiple joists

Rim Board

WARNING Safety bracing required to ensure adequate bracing during construction

Hanger on Beam Refer to detail 4 on page 11

.pdf file

Joist hanger Joist hanger Ledger

The potential for top plate rotation may reduce hanger capacities. Contact RedBuilt™ for assistance.

4 Hanger on Beam

Download AutoCAD .pdf file

.dwg file

5 Hanger on Steel Beam Download AutoCAD .dwg file

Web stiffener each side of joist (if required)

.pdf file

Nailer thickness must accommodate hanger nail length and may affect capacity. Refer to hanger manufacturer’s literature for details.

Web stiffener each side of joist (if required)

Joist hanger. Hanger height must be a minimum of 60% of the joist depth.

Red-I™ joist overhang must be protected from the weather Cantilever

Red-I™ Blocking Panel Refer to page 15

Sheathing provides sway bracing

6 Hanger on Masonry Wall

Download AutoCAD .dwg file

.pdf file

Fasteners to bond beam as required

11⁄2" rim board

General Notes

Rim board or Red-I™ blocking panels (or an equivalent alternative) must always be used to prevent rollover and to provide structural attachment of the deck sheathing to the supporting structure in accordance with the specific design requirements.

10

Nails may need to be driven at an angle to minimize splitting of bearing plate

For 11⁄2" thick flanges, attach with one 10d (3") box nail, minimum, each side of Red-I™ joist at bearing. Use 12d (31⁄4") box nails with 13⁄4" thick flanges. Maintain 11⁄2" minimum end distance to minimize splitting.

Web stiffener each side of joist (if required)

.dwg file

.pdf file

1,050 plf ­maximum load (or 2,100 lbs at 2' on-center ­minimum)

Header hanger

Filler block (nail to joist web)

Web stiffener. See page 16.

Download AutoCAD

Double Red-I™ joists sized for side load

Blocking as required

1 Nailing Red-I™ Joist to Bearing Plate

Details shown on pages 10–14 are conceptual. Attachments and connections shall be made to the supporting structure in accordance with the specific design requirements.

7 Side-Loaded Double Joist

If seismic tension ties are required, see page 18

Outriggers Refer to page 12

Joist hanger

Web stiffeners are required if the sides of the hanger do not laterally ­ support at least 3⁄ 8 " of the Red-I™ joist top flange

Header

Masonry or concrete wall Masonry hanger Field-installed backer block at reactions over 250 lbs

Traditional masonry hangers will not support construction loads ­without a minimum amount of cured masonry construction above ­hanger level. Refer to hanger manufacturer’s literature for information on the correct installation and use of masonry hangers.

When supported by a Red-I™ joist, maximum hanger capacity is approximately 2,000 lbs. Refer to hanger manufacturer’s literature for details.

11