Page 1

Tin No.33814883499, CST No.166198 Dt 25.03.2009

Date: 17.10.2012 To M/S. Madurai Es Consultancy services Private Ltd Civil Engineering Consultants 37/17, West Masi Street, Madurai-625001

Ref No: 4847/2012/B/10 Project: IT Block at ELCOT IIandaikulam IT/ITES SEZ park in Madurai for M/s Chella Software p ltd Sub: Tender Clarifications Revised Rate Details Dear Sir, Today Discussion about with our Tender Revised Rate Clarification to your Office at Meeting Conducted on 11.30am.so Finally Approved by the New Revised Rate of the Tender. The Following New Rate Details Item No 1.1 1.2a 1.2b 1.2c 1.3 1.4 1.5 1.8 3.1 3.2a 3.2b

Item Site clearance Excavation 0-1.5m Excavation 1.5-3m Excavation 3.0-4.5m Shallow excavation Sand filling Gravel Filling Selected Excavated earth Filling Mix 1:2:4 Supplying RMC M20 Supplying RMC M25

Quoted Rate 9 411 446 481 489 2800 920 200

Revised Rate 6.30 350 386 450 250 2310 750 131

6642 5103 1000

6350 5103 925


3.3 4.4 4.5 4.6 5

Spreading RMC Fly Ash Brick Work 115mm Fly Ash Brick Work 75mm Fly Ash Brick Work Joinery

7.3 7.4 7.6 9.2 9.3

Ceramic Tile Floor Vitrified Tile Flooring Pressed Tiles Cement Paint Distemper

6690 1022 1022 1022 25,23,082.00

6300 850 850 750 24,22,159.00

1000 1250 850 85 90

900 1200 650 80 85

With Discount @ 4%

Note: 1) Item No:1.1- Surveying Work Not Included in this Rate. At the Same time Ruppish Material Dispose to Out side. 2) Item No: 4.4, 4.5,4.6 in Earlier Rate Calculate on the Basic Rate of Brick has Rs 7/- per number. 3) As per Your Request for Item No:5- We Cannot reduce the Price as Revised Above Because of Architect Specification.

Your Sincerly