U.S. STEEL SERBIA – BF PCI PROJECT DAILY MEETING REPORT CONTRACTOR: VIG/ITG Site Safety:

     

Proper PPE – hard hats, safety glasses, metatarsal work boots, fire retardent work wear, hearing protection, appropriate work gloves, gas   monitor and fall protection harness. Hot Weather – drink plenty of fluids; take appropriate rests Fall Protection – inspect fall protection before use; inspect scaffold tagging before using; always tie off using beam straps or retractable   safety lines; Always tie off when in manlifts. Lifting – use proper rigging; secure area under lifts; no hands on loads Hot Work – check work area for flammables; protect people and equipment below hot work areas; have fire extinguishers nearby. Housekeeping – maintain clean and organized work area; keep walkways clear

6KV Substation and cable ducts CONSTRUCTION UPDATE  MEETING M O M of 6 August 2011

Electrical room and pump station  CONSTRUCTION UPDATE MEETING M O M of 4 6 August 2011 1)

WORK PLANNED FOR NEXT 24 HOURS:  a. Work in progresson hold ­on f installing first industrial water valve pit – On  1) WORK PLANNED FOR NEXT  hold, waiting for installation of pipe connection in pipe channel. – To be done  24 HOURS: after both valve pits are installed water line is installed byby Grapps  a. USS has requested ITG  Technomeering Grapps now has the list of parts required and the valve and  to construct additional road  will start work when personnel available.in pipe tunnel. from the 6KV building to MH1,  b. Road construction in progress behind coal bunker.  BFComplete pouring of  c.  Area  #1 ­  second layer of backfill completed and compaction test  concrete for additional road  acceptable begin curbing and shutteringContinue pouring concrete today;  today. The second layer passed  compaction test and starting  d. Area #2 will be retested and if acceptable second layer of backfill will  shuttering and preparing for  begin. – Install membrane, rebar and shuttering today. concrete. e. Area #3 on  hold waiting for decision on Rotary Dumper foundation  installation. Further work on the roadway can not proceed as it would  2) BRIEF DESCRIPTION OF  interfere with HM work areas. Tour today with HM to determine if they can  ANY DELAYS AND  free up additional area. Truck area in front of the Coal  REASONS:  f. Receiving Hopper can begin on August 8, 2011. a. Delays ­ none g. Hydrant line in front of PCI building completed last night. Remaining 8m  of line connection connection for hydrant line to the valve chamber ­ USSS  3) INTERFERENCES OR  decided on plastic pipe installation and work will proceed. needs to be  completed.  To be done 8Aug2011. SPECIAL REQUIREMENTS:  a. Globex to make “As Built”  h. Repairs to Securiton pipe penetrations in pump house wall in progress. Two  drawings for the manholes and  openings remain to be done.  Opening for diesel engine exhaust can not be  conduit runs. done until line is installed. i.  Installation of potable water line in pipe tunnel to st art on8Aug2011.     4) SAFETY: j.  Work on installing pipe trench between pump house and water tank to start   a.   as soon as USS furnishes drawings for work.  Promised they would have  drawings today. k.  Installation of the storm sewer drainage pipe under the roadway will be   done during the 60hour stop of #2 Blast Furnace starting on 10Aug2011. l. All work which can be done presently has been completed however further  openings will be required.  m.  CRS equipment ready for grouting – HM prepared the shims, formwork  for grouting will start August 8 2011.. 2)  BRIEF DESCRIPTION OF ANY DELAYS & REASONS: a. None 3)  INTERFERENCES OR SPECIAL REQUIREMENTS: a. Outstanding work –install potable water line, install hydrant line, install  road, install sewers.  b. Sanitary lift station pumps due to deliver 11Aug2011. 1/2


U.S. STEEL SERBIA – BF PCI PROJECT DAILY MEETING REPORT CONTRACTOR: VIG/ITG Site Safety:

     

Proper PPE – hard hats, safety glasses, metatarsal work boots, fire retardent work wear, hearing protection, appropriate work gloves, gas   monitor and fall protection harness. Hot Weather – drink plenty of fluids; take appropriate rests Fall Protection – inspect fall protection before use; inspect scaffold tagging before using; always tie off using beam straps or retractable   safety lines; Always tie off when in manlifts. Lifting – use proper rigging; secure area under lifts; no hands on loads Hot Work – check work area for flammables; protect people and equipment below hot work areas; have fire extinguishers nearby. Housekeeping – maintain clean and organized work area; keep walkways clear

c.  Road at  receiving     hopper for CRS can start as soon as the 300 ton crane is      d. e. f. g.

dismantled.  A concrete pad needs to be installed for the electric building air   conditioning system equipment.  A concrete pad needs to be installed for the stair to #2 BF distributor.   Reinforcement pockets on both the FCS and RCS need to be filled with   concrete.

4) SAFETY:  Housekeeing 5) VIG has 18 workers on site.

2/2


VIG_a_ITG_Aug_6  

openings remain to be done. Opening for diesel engine exhaust can not be done until line is installed. j. Work on installing pipe trench bet...