Issuu on Google+

KOC CONTRACT NO.: 39848

IMCO PROJECT NO .: P87/09

PLANNING PACKAGE REPLACEMENT OF EXISTING OILY AND EFFLUENT WATER LINES WITH RTRP IN GC-23 AND GC-25

1

05.05.09

ISSUED FOR APPROVAL

THK

JC

AKM

0

08.04.09

ISSUED FOR APPROVAL

REV.

DATE

DESCRIPTION

THK PREPARED BY

JC REVIEWED BY

AKM APPROVED BY

P.O. BOX 9309, AHMADI - 61004, KUWAIT – TEL.: +965 23981661/2 – FAX: +965 23984708 E-MAIL: projects@imcokw.com


KOC CONTRACT NO.: 39848

IMCO CONTRACT NO. P87/09

PLANNING PACKAGE

INDEX SL. NO.

CONTENT

1.

MANAGENMENT SUMMARY

2.

PROJECT SCHEDULE

3.

LEVEL-1 - PROGRAME OF WORK

LEVEL-5 PROGRAME OF WORK

CRITICAL PATH LISTING

MILESTONE LISTING

LEVEL-1 WEIGHTAGE SPLIT UP

W.B.S CHART UPTO LEVEL 3

PROJECT ORGANIZATION CHART

PROGRESS ‘S’ CURVES 

ENGINEERING ‘S’ CURVE

PROCUREMENT ‘S’ CURVE

CONSTRUCTION ‘S’ CURVE

PRECOM. & COMM. ‘S’ CURVE

OVERALL ‘S’ CURVE

4.

MANPOWER HISTOGTRAM

5.

PROCUREMENT LOG

6.

EQUIPMENT DEPLOYMENT PLAN

7.

MONTHLY PROGRESS REPORT FORMAT

8.

INVOICE FORMAT

9.

CASH FLOW

10.

PROGRESS MEASUREMENT SUMMARY


KOC CONTRACT NO.: 39848

IMCO PROJECT NO.: P87/09

MANAGEMENT SUMMARY REPLACEMENT OF EXISTING OILY AND EFFLUENT WATER LINES WITH RTRP IN GC-23 AND GC-25

P.O. BOX 9309, AHMADI - 61004, KUWAIT – TEL.: +965 23981661/2 – FAX: +965 23984708 E-MAIL: projects@imcokw.com


REPLACEMENT OF EXISTING OILY AND EFFLUENT WATER LINES WITH RTRP IN GC 23 AND 25

MANAGEMENT SUMMARY KOC CONTRACT NO.: 39848

IMCO PROJECT NO.: P87/09

1. Contract Execution Dates: Project Commencement Date

–

22nd March 2009

Project Completion Date

-

12th September 2010

Project Duration

-

540 Calendar Days

2. Brief Description of Project The project is basically Engineering, procurement & installation for replacement of existing pipes inside GC23 & GC25 and related works. Carbon steel piping for wash water, recycle water, effluent water and drain lines at GC 23 to be replaced with RTRP pipes. Existing off spec crude recycle line at GC25 to be replaced from below ground to above ground and the new line shall be constructed using NACE carbon steel pipe lined with factory applied fusion bonded Epoxy lining. Also Effluent water carbon steel lines in GC25 to be replaced with RTRP pipe. All related inline instruments and piping valves to be replaced with new instruments and piping valves. Supply and installation of Mech valves, control valves, ESD valves, relevant instruments & cables. 3. Overview Of Planning Package The planning package is developed in a way to measure and monitor project progress. Schedules will be prepared using PRIMAVERA V3.1. up to Level 5 of Engineering, Procurement & Installation. Measurement of the progress will be carried out with physical progress updated in the Progress Measurement System using Excel Ver 2007. Progress S-curves for each phases of project are included in the package to monitor the progress statistics. Manpower & Equipment histogram for overall project are also included for resource monitoring.

Page 1 of 5


MANAGEMENT SUMMARY REPLACEMENT OF EXISTING OILY AND EFFLUENT WATER LINES WITH RTRP IN GC 23 AND 25

4. Schedule Highlights a. Engineering: Engineering milestone to commence with the site survey & data collection. Further upon Site Survey, Detailed Design & Engineering of all discipline to commence. Engineering drawings & documents will be submitted to KOC approval .Upon approval Material Specification of all project Materials to be submitted to KOC for approval. The weight factor loaded in the schedule is as per the payment term cost breakdown given in the contract specification clause 12, General conditions of contract clause 50. b. Procurement: Long Lead procurement items are detailed in the P3 program, due to their criticality, while the remaining procurement items are indicated under Procurement items for simplicity. Long Lead Procurement items are scheduled to arrive at site by First week of May 2010. Procurement milestone to commence with Technical Bid analysis of Project Materials after submission of material specification to KOC. Purchase order to be issued after approval of material specification and Technical Proposal by KOC. After issuance of P.O. Vendor/ Manufacturer will prepare & submit the Data sheets and Drawings for RTRP Pipe spools, Control & ESD Valves, Mech. Valves, Corrosion Fittings and Instrument Items for KOC approval. After approval of the data sheets Manufacturer/ Vendor to commence the manufacturing. The weight factor loaded in the schedule is as per the payment term cost breakdown given in the contract specification clause 12, General conditions of contract clause 50.

Page 2 of 5


MANAGEMENT SUMMARY REPLACEMENT OF EXISTING OILY AND EFFLUENT WATER LINES WITH RTRP IN GC 23 AND 25

c. Construction / Pre-commissioning & Commissioning: The construction, pre-commissioning, and commissioning activities are detailed in the P3 program with the estimated weight factors assigned for each activity as per the payment term cost breakdown given in the contract specification clause 12, General conditions of contract clause 50. The activities are linked together with an appropriate and executable logic and also linked with the relevant material arrival at site. Construction activities commence from October 2009 with Prefabrication of CS Piping. FBE coating of CS Pipe spools will start parallel with later 20 days start Prefabrication works. All FBE Coated Pipe spools to be delivered to site for site Installation. RTRP Pipe spools to be delivered to site for Installation after completion of procurement of RTRP. Mech. Valves, ESD & Control valves to be delivered to site for installation after completion of procurement of all valves. Civil & Structural work will start before site installation to start and it will finish parallel with site installation of piping. Instrumentation works will start 3 months before tie in and it will be finished with demolition of redundant instruments. Hydro testing will start after completion of all site installation. Pre commissioning will start parallel with Hydro testing of system. Tie in Activities will start after completion of pre commissioning and testing. Separate schedule to be prepared and submitted to KOC for approval after discussion with KOC. Commissioning will start parallel during shutdown and it will complete after 5 days of shutdown completion. Demolition of redundant pipe lines and valves to start parallel with tie in works and it will be finished 4 days earlier than completion date.

Page 3 of 5


MANAGEMENT SUMMARY REPLACEMENT OF EXISTING OILY AND EFFLUENT WATER LINES WITH RTRP IN GC 23 AND 25

Procurement Long Lead / Critical items: The Following are considered long lead items for the project: 

Mechanical Valves

Control Valves

ESD valves

Corrosion monitoring Fittings

5. Critical Paths: Following activities are scheduled in the critical path, 1. Preparation, Submission & Approval of project key personnel. 2. Site Survey & Data Collection. 3. Preparation, Submission and Approval of Material Spec Control Valves, ESD Valves and Mechanical Valves. 4. Preparation & Submission of P&ID. 5. Procurement and Installation of Control Valves, ESD Valves and Mechanical Valves. 6. Hydro testing of new pipelines. 7. Shutdown for Tie in works & Demolition of redundant lines, Valves and Instruments. 8. Commissioning work.

Page 4 of 5


MANAGEMENT SUMMARY REPLACEMENT OF EXISTING OILY AND EFFLUENT WATER LINES WITH RTRP IN GC 23 AND 25

6. Cut-off and Submission Dates for Progress Reports: Cut-off date for weekly progress report is on Thursday and the reports will be submitted not later than three days from the cut-off date. If required, electronic copy of the weekly report will be submitted through E-mail. Last day of the month ( 30th ) is considered as the cut-off date for monthly progress report and the report will be submitted not later than first 7 days of each month. 7. Calendar Used for P3 Activities: Working hours are considered as follows:  Engineering

- 8 hours per day

 Procurement - 8 hours per day  Construction

- 8 hours per day

 Tie-in

- 8~14hrs ( as required during shutdown)

However KOC approval will be obtained for working beyond contractual working hours. Holidays are considered in the schedule as follows:  Ascension of the Prophet on 20th July 2009.  Holy Eid Al - Fiter on 20th & 21st of September 2009.  Holy Eid Al - Adha on 26th & 28th of November 2009.  Islamic New year on 18th December 2009.  New Year’s Day on 1st of January 2010.  Kuwait National Day on 25th February 2010.  Prophet Mohamed Birthday on 09th March 2010.  Holy Eid Al - Fiter on 10th September 2010.

Page 5 of 5


KOC CONTRACT NO.: 39848

IMCO PROJECT NO.: P87/09

PROJECT SCHEDULE REPLACEMENT OF EXISTING OILY AND EFFLUENT WATER LINES WITH RTRP IN GC-23 AND GC-25

CONTENT ¾ ¾ ¾ ¾ ¾ ¾ ¾

LEVEL-1 PROGRAM OF WORK LEVEL-5 PROGRAM OF WORK CRITICAL PATH LISTING MILESTONE LISTING LEVEL-1 WEIGHTAGE SPLIT UP W.B.S CHART UPTO LEVEL-3 PROJECT ORGANIZATION CHART

P.O. BOX 9309, AHMADI - 61004, KUWAIT – TEL.: +965 23981661/2 – FAX: +965 23984708 E-MAIL: projects@imcokw.com


LEVEL-1 PROGRAM OF WORK REPLACEMENT OF EXISTING OILY AND EFFLUENT WATER LINES WITH RTRP IN GC-23 AND GC-25


Activity ID

Activity Description

Orig Dur

Early Start

Early AREA PROJ PHAS TRAK MATL SUB Total UNIT DIS Cal % Finish Float ID WT

M APR MAY JUN

JUL

2009 AUG SEP

OCT NOV DEC

2010 JAN FEB MAR APR MAY JUN

JUL

AUG SEP O

Replacement of Existing Oily and Effluent Water Subtotal

536 22MAR09

12SEP10

100.00

158 22MAR09

27AUG09

0.00

124 22APR09

24AUG09

4.00

121 23APR09

22AUG09

3.00

333 31MAY09

01MAY10

52.00

331 10OCT09

08SEP10

36.00

87 09JUN10

04SEP10

5.00

26 14AUG10

12SEP10

0.00

+ GENERAL

+ DESIGN & ENGINEERING

+ HAZOP/QRA/EIA STUDIES

+ PROCUREMENT

+ CONSTRUCTION

+ PRECOMMISSIONING & COMMISSIONING

+ PROJECT CLOSEOUT

Start Date Finish Date Data Date Critical Activity Run Date Early Bar

Progress Bar

© Primavera Systems, Inc.

P87/09 Sheet 1 of 1 22MAR09 87R1 12SEP10 REPLACEMENT OF EXISTING OILY & EFFLUENT WATER LINES WITH 22MAR09 RTRP IN GC-23 & GC-25 06MAY09 17:01 IMCO ENGINEERING AND CONSTRUCTION COMPANY BASELINE SCHEDULE (LEVEL-1 SUMMARY)

Date 04APR09

Revision-0

Checked THK

Approved JC

30APR09

Revision-1

Revision

THK

JC


LEVEL-5 PROGRAM OF WORK REPLACEMENT OF EXISTING OILY AND EFFLUENT WATER LINES WITH RTRP IN GC-23 AND GC-25


Activity ID

Activity Description

Orig Dur

Early Start

Early Finish

Late Start

Late CalTotal PROJ PHAS TRAK MATL AREA SUB UNIT DIS % Finish IDFloat WT

2009 2010 M APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP O

Replacement of Existing Oily and Effluent Water Subtotal

536 22MAR09 12SEP10 22MAR09 12SEP10

0100.00

158 22MAR09 27AUG09 22MAR09 11NOV09

0

0.00

158 22MAR09 27AUG09 22MAR09 11NOV09

0

0.00

158 22MAR09 27AUG09 22MAR09 11NOV09

0

0.00

0

0.00

0

0.00

GENERAL Subtotal COMMON Subtotal

Subtotal

GENE0100

Project Start

0 22MAR09

GENE0210

Prepare & Submit Key Personnels

22MAR09

22 23MAR09 16APR09 23MAR09 16APR09

Project Start Prepare & Submit Key Personnels

GENE0270

Prepare & Submit Safety Plan

3 26MAR09 29MAR09 12APR09 14APR09

14

0.00

Prepare & Submit Safety Plan

GENE0250

Prepare & Submit Sit office loc. & layout

3 30MAR09 01APR09 15APR09 18APR09

14

0.00

Prepare & Submit Sit office loc. & layout

GENE0280

Rev. & App. Safety Plan

21 30MAR09 19APR09 22OCT09 11NOV09

206

0.00

Rev. & App. Safety Plan

GENE0190

Prepare & Submit QA/QC Plan

3 02APR09 05APR09 19OCT09 21OCT09

168

0.00

Prepare & Submit QA/QC Plan

GENE0260

Rev. & App. Site Office location & layout

21 02APR09 22APR09 19APR09 09MAY09

17

0.00

GENE0200

Rev. & App. QA/QC Plan

21 06APR09 26APR09 22OCT09 11NOV09

199

0.00

GENE0220

Rev. & App. Key Personnels

24 14APR09 07MAY09 14APR09 07MAY09

0

0.00

27AUG09 15AUG09 13SEP09

14

0.00

124 22APR09 24AUG09 22APR09 31AUG09

0

4.00

124 22APR09 24AUG09 22APR09 31AUG09

0

2.00

30 22APR09 26MAY09 22APR09 26MAY09

0

0.20

0

0.00

Start Engineering for GC-23 & GC-25

0

0.20

Site Survey & Data Collection

GENE0340 Site Office Mobilization DESIGN & ENGINEERING Subtotal

26 29JUL09

Rev. & App. Site Office location & layout Rev. & App. QA/QC Plan Rev. & App. Key Personnels Site Office Mobilization

GC-23 Subtotal SITE SURVEY Subtotal

ENGS0090

Start Engineering for GC-23 & GC-25

0 22APR09

22APR09

ENGS0100 Site Survey & Data Collection CIVIL & STRUCTURAL

30 22APR09 26MAY09 22APR09 26MAY09

Subtotal

56 23JUN09 18AUG09 06JUL09

31AUG09

12

0.20

DESIGN DRAWINGS & DOCUMENTS ENCD0120

Preparation of Civil Drawings

30 23JUN09 28JUL09

06JUL09

10AUG09

11

0.00

Preparation of Civil Drawings

ENCD0160

Preparation of Dwg for Str.Support

30 23JUN09 28JUL09

06JUL09

10AUG09

11

0.00

Preparation of Dwg for Str.Support

ENCD0140

Review & Approval of Civil Drawings

21 29JUL09

18AUG09 11AUG09 31AUG09

13

0.07

Review & Approval of Civil Drawings

ENCD0150 Review & Approval of dwg for str. STRUCTURAL STEEL SUPPORT

21 29JUL09

18AUG09 11AUG09 31AUG09

13

0.07

Review & Approval of dwg for str. support

ENCS0140

30 23JUN09 28JUL09

11

0.00

Prep. & Sub. of Material Spec for Stru. Start Date Finish Date Data Date Critical Activity Run Date Early Bar

Progress Bar

© Primavera Systems, Inc.

06JUL09

10AUG09

Prep. & Sub. of Material Spec for Stru. Supports

P87/09 Sheet 1 of 20 22MAR09 87R1 12SEP10 REPLACEMENT OF EXISTING OILY & EFFLUENT WATER LINES WITH 22MAR09 RTRP IN GC-23 & GC-25 06MAY09 16:57 IMCO ENGINEERING AND CONSTRUCTION COMPANY BASELINE SCHEDULE (LEVEL-5)

Date 04APR09

Revision-0

Checked THK

Approved JC

30APR09

Revision-1

Revision

THK

JC


Activity ID

Activity Description

Orig Dur

Early Start

Early Finish

Late Start

Late CalTotal PROJ PHAS TRAK MATL AREA SUB UNIT DIS % Finish IDFloat WT

2009 2010 M APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP O

STRUCTURAL STEEL SUPPORT ENCS0150

Review& Approval Material Spec for

21 29JUL09

18AUG09 11AUG09 31AUG09

13

0.03

10AUG09

11

0.00

18AUG09 11AUG09 31AUG09

13

0.03

10MAY09 17AUG09

0

1.10

Review& Approval Material Spec for Stru. Support

CIVIL MATERIALS ENCS0180

Prep.& Sub. of Material Spec for Civil

30 23JUN09 28JUL09

ENCS0190

Review & Approval Material Spec for

21 29JUL09

06JUL09

Prep.& Sub. of Material Spec for Civil Matl Review & Approval Material Spec for Civil Matl

MECHANICAL & PIPING Subtotal

66 10MAY09 15JUL09

DESIGN DRAWINGS & DOCUMENTS Prep.& Sub. of Hydraulic Calculations

ENMD0080

Prep.& Sub. of Hydraulic Calculations

19 10MAY09 31MAY09 28MAY09 18JUN09

16

0.00

ENMD0100

Prep.& Sub. of layout Dwg for CS & SS

24 10MAY09 06JUN09 29JUN09 27JUL09

43

0.00

Prep.& Sub. of layout Dwg for CS & SS Pipeline

ENMD0110

Prep.& Sub. of Iso. Drg.for CS & SS

24 10MAY09 06JUN09 28MAY09 24JUN09

16

0.00

Prep.& Sub. of Iso. Drg.for CS & SS Pipeline

ENMD0140

Prep. of layout Drawing for RTRP

20 10MAY09 01JUN09 17MAY09 08JUN09

6

0.00

Prep. of layout Drawing for RTRP

ENMD0220

Prep.& Sub. of Stress analysis report

20 10MAY09 01JUN09 04JUL09

27JUL09

47

0.00

Prep.& Sub. of Stress analysis report

ENMD0090

Review & Approval of Hydraulic

21 01JUN09 21JUN09 28JUL09

17AUG09

57

0.10

Review & Approval of Hydraulic calculations

ENMD0230

Review & Approval of Stress Analysis

21 02JUN09 22JUN09 28JUL09

17AUG09

56

0.22

Review & Approval of Stress Analysis Report

ENMD0120

Review & Approve layout Dwg for CS &

21 07JUN09 27JUN09 28JUL09

17AUG09

51

0.17

ENMD0130

Review & Approval Iso Drg. for CS & SS

21 07JUN09 27JUN09 28JUL09

17AUG09

51

0.17

ENMD0170

Approval of Stress Analysis report

0

22JUN09

17AUG09

55

0.00

ENMD0150

Approval of Layout drawing for CS & SS

0

27JUN09

17AUG09

50

0.00

Approval of Layout drawing for CS & SS Pipeline

ENMD0160

Approval of Iso drawing for CS & SS

0

27JUN09

17AUG09

50

0.00

Approval of Iso drawing for CS & SS Pipeline

Review & Approve layout Dwg for CS & SS Pipeline Review & Approval Iso Drg. for CS & SS Pipeline Approval of Stress Analysis report

CS PIPES Prep.& Sub. of Material Spec for CS Pipes

ENMS0100

Prep.& Sub. of Material Spec for CS

24 10MAY09 06JUN09 28MAY09 24JUN09

16

0.00

ENMS0110

Review & Approval Material Spec for CS

21 07JUN09 27JUN09 30JUN09 20JUL09

23

0.08

Review & Approval Material Spec for CS Pipes

ENMS0160

Approval Material Spec for CS Pipes

20JUL09

22

0.00

Approval Material Spec for CS Pipes Prep.& Sub. of Material Spec for CS Fittings

0

27JUN09

CS FITTING ENMS0120

Prep.& Sub. of Material Spec for CS

24 10MAY09 06JUN09 28MAY09 24JUN09

16

0.00

ENMS0130

Review & Approval Material Spec for CS

21 07JUN09 27JUN09 07JUL09

27JUL09

30

0.08

Review & Approval Material Spec for CS Fittings

RTRP PIPE SPOOLS Prep.& Sub. of Material Spec for RTR Pipe spool

ENMS0140

Prep.& Sub. of Material Spec for RTR

18 10MAY09 30MAY09 17MAY09 06JUN09

6

0.00

ENMS0150

Review & Approve Matl. Spec for RTRP

21 31MAY09 20JUN09 07JUN09 27JUN09

7

0.08

Review & Approve Matl. Spec for RTRP Pipe spool

ENMS0170

Approval Material Spec for RTRP

27JUN09

7

0.00

Approval Material Spec for RTRP

0

20JUN09

MECH VALVES Prep.& Sub. of Material Spec for Mech valves

ENMS0180

Prep.& Sub. of Material Spec for Mech

40 10MAY09 24JUN09 10MAY09 24JUN09

0

0.00

ENMS0190

Review & Approval Material Spec for

21 25JUN09 15JUL09

25JUN09 15JUL09

0

0.08

Review & Approval Material Spec for Mech valves

ENMS0200

Approval Material Spec for Mech. Valves

15JUL09

0

0.00

Approval Material Spec for Mech. Valves

0

15JUL09

SS PIPES ENMS0240

Prep.& Sub. of Material Spec for SS

25 26MAY09 23JUN09 18JUN09 16JUL09

20

0.00

ENMS0260

Review & Approval Material Spec for SS

21 24JUN09 14JUL09

25

0.03

Start Date Finish Date Data Date Critical Activity Run Date Early Bar

Progress Bar

Š Primavera Systems, Inc.

19JUL09

08AUG09

Prep.& Sub. of Material Spec for SS Pipes Review & Approval Material Spec for SS Pipes

P87/09 Sheet 2 of 20 22MAR09 87R1 12SEP10 REPLACEMENT OF EXISTING OILY & EFFLUENT WATER LINES WITH 22MAR09 RTRP IN GC-23 & GC-25 06MAY09 16:57 IMCO ENGINEERING AND CONSTRUCTION COMPANY BASELINE SCHEDULE (LEVEL-5)

Date 04APR09

Revision-0

Checked THK

Approved JC

30APR09

Revision-1

Revision

THK

JC


Activity ID

Activity Description

Orig Dur

Early Start

Early Finish

Late Start

Late CalTotal PROJ PHAS TRAK MATL AREA SUB UNIT DIS % Finish IDFloat WT

2009 2010 M APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP O

SS FITTINGS ENMS0250

Prep.& Sub. of Material Spec for SS

25 26MAY09 23JUN09 18JUN09 16JUL09

20

0.00

ENMS0270

Review & Approval Material Spec for SS

21 24JUN09 14JUL09

08AUG09

25

0.02

19JUL09

Prep.& Sub. of Material Spec for SS Fittings Review & Approval Material Spec for SS Fittings

CORROSION MONITORING FITTING ENMS0280

Prep.& Sub. Matl. Spec for corrosion

23 10MAY09 04JUN09 28MAY09 23JUN09

16

0.00

ENMS0290

Review& Approv. Matl. Spec-corrosion

21 05JUN09 25JUN09 24JUN09 14JUL09

19

0.07

106 10MAY09 24AUG09 10MAY09 31AUG09

0

0.50

Prep.& Sub. Matl. Spec for corrosion mont. fitti Review& Approv. Matl. Spec-corrosion mont. fitti

INSTRUMENTATION Subtotal DESIGN DRAWINGS & DOCUMENTS ENID0100

Prep.& Sub. of P&ID Diagram

26 10MAY09 08JUN09 10MAY09 08JUN09

0

0.00

Prep.& Sub. of P&ID Diagram

ENID0110

Prep.& Sub. of Instrument Hook up

20 19MAY09 10JUN09 24JUN09 16JUL09

31

0.00

Prep.& Sub. of Instrument Hook up Drwgs

ENID0160

Prep.& Sub. of Inst loc plan & cable

20 19MAY09 10JUN09 18JUL09

10AUG09

51

0.00

Prep.& Sub. of Inst loc plan & cable routing drg

ENID0180

Prep. & Sub. of loop diagram

20 19MAY09 10JUN09 18JUL09

10AUG09

51

0.00

Prep. & Sub. of loop diagram

ENID0200

Prep. & Sub. of Cable Schedule

20 19MAY09 10JUN09 18JUL09

10AUG09

51

0.00

Prep. & Sub. of Cable Schedule

ENID0130

Review & Approval of P&ID Diagram

21 09JUN09 29JUN09 11AUG09 31AUG09

63

0.06

Review & Approval of P&ID Diagram

ENID0140

Review & Approval of Instrument Hook

21 11JUN09 01JUL09

11AUG09 31AUG09

61

0.06

Review & Approval of Instrument Hook up drg

ENID0170

Rev. & Appr. Inst loc plan & cable

21 11JUN09 01JUL09

11AUG09 31AUG09

61

0.06

Rev. & Appr. Inst loc plan & cable routing drg

ENID0190

Review & Approval of loop diagram

21 11JUN09 01JUL09

11AUG09 31AUG09

61

0.06

Review & Approval of loop diagram

ENID0210

Review & Approval of Cable Schedule

21 11JUN09 01JUL09

11AUG09 31AUG09

61

0.04

Review & Approval of Cable Schedule

ENID0120

Prep.& Sub. of Cable Layout Drg

17 15JUN09 04JUL09

22JUL09

10AUG09

31

0.00

ENID0220

Approval of P&ID Diagram

29JUN09

31AUG09

62

0.00

ENID0150

Review & Approval of Cable layout drg

25JUL09

11AUG09 31AUG09

37

0.06

Review & Approval of Cable layout drg

ENID0230

Approval of Cable layout drg

25JUL09

31AUG09

37

0.00

Approval of Cable layout drg

0 21 05JUL09 0

Prep.& Sub. of Cable Layout Drg Approval of P&ID Diagram

CONTROL VALVES Prep.& Sub. of Material Spec for Control Valves

ENIS0100

Prep.& Sub. of Material Spec for Control

27 17MAY09 16JUN09 17MAY09 16JUN09

0

0.00

ENIS0110

Review& Approval Material Spec for

21 17JUN09 07JUL09

17JUN09 07JUL09

0

0.03

Review& Approval Material Spec for Control Valve

ENIS0120

Approval Matl Spec for Control Valves

07JUL09

07JUL09

0

0.00

Approval Matl Spec for Control Valves

03AUG09 23JUL09

0

TEMP RELIEF VALVES ENIS0240

Prep.& Sub. of Material Spec for TSV

16 15JUL09

10AUG09

6

0.00

ENIS0250

Review & Approval of Material Spec for

21 04AUG09 24AUG09 11AUG09 31AUG09

ENIS0260

Approval of Matl Spec for TSV

0

Prep.& Sub. of Material Spec for TSV

7

0.03

Review & Approval of Material Spec for TSV

24AUG09

31AUG09

7

0.00

Approval of Matl Spec for TSV

03AUG09 23JUL09

FLOW ELEMENTS ENIS0200

Prep.& Sub. of Material Spec for Flow

16 15JUL09

10AUG09

6

0.00

ENIS0210

Review & Approval Material Spec for

21 04AUG09 24AUG09 11AUG09 31AUG09

7

0.03

Prep.& Sub. of Material Spec for Flow Elements Review & Approval Material Spec for Flow Element

TEMP ELEMENTS ENIS0220

Prep.& Sub. of Material Spec for

16 15JUL09

03AUG09 23JUL09

10AUG09

6

0.00

ENIS0230

Review & Approval Material Spec for

21 04AUG09 24AUG09 11AUG09 31AUG09

7

0.02

16 15JUL09

6

0.00

Prep.& Sub. of Material Spec for Temp.Elements Review & Approval Material Spec for Temp Element

INST. CABLES ENIS0140

Prep.& Sub. of Material Spec for Inst. Start Date Finish Date Data Date Critical Activity Run Date Early Bar

Progress Bar

Š Primavera Systems, Inc.

03AUG09 23JUL09

10AUG09

Prep.& Sub. of Material Spec for Inst. Cables

P87/09 Sheet 3 of 20 22MAR09 87R1 12SEP10 REPLACEMENT OF EXISTING OILY & EFFLUENT WATER LINES WITH 22MAR09 RTRP IN GC-23 & GC-25 06MAY09 16:57 IMCO ENGINEERING AND CONSTRUCTION COMPANY BASELINE SCHEDULE (LEVEL-5)

Date 04APR09

Revision-0

Checked THK

Approved JC

30APR09

Revision-1

Revision

THK

JC


Activity ID

Activity Description

Orig Dur

Early Start

Early Finish

Late Start

Late CalTotal PROJ PHAS TRAK MATL AREA SUB UNIT DIS % Finish IDFloat WT

2009 2010 M APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP O

INST. CABLES ENIS0150

Review & Approval Material Spec for

21 04AUG09 24AUG09 11AUG09 31AUG09

7

0.03

Review & Approval Material Spec for Inst. Cables

JUNCTION BOX 03AUG09 23JUL09

Prep.& Sub. of Material Spec for JB's

ENIS0270

Prep.& Sub. of Material Spec for JB's

16 15JUL09

10AUG09

6

0.00

ENIS0280

Review & Approval Material Spec for

21 04AUG09 24AUG09 11AUG09 31AUG09

7

0.00

Review & Approval Material Spec for JB's

BULK MATERIAL ENIS0180

Prep.& Sub. of Material Spec for Bulk

16 15JUL09

10AUG09

6

0.00

Prep.& Sub. of Material Spec for Bulk Material

ENIS0190

Review & Approval of Bulk Material

21 04AUG09 24AUG09 11AUG09 31AUG09

7

0.02

Review & Approval of Bulk Material Spec.

124 22APR09 24AUG09 22APR09 31AUG09

0

2.00

35 22APR09 01JUN09 22APR09 01JUN09

0

0.20

35 22APR09 01JUN09 22APR09 01JUN09

0

0.20

03AUG09 23JUL09

GC-25 Subtotal SITE SURVEY Subtotal

ENGS0400

Site Survey & Data Collection

Site Survey & Data Collection

CIVIL & STRUCTURAL Subtotal

56 23JUN09 18AUG09 06JUL09

31AUG09

12

0.20

DESIGN DRAWINGS & DOCUMENTS ENCD0410

Prep. & Sub. of Civil Drawings

30 23JUN09 28JUL09

06JUL09

10AUG09

11

0.00

Prep. & Sub. of Civil Drawings

ENCD0450

Preparation of Dwg for Str. Steel Support

30 23JUN09 28JUL09

06JUL09

10AUG09

11

0.00

Preparation of Dwg for Str. Steel Support

ENCD0400

Review & Approval of civil drawings

21 29JUL09

18AUG09 11AUG09 31AUG09

13

0.07

Review & Approval of civil drawings

ENCD0440

Review & Approval of dwg for str. steel

21 29JUL09

18AUG09 11AUG09 31AUG09

13

0.07

Review & Approval of dwg for str. steel support

10AUG09

11

0.00

18AUG09 11AUG09 31AUG09

13

0.03

10AUG09

11

0.00

18AUG09 11AUG09 31AUG09

13

0.03

10MAY09 08AUG09

0

1.10

STRUCTURAL STEEL SUPPORT ENCS0420

Prep. & Sub. of Material Spec for Stru.

30 23JUN09 28JUL09

ENCS0430

Review& Approval Material Spec for

21 29JUL09

06JUL09

Prep. & Sub. of Material Spec for Stru. Supports Review& Approval Material Spec for Stru. Support

CIVIL MATERIALS ENCS0440

Prep.& Sub. of Material Spec for Civil

30 23JUN09 28JUL09

ENCS0450

Review & Approval Material Spec for

21 29JUL09

06JUL09

Prep.& Sub. of Material Spec for Civil Matls Review & Approval Material Spec for Civil Matls

MECHANICAL & PIPING Subtotal

66 10MAY09 15JUL09

DESIGN DRAWINGS & DOCUMENTS Prep.& Sub. of Hydraulic Calculations

ENMD0400

Prep.& Sub. of Hydraulic Calculations

19 10MAY09 31MAY09 28MAY09 18JUN09

16

0.00

ENMD0420

Prep.& Sub. of layout Dwg for CS & SS

24 10MAY09 06JUN09 28MAY09 24JUN09

16

0.00

ENMD0430

Prep.& Sub. of Iso. Drg.for CS & SS

24 10MAY09 06JUN09 28MAY09 24JUN09

16

0.00

ENMD0460

Prep. of layout Drawing for RTRP line

20 10MAY09 01JUN09 23MAY09 14JUN09

11

0.00

Prep. of layout Drawing for RTRP line

ENMD0500

Prep.& Sub. of Stress analysis report

20 10MAY09 01JUN09 07JUN09 29JUN09

24

0.00

Prep.& Sub. of Stress analysis report

ENMD0410

Review & Approval of Hydraulic

21 01JUN09 21JUN09 30JUN09 20JUL09

29

0.10

Review & Approval of Hydraulic calculations

ENMD0510

Review & Approval of Stress Analysis

21 02JUN09 22JUN09 30JUN09 20JUL09

28

0.22

Review & Approval of Stress Analysis Report

ENMD0440

Review & Approve layout Dwg for CS &

21 07JUN09 27JUN09 30JUN09 20JUL09

23

0.17

Review & Approve layout Dwg for CS & SS Pipeline

ENMD0450

Review & Approval Iso Drg. for CS & SS

21 07JUN09 27JUN09 30JUN09 20JUL09

23

0.17

Review & Approval Iso Drg. for CS & SS Pipeline

Start Date Early Bar Finish Date Progress Bar Data Date Critical Activity Run Date

Š Primavera Systems, Inc.

Prep.& Sub. of layout Dwg for CS & SS Pipeline Prep.& Sub. of Iso. Drg.for CS & SS Pipeline

P87/09 Sheet 4 of 20 22MAR09 87R1 12SEP10 REPLACEMENT OF EXISTING OILY & EFFLUENT WATER LINES WITH 22MAR09 RTRP IN GC-23 & GC-25 06MAY09 16:57 IMCO ENGINEERING AND CONSTRUCTION COMPANY BASELINE SCHEDULE (LEVEL-5)

Date 04APR09

Revision-0

Checked THK

Approved JC

30APR09

Revision-1

Revision

THK

JC


Activity ID

Activity Description

Orig Dur

Early Start

Early Finish

Late Start

Late CalTotal PROJ PHAS TRAK MATL AREA SUB UNIT DIS % Finish IDFloat WT

2009 2010 M APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP O

DESIGN DRAWINGS & DOCUMENTS Approval of Stress Analysis report

ENMD0490

Approval of Stress Analysis report

0

22JUN09

20JUL09

27

0.00

ENMD0470

Approval of layout drg for CS & SS

0

27JUN09

20JUL09

22

0.00

Approval of layout drg for CS & SS Pipeline

ENMD0480

Approval Iso drg for CS & SS Pipeline

0

27JUN09

20JUL09

22

0.00

Approval Iso drg for CS & SS Pipeline Prep.& Sub. of Material Spec for CS Pipes

CS PIPES ENMS0400

Prep.& Sub. of Material Spec for CS

24 10MAY09 06JUN09 28MAY09 24JUN09

16

0.00

ENMS0410

Review & Approval Material Spec for CS

21 07JUN09 27JUN09 07JUL09

27JUL09

30

0.08

Review & Approval Material Spec for CS Pipes

ENMS0520

Approval of Material Spec for CS Pipes

27JUL09

29

0.00

Approval of Material Spec for CS Pipes Prep.& Sub. of Material Spec for CS Fittings

0

27JUN09

CS FITTING ENMS0420

Prep.& Sub. of Material Spec for CS

24 10MAY09 06JUN09 08JUN09 05JUL09

25

0.00

ENMS0430

Review & Approval Material Spec for CS

21 07JUN09 27JUN09 07JUL09

27JUL09

30

0.08

Review & Approval Material Spec for CS Fittings

RTRP PIPE SPOOLS Prep.& Sub. of Material Spec for RTR Pipe spool

ENMS0440

Prep.& Sub. of Material Spec for RTR

18 10MAY09 30MAY09 23MAY09 11JUN09

11

0.00

ENMS0450

Review & Approve Matl. Spec for RTRP

21 31MAY09 20JUN09 13JUN09 03JUL09

13

0.08

Review & Approve Matl. Spec for RTRP Pipe spool

ENMS0530

Approval of Materail Spec for RTRP

02JUL09

12

0.00

Approval of Materail Spec for RTRP

0

20JUN09

MECH VALVES Prep.& Sub. of Material Spec for Mech valves

ENMS0460

Prep.& Sub. of Material Spec for Mech

40 10MAY09 24JUN09 10MAY09 24JUN09

0

0.00

ENMS0470

Review & Approval Material Spec for

21 25JUN09 15JUL09

25JUN09 15JUL09

0

0.08

Review & Approval Material Spec for Mech valves

ENMS0540

Approval Matl Spec for Mech Valves

15JUL09

0

0.00

Approval Matl Spec for Mech Valves

0

15JUL09

SS PIPES ENMS0480

Prep.& Sub. of Material Spec for SS

25 26MAY09 23JUN09 18JUN09 16JUL09

20

0.00

ENMS0500

Review & Approval Material Spec for SS

21 24JUN09 14JUL09

25

0.03

ENMS0490

Prep.& Sub. of Material Spec for SS

25 26MAY09 23JUN09 18JUN09 16JUL09

20

0.00

ENMS0510

Review & Approval Material Spec for SS

21 24JUN09 14JUL09

08AUG09

25

0.02

19JUL09

08AUG09

Prep.& Sub. of Material Spec for SS Pipes Review & Approval Material Spec for SS Pipes

SS FITTINGS 19JUL09

Prep.& Sub. of Material Spec for SS Fittings Review & Approval Material Spec for SS Fittings

CORROSION MONITORING FITTING ENMS0495

Prep.& Sub. Matl. Spec for corrosion

23 10MAY09 04JUN09 28MAY09 23JUN09

16

0.00

ENMS0515

Review& Approv. Matl. Spec-corrosion

21 05JUN09 25JUN09 24JUN09 14JUL09

19

0.07

106 10MAY09 24AUG09 10MAY09 31AUG09

0

0.50

Prep.& Sub. Matl. Spec for corrosion mont. fitti Review& Approv. Matl. Spec-corrosion mont. fitti

INSTRUMENTATION Subtotal DESIGN DRAWINGS & DOCUMENTS ENID0400

Prep.& Sub. of P&ID Diagram

26 10MAY09 08JUN09 10MAY09 08JUN09

0

0.00

Prep.& Sub. of P&ID Diagram

ENID0410

Prep.& Sub. of Instrument Hook up

20 20MAY09 11JUN09 25JUN09 18JUL09

31

0.00

Prep.& Sub. of Instrument Hook up Drwgs

ENID0460

Prep.& Sub. of Inst loc plan & cable

20 20MAY09 11JUN09 25JUN09 18JUL09

31

0.00

Prep.& Sub. of Inst loc plan & cable routing drg

ENID0480

Prep. & Sub. of loop diagram

20 20MAY09 11JUN09 25JUN09 18JUL09

31

0.00

Prep. & Sub. of loop diagram

ENID0500

Prep. & Sub. of Cable Schedule

20 20MAY09 11JUN09 25JUN09 18JUL09

31

0.00

Prep. & Sub. of Cable Schedule

ENID0430

Review & Approval of P&ID Diagram

21 09JUN09 29JUN09 19JUL09

08AUG09

40

0.06

Review & Approval of P&ID Diagram

ENID0440

Review & Approval of Instrument Hook

21 12JUN09 02JUL09

19JUL09

08AUG09

37

0.06

Review & Approval of Instrument Hook up drg

ENID0470

Rev. & Appr. Inst loc plan & cable

21 12JUN09 02JUL09

19JUL09

08AUG09

37

0.06

Rev. & Appr. Inst loc plan & cable routing drg

Start Date Finish Date Data Date Critical Activity Run Date Early Bar

Progress Bar

Š Primavera Systems, Inc.

P87/09 Sheet 5 of 20 22MAR09 87R1 12SEP10 REPLACEMENT OF EXISTING OILY & EFFLUENT WATER LINES WITH 22MAR09 RTRP IN GC-23 & GC-25 06MAY09 16:57 IMCO ENGINEERING AND CONSTRUCTION COMPANY BASELINE SCHEDULE (LEVEL-5)

Date 04APR09

Revision-0

Checked THK

Approved JC

30APR09

Revision-1

Revision

THK

JC


Activity ID

Activity Description

Orig Dur

Early Start

Early Finish

Late Start

Late CalTotal PROJ PHAS TRAK MATL AREA SUB UNIT DIS % Finish IDFloat WT

2009 2010 M APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP O

DESIGN DRAWINGS & DOCUMENTS ENID0490

Review & Approval of loop diagram

21 12JUN09 02JUL09

19JUL09

08AUG09

37

0.06

Review & Approval of loop diagram

ENID0510

Review & Approval of Cable Schedule

21 12JUN09 02JUL09

19JUL09

08AUG09

37

0.05

Review & Approval of Cable Schedule

ENID0420

Prep.& Sub. of Cable Layout Drg

17 15JUN09 04JUL09

22JUL09

10AUG09

31

0.00

ENID0530

Approval of P&ID Diagram

29JUN09

08AUG09

39

0.00

ENID0450

Review & Approval of Cable layout drg

25JUL09

11AUG09 31AUG09

37

0.06

Review & Approval of Cable layout drg

ENID0540

Approval of Cable Layout drg

25JUL09

31AUG09

37

0.00

Approval of Cable Layout drg

0 21 05JUL09 0

Prep.& Sub. of Cable Layout Drg Approval of P&ID Diagram

CONTROL VALVES Prep.& Sub. of Material Spec for Control Valves

ENIS0400

Prep.& Sub. of Material Spec for Control

27 17MAY09 16JUN09 17MAY09 16JUN09

0

0.00

ENIS0410

Review& Approval Material Spec for

21 17JUN09 07JUL09

17JUN09 07JUL09

0

0.03

Review& Approval Material Spec for Control Valve

ENIS0460

Approval of Matl Spec for control valves

07JUL09

0

0.00

Approval of Matl Spec for control valves Prep.& Sub. of Material Spec for ESD Valves

0

07JUL09

ESD VALVES ENIS0420

Prep.& Sub. of Material Spec for ESD

27 17MAY09 16JUN09 24MAY09 23JUN09

6

0.00

ENIS0430

Review & Approval Material Spec for

21 17JUN09 07JUL09

24JUN09 14JUL09

7

0.03

Review & Approval Material Spec for ESD Valves

ENIS0470

Approval Matl Spec for ESD Valves

07JUL09

14JUL09

7

0.00

Approval Matl Spec for ESD Valves

03AUG09 23JUL09

0

FLOW ELEMENTS ENIS0500

Prep.& Sub. of Material Spec for Flow

16 15JUL09

10AUG09

6

0.00

ENIS0510

Review & Approval Material Spec for

21 04AUG09 24AUG09 11AUG09 31AUG09

7

0.03

Prep.& Sub. of Material Spec for Flow Elements Review & Approval Material Spec for Flow Element

INST. CABLES ENIS0440

Prep.& Sub. of Material Spec for Inst.

16 15JUL09

10AUG09

6

0.00

ENIS0450

Review & Approval Material Spec for

21 04AUG09 24AUG09 11AUG09 31AUG09

03AUG09 23JUL09

7

0.03

Prep.& Sub. of Material Spec for Inst. Cables Review & Approval Material Spec for Inst. Cables

JUNCTION BOX 03AUG09 23JUL09

Prep.& Sub. of Material Spec for JB's

ENIS0520

Prep.& Sub. of Material Spec for JB's

16 15JUL09

10AUG09

6

0.00

ENIS0530

Review & Approval Material Spec for

21 04AUG09 24AUG09 11AUG09 31AUG09

7

0.00

Review & Approval Material Spec for JB's

BULK MATERIAL ENIS0480

Prep.& Sub. of Material Spec for Bulk

16 15JUL09

10AUG09

6

0.00

Prep.& Sub. of Material Spec for Bulk Material

ENIS0490

Review & Approval of Bulk Material

21 04AUG09 24AUG09 11AUG09 31AUG09

7

0.03

Review & Approval of Bulk Material Spec.

ENID0520

Finish Engineering for GC-23 & GC-25

31AUG09

6

0.00

Finish Engineering for GC-23 & GC-25

121 23APR09 22AUG09 15MAY10 12SEP10

384

3.00

121 23APR09 22AUG09 15MAY10 12SEP10

384

1.50

121 23APR09 22AUG09 15MAY10 12SEP10

384

1.50

0

03AUG09 23JUL09 24AUG09

HAZOP/QRA/EIA STUDIES Subtotal GC-23 Subtotal

Subtotal

Hazop /QRA / EIA/ PSHER Studies

ENGS0110

Hazop /QRA / EIA/ PSHER Studies

85 23APR09 01AUG09 15MAY10 22AUG10

322

0.00

ENGS0120

Review & Approval of HAZOP

21 02AUG09 22AUG09 23AUG10 12SEP10

386

1.50

Review & Approval of HAZOP /QRA/EIA/PSHER report

ENGS0130

Approval of Hazop reports

383

0.00

Approval of Hazop reports

Start Date Finish Date Data Date Critical Activity Run Date Early Bar

Progress Bar

Š Primavera Systems, Inc.

0

22AUG09

12SEP10

P87/09 Sheet 6 of 20 22MAR09 87R1 12SEP10 REPLACEMENT OF EXISTING OILY & EFFLUENT WATER LINES WITH 22MAR09 RTRP IN GC-23 & GC-25 06MAY09 16:57 IMCO ENGINEERING AND CONSTRUCTION COMPANY BASELINE SCHEDULE (LEVEL-5)

Date 04APR09

Revision-0

Checked THK

Approved JC

30APR09

Revision-1

Revision

THK

JC


Activity ID

Activity Description

Orig Dur

Early Start

Early Finish

Late Start

Late CalTotal PROJ PHAS TRAK MATL AREA SUB UNIT DIS % Finish IDFloat WT

2009 2010 M APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP O

GC-25 Subtotal

Subtotal

121 23APR09 22AUG09 15MAY10 12SEP10

384

1.50

121 23APR09 22AUG09 15MAY10 12SEP10

384

1.50 Hazop /QRA / EIA / PSHER Studies

ENGS0410

Hazop /QRA / EIA / PSHER Studies

85 23APR09 01AUG09 15MAY10 22AUG10

322

0.00

ENGS0420

Review & Approval of HAZOP

21 02AUG09 22AUG09 23AUG10 12SEP10

386

1.50

Review & Approval of HAZOP /QRA/EIA/PSHER report

383

0.00

Approval of Hazop reports

ENGS0430 Approval of Hazop reports PROCUREMENT Subtotal

0

22AUG09

12SEP10

333 31MAY09 01MAY10 07JUN09 19MAY10

7 52.00

333 31MAY09 01MAY10 07JUN09 19MAY10

7 15.60

GC-23 Subtotal CIVIL & STRUCTURAL Subtotal

131 29JUL09

06DEC09 07SEP09 14JAN10

40

0.00

STRUCTURAL STEEL SUPPORT PROC0160

Proposal & Technical Bid Analysis

18 29JUL09

18AUG09 23SEP09 13OCT09

46

0.00

PROC0180

Sub. & Approval of Technical Proposal

21 19AUG09 08SEP09 14OCT09 03NOV09

56

0.00

PROC0150

Processing & Placing of P.O

7 09SEP09 16SEP09 04NOV09 11NOV09

46

0.00

PROC0170

Procurement of Materials

45 17SEP09 31OCT09 12NOV09 26DEC09

56

0.00

7 01NOV09 08NOV09 27DEC09 04JAN10

45

0.00

PROC0190 Material Delivery CIVIL MATERIALS PROC0260

Proposal & Technical Bid Analysis

18 29JUL09

18AUG09 07SEP09 29SEP09

34

0.00

PROC0280

Sub. & Approval of Technical Proposal

21 19AUG09 08SEP09 30SEP09 20OCT09

42

0.00

PROC0250

Processing & Placing of P.O

7 09SEP09 16SEP09 21OCT09 28OCT09

34

0.00

PROC0270

Procurement of Materials

70 17SEP09 25NOV09 29OCT09 06JAN10

42

0.00

7 29NOV09 06DEC09 07JAN10 14JAN10

32

0.00

PROC0290 Material Delivery MECHANICAL & PIPING Subtotal

333 31MAY09 01MAY10 07JUN09 19MAY10

Proposal & Technical Bid Analysis Sub. & Approval of Technical Proposal Processing & Placing of P.O Procurement of Materials Material Delivery Proposal & Technical Bid Analysis Sub. & Approval of Technical Proposal Processing & Placing of P.O Procurement of Materials Material Delivery

7 15.60

CS PIPES Proposal & Technical Bid Analysis

PROM0110

Proposal & Technical Bid Analysis

18 07JUN09 27JUN09 06JUL09

27JUL09

25

0.00

PROM0130

Sub. & Approval of Technical Proposal

21 28JUN09 18JUL09

17AUG09

30

0.00

PROM0100

Processing & Placing of P.O

18AUG09 24AUG09

25

0.00

PROM0120

Procurement of Materials

11OCT09 25AUG09 09NOV09

29

0.00

Procurement of Materials

PROM0140

Material Delivery

2 12OCT09 13OCT09 10NOV09 11NOV09

25

2.00

Material Delivery

0

11NOV09

25

0.00

CS Pipes receipt

PROM0160 CS Pipes receipt CS FITTING

6 19JUL09 77 27JUL09

26JUL09

28JUL09

13OCT09

PROM0180

Proposal & Technical Bid Analysis

18 07JUN09 27JUN09 06JUL09

27JUL09

25

0.00

PROM0185

Sub. & Approval of Technical Proposal

21 28JUN09 18JUL09

17AUG09

30

0.00

Start Date Finish Date Data Date Critical Activity Run Date Early Bar

Progress Bar

Š Primavera Systems, Inc.

28JUL09

Sub. & Approval of Technical Proposal Processing & Placing of P.O

Proposal & Technical Bid Analysis Sub. & Approval of Technical Proposal

P87/09 Sheet 7 of 20 22MAR09 87R1 12SEP10 REPLACEMENT OF EXISTING OILY & EFFLUENT WATER LINES WITH 22MAR09 RTRP IN GC-23 & GC-25 06MAY09 16:57 IMCO ENGINEERING AND CONSTRUCTION COMPANY BASELINE SCHEDULE (LEVEL-5)

Date 04APR09

Revision-0

Checked THK

Approved JC

30APR09

Revision-1

Revision

THK

JC


Activity ID

Activity Description

Orig Dur

Early Start

Early Finish

Late Start

Late CalTotal PROJ PHAS TRAK MATL AREA SUB UNIT DIS % Finish IDFloat WT

2009 2010 M APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP O

CS FITTING PROM0150

Processing & Placing of P.O

6 19JUL09

PROM0170

Procurement of Materials

PROM0190

Material Delivery

PROM0280

CS Fitting receipt

0

Processing & Placing of P.O

18AUG09 24AUG09

25

0.00

11OCT09 25AUG09 09NOV09

29

0.00

Procurement of Materials

2 12OCT09 13OCT09 10NOV09 11NOV09

25

0.64

Material Delivery

25

0.00

CS Fitting receipt

77 27JUL09

26JUL09

13OCT09

11NOV09

RTRP PIPE SPOOLS 0 31MAY09

Start Procurement in GC-23 & 25

6

0.00

PROM0175

Proposal & Technical Bid Analysis

18 31MAY09 20JUN09 07JUN09 27JUN09

6

0.00

PROM0195

Sub. & Approval of Technical Proposal

21 21JUN09 11JUL09

28JUN09 18JUL09

7

0.00

PROM0200

Processing & Placing of P.O

19JUL09

26JUL09

6

0.00

PROM0210

Prep. & Sub. of Drg. & Data sheets

16 19JUL09

13AUG09

6

0.00

PROM0230

Rev. & Approval of Drg. & Data Sheets

21 07AUG09 27AUG09 15AUG09 04SEP09

8

0.00

PROM0220

Procurement of Materials

122 28AUG09 27DEC09 05SEP09 04JAN10

8

0.00

PROM0240

Material Delivery

4 28DEC09 02JAN10 05JAN10 09JAN10

6

1.76

Material Delivery

PROM0300

RTRP Pipe spools receipt

0

RTRP Pipe spools receipt

6 12JUL09

07JUN09

Start Procurement in GC-23 & 25

PROM0165

18JUL09

06AUG09 27JUL09

02JAN10

09JAN10

6

0.00

25JUN09 15JUL09

Proposal & Technical Bid Analysis Sub. & Approval of Technical Proposal Processing & Placing of P.O Prep. & Sub. of Drg. & Data sheets Rev. & Approval of Drg. & Data Sheets Procurement of Materials

MECH VALVES PROM0320

Proposal & Technical Bid Analysis

18 25JUN09 15JUL09

PROM0330

Sub. & Approval of Technical Proposal

21 16JUL09

PROM0250

Processing & Placing of P.O

PROM0260

Sub. & Appr. of Drg. & Data sheets

PROM0270

Procurement of Materials

PROM0290 PROM0310

Proposal & Technical Bid Analysis

0

0.00

05AUG09

0

0.00

4 06AUG09 10AUG09 06AUG09 10AUG09

0

0.00

41 11AUG09 20SEP09 11AUG09 20SEP09

0

0.00

205 21SEP09 13APR10 21SEP09 13APR10

0

0.00

Material Delivery

6 14APR10 20APR10 14APR10 20APR10

0

9.92

Material Delivery

Mech Valves receipt

0

20APR10

0

0.00

Mech Valves receipt

05AUG09 16JUL09

20APR10

Sub. & Approval of Technical Proposal Processing & Placing of P.O Sub. & Appr. of Drg. & Data sheets Procurement of Materials

SS PIPES PROM0360

Proposal & Technical Bid Analysis

18 24JUN09 14JUL09

PROM0380

Sub. & Approval of Technical Proposal

21 15JUL09

08AUG09

20

0.00

04AUG09 09AUG09 29AUG09

PROM0350

Processing & Placing of P.O

PROM0370

Procurement of Materials

PROM0390

Material Delivery

18JUL09

25

0.00

6 05AUG09 11AUG09 30AUG09 05SEP09

21

0.00

60 12AUG09 10OCT09 06SEP09 04NOV09

25

0.00

6 11OCT09 17OCT09 05NOV09 11NOV09

22

0.18

Proposal & Technical Bid Analysis Sub. & Approval of Technical Proposal Processing & Placing of P.O Procurement of Materials Material Delivery

SS FITTINGS PROM0410

Proposal & Technical Bid Analysis

18 24JUN09 14JUL09

PROM0430

Sub. & Approval of Technical Proposal

21 15JUL09

08AUG09

20

0.00

04AUG09 09AUG09 29AUG09

PROM0400

Processing & Placing of P.O

PROM0420

Procurement of Materials

PROM0440

Material Delivery

18JUL09

25

0.00

6 05AUG09 11AUG09 30AUG09 05SEP09

21

0.00

60 12AUG09 10OCT09 06SEP09 04NOV09

25

0.00

6 11OCT09 17OCT09 05NOV09 11NOV09

22

0.06

Proposal & Technical Bid Analysis Sub. & Approval of Technical Proposal Processing & Placing of P.O Procurement of Materials Material Delivery

CORROSION MONITORING FITTING PROM0450

Proposal & Technical Bid Analysis

18 06JUN09 25JUN09 24JUN09 14JUL09

16

0.00

PROM0460

Sub. & Approval of Technical Proposal

21 26JUN09 16JUL09

04AUG09

19

0.00

PROM0470

Processing & Placing of P.O

05AUG09 09AUG09

15

0.00

Start Date Finish Date Data Date Critical Activity Run Date Early Bar

Progress Bar

Š Primavera Systems, Inc.

4 18JUL09

22JUL09

15JUL09

Proposal & Technical Bid Analysis Sub. & Approval of Technical Proposal Processing & Placing of P.O

P87/09 Sheet 8 of 20 22MAR09 87R1 12SEP10 REPLACEMENT OF EXISTING OILY & EFFLUENT WATER LINES WITH 22MAR09 RTRP IN GC-23 & GC-25 06MAY09 16:57 IMCO ENGINEERING AND CONSTRUCTION COMPANY BASELINE SCHEDULE (LEVEL-5)

Date 04APR09

Revision-0

Checked THK

Approved JC

30APR09

Revision-1

Revision

THK

JC


Activity ID

Activity Description

Orig Dur

Early Start

Early Finish

Late Start

Late CalTotal PROJ PHAS TRAK MATL AREA SUB UNIT DIS % Finish IDFloat WT

2009 2010 M APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP O

CORROSION MONITORING FITTING PROM0480

Sub. & Approv. of Details and

PROM0490

Procurement of Materials

PROM0500

Material Delivery

PROM0510

Corrosion Monitoring Fitting receipt

39 23JUL09

30AUG09 10AUG09 17SEP09

18

0.00

236 31AUG09 23APR10 18SEP09 11MAY10

18

0.00

7 24APR10 01MAY10 12MAY10 19MAY10

16

1.04

0

19MAY10

16

0.00

307 17JUN09 22APR10 17JUN09 19MAY10

0

0.00

01MAY10

Sub. & Approv. of Details and Documents Procurement of Materials Material Delivery Corrosion Monitoring Fitting receipt

INSTRUMENTATION Subtotal CONTROL VALVES PROI0330

Proposal & Technical Bid Analysis

18 17JUN09 07JUL09

17JUN09 07JUL09

0

0.00

PROI0280

Sub. & Approval of Technical Proposal

21 08JUL09

08JUL09

28JUL09

0

0.00

PROI0250

Processing & Placing of P.O

PROI0260

Sub. & Appr. of Drg. & Data sheets

PROI0270

Procurement of Materials

PROI0290 PROI0310

3 29JUL09

28JUL09

01AUG09 29JUL09

Proposal & Technical Bid Analysis Sub. & Approval of Technical Proposal Processing & Placing of P.O

01AUG09

0

0.00

31 02AUG09 01SEP09 02AUG09 01SEP09

0

0.00

229 02SEP09 18APR10 02SEP09 18APR10

0

0.00

Material Delivery

4 19APR10 22APR10 19APR10 22APR10

0

0.00

Material Delivery

Control Valves receipt

0

22APR10

0

0.00

Control Valves receipt

22APR10

Sub. & Appr. of Drg. & Data sheets Procurement of Materials

TEMP RELIEF VALVES Proposal & Technical Bid Analysis

PROI0460

Proposal & Technical Bid Analysis

18 04AUG09 24AUG09 01SEP09 23SEP09

24

0.00

PROI0530

Sub. & Approval of Technical Proposal

21 25AUG09 14SEP09 24SEP09 14OCT09

30

0.00

PROI0450

Processing & Placing of P.O

6 15SEP09 23SEP09 15OCT09 21OCT09

24

0.00

PROI0470

Sub. & Appr. of Drg. & Data sheets

30 24SEP09 23OCT09 22OCT09 20NOV09

28

0.00

PROI0480

Procurement of Materials

175 24OCT09 16APR10 21NOV09 14MAY10

28

0.00

PROI0490

Material Delivery

5 17APR10 21APR10 15MAY10 19MAY10

24

0.00

Material Delivery

PROI0510

Temp relief Valve receipt

0

19MAY10

24

0.00

Temp relief Valve receipt

21APR10

Sub. & Approval of Technical Proposal Processing & Placing of P.O Sub. & Appr. of Drg. & Data sheets Procurement of Materials

FLOW ELEMENTS PROI0380

Proposal & Technical Bid Analysis

18 04AUG09 24AUG09 06SEP09 28SEP09

28

0.00

PROI0410

Sub. & Approval of Technical Proposal

21 25AUG09 14SEP09 29SEP09 19OCT09

35

0.00

PROI0350

Processing & Placing of P.O

6 15SEP09 23SEP09 20OCT09 26OCT09

28

0.00

PROI0560

Sub. & Appr. of Drg. & Data sheets

30 24SEP09 23OCT09 27OCT09 25NOV09

33

0.00

PROI0370

Procurement of Materials

170 24OCT09 11APR10 26NOV09 14MAY10

33

0.00

PROI0390

Material Delivery

5 12APR10 17APR10 15MAY10 19MAY10

28

0.00

Proposal & Technical Bid Analysis Sub. & Approval of Technical Proposal Processing & Placing of P.O Sub. & Appr. of Drg. & Data sheets Procurement of Materials Material Delivery

TEMP ELEMENTS PROI0430

Proposal & Technical Bid Analysis

18 04AUG09 24AUG09 06SEP09 28SEP09

28

0.00

PROI0550

Sub. & Approval of Technical Proposal

21 25AUG09 14SEP09 29SEP09 19OCT09

35

0.00

PROI0400

Processing & Placing of P.O

6 15SEP09 23SEP09 20OCT09 26OCT09

28

0.00

PROI0570

Sub. & Appr. of Drg. & Data sheets

30 24SEP09 23OCT09 27OCT09 25NOV09

33

0.00

PROI0420

Procurement of Materials

170 24OCT09 11APR10 26NOV09 14MAY10

33

0.00

PROI0440

Material Delivery

5 12APR10 17APR10 15MAY10 19MAY10

28

0.00

7 25AUG09 01SEP09 15NOV09 22NOV09

68

0.00

Proposal & Technical Bid Analysis Sub. & Approval of Technical Proposal Processing & Placing of P.O Sub. & Appr. of Drg. & Data sheets Procurement of Materials Material Delivery

INST. CABLES PROI0100

Processing & Placing of P.O Start Date Finish Date Data Date Critical Activity Run Date Early Bar

Progress Bar

Š Primavera Systems, Inc.

Processing & Placing of P.O

P87/09 Sheet 9 of 20 22MAR09 87R1 12SEP10 REPLACEMENT OF EXISTING OILY & EFFLUENT WATER LINES WITH 22MAR09 RTRP IN GC-23 & GC-25 06MAY09 16:57 IMCO ENGINEERING AND CONSTRUCTION COMPANY BASELINE SCHEDULE (LEVEL-5)

Date 04APR09

Revision-0

Checked THK

Approved JC

30APR09

Revision-1

Revision

THK

JC


Activity ID

Activity Description

Orig Dur

Early Start

Early Finish

Late Start

Late CalTotal PROJ PHAS TRAK MATL AREA SUB UNIT DIS % Finish IDFloat WT

2009 2010 M APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP O

INST. CABLES PROI0120

Procurement of Materials

PROI0140

Material Delivery

170 02SEP09 18FEB10 23NOV09 11MAY10

82

0.00

7 20FEB10 28FEB10 12MAY10 19MAY10

68

0.00

Procurement of Materials Material Delivery

JUNCTION BOX PROI0500

Processing & Placing of P.O

PROI0520

Procurement of Materials

PROI0540

Material Delivery

7 25AUG09 01SEP09 24JAN10 31JAN10

124

0.00

100 02SEP09 10DEC09 01FEB10 11MAY10

152

0.00

7 12DEC09 20DEC09 12MAY10 19MAY10

126

0.00

7 25AUG09 01SEP09 02NOV09 09NOV09

57

0.00

50 02SEP09 21OCT09 10NOV09 29DEC09

69

0.00

7 22OCT09 29OCT09 30DEC09 07JAN10

56

0.00

Processing & Placing of P.O Procurement of Materials Material Delivery

BULK MATERIAL PROI0300

Processing & Placing of P.O

PROI0320

Procurement of Materials

PROI0340

Material Delivery

Processing & Placing of P.O Procurement of Materials Material Delivery

GC-25 Subtotal

333 31MAY09 01MAY10 13JUN09 19MAY10

13 36.40

131 29JUL09

06DEC09 23AUG09 16JAN10

25

0.00

CIVIL & STRUCTURAL Subtotal STRUCTURAL STEEL SUPPORT PROC0760

Proposal & Technical Bid Analysis

18 29JUL09

18AUG09 06OCT09 26OCT09

57

0.00

PROC0780

Sub. & Approval of Technical Proposal

21 19AUG09 08SEP09 27OCT09 16NOV09

69

0.00

PROC0750

Processing & Placing of P.O

7 09SEP09 16SEP09 17NOV09 24NOV09

57

0.00

PROC0770

Procurement of Materials

45 17SEP09 31OCT09 25NOV09 08JAN10

69

0.00

PROC0790

Material Delivery

7 01NOV09 08NOV09 09JAN10 16JAN10

55

0.00

Proposal & Technical Bid Analysis Sub. & Approval of Technical Proposal Processing & Placing of P.O Procurement of Materials Material Delivery

CIVIL MATERIALS PROC0860

Proposal & Technical Bid Analysis

18 29JUL09

18AUG09 23AUG09 12SEP09

21

0.00

PROC0880

Sub. & Approval of Technical Proposal

21 19AUG09 08SEP09 13SEP09 03OCT09

25

0.00

PROC0850

Processing & Placing of P.O

7 09SEP09 16SEP09 04OCT09 11OCT09

19

0.00

PROC0870

Procurement of Materials

70 17SEP09 25NOV09 12OCT09 20DEC09

25

0.00

PROC0890

Material Delivery

7 29NOV09 06DEC09 21DEC09 28DEC09

18

0.00

Proposal & Technical Bid Analysis Sub. & Approval of Technical Proposal Processing & Placing of P.O Procurement of Materials Material Delivery

MECHANICAL & PIPING Subtotal

333 31MAY09 01MAY10 13JUN09 19MAY10

13 36.40

CS PIPES Proposal & Technical Bid Analysis

PROM0710

Proposal & Technical Bid Analysis

18 07JUN09 27JUN09 06JUL09

27JUL09

25

0.00

PROM0730

Sub. & Approval of Technical Proposal

21 28JUN09 18JUL09

17AUG09

30

0.00

PROM0700

Processing & Placing of P.O

18AUG09 24AUG09

25

0.00

PROM0720

Procurement of Materials

11OCT09 25AUG09 09NOV09

29

0.00

Procurement of Materials

PROM0740

Material Delivery

2 12OCT09 13OCT09 10NOV09 11NOV09

25

4.67

Material Delivery

PROM0760

CS Pipes receipt

0

11NOV09

25

0.00

CS Pipes receipt

6 19JUL09 77 27JUL09

26JUL09

28JUL09

13OCT09

Sub. & Approval of Technical Proposal Processing & Placing of P.O

CS FITTING PROM0780

Proposal & Technical Bid Analysis

18 07JUN09 27JUN09 06JUL09

27JUL09

25

0.00

PROM0920

Sub. & Approval of Technical Proposal

21 28JUN09 18JUL09

17AUG09

30

0.00

Start Date Finish Date Data Date Critical Activity Run Date Early Bar

Progress Bar

Š Primavera Systems, Inc.

28JUL09

Proposal & Technical Bid Analysis Sub. & Approval of Technical Proposal

P87/09 Sheet 10 of 20 22MAR09 87R1 12SEP10 REPLACEMENT OF EXISTING OILY & EFFLUENT WATER LINES WITH 22MAR09 RTRP IN GC-23 & GC-25 06MAY09 16:58 IMCO ENGINEERING AND CONSTRUCTION COMPANY BASELINE SCHEDULE (LEVEL-5)

Date 04APR09

Revision-0

Checked THK

Approved JC

30APR09

Revision-1

Revision

THK

JC


Activity ID

Activity Description

Orig Dur

Early Start

Early Finish

Late Start

Late CalTotal PROJ PHAS TRAK MATL AREA SUB UNIT DIS % Finish IDFloat WT

2009 2010 M APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP O

CS FITTING PROM0750

Processing & Placing of P.O

6 19JUL09

PROM0770

Procurement of Materials

PROM0790

Material Delivery

PROM0880

CS Fitting receipt

0

Processing & Placing of P.O

18AUG09 24AUG09

25

0.00

11OCT09 25AUG09 09NOV09

29

0.00

Procurement of Materials

2 12OCT09 13OCT09 10NOV09 11NOV09

25

1.49

Material Delivery

25

0.00

CS Fitting receipt

77 27JUL09

26JUL09

13OCT09

11NOV09

RTRP PIPE SPOOLS PROM0785

Proposal & Technical Bid Analysis

18 31MAY09 20JUN09 13JUN09 02JUL09

PROM0795

Sub. & Approval of Technical Proposal

21 21JUN09 11JUL09

PROM0800

Processing & Placing of P.O

PROM0810

Prep. & Sub. of Drg. & Data sheets

16 19JUL09

PROM0830

Rev. & App. of Drg. & Data sheets

PROM0820

Procurement of Materials

PROM0840 PROM0900

Proposal & Technical Bid Analysis

11

0.00

04JUL09

24JUL09

13

0.00

25JUL09

30JUL09

10

0.00

06AUG09 01AUG09 18AUG09

10

0.00

21 07AUG09 27AUG09 19AUG09 08SEP09

12

0.00

122 28AUG09 27DEC09 09SEP09 08JAN10

12

0.00

Material Delivery

4 28DEC09 02JAN10 09JAN10 12JAN10

9

4.11

Material Delivery

RTRP Pipe spools receipt

0

RTRP Pipe spools receipt

6 12JUL09

18JUL09

02JAN10

12JAN10

9

0.00

25JUN09 15JUL09

Sub. & Approval of Technical Proposal Processing & Placing of P.O Prep. & Sub. of Drg. & Data sheets Rev. & App. of Drg. & Data sheets Procurement of Materials

MECH VALVES 0

0.00

05AUG09

0

0.00

4 06AUG09 10AUG09 06AUG09 10AUG09

0

0.00

41 11AUG09 20SEP09 11AUG09 20SEP09

0

0.00

205 21SEP09 13APR10 21SEP09 13APR10

0

0.00

Proposal & Technical Bid Analysis

PROM0930

Proposal & Technical Bid Analysis

18 25JUN09 15JUL09

PROM0940

Sub. & Approval of Technical Proposal

21 16JUL09

PROM0850

Processing & Placing of P.O

PROM0860

Sub. & Appr. of Drg. & Data sheets

PROM0870

Procurement of Materials

PROM0890

Material Delivery

6 14APR10 20APR10 14APR10 20APR10

0 23.16

Material Delivery

PROM0910

Mech Valves receipt

0

20APR10

0

0.00

Mech Valves receipt

05AUG09 16JUL09

20APR10

Sub. & Approval of Technical Proposal Processing & Placing of P.O Sub. & Appr. of Drg. & Data sheets Procurement of Materials

SS PIPES PROM0960

Proposal & Technical Bid Analysis

18 24JUN09 14JUL09

PROM0980

Sub. & Approval of Technical Proposal

21 15JUL09

08AUG09

20

0.00

04AUG09 09AUG09 29AUG09

PROM0950

Processing & Placing of P.O

PROM0970

Procurement of Materials

PROM0990

Material Delivery

18JUL09

25

0.00

6 05AUG09 11AUG09 30AUG09 05SEP09

21

0.00

60 12AUG09 10OCT09 06SEP09 04NOV09

25

0.00

6 11OCT09 17OCT09 05NOV09 11NOV09

22

0.41

Proposal & Technical Bid Analysis Sub. & Approval of Technical Proposal Processing & Placing of P.O Procurement of Materials Material Delivery

SS FITTINGS PROM1010

Proposal & Technical Bid Analysis

18 24JUN09 14JUL09

PROM1030

Sub. & Approval of Technical Proposal

21 15JUL09

08AUG09

20

0.00

04AUG09 09AUG09 29AUG09

PROM1000

Processing & Placing of P.O

PROM1020

Procurement of Materials

PROM1040

Material Delivery

18JUL09

25

0.00

6 05AUG09 11AUG09 30AUG09 05SEP09

21

0.00

60 12AUG09 10OCT09 06SEP09 04NOV09

25

0.00

6 11OCT09 17OCT09 05NOV09 11NOV09

22

0.13

Proposal & Technical Bid Analysis Sub. & Approval of Technical Proposal Processing & Placing of P.O Procurement of Materials Material Delivery

CORROSION MONITORING FITTING PROM1050

Proposal & Technical Bid Analysis

18 06JUN09 25JUN09 24JUN09 14JUL09

16

0.00

PROM1060

Sub. & Approval of Technical Proposal

21 26JUN09 16JUL09

04AUG09

19

0.00

PROM1070

Processing & Placing of P.O

05AUG09 09AUG09

15

0.00

PROM1080

Sub. & Appr. of Drg. & Data sheets

30AUG09 10AUG09 17SEP09

18

0.00

Start Date Finish Date Data Date Critical Activity Run Date Early Bar

Progress Bar

Š Primavera Systems, Inc.

4 18JUL09 39 23JUL09

22JUL09

15JUL09

Proposal & Technical Bid Analysis Sub. & Approval of Technical Proposal Processing & Placing of P.O Sub. & Appr. of Drg. & Data sheets

P87/09 Sheet 11 of 20 22MAR09 87R1 12SEP10 REPLACEMENT OF EXISTING OILY & EFFLUENT WATER LINES WITH 22MAR09 RTRP IN GC-23 & GC-25 06MAY09 16:58 IMCO ENGINEERING AND CONSTRUCTION COMPANY BASELINE SCHEDULE (LEVEL-5)

Date 04APR09

Revision-0

Checked THK

Approved JC

30APR09

Revision-1

Revision

THK

JC


Activity ID

Activity Description

Orig Dur

Early Start

Early Finish

Late Start

Late CalTotal PROJ PHAS TRAK MATL AREA SUB UNIT DIS % Finish IDFloat WT

2009 2010 M APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP O

CORROSION MONITORING FITTING PROM1090

Procurement of Materials

PROM1100 PROM1110

Procurement of Materials

236 31AUG09 23APR10 18SEP09 11MAY10

18

0.00

Material Delivery

7 24APR10 01MAY10 12MAY10 19MAY10

16

2.43

Material Delivery

Corrosion Monitoring receipt

0

19MAY10

16

0.00

Corrosion Monitoring receipt

316 17JUN09 01MAY10 17JUN09 19MAY10

0

0.00

01MAY10

INSTRUMENTATION Subtotal CONTROL VALVES PROI0980

Proposal & Technical Bid Analysis

18 17JUN09 07JUL09

17JUN09 07JUL09

0

0.00

PROI1010

Sub. & Approval of Technical Proposal

21 08JUL09

08JUL09

28JUL09

0

0.00

PROI0850

Processing & Placing of P.O

01AUG09

0

0.00

PROI0860

Sub. & Appr. of Drg. & Data sheets

PROI0870

Procurement of Materials

PROI0890

3 29JUL09

28JUL09

01AUG09 29JUL09

31 02AUG09 01SEP09 02AUG09 01SEP09

0

0.00

229 02SEP09 18APR10 02SEP09 18APR10

0

0.00

Material Delivery

4 19APR10 22APR10 19APR10 22APR10

0

0.00

PROI0910

Control Valves receipt

0

22APR10

22APR10

0

0.00

PROI0960

Finish Procurement for GC-23 & 25

0

01MAY10

19MAY10

16

0.00

Proposal & Technical Bid Analysis Sub. & Approval of Technical Proposal Processing & Placing of P.O Sub. & Appr. of Drg. & Data sheets Procurement of Materials Material Delivery Control Valves receipt Finish Procurement for GC-23 & 25

ESD VALVES Proposal & Technical Bid Analysis

PROI1030

Proposal & Technical Bid Analysis

18 17JUN09 07JUL09

24JUN09 14JUL09

6

0.00

PROI1050

Sub. & Approval of Technical Proposal

21 08JUL09

15JUL09

04AUG09

7

0.00

PROI0800

Processing & Placing of P.O

01AUG09 05AUG09 08AUG09

6

0.00

PROI0810

Sub. & Appr. of Drg. & Data sheets

31 02AUG09 01SEP09 09AUG09 08SEP09

7

0.00

PROI0820

Procurement of Materials

229 02SEP09 18APR10 09SEP09 25APR10

7

0.00

PROI0840

Material Delivery

4 19APR10 22APR10 26APR10 29APR10

6

0.00

Material Delivery

PROI0880

ESD Valves receipt

0

29APR10

6

0.00

ESD Valves receipt

3 29JUL09

28JUL09

22APR10

Sub. & Approval of Technical Proposal Processing & Placing of P.O Sub. & Appr. of Drg. & Data sheets Procurement of Materials

FLOW ELEMENTS PROI1060

Proposal & Technical Bid Analysis

18 04AUG09 24AUG09 06SEP09 28SEP09

28

0.00

PROI1070

Sub. & Approval of Technical Proposal

21 25AUG09 14SEP09 29SEP09 19OCT09

35

0.00

PROI0950

Processing & Placing of P.O

6 15SEP09 23SEP09 20OCT09 26OCT09

28

0.00

PROI1000

Sub. & Appr. of Drg. & Data sheets

30 24SEP09 23OCT09 27OCT09 25NOV09

33

0.00

PROI0970

Procurement of Materials

170 24OCT09 11APR10 26NOV09 14MAY10

33

0.00

PROI0990

Material Delivery

5 12APR10 17APR10 15MAY10 19MAY10

28

0.00

Proposal & Technical Bid Analysis Sub. & Approval of Technical Proposal Processing & Placing of P.O Sub. & Appr. of Drg. & Data sheets Procurement of Materials Material Delivery

INST. CABLES PROI0700

Processing & Placing of P.O

PROI0720

Procurement of Materials

PROI0740

Material Delivery

7 25AUG09 01SEP09 15NOV09 22NOV09

68

0.00

170 02SEP09 18FEB10 23NOV09 11MAY10

82

0.00

7 20FEB10 28FEB10 12MAY10 19MAY10

68

0.00

7 25AUG09 01SEP09 24JAN10 31JAN10

124

0.00

100 02SEP09 10DEC09 01FEB10 11MAY10

152

0.00

7 12DEC09 20DEC09 12MAY10 19MAY10

126

0.00

Processing & Placing of P.O Procurement of Materials Material Delivery

JUNCTION BOX PROI1100

Processing & Placing of P.O

PROI1120

Procurement of Materials

PROI1140

Material Delivery

Start Date Finish Date Data Date Critical Activity Run Date Early Bar

Progress Bar

Š Primavera Systems, Inc.

Processing & Placing of P.O Procurement of Materials Material Delivery

P87/09 Sheet 12 of 20 22MAR09 87R1 12SEP10 REPLACEMENT OF EXISTING OILY & EFFLUENT WATER LINES WITH 22MAR09 RTRP IN GC-23 & GC-25 06MAY09 16:58 IMCO ENGINEERING AND CONSTRUCTION COMPANY BASELINE SCHEDULE (LEVEL-5)

Date 04APR09

Revision-0

Checked THK

Approved JC

30APR09

Revision-1

Revision

THK

JC


Activity ID

Activity Description

Orig Dur

Early Start

Early Finish

Late Start

Late CalTotal PROJ PHAS TRAK MATL AREA SUB UNIT DIS % Finish IDFloat WT

2009 2010 M APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP O

BULK MATERIAL PROI0900

Processing & Placing of P.O

PROI0920

Procurement of Materials

PROI0940

Material Delivery

7 25AUG09 01SEP09 08OCT09 15OCT09

36

0.00

50 02SEP09 21OCT09 16OCT09 04DEC09

44

0.00

7 22OCT09 29OCT09 05DEC09 12DEC09

35

0.00

Processing & Placing of P.O Procurement of Materials Material Delivery

CONSTRUCTION Subtotal

331 10OCT09 08SEP10 26OCT09 12SEP10

16 36.00

113 10OCT09 01FEB10 26OCT09 20FEB10

16

1.86

113 10OCT09 01FEB10 26OCT09 20FEB10

16

1.86

26 10OCT09 08NOV09 26OCT09 24NOV09

14

0.00

GENERAL Subtotal

Subtotal

Site Mobilization of Manpower & Equipment

CNGE0100

Site Mobilization of Manpower &

CNGE0110

Start Construction for GC-23 & 25

16

0.00

CNGE0120

Steel Piping Prefabrication,NDE &

56 25OCT09 02JAN10 12NOV09 20JAN10

16

1.86

CNGE0130

FBE Coating of CS Pipespools

60 19NOV09 01FEB10 10DEC09 20FEB10

16

0.00

FBE Coating of CS Pipespools

CNGE0140

Finish FBE Coating works

19

0.00

Finish FBE Coating works

0 25OCT09

0

12NOV09

01FEB10

20FEB10

Start Construction for GC-23 & 25 Steel Piping Prefabrication,NDE & Hydrotesting

GC-23 Subtotal

271 09DEC09 08SEP10 05JAN10 08SEP10

25 11.69

188 09DEC09 21JUL10

05JAN10 29AUG10

21

1.25

CN3AC0180 Pipe Support Foundation / Valve Pit

82 09DEC09 18MAR10 16JAN10 22APR10

30

0.10

CN3AC0130 Installation of new Pipe supports RTRP

77 26DEC09 28MAR10 05JAN10 06APR10

8

0.19

CN3AC0110 Excavation for UG Piping for RTRP

90 06JAN10 22APR10 13JAN10 29APR10

6

0.19

Excavation for UG Piping for RTRP

CN3AC0100 Excavation for UG Piping for Stl PIpes

77 16JAN10 17APR10 15FEB10 17MAY10

26

0.04

Excavation for UG Piping for Stl PIpes

CN3AC0120 Installation of new Pipe supports Stl Pipe

77 21JAN10 22APR10 15FEB10 17MAY10

21

0.04

CN3AC0140 Civil Works for Cable Trenches

15 05APR10 21APR10 07JUN10 23JUN10

54

0.04

CIVIL & STRUCTURAL Subtotal DESALTER A&B AREA

CN3AC0170 Backfilling for All excavations

35 10JUN10 21JUL10

24JUN10 04AUG10

12

0.15

CN3SC0110 Pipe Support Foundation / Valve Pit

86 27DEC09 08APR10 13JAN10 25APR10

14

0.10

CN3SC0130 Installation of new Pipe supports RTRP

91 27JAN10 15MAY10 13FEB10 31MAY10

14

0.20

CN3SC0170 Backfilling for All excavations

35 10JUN10 21JUL10

29AUG10

33

0.20

214 27JAN10 29AUG10 06FEB10 29AUG10

10

4.62

10

0.00

Pipe Support Foundation / Valve Pit works Installation of new Pipe supports RTRP

Installation of new Pipe supports Stl Pipe Civil Works for Cable Trenches Backfilling for All excavations

SEPERATOR AREA

19JUL10

Pipe Support Foundation / Valve Pit works Installation of new Pipe supports RTRP Backfilling for All excavations

MECHANICAL & PIPING Subtotal DESALTER A&B AREA CN3AM0115 Start Installation of RTRP Pipes

0 27JAN10

06FEB10

CN3AM0120 Installation of all AG RTRP Pipes

100 27JAN10 25MAY10 06FEB10 03JUN10

8

0.09

CN3AM0130 Installation of UG RTRP Pipes

100 30JAN10 27MAY10 06FEB10 03JUN10

6

0.09

Start Date Finish Date Data Date Critical Activity Run Date Early Bar

Progress Bar

© Primavera Systems, Inc.

Start Installation of RTRP Pipes Installation of all AG RTRP Pipes Installation of UG RTRP Pipes

P87/09 Sheet 13 of 20 22MAR09 87R1 12SEP10 REPLACEMENT OF EXISTING OILY & EFFLUENT WATER LINES WITH 22MAR09 RTRP IN GC-23 & GC-25 06MAY09 16:58 IMCO ENGINEERING AND CONSTRUCTION COMPANY BASELINE SCHEDULE (LEVEL-5)

Date 04APR09

Revision-0

Checked THK

Approved JC

30APR09

Revision-1

Revision

THK

JC


Activity ID

Activity Description

Orig Dur

Early Start

Early Finish

Late Start

Late CalTotal PROJ PHAS TRAK MATL AREA SUB UNIT DIS % Finish IDFloat WT

2009 2010 M APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP O

DESALTER A&B AREA CN3AM0105 Start Installation of Steel Pipes

0 02FEB10

06MAR10

32

CN3AM0110 Installation of all UG Steel Pipes

77 02FEB10 04MAY10 06MAR10 03JUN10

26

0.01

CN3AM0100 Installation of all AG Steel Pipes

77 08FEB10 10MAY10 06MAR10 03JUN10

21

0.03

CN3AM0140 Install Control Valves

36 24APR10 03JUN10 24APR10 03JUN10

0

1.57

CN3AM0160 Install Mech Valves

30 01MAY10 03JUN10 01MAY10 03JUN10

0

0.42

CN3AM0220 Installation of Corrosion Monitoring

28 02MAY10 02JUN10 03JUL10

53

0.03

CN3AM0190 Installation of Flow Elements

14 19MAY10 03JUN10 22JUN10 07JUL10

29

0.05

CN3AM0145 Finish Install control valves CN3AM0165 Finish Install Mech. Valves

04AUG10

Start Installation of Steel Pipes

0.00 Installation of all UG Steel Pipes Installation of all AG Steel Pipes

Install Control Valves Install Mech Valves Installation of Corrosion Monitoring Fittings Installation of Flow Elements

0

03JUN10

03JUN10

0

0.00

Finish Install control valves

0

03JUN10

Finish Install Mech. Valves

03JUN10

0

0.00

CN3AM0170 Hydrotesting of Pipelines

20 05JUN10 27JUN10 05JUN10 27JUN10

0

0.13

Hydrotesting of Pipelines

CN3AM0180 Painting of A/G Piping & Supports

11 28JUN10 10JUL10

0

0.01

Painting of A/G Piping & Supports

CN3AM0210 Tentative S/D to be discussed with KOC

25 11JUL10

04AUG10

0

0.43

100 03FEB10 01JUN10 20FEB10 17JUN10

14

0.20

CN3SM0160 Install Mech Valves

31 01MAY10 05JUN10 13MAY10 17JUN10

11

0.33

CN3SM0110 Installation of Corrosion Monitoring

28 02MAY10 02JUN10 28JUL10

74

0.07

CN3SM0170 Hydrotesting of Pipelines

20 06JUN10 28JUN10 19JUN10 11JUL10

11

0.14

CN3SM0180 Painting of Supports

20 29JUN10 22JUL10

11

0.00

28JUN10 10JUL10

04AUG10 11JUL10

Tentative S/D to be discussed with KOC staff

SEPERATOR AREA CN3SM0120 Installation of all AG RTRP Pipes

CN3SM0210 Tentative S/D to be discussed with KOC CN3SM0220 Finish Construction

12JUL10

29AUG10 04AUG10

25 05AUG10 29AUG10 05AUG10 29AUG10

0

1.02

29AUG10

0

0.00

155 02MAR10 04AUG10 08MAY10 16AUG10

67

5.30

0

29AUG10

Installation of all AG RTRP Pipes Install Mech Valves Installation of Corrosion Monitoring Fittings Hydrotesting of Pipelines Painting of Supports Tentative S/D to be discussed with KOC staff Finish Construction

INSTRUMENTATION Subtotal DESALTER A&B AREA CN3AI0155

Start Instrumentation works

67

0.00

CN3AI0160

Install Cable Trays

25 02MAR10 31MAR10 08MAY10 05JUN10

0 02MAR10

08MAY10

56

0.32

CN3AI0180

Installation of JB

25 01APR10 29APR10 06JUN10 04JUL10

56

0.02

Start Instrumentation works Install Cable Trays Installation of JB Installation of Inst. cables/ Tubing

CN3AI0140

Installation of Inst. cables/ Tubing

13 13APR10 27APR10 20JUN10 04JUL10

58

0.14

CN3AI0210

Calibration of instruments

27 18APR10 18MAY10 22MAY10 21JUN10

29

0.11

CN3AI0190

Air Supply Piping/ Tubing for Valves

25 19MAY10 16JUN10 06JUN10 04JUL10

15

0.70

CN3AI0120

Installation of Temp Elements

12 05JUN10 17JUN10 08JUL10

22JUL10

29

0.24

Installation of Temp Elements

CN3AI0130

Installation of Temp Relief Valve

12 05JUN10 17JUN10 08JUL10

22JUL10

29

2.61

Installation of Temp Relief Valve

CN3AI0170

Glanding & Termination works

15 17JUN10 04JUL10

22JUL10

15

0.34

CN3AI0200

Shutdown- Instrument work

25 11JUL10

04AUG10 23JUL10

16AUG10

12

0.82

CN3AI0230

Finish Instrumentation works

04AUG10

16AUG10

12

0.00

26 10AUG10 08SEP10 10AUG10 08SEP10

0

0.52

0

0.00

0

05JUL10

Calibration of instruments Air Supply Piping/ Tubing for Valves

Glanding & Termination works Shutdown- Instrument work Finish Instrumentation works

DEMOLITION Subtotal DESALTER A&B AREA CN3AD0115 Start Demolition Start Date Finish Date Data Date Critical Activity Run Date Early Bar

Progress Bar

Š Primavera Systems, Inc.

0 10AUG10

10AUG10

P87/09 Sheet 14 of 20 22MAR09 87R1 12SEP10 REPLACEMENT OF EXISTING OILY & EFFLUENT WATER LINES WITH 22MAR09 RTRP IN GC-23 & GC-25 06MAY09 16:58 IMCO ENGINEERING AND CONSTRUCTION COMPANY BASELINE SCHEDULE (LEVEL-5)

Start Demolition Date 04APR09

Revision-0

Checked THK

Approved JC

30APR09

Revision-1

Revision

THK

JC


Activity ID

Activity Description

Orig Dur

Early Start

Early Finish

Late Start

Late CalTotal PROJ PHAS TRAK MATL AREA SUB UNIT DIS % Finish IDFloat WT

2009 2010 M APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP O

DESALTER A&B AREA Demolition of Old reduntant Instruments & Cables

CN3AD0120 Demolition of Old reduntant Instruments

10 10AUG10 21AUG10 17AUG10 28AUG10

6

0.03

CN3AD0100 Demolition of Old Redundant pipe lines

10 22AUG10 01SEP10 29AUG10 08SEP10

6

0.19

Demolition of Old Redundant pipe lines

CN3AD0110 Demolition of Old redundant valves

10 22AUG10 01SEP10 29AUG10 08SEP10

6

0.05

Demolition of Old redundant valves

CN3SD0100 Demolition of Old reduntant Instruments

26 10AUG10 08SEP10 10AUG10 08SEP10

0

0.20

Demolition of Old reduntant Instruments & Cables

CN3SD0110 Demolition of Old redundant valves

26 10AUG10 08SEP10 10AUG10 08SEP10

0

0.05

Demolition of Old redundant valves

0

0.00

SEPERATOR AREA

CN3SD0130 Finish Demolition

0

08SEP10

08SEP10

Finish Demolition

GC-25 Subtotal

271 09DEC09 08SEP10 29DEC09 12SEP10

19 22.45

195 09DEC09 29JUL10

29DEC09 08SEP10

16

3.75

CN5AC0200 Pipe Support Foundation / Valve Pit

87 09DEC09 24MAR10 29DEC09 12APR10

16

0.04

CN5AC0120 Installation of new Pipe supports

87 16JAN10 28APR10 03FEB10 17MAY10

16

0.05

CN5AC0160 Civil Works for Cable Trenches

15 21APR10 08MAY10 03JUN10 20JUN10

37

0.02

CN5AC0190 Backfilling for All excavations

42 10JUN10 29JUL10

08SEP10

35

0.05

CN5WC0200 Pipe Support Foundation / Valve Pit

82 09DEC09 18MAR10 19JAN10 26APR10

33

0.09

CN5WC0100 Excavation for UG SteelPiping

77 28DEC09 30MAR10 17FEB10 19MAY10

43

0.32

CN5WC0120 Installation of new Pipe supports Steel

77 16JAN10 17APR10 23FEB10 25MAY10

33

0.14

CN5WC0160 Civil work for Cable trenches

15 10APR10 26APR10 23JUN10 10JUL10

64

0.05

CN5WC0190 Backfilling for All excavations

20 10JUN10 03JUL10

11JUL10

03AUG10

26

0.27

CN5WC0170 Fire Proofing Works

22 04JUL10

04AUG10 29AUG10

26

0.05

CN5EC0200 Pipe Support Foundation / Valve Pit

82 09DEC09 18MAR10 29DEC09 06APR10

16

0.33

CN5EC0140 Installation of new Pipe supports RTRP

77 24DEC09 27MAR10 15FEB10 17MAY10

44

0.22

CN5EC0120 Installation of new Pipe supports Steel

77 28DEC09 30MAR10 17JAN10 18APR10

16

0.22

CN5EC0110 Excavation of UG RTRP Pipes

90 03JAN10 19APR10 13JAN10 29APR10

9

0.66

Excavation of UG RTRP Pipes

CN5EC0100 Excavation for UG Steel Piping

77 16JAN10 17APR10 15FEB10 17MAY10

26

0.33

Excavation for UG Steel Piping

CN5EC0160 Civil works for cable trenches

15 07MAR10 24MAR10 06JUL10

103

0.11

CIVIL & STRUCTURAL Subtotal DESALTER A&B AREA

22JUL10

Pipe Support Foundation / Valve Pit works Installation of new Pipe supports Civil Works for Cable Trenches Backfilling for All excavations

WET CRUDE TANK AREA

29JUL10

Pipe Support Foundation / Valve Pit works Excavation for UG SteelPiping Installation of new Pipe supports Steel Pipe Civil work for Cable trenches Backfilling for All excavations Fire Proofing Works

PIPE WAY

CN5EC0190 Backfilling for All excavations

35 10JUN10 21JUL10

31JUL10

24JUL10

Pipe Support Foundation / Valve Pit works Installation of new Pipe supports RTRP Installation of new Pipe supports Steel Pipe

Civil works for cable trenches Backfilling for All excavations

08SEP10

42

0.33

CN5PC0200 Pipe Support Foundation / Valve Pit

82 09DEC09 18MAR10 16JAN10 22APR10

30

0.05

CN5PC0140 Installation of new Pipe supports RTRP

77 24DEC09 27MAR10 15FEB10 17MAY10

44

0.16

Installation of new Pipe supports RTRP

CN5PC0120 Installation of new Pipe supports Steel

77 16JAN10 17APR10 15FEB10 17MAY10

26

0.12

Installation of new Pipe supports Steel Pipe

CN5PC0160 Civil works for cable trenches

15 25MAR10 11APR10 12JUL10

93

0.05

PUMPING AREA

CN5PC0190 Backfilling for All excavations

Start Date Finish Date Data Date Critical Activity Run Date Early Bar

Progress Bar

Š Primavera Systems, Inc.

35 10JUN10 21JUL10

31JUL10

29JUL10 08SEP10

42

0.09

Pipe Support Foundation / Valve Pit works

Civil works for cable trenches Backfilling for All excavations

P87/09 Sheet 15 of 20 22MAR09 87R1 12SEP10 REPLACEMENT OF EXISTING OILY & EFFLUENT WATER LINES WITH 22MAR09 RTRP IN GC-23 & GC-25 06MAY09 16:58 IMCO ENGINEERING AND CONSTRUCTION COMPANY BASELINE SCHEDULE (LEVEL-5)

Date 04APR09

Revision-0

Checked THK

Approved JC

30APR09

Revision-1

Revision

THK

JC


Activity ID

Activity Description

Orig Dur

Early Start

Early Finish

Late Start

Late CalTotal PROJ PHAS TRAK MATL AREA SUB UNIT DIS % Finish IDFloat WT

2009 2010 M APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP O

MECHANICAL & PIPING Subtotal

235 06JAN10 29AUG10 25JAN10 29AUG10

19 11.92

DESALTER A&B AREA CN5AM0100 Installation of all AG Steel Pipes

95 24JAN10 16MAY10 11FEB10 03JUN10

16

0.15

CN5AM0150 Install Mech Valves

38 21APR10 03JUN10 21APR10 03JUN10

0

0.09

CN5AM0180 Installation of Corrosion Monitoring

28 02MAY10 02JUN10 03JUL10

CN5AM0190 Installation of Flow Elements

14 19MAY10 03JUN10 24JUN10 10JUL10

CN5AM0155 Finish Install Mech Valves CN5AM0160 Hydrotesting of Pipelines

0.01

31

0.05

03JUN10

0

0.00

20 05JUN10 27JUN10 05JUN10 27JUN10

0

0.01

Hydrotesting of Pipelines

0

0.03

Painting of A/G Piping & Supports

0

0.10

52

0.00

43

0.45

03JUN10

CN5AM0170 Painting of A/G Piping & Supports

11 28JUN10 10JUL10

CN5AM0200 Tentative S/D to be discussed with KOC WET CRUDE TANK AREA

25 11JUL10

04AUG10 11JUL10

0 06JAN10

27FEB10

CN5WM0105 Start Installation of Steel Pipes CN5WM0110 Installation of all UG Steel Pipes

28JUN10 10JUL10 04AUG10

90 06JAN10 22APR10 27FEB10 12JUN10

CN5WM0100 Installation of all AG Steel Pipes

90 18JAN10 04MAY10 27FEB10 12JUN10

33

0.07

CN5WM0150 Install Mech Valves

39 21APR10 05JUN10 28APR10 12JUN10

6

0.12

CN5WM0140 Install ESD Valves

37 24APR10 05JUN10 01MAY10 12JUN10

6

5.63

CN5WM0210 Installation of Corrosion Monitoring CN5WM0230 Finish Install ESD Valves

28 02MAY10 02JUN10 28JUL10 0

05JUN10

Install Mech Valves Install ESD Valves Installation of Corrosion Monitoring Fittings

0.00

Finish Install ESD Valves Hydrotesting of Pipelines

0.03

6

0.01

04AUG10

25 05AUG10 29AUG10 05AUG10 29AUG10

0

0.18

CN5EM0100 Installation of all AG Steel Pipes

110 06JAN10 16MAY10 25JAN10 03JUN10

16

1.90

CN5EM0110 Installation of all UG Steel Pipes

90 18JAN10 04MAY10 17FEB10 03JUN10

26

0.36

54

0.00

44

0.01

CN5EM0130 Installation of UG RTRP Pipes

Installation of all UG Steel Pipes Installation of all AG Steel Pipes

0.01

6

CN5EM0120 Installation of all AG RTRP Pipes

Start Installation of Steel Pipes

7

25 29JUN10 28JUL10

0 20JAN10

Tentative S/D to be discussed with KOC staff

74

20 06JUN10 28JUN10 13JUN10 05JUL10

CN5EM0115 Start Installation of RTRP

Finish Install Mech Valves

12JUN10

CN5WM0170 Painting of A/G Piping & Supports

06JUL10

Installation of Flow Elements

29AUG10

CN5WM0160 Hydrotesting of Pipelines CN5WM0200 Tentative S/D to be discussed with KOC PIPE WAY

Install Mech Valves Installation of Corrosion Monitoring Fittings

53

0

04AUG10

Installation of all AG Steel Pipes

15MAR10

70 20JAN10 13APR10 15MAR10 03JUN10

Painting of A/G Piping & Supports Tentative S/D to be discussed with KOC staff Installation of all AG Steel Pipes Installation of all UG Steel Pipes Start Installation of RTRP Installation of all AG RTRP Pipes Installation of UG RTRP Pipes

100 26JAN10 24MAY10 06FEB10 03JUN10

9

0.28

CN5EM0150 Install Mech Valves

38 21APR10 03JUN10 21APR10 03JUN10

0

0.07

CN5EM0210 Installation of Corrosion Monitoring

28 02MAY10 02JUN10 03JUL10

04AUG10

53

0.01

CN5EM0160 Hydrotesting of Pipelines

20 05JUN10 27JUN10 05JUN10 27JUN10

0

0.40

Hydrotesting of Pipelines Painting of A/G Piping & Supports

CN5EM0170 Painting of A/G Piping & Supports

11 28JUN10 10JUL10

0

0.60

CN5EM0200 Tentative S/D to be discussed with KOC PUMPING AREA

25 11JUL10

04AUG10

0

0.17

CN5PM0100 Installation of all AG Steel Pipes

90 18JAN10 04MAY10 17FEB10 03JUN10

26

0.05

CN5PM0120 Installation of all AG RTRP Pipes

70 20JAN10 13APR10 15MAR10 03JUN10

44

0.04

CN5PM0150 Install Mech Valves

38 21APR10 03JUN10 21APR10 03JUN10

0

0.10

CN5PM0135 Install Control Valves

36 24APR10 03JUN10 24APR10 03JUN10

0

0.70

CN5PM0130 Installation of Corrosion Monitoring Start Date Finish Date Data Date Critical Activity Run Date Early Bar

Progress Bar

Š Primavera Systems, Inc.

28JUN10 10JUL10

04AUG10 11JUL10

28 02MAY10 02JUN10 28JUL10

29AUG10

74

0.01

Install Mech Valves Installation of Corrosion Monitoring Fittings

Tentative S/D to be discussed with KOC staff Installation of all AG Steel Pipes Installation of all AG RTRP Pipes Install Mech Valves Install Control Valves Installation of Corrosion Monitoring Fittings

P87/09 Sheet 16 of 20 22MAR09 87R1 12SEP10 REPLACEMENT OF EXISTING OILY & EFFLUENT WATER LINES WITH 22MAR09 RTRP IN GC-23 & GC-25 06MAY09 16:58 IMCO ENGINEERING AND CONSTRUCTION COMPANY BASELINE SCHEDULE (LEVEL-5)

Date 04APR09

Revision-0

Checked THK

Approved JC

30APR09

Revision-1

Revision

THK

JC


Activity ID

Activity Description

Orig Dur

Early Start

Early Finish

Late Start

Late CalTotal PROJ PHAS TRAK MATL AREA SUB UNIT DIS % Finish IDFloat WT

2009 2010 M APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP O

PUMPING AREA CN5PM0140 Installation of Flow Elements

Installation of Flow Elements

32

0.05

03JUN10

0

0.00

CN5PM0160 Hydrotesting of Pipelines

20 05JUN10 27JUN10 05JUN10 27JUN10

0

0.03

Hydrotesting of Pipelines

CN5PM0170 Painting of A/G Piping & Supports

11 28JUN10 10JUL10

0

0.02

Painting of A/G Piping & Supports

CN5PM0200 Tentative S/D to be discussed with KOC

50 11JUL10

CN5PM0138 Finish Install control valves

CN5PM0210 Finish Construction

15 17MAY10 02JUN10 23JUN10 10JUL10 0

03JUN10

28JUN10 10JUL10

29AUG10 11JUL10

29AUG10

0

0.18

29AUG10

29AUG10

0

0.00

180 02MAR10 29AUG10 13APR10 12SEP10

42

6.00

0

Finish Install control valves

Tentative S/D to be discussed with KOC staff Finish Construction

INSTRUMENTATION Subtotal DESALTER A&B AREA CN5AI0155

Start Instrumentation works

42

0.00

CN5AI0160

Install Cable Trays

25 02MAR10 31MAR10 13APR10 11MAY10

0 02MAR10

13APR10

35

0.11

CN5AI0180

Installation of JB

25 01APR10 29APR10 29MAY10 26JUN10

49

0.02

CN5AI0210

Calibration of Instruments

27 18APR10 18MAY10 24MAY10 23JUN10

31

0.02

CN5AI0140

Installation of Inst. cables/ Tubing

13 29APR10 13MAY10 12JUN10 26JUN10

37

0.03

CN5AI0170

Glanding & Termination works

17 15MAY10 02JUN10 27JUN10 15JUL10

37

0.07

CN5AI0190

Instrument Air Supply Piping/ Tubing

26 03JUN10 03JUL10

CN5AI0200

Shut down - Instrument work

25 11JUL10

16AUG10

37

0.05

04AUG10 17AUG10 10SEP10

17JUL10

37

0.10

CN5WI0160 Install Cable Trays

25 01APR10 29APR10 12MAY10 09JUN10

35

0.94

CN5WI0140 Installation of Inst. cables/ Tubing

15 01MAY10 17MAY10 25JUL10

72

0.39

CN5WI0180 Installation of JB

26 01MAY10 30MAY10 10JUN10 10JUL10

35

0.03

Start Instrumentation works Install Cable Trays Installation of JB Calibration of Instruments Installation of Inst. cables/ Tubing Glanding & Termination works Instrument Air Supply Piping/ Tubing Shut down - Instrument work

WET CRUDE TANK AREA 10AUG10

Install Cable Trays Installation of Inst. cables/ Tubing Installation of JB

CN5WI0190 Instrument Air Supply Piping/ Tubing

28 29MAY10 29JUN10 08JUL10

10AUG10

35

0.46

Instrument Air Supply Piping/ Tubing

CN5WI0210 Calibration of Instruments

26 31MAY10 29JUN10 11JUL10

10AUG10

35

0.02

Calibration of Instruments

CN5WI0170 Glanding & Termination works

20 30JUN10 24JUL10

11AUG10 02SEP10

35

0.59

CN5WI0200 Shutdown - Instrument work

25 05AUG10 29AUG10 10AUG10 03SEP10

5

0.15

25 02MAR10 31MAR10 28APR10 26MAY10

48

0.17

Glanding & Termination works Shutdown - Instrument work

PIPE WAY CN5EI0160

Install Cable Trays

CN5EI0140

Installation of Inst. cables / Tubing

17 01APR10 20APR10 10JUL10

29JUL10

85

0.07

CN5EI0180

Installation of JB

25 01APR10 29APR10 30JUN10 29JUL10

77

0.01

CN5EI0210

Calibration of Instruments

25 18APR10 16MAY10 25MAY10 22JUN10

32

0.07

CN5EI0190

Air Supply Piping/Tubing for valves

30 17MAY10 20JUN10 24JUN10 29JUL10

33

0.11

CN5EI0170

Glanding & Termination works

17 21JUN10 10JUL10

18AUG10

33

0.13

CN5EI0200

Shutdown - Instrument work

25 11JUL10

04AUG10 19AUG10 12SEP10

39

0.07

31JUL10

Install Cable Trays Installation of Inst. cables / Tubing Installation of JB Calibration of Instruments Air Supply Piping/Tubing for valves Glanding & Termination works Shutdown - Instrument work

PUMPING AREA CN5PI0160

Install Cable Trays

25 01APR10 29APR10 27MAY10 24JUN10

48

0.32

CN5PI0210

Calibration of Instruments

25 18APR10 16MAY10 25MAY10 22JUN10

32

0.09

CN5PI0180

Installation of JB

25 01MAY10 29MAY10 26JUN10 25JUL10

48

0.01

CN5PI0140

Installation of Inst. cables/ Tubing

19 30MAY10 20JUN10 26JUL10

48

0.36

Start Date Finish Date Data Date Critical Activity Run Date Early Bar

Progress Bar

Š Primavera Systems, Inc.

16AUG10

Install Cable Trays Calibration of Instruments Installation of JB Installation of Inst. cables/ Tubing

P87/09 Sheet 17 of 20 22MAR09 87R1 12SEP10 REPLACEMENT OF EXISTING OILY & EFFLUENT WATER LINES WITH 22MAR09 RTRP IN GC-23 & GC-25 06MAY09 16:58 IMCO ENGINEERING AND CONSTRUCTION COMPANY BASELINE SCHEDULE (LEVEL-5)

Date 04APR09

Revision-0

Checked THK

Approved JC

30APR09

Revision-1

Revision

THK

JC


Activity ID

Activity Description

Orig Dur

Early Start

Early Finish

Late Start

Late CalTotal PROJ PHAS TRAK MATL AREA SUB UNIT DIS % Finish IDFloat WT

2009 2010 M APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP O

PUMPING AREA CN5PI0190

Air Supply Piping/ Tubing for Valves

24 31MAY10 27JUN10 19JUL10

CN5PI0170

Glanding & Termination works

15 28JUN10 14JUL10

CN5PI0200

Shutdown - Instrument work

25 11JUL10

CN5PI0220

Finish Instrumentation works

Air Supply Piping/ Tubing for Valves

16AUG10

42

0.60

17AUG10 02SEP10

42

0.76

04AUG10 10AUG10 03SEP10

30

0.25

04AUG10

03SEP10

30

0.00

26 10AUG10 08SEP10 10AUG10 08SEP10

0

0.78

0

0.00

Start Demolition Demolition of Old reduntant Instruments & Cables

0

Glanding & Termination works Shutdown - Instrument work Finish Instrumentation works

DEMOLITION Subtotal DESALTER A&B AREA CN5AD0115 Start Demolition

0 10AUG10

10AUG10

CN5AD0120 Demolition of Old reduntant Instruments

10 10AUG10 21AUG10 17AUG10 28AUG10

6

0.02

CN5AD0100 Demolition of Old Redundant pipe lines

10 22AUG10 01SEP10 29AUG10 08SEP10

6

0.12

Demolition of Old Redundant pipe lines

CN5AD0110 Demolition of Old redundant valves

10 22AUG10 01SEP10 29AUG10 08SEP10

6

0.04

Demolition of Old redundant valves

CN5WD0100 Demolition of Old Redundant pipe lines

26 10AUG10 08SEP10 10AUG10 08SEP10

0

0.14

CN5WD0110 Demolition of Old redundant valves

26 10AUG10 08SEP10 10AUG10 08SEP10

0

0.04

Demolition of Old redundant valves

CN5WD0120 Demolition of Old reduntant Instruments

26 10AUG10 08SEP10 10AUG10 08SEP10

0

0.02

Demolition of Old reduntant Instruments & Cables

CN5ED0100 Demolition of Old Redundant pipe lines

10 10AUG10 21AUG10 29AUG10 08SEP10

16

0.14

Demolition of Old Redundant pipe lines

CN5ED0110 Demolition of Old redundant valves

10 10AUG10 21AUG10 29AUG10 08SEP10

16

0.04

Demolition of Old redundant valves

CN5ED0120 Demolition of Old reduntant Cables/

10 10AUG10 21AUG10 29AUG10 08SEP10

16

0.02

Demolition of Old reduntant Cables/ Tubes

CN5PD0100 Demolition of Old Redundant pipe lines

26 10AUG10 08SEP10 10AUG10 08SEP10

0

0.14

Demolition of Old Redundant pipe lines

CN5PD0110 Demolition of Old redundant valves

26 10AUG10 08SEP10 10AUG10 08SEP10

0

0.04

Demolition of Old redundant valves Demolition of Old reduntant Instruments & Cables

WET CRUDE TANK AREA Demolition of Old Redundant pipe lines

PIPE WAY

PUMPING AREA

CN5PD0120 Demolition of Old reduntant Instruments CN5PD0130 Finish Demolition

26 10AUG10 08SEP10 10AUG10 08SEP10

0

0.02

08SEP10

0

0.00

87 09JUN10 04SEP10 05JUL10

04SEP10

26

5.00

86 10JUN10 04SEP10 06JUL10

04SEP10

25

2.00

86 10JUN10 04SEP10 06JUL10

04SEP10

25

2.00

05AUG10

22

0.70

09AUG10 07AUG10 16AUG10

7

0.30

0

08SEP10

Finish Demolition

PRECOMMISSIONING & COMMISSIONING Subtotal GC-23 Subtotal . Subtotal DESALTER A&B AREA PC3A0100

Precommissioning work

26 10JUN10 10JUL10

PC3A0110

Commissioning work

10 31JUL10

06JUL10

Precommissioning work Commissioning work

SEPERATOR AREA PC3S0100

Precommissioning work

26 24JUN10 25JUL10

24AUG10

26

0.70

PC3S0110

Commissioning work

10 25AUG10 03SEP10 25AUG10 03SEP10

0

0.30

PC3S0120

Finish Commissioning

0

0.00

Start Date Finish Date Data Date Critical Activity Run Date Early Bar

Progress Bar

Š Primavera Systems, Inc.

0

04SEP10

26JUL10

04SEP10

Precommissioning work

P87/09 Sheet 18 of 20 22MAR09 87R1 12SEP10 REPLACEMENT OF EXISTING OILY & EFFLUENT WATER LINES WITH 22MAR09 RTRP IN GC-23 & GC-25 06MAY09 16:58 IMCO ENGINEERING AND CONSTRUCTION COMPANY BASELINE SCHEDULE (LEVEL-5)

Commissioning work Finish Commissioning

Date 04APR09

Revision-0

Checked THK

Approved JC

30APR09

Revision-1

Revision

THK

JC


Activity ID

Activity Description

Orig Dur

Early Start

Early Finish

Late Start

Late CalTotal PROJ PHAS TRAK MATL AREA SUB UNIT DIS % Finish IDFloat WT

2009 2010 M APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP O

GC-25 Subtotal

86 09JUN10 03SEP10 05JUL10

03SEP10

26

3.00

86 09JUN10 03SEP10 05JUL10

03SEP10

26

3.00

27 09JUN10 10JUL10

05AUG10

22

0.53

09AUG10 07AUG10 16AUG10

7

0.22

. Subtotal DESALTER A&B AREA PC5A0100

Precommissioning work

05JUL10

PC5A0110 Commissioning work WET CRUDE TANK AREA

10 31JUL10

PC5W0100

Precommissioning work

33 27JUN10 04AUG10 17JUL10

24AUG10

17

0.53

PC5W0110 PIPE WAY

Commissioning work

10 25AUG10 03SEP10 25AUG10 03SEP10

0

0.22

PC5E0100

Precommissioning work

27 09JUN10 10JUL10

18AUG10

33

0.53

09AUG10 19AUG10 28AUG10

19

0.22

18JUL10

PC5E0110 Commissioning work PUMPING AREA

10 31JUL10

PC5P0100

Precommissioning work

27 09JUN10 10JUL10

24AUG10

38

0.53

PC5P0110

Commissioning work

10 25AUG10 03SEP10 25AUG10 03SEP10

0

0.22

03SEP10

0

0.00

26 14AUG10 12SEP10 14AUG10 12SEP10

0

0.00

26 14AUG10 12SEP10 14AUG10 12SEP10

0

0.00

26 14AUG10 12SEP10 14AUG10 12SEP10

0

0.00

PC5P0120 Finish Commissioning PROJECT CLOSEOUT Subtotal

0

03SEP10

25JUL10

Precommissioning work Commissioning work Precommissioning work Commissioning work Precommissioning work Commissioning work Precommissioning work Commissioning work Finish Commissioning

GC-23 Subtotal

Subtotal

PCL30100

Submission of As Built Drawings

26 14AUG10 12SEP10 14AUG10 12SEP10

0

0.00

Submission of As Built Drawings

PCL30110 GC-25

Submission of As Built Packages

26 14AUG10 12SEP10 14AUG10 12SEP10

0

0.00

Submission of As Built Packages

26 14AUG10 12SEP10 14AUG10 12SEP10

0

0.00

26 14AUG10 12SEP10 14AUG10 12SEP10

0

0.00

26 14AUG10 12SEP10 14AUG10 12SEP10

0

0.00

Submission of As Built Drawings Submission of As Built Packages

Subtotal

Subtotal

PCL50100 PCL50110

Submission of As Built Drawings Submission of As Built Packages

Subtotal

26 14AUG10 12SEP10 14AUG10 12SEP10

0

0.00

10 01SEP10 12SEP10 01SEP10 12SEP10

0

0.00

10 01SEP10 12SEP10 01SEP10 12SEP10

0

0.00

. Subtotal Start Date Finish Date Data Date Critical Activity Run Date Early Bar

Progress Bar

© Primavera Systems, Inc.

P87/09 Sheet 19 of 20 22MAR09 87R1 12SEP10 REPLACEMENT OF EXISTING OILY & EFFLUENT WATER LINES WITH 22MAR09 RTRP IN GC-23 & GC-25 06MAY09 16:58 IMCO ENGINEERING AND CONSTRUCTION COMPANY BASELINE SCHEDULE (LEVEL-5)

Date 04APR09

Revision-0

Checked THK

Approved JC

30APR09

Revision-1

Revision

THK

JC


Activity ID

Activity Description

PCLC0100

Demobilization

PCLC0110

Project Finish

Start Date Finish Date Data Date Critical Activity Run Date Early Bar

Progress Bar

© Primavera Systems, Inc.

Orig Dur

Early Start

Early Finish

Late Start

Late CalTotal PROJ PHAS TRAK MATL AREA SUB UNIT DIS % Finish IDFloat WT

10 01SEP10 12SEP10 01SEP10 12SEP10 0

12SEP10

12SEP10

0

0.00

0

0.00

2009 2010 M APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP O

P87/09 Sheet 20 of 20 22MAR09 87R1 12SEP10 REPLACEMENT OF EXISTING OILY & EFFLUENT WATER LINES WITH 22MAR09 RTRP IN GC-23 & GC-25 06MAY09 16:58 IMCO ENGINEERING AND CONSTRUCTION COMPANY BASELINE SCHEDULE (LEVEL-5)

Demobilization Project Finish

Date 04APR09

Revision-0

Checked THK

Approved JC

30APR09

Revision-1

Revision

THK

JC


CRITICAL PATH LISTING REPLACEMENT OF EXISTING OILY AND EFFLUENT WATER LINES WITH RTRP IN GC-23 AND GC-25


Activity ID

Activity Description

Orig Dur

Early Start

Early Finish

M

APR

MAY

JUN

JUL

2009 AUG

SEP

OCT

NOV

DEC

JAN

FEB

MAR

APR

2010 MAY

JUN

JUL

AUG

SEP

Replacement of Existing Oily and Effluent Water GENERAL COMMON

Project Start

GENE0100

Project Start

0 22MAR09

GENE0210

Prepare & Submit Key Personnels

22 23MAR09

16APR09

GENE0220

Rev. & App. Key Personnels

24 14APR09

07MAY09

Prepare & Submit Key Personnels Rev. & App. Key Personnels

DESIGN & ENGINEERING GC-23 SITE SURVEY ENGS0090

Start Engineering for GC-23 & GC-25

ENGS0100

Site Survey & Data Collection

Start Engineering for GC-23 & GC-25

0 22APR09 30 22APR09

26MAY09

Site Survey & Data Collection

MECHANICAL & PIPING MECH VALVES Prep.& Sub. of Material Spec for Mech valves

ENMS0180

Prep.& Sub. of Material Spec for Mech valves

40 10MAY09

24JUN09

ENMS0190

Review & Approval Material Spec for Mech

21 25JUN09

15JUL09

Review & Approval Material Spec for Mech valves

ENMS0200

Approval Material Spec for Mech. Valves

15JUL09

Approval Material Spec for Mech. Valves

0

INSTRUMENTATION DESIGN DRAWINGS & DOCUMENTS ENID0100

Prep.& Sub. of P&ID Diagram

26 10MAY09

08JUN09

Prep.& Sub. of P&ID Diagram

CONTROL VALVES Prep.& Sub. of Material Spec for Control Valves

ENIS0100

Prep.& Sub. of Material Spec for Control Valves

27 17MAY09

16JUN09

ENIS0110

Review& Approval Material Spec for Control

21 17JUN09

07JUL09

Review& Approval Material Spec for Control Valve

ENIS0120

Approval Matl Spec for Control Valves

07JUL09

Approval Matl Spec for Control Valves

0

GC-25 SITE SURVEY ENGS0400

Site Survey & Data Collection

35 22APR09

01JUN09

Site Survey & Data Collection

MECHANICAL & PIPING MECH VALVES Prep.& Sub. of Material Spec for Mech valves

ENMS0460

Prep.& Sub. of Material Spec for Mech valves

40 10MAY09

24JUN09

ENMS0470

Review & Approval Material Spec for Mech

21 25JUN09

15JUL09

Review & Approval Material Spec for Mech valves

ENMS0540

Approval Matl Spec for Mech Valves

15JUL09

Approval Matl Spec for Mech Valves

0

INSTRUMENTATION DESIGN DRAWINGS & DOCUMENTS ENID0400

Prep.& Sub. of P&ID Diagram Start Date Finish Date Data Date Critical Activity Run Date Early Bar

Progress Bar

Š Primavera Systems, Inc.

26 10MAY09

08JUN09

Prep.& Sub. of P&ID Diagram

P87/09 Sheet 1 of 5 22MAR09 87R1 12SEP10 REPLACEMENT OF EXISTING OILY & EFFLUENT WATER LINES WITH 22MAR09 RTRP IN GC-23 & GC-25 06MAY09 17:00 IMCO ENGINEERING AND CONSTRUCTION COMPANY BASELINE SCHEDULE (CRITICAL ACTIVITIES)

Date 04APR09

Revision-0

Checked THK

Approved JC

30APR09

Revision-1

Revision

THK

JC


Activity ID

Activity Description

Orig Dur

Early Start

Early Finish

M

APR

MAY

JUN

JUL

2009 AUG

SEP

OCT

NOV

DEC

JAN

FEB

MAR

APR

2010 MAY

JUN

JUL

AUG

SEP

CONTROL VALVES Prep.& Sub. of Material Spec for Control Valves

ENIS0400

Prep.& Sub. of Material Spec for Control Valves

27 17MAY09

16JUN09

ENIS0410

Review& Approval Material Spec for Control

21 17JUN09

07JUL09

Review& Approval Material Spec for Control Valve

ENIS0460

Approval of Matl Spec for control valves

07JUL09

Approval of Matl Spec for control valves

0

PROCUREMENT GC-23 MECHANICAL & PIPING MECH VALVES PROM0320

Proposal & Technical Bid Analysis

18 25JUN09

15JUL09

PROM0330

Sub. & Approval of Technical Proposal

21 16JUL09

05AUG09

PROM0250

Processing & Placing of P.O

PROM0260

Sub. & Appr. of Drg. & Data sheets

PROM0270

Procurement of Materials

PROM0290 PROM0310

Proposal & Technical Bid Analysis Sub. & Approval of Technical Proposal Processing & Placing of P.O

4 06AUG09

10AUG09

41 11AUG09

20SEP09

205 21SEP09

13APR10

Material Delivery

6 14APR10

20APR10

Material Delivery

Mech Valves receipt

0

20APR10

Mech Valves receipt

Sub. & Appr. of Drg. & Data sheets Procurement of Materials

INSTRUMENTATION CONTROL VALVES Proposal & Technical Bid Analysis

PROI0330

Proposal & Technical Bid Analysis

18 17JUN09

07JUL09

PROI0280

Sub. & Approval of Technical Proposal

21 08JUL09

28JUL09

PROI0250

Processing & Placing of P.O

3 29JUL09

01AUG09

PROI0260

Sub. & Appr. of Drg. & Data sheets

31 02AUG09

01SEP09

PROI0270

Procurement of Materials

229 02SEP09

18APR10

PROI0290

Material Delivery

4 19APR10

22APR10

Material Delivery

PROI0310

Control Valves receipt

0

22APR10

Control Valves receipt

Sub. & Approval of Technical Proposal Processing & Placing of P.O Sub. & Appr. of Drg. & Data sheets Procurement of Materials

GC-25 MECHANICAL & PIPING MECH VALVES PROM0930

Proposal & Technical Bid Analysis

18 25JUN09

15JUL09

PROM0940

Sub. & Approval of Technical Proposal

21 16JUL09

05AUG09

PROM0850

Processing & Placing of P.O

PROM0860

Sub. & Appr. of Drg. & Data sheets

PROM0870

Procurement of Materials

PROM0890 PROM0910

Proposal & Technical Bid Analysis Sub. & Approval of Technical Proposal Processing & Placing of P.O

4 06AUG09

10AUG09

41 11AUG09

20SEP09

205 21SEP09

13APR10

Material Delivery

6 14APR10

20APR10

Material Delivery

Mech Valves receipt

0

20APR10

Mech Valves receipt

Sub. & Appr. of Drg. & Data sheets Procurement of Materials

INSTRUMENTATION CONTROL VALVES PROI0980

Proposal & Technical Bid Analysis Start Date Finish Date Data Date Critical Activity Run Date Early Bar

Progress Bar

Š Primavera Systems, Inc.

18 17JUN09

07JUL09

Proposal & Technical Bid Analysis

P87/09 Sheet 2 of 5 22MAR09 87R1 12SEP10 REPLACEMENT OF EXISTING OILY & EFFLUENT WATER LINES WITH 22MAR09 RTRP IN GC-23 & GC-25 06MAY09 17:00 IMCO ENGINEERING AND CONSTRUCTION COMPANY BASELINE SCHEDULE (CRITICAL ACTIVITIES)

Date 04APR09

Revision-0

Checked THK

Approved JC

30APR09

Revision-1

Revision

THK

JC


Activity ID

Activity Description

PROI1010

Sub. & Approval of Technical Proposal

PROI0850

Processing & Placing of P.O

PROI0860

Sub. & Appr. of Drg. & Data sheets

PROI0870

Procurement of Materials

PROI0890 PROI0910

Orig Dur

Early Start

Early Finish

21 08JUL09

28JUL09

3 29JUL09

01AUG09

M

APR

MAY

JUN

JUL

2009 AUG

SEP

OCT

NOV

DEC

JAN

FEB

MAR

APR

2010 MAY

JUN

JUL

AUG

SEP

Sub. & Approval of Technical Proposal Processing & Placing of P.O Sub. & Appr. of Drg. & Data sheets

31 02AUG09

01SEP09

229 02SEP09

18APR10

Material Delivery

4 19APR10

22APR10

Material Delivery

Control Valves receipt

0

22APR10

Control Valves receipt

Procurement of Materials

CONSTRUCTION GC-23 MECHANICAL & PIPING DESALTER A&B AREA CN3AM0140

Install Control Valves

36 24APR10

03JUN10

Install Control Valves

CN3AM0160

Install Mech Valves

30 01MAY10

03JUN10

Install Mech Valves

CN3AM0145

Finish Install control valves

0

03JUN10

Finish Install control valves

CN3AM0165

Finish Install Mech. Valves

0

03JUN10

Finish Install Mech. Valves

CN3AM0170

Hydrotesting of Pipelines

20 05JUN10

27JUN10

CN3AM0180

Painting of A/G Piping & Supports

11 28JUN10

10JUL10

CN3AM0210

Tentative S/D to be discussed with KOC staff

25 11JUL10

04AUG10

25 05AUG10

29AUG10

Hydrotesting of Pipelines Painting of A/G Piping & Supports Tentative S/D to be discussed with KOC staff

SEPERATOR AREA CN3SM0210

Tentative S/D to be discussed with KOC staff

CN3SM0220

Finish Construction

0

Tentative S/D to be discussed with KOC staff Finish Construction

29AUG10

DEMOLITION DESALTER A&B AREA CN3AD0115

Start Demolition

Start Demolition

0 10AUG10

SEPERATOR AREA CN3SD0100

Demolition of Old reduntant Instruments &

26 10AUG10

08SEP10

Demolition of Old reduntant Instruments & Cables

CN3SD0110

Demolition of Old redundant valves

26 10AUG10

08SEP10

Demolition of Old redundant valves

CN3SD0130

Finish Demolition

0

Finish Demolition

08SEP10

GC-25 MECHANICAL & PIPING DESALTER A&B AREA CN5AM0150

Install Mech Valves

CN5AM0155

Finish Install Mech Valves

38 21APR10 0

Hydrotesting of Pipelines

20 05JUN10

27JUN10

CN5AM0170

Painting of A/G Piping & Supports

11 28JUN10

10JUL10

Tentative S/D to be discussed with KOC staff

Finish Install Mech Valves

03JUN10

CN5AM0160

CN5AM0200

Install Mech Valves

03JUN10

25 11JUL10

04AUG10

25 05AUG10

29AUG10

Hydrotesting of Pipelines Painting of A/G Piping & Supports Tentative S/D to be discussed with KOC staff

WET CRUDE TANK AREA CN5WM0200

Tentative S/D to be discussed with KOC staff Start Date Finish Date Data Date Critical Activity Run Date Early Bar

Progress Bar

Š Primavera Systems, Inc.

Tentative S/D to be discussed with KOC staff

P87/09 Sheet 3 of 5 22MAR09 87R1 12SEP10 REPLACEMENT OF EXISTING OILY & EFFLUENT WATER LINES WITH 22MAR09 RTRP IN GC-23 & GC-25 06MAY09 17:00 IMCO ENGINEERING AND CONSTRUCTION COMPANY BASELINE SCHEDULE (CRITICAL ACTIVITIES)

Date 04APR09

Revision-0

Checked THK

Approved JC

30APR09

Revision-1

Revision

THK

JC


Activity ID

Activity Description

Orig Dur

Early Start

Early Finish

M

APR

MAY

JUN

JUL

2009 AUG

SEP

OCT

NOV

DEC

JAN

FEB

MAR

APR

2010 MAY

JUN

JUL

AUG

SEP

PIPE WAY CN5EM0150

Install Mech Valves

38 21APR10

03JUN10

CN5EM0160

Hydrotesting of Pipelines

20 05JUN10

27JUN10

CN5EM0170

Painting of A/G Piping & Supports

11 28JUN10

10JUL10

CN5EM0200

Tentative S/D to be discussed with KOC staff

25 11JUL10

04AUG10

Install Mech Valves Hydrotesting of Pipelines Painting of A/G Piping & Supports Tentative S/D to be discussed with KOC staff

PUMPING AREA CN5PM0150

Install Mech Valves

38 21APR10

03JUN10

Install Mech Valves

CN5PM0135

Install Control Valves

36 24APR10

03JUN10

Install Control Valves

CN5PM0138

Finish Install control valves

CN5PM0160

Hydrotesting of Pipelines

CN5PM0170

Painting of A/G Piping & Supports

CN5PM0200

Tentative S/D to be discussed with KOC staff

CN5PM0210

Finish Construction

03JUN10

Finish Install control valves

20 05JUN10

27JUN10

Hydrotesting of Pipelines

11 28JUN10

10JUL10

0

50 11JUL10 0

29AUG10

Painting of A/G Piping & Supports Tentative S/D to be discussed with KOC staff Finish Construction

29AUG10

DEMOLITION DESALTER A&B AREA CN5AD0115

Start Demolition

Start Demolition

0 10AUG10

WET CRUDE TANK AREA Demolition of Old Redundant pipe lines

CN5WD0100

Demolition of Old Redundant pipe lines

26 10AUG10

08SEP10

CN5WD0110

Demolition of Old redundant valves

26 10AUG10

08SEP10

Demolition of Old redundant valves

26 10AUG10

08SEP10

Demolition of Old reduntant Instruments & Cables

CN5WD0120

Demolition of Old reduntant Instruments &

PUMPING AREA CN5PD0100

Demolition of Old Redundant pipe lines

26 10AUG10

08SEP10

Demolition of Old Redundant pipe lines

CN5PD0110

Demolition of Old redundant valves

26 10AUG10

08SEP10

Demolition of Old redundant valves

CN5PD0120

Demolition of Old reduntant Instruments &

26 10AUG10

08SEP10

Demolition of Old reduntant Instruments & Cables

CN5PD0130

Finish Demolition

0

Finish Demolition

08SEP10

PRECOMMISSIONING & COMMISSIONING GC-23 . SEPERATOR AREA PC3S0110

Commissioning work

PC3S0120

Finish Commissioning

10 25AUG10 0

Commissioning work

03SEP10

Finish Commissioning

04SEP10

GC-25 . WET CRUDE TANK AREA PC5W0110

Commissioning work

10 25AUG10

03SEP10

Commissioning work

10 25AUG10

03SEP10

Commissioning work

PUMPING AREA PC5P0110

Commissioning work Start Date Finish Date Data Date Critical Activity Run Date Early Bar

Progress Bar

Š Primavera Systems, Inc.

P87/09 Sheet 4 of 5 22MAR09 87R1 12SEP10 REPLACEMENT OF EXISTING OILY & EFFLUENT WATER LINES WITH 22MAR09 RTRP IN GC-23 & GC-25 06MAY09 17:00 IMCO ENGINEERING AND CONSTRUCTION COMPANY BASELINE SCHEDULE (CRITICAL ACTIVITIES)

Date 04APR09

Revision-0

Checked THK

Approved JC

30APR09

Revision-1

Revision

THK

JC


Activity ID PC5P0120

Activity Description Finish Commissioning

Orig Dur

Early Start

0

Early Finish

M

APR

MAY

JUN

JUL

2009 AUG

SEP

OCT

NOV

DEC

JAN

FEB

MAR

APR

2010 MAY

JUN

JUL

AUG

SEP

Finish Commissioning

03SEP10

PROJECT CLOSEOUT GC-23

PCL30100 PCL30110

Submission of As Built Drawings

26 14AUG10

12SEP10

Submission of As Built Drawings Submission of As Built Packages

Submission of As Built Packages

26 14AUG10

12SEP10

Submission of As Built Drawings

26 14AUG10

12SEP10

Submission of As Built Drawings Submission of As Built Packages

GC-25

PCL50100 PCL50110

Submission of As Built Packages

26 14AUG10

12SEP10

PCLC0100

Demobilization

10 01SEP10

12SEP10

PCLC0110

Project Finish

.

Start Date Finish Date Data Date Critical Activity Run Date Early Bar

Progress Bar

© Primavera Systems, Inc.

0

Demobilization Project Finish

12SEP10

P87/09 Sheet 5 of 5 22MAR09 87R1 12SEP10 REPLACEMENT OF EXISTING OILY & EFFLUENT WATER LINES WITH 22MAR09 RTRP IN GC-23 & GC-25 06MAY09 17:00 IMCO ENGINEERING AND CONSTRUCTION COMPANY BASELINE SCHEDULE (CRITICAL ACTIVITIES)

Date 04APR09

Revision-0

Checked THK

Approved JC

30APR09

Revision-1

Revision

THK

JC


MILESTONE LISTING REPLACEMENT OF EXISTING OILY AND EFFLUENT WATER LINES WITH RTRP IN GC-23 AND GC-25


Activity ID

Activity Description

Orig Dur

Early Start

Early Finish

M

APR

MAY

JUN

JUL

2009 AUG

SEP

OCT

NOV

DEC

JAN

FEB

MAR

APR

2010 MAY

JUN

JUL

AUG

SEP

GENERAL COMMON GENE0100

Project Start

0 22MAR09

Project Start

DESIGN & ENGINEERING GC-23 ENGS0090

Start Engineering for GC-23 & GC-25

0 22APR09

ENMS0170

Approval Material Spec for RTRP

0

20JUN09

ENMD0170

Approval of Stress Analysis report

0

22JUN09

ENMD0150

Approval of Layout drawing for CS & SS

0

27JUN09

Approval of Layout drawing for CS & SS Pipeline

ENMD0160

Approval of Iso drawing for CS & SS Pipeline

0

27JUN09

Approval of Iso drawing for CS & SS Pipeline

ENMS0160

Approval Material Spec for CS Pipes

0

27JUN09

Approval Material Spec for CS Pipes

ENID0220

Approval of P&ID Diagram

0

29JUN09

ENIS0120

Approval Matl Spec for Control Valves

0

07JUL09

ENMS0200

Approval Material Spec for Mech. Valves

0

15JUL09

ENID0230

Approval of Cable layout drg

0

25JUL09

ENIS0260

Approval of Matl Spec for TSV

0

24AUG09

ENMS0530

Approval of Materail Spec for RTRP

0

20JUN09

Approval of Materail Spec for RTRP

ENMD0490

Approval of Stress Analysis report

0

22JUN09

Approval of Stress Analysis report

ENMD0470

Approval of layout drg for CS & SS Pipeline

0

27JUN09

Approval of layout drg for CS & SS Pipeline

ENMD0480

Approval Iso drg for CS & SS Pipeline

0

27JUN09

Approval Iso drg for CS & SS Pipeline

ENMS0520

Approval of Material Spec for CS Pipes

0

27JUN09

Approval of Material Spec for CS Pipes

ENID0530

Approval of P&ID Diagram

0

29JUN09

ENIS0460

Approval of Matl Spec for control valves

0

07JUL09

Approval of Matl Spec for control valves

ENIS0470

Approval Matl Spec for ESD Valves

0

07JUL09

Approval Matl Spec for ESD Valves

ENMS0540

Approval Matl Spec for Mech Valves

0

15JUL09

Approval Matl Spec for Mech Valves

ENID0540

Approval of Cable Layout drg

0

25JUL09

Approval of Cable Layout drg

ENID0520

Finish Engineering for GC-23 & GC-25

0

24AUG09

Approval of Hazop reports

0

22AUG09

Approval of Hazop reports

Approval of Hazop reports

0

22AUG09

Approval of Hazop reports

Start Engineering for GC-23 & GC-25 Approval Material Spec for RTRP Approval of Stress Analysis report

Approval of P&ID Diagram Approval Matl Spec for Control Valves Approval Material Spec for Mech. Valves Approval of Cable layout drg Approval of Matl Spec for TSV

GC-25

Approval of P&ID Diagram

Finish Engineering for GC-23 & GC-25

HAZOP/QRA/EIA STUDIES GC-23 ENGS0130

GC-25 ENGS0430

PROCUREMENT GC-23 PROM0165

Start Procurement in GC-23 & 25

0 31MAY09

PROM0160

CS Pipes receipt

0

13OCT09

CS Pipes receipt

PROM0280

CS Fitting receipt

0

13OCT09

CS Fitting receipt

PROM0300

RTRP Pipe spools receipt

0

02JAN10

PROM0310

Mech Valves receipt

0

20APR10

Mech Valves receipt

PROI0510

Temp relief Valve receipt

0

21APR10

Temp relief Valve receipt

PROI0310

Control Valves receipt

0

22APR10

Control Valves receipt

PROM0510

Corrosion Monitoring Fitting receipt

0

01MAY10

PROM0760

CS Pipes receipt

0

13OCT09

CS Pipes receipt

PROM0880

CS Fitting receipt

0

13OCT09

CS Fitting receipt

PROM0900

RTRP Pipe spools receipt

0

02JAN10

PROM0910

Mech Valves receipt

0

20APR10

Mech Valves receipt

PROI0880

ESD Valves receipt

0

22APR10

ESD Valves receipt

PROI0910

Control Valves receipt

0

22APR10

Control Valves receipt

PROI0960

Finish Procurement for GC-23 & 25

0

01MAY10

Finish Procurement for GC-23 & 25

PROM1110

Corrosion Monitoring receipt

0

01MAY10

Corrosion Monitoring receipt

Start Procurement in GC-23 & 25

RTRP Pipe spools receipt

Corrosion Monitoring Fitting receipt

GC-25

Start Date Early Bar Finish Date Progress Bar Data Date Critical Activity Run Date

Š Primavera Systems, Inc.

RTRP Pipe spools receipt

P87/09 Sheet 1 of 2 22MAR09 87R1 12SEP10 REPLACEMENT OF EXISTING OILY & EFFLUENT WATER LINES WITH 22MAR09 RTRP IN GC-23 & GC-25 06MAY09 16:59 IMCO ENGINEERING AND CONSTRUCTION COMPANY BASELINE SCHEDULE (MILESTONES & FLAGS)

Date 04APR09

Revision-0

Checked THK

Approved JC

30APR09

Revision-1

Revision

THK

JC


Activity ID

Activity Description

Orig Dur

Early Start

Early Finish

M

APR

MAY

JUN

JUL

2009 AUG

SEP

OCT

NOV

DEC

JAN

FEB

MAR

2010 MAY

APR

JUN

JUL

AUG

SEP

CONSTRUCTION GENERAL CNGE0110

Start Construction for GC-23 & 25

0 25OCT09

CNGE0140

Finish FBE Coating works

0

CN3AM0115

Start Installation of RTRP Pipes

0 27JAN10

CN3AM0105

Start Installation of Steel Pipes

0 02FEB10

CN3AI0155

Start Instrumentation works

0 02MAR10

CN3AM0145

Finish Install control valves

0

03JUN10

CN3AM0165

Finish Install Mech. Valves

0

03JUN10

CN3AI0230

Finish Instrumentation works

0

04AUG10

CN3AD0115

Start Demolition

0 10AUG10

CN3SM0220

Finish Construction

0

29AUG10

CN3SD0130

Finish Demolition

0

08SEP10

CN5WM0105

Start Installation of Steel Pipes

0 06JAN10

Start Installation of Steel Pipes

CN5EM0115

Start Installation of RTRP

0 20JAN10

Start Installation of RTRP

CN5AI0155

Start Instrumentation works

0 02MAR10

CN5AM0155

Finish Install Mech Valves

0

03JUN10

Finish Install Mech Valves

CN5PM0138

Finish Install control valves

0

03JUN10

Finish Install control valves

CN5WM0230

Finish Install ESD Valves

0

05JUN10

CN5PI0220

Finish Instrumentation works

0

04AUG10

CN5AD0115

Start Demolition

0 10AUG10

CN5PM0210

Finish Construction

0

29AUG10

CN5PD0130

Finish Demolition

0

08SEP10

Finish Commissioning

0

04SEP10

Finish Commissioning

Finish Commissioning

0

03SEP10

Finish Commissioning

0

12SEP10

Start Construction for GC-23 & 25 01FEB10

Finish FBE Coating works

GC-23 Start Installation of RTRP Pipes Start Installation of Steel Pipes Start Instrumentation works Finish Install control valves Finish Install Mech. Valves Finish Instrumentation works Start Demolition Finish Construction Finish Demolition

GC-25

Start Instrumentation works

Finish Install ESD Valves Finish Instrumentation works Start Demolition Finish Construction Finish Demolition

PRECOMMISSIONING & COMMISSIONING GC-23 PC3S0120

GC-25 PC5P0120

PROJECT CLOSEOUT PCLC0110

Project Finish

Start Date Finish Date Data Date Critical Activity Run Date Early Bar

Progress Bar

Š Primavera Systems, Inc.

P87/09 Sheet 2 of 2 22MAR09 87R1 12SEP10 REPLACEMENT OF EXISTING OILY & EFFLUENT WATER LINES WITH 22MAR09 RTRP IN GC-23 & GC-25 06MAY09 16:59 IMCO ENGINEERING AND CONSTRUCTION COMPANY BASELINE SCHEDULE (MILESTONES & FLAGS)

Project Finish

Date 04APR09

Revision-0

Checked THK

Approved JC

30APR09

Revision-1

Revision

THK

JC


LEVEL-1 WEIGHTAGE SPLIT UP REPLACEMENT OF EXISTING OILY AND EFFLUENT WATER LINES WITH RTRP IN GC-23 AND GC-25


REPLACEMENT OF EXISTING OILY & EFFLUENT WATER LINES WITH RTRP IN GC-23 & 25 WEIGHTAGE SPLIT UP (LEVEL-1 SUMMARY) IMCO JOB # P87/09

KOC CONTRACT # 39848

WEIGHTAGE SPLIT UP Item

Activity

WEIGHTAGE AS PER CONTRACT

**

Design & Engineering

Procurement

Construction

Precommissioning & Commissioning

4%

Total

1

Design and engineering works

4%

2

Material and equipment supply Mechanical works material upon delivery to Site and acceptance by the Company

52%

3

Material and equipment supply Electrical and instrumentation works material upon installation

12%

12%

12%

4

Construction

4% 52%

52%

4.1

Civil works (including civil material)

5%

5%

5%

4.2

Mechanical installation and demolition works

11%

11.0%

11%

4.3

Instrument / Electrical installation works

8%

8%

8%

5

Any other item (HAZOP, QRA, EIA Studies)

3%

6

Testing, precommissioning and Commissioning

5%

TOTAL

100%

3%

7.0%

NOTE: ** AS PER CONTRACT SPECIFICATION CLAUSE 12, GENERAL CONDITIONS OF CONTRACT CLAUSE 50.

Remarks

3%

52.0%

36.0%

5%

5%

5.0%

100%

Procurement Included in Constrcution as per method of payment terms in contract


W.B.S CHART UPTO LEVEL-3 REPLACEMENT OF EXISTING OILY AND EFFLUENT WATER LINES WITH RTRP IN GC-23 AND GC-25


REPLACEMENT OF EXISTING OILY & EFFLUENT WATER LINES WITH RTRP IN GC-23 & 25 W.B.S CHART UPTO LEVEL-3

**

IMCO JOB # P87/09

KOC CONTRACT # 39848

REPLACEMENT OF EXITING OILY & EFFLUENT WATER LINES (100.00%)

DESIGN & ENGINEERING (7.00%)

GC-23 (2.00%)

GC-25 (2.00%)

PROCUREMENT (52.00%)

HAZOP STUDIES (3.00%)

GC-23 (15.60%)

PRECOMMISSIONING & COMMISSIONING (5.00%)

CONSTRUCTION (36.00%)

GC-25 (36.40%)

GENERAL (1.86%)

GC-23 (11.69%)

GC-25 (22.45%)

SITE SURVEY (0.20%)

SITE SURVEY (0.20%)

GC-23 (1.50%)

CIVIL & STRUCTURAL (0.00%)

CIVIL & STRUCTURAL (0.00%)

CIVIL & STRUCTURAL (1.25%)

CIVIL & STRUCTURAL (3.75%)

CIVIL & STRUCTURAL (0.20%)

CIVIL & STRUCTURAL (0.20%)

GC-25 (1.50%)

MECHANICAL & PIPING (15.60%)

MECHANICAL & PIPING (36.40%)

MECHANICAL & PIPING (4.62%)

MECHANICAL & PIPING (11.92%)

MECHANICAL & PIPING (1.10%)

MECHANICAL & PIPING (1.10%)

INSTRUMENTATION (0.00%)

INSTRUMENTATION (0.00%)

INSTRUMENTATION (5.30%)

INSTRUMENTATION (6.00%)

INSTRUMENTATION (0.50%)

INSTRUMENTATION (0.50%)

DEMOLITION (0.52%)

DEMOLITION (0.78%)

NOTE: ** AS PER CONTRACT SPECIFICATION CLAUSE 12, GENERAL CONDITIONS OF CONTRACT CLAUSE 50.

Page 1 of 1

GC-23 (2.00%)

GC-25 (3.00%)


PROJECT ORGANIZATION CHART REPLACEMENT OF EXISTING OILY AND EFFLUENT WATER LINES WITH RTRP IN GC-23 AND GC-25


KOC CONTRACT NO.: 39848

IMCO PROJECT NO.: P87/09

PROGRESS ‘S’ CURVES REPLACEMENT OF EXISTING OILY AND EFFLUENT WATER LINES WITH RTRP IN GC-23 AND GC-25

CONTENT

 ENGINEERING ‘S’ CURVE  PROCUREMENT ‘S’ CURVE  CONSTRUCTION ‘S’ CURVE  PRECOMM.& COMM. ‘S’ CURVE  OVERALL ‘S’ CURVE

P.O. BOX 9309, AHMADI - 61004, KUWAIT – TEL.: +965 23981661/2 – FAX: +965 23984708 E-MAIL: projects@imcokw.com


ENGINEERING ‘S’ CURVE REPLACEMENT OF EXISTING OILY AND EFFLUENT WATER LINES WITH RTRP IN GC-23 AND GC-25


REPLACEMENT OF EXISTING OILY & EFFLUENT WATER LINES WITH RTRP IN GC-23 & 25 ENGINEERING "S" CURVE

IMCO REF # P87/09

KOC CONTRACT# 39848

100%

60%

90% 50%

70% 40% 60%

50%

30%

40% 20% 30%

CUMULATIV VE PROGRESS (%)

M MONTHLY PROGRESS (%)

80%

20% 10% 10%

0%

0% Mar-09

Apr-09

May-09

Jun-09

Jul-09

Aug-09

Sep-09

Oct-09

Nov-09

Dec-09

Jan-10

Feb-10

Mar-10

Apr-10

May-10

Jun-10

Jul-10

Aug-10

Sep-10

MONTHS Plan Monthly Progress (Rev.1 Baseline Schedule)

MONTH Plan Monthly Progress (Rev.1 Baseline Schedule)

Actual Monthly Progress (Rev.1 Baseline Schedule)

Plan Cumullative Progress (Rev.1 Baseline Schedule)

Actual Cumullative Progress (Rev.1 Baseline Schedule)

Mar-09

Apr-09

May-09

Jun-09

Jul-09

Aug-09

Sep-09

Oct-09

Nov-09

Dec-09

Jan-10

Feb-10

Mar-10

Apr-10

May-10

Jun-10

Jul-10

Aug-10

Sep-10

0.00%

1.41%

4.33%

37.64%

6.01%

50.61%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

1.41%

5.74%

43.38%

49.39%

100.00%

100.00%

100.00%

100.00%

100.00%

100.00%

100.00%

100.00%

100.00%

100.00%

100.00%

100.00%

100.00%

100.00%

Actual Monthly Progress (Rev.1 Baseline Schedule) Plan Cumullative Progress (Rev.1 Baseline Schedule) Actual Cumullative Progress (Rev.1 Baseline Schedule)


PROCUREMENT ‘S’ CURVE REPLACEMENT OF EXISTING OILY AND EFFLUENT WATER LINES WITH RTRP IN GC-23 AND GC-25


REPLACEMENT OF EXISTING OILY & EFFLUENT WATER LINES WITH RTRP IN GC-23 & 25 PROCUREMENT "S" CURVE

IMCO REF # P87/09

KOC CONTRACT# 39848

100%

80%

90% 70%

80%

70%

50% 60%

50%

40%

40% 30%

30%

CUMULATIV VE PROGRESS (%)

M MONTHLY PROGRESS (%)

60%

20% 20%

10% 10%

0%

0% Mar-09

Apr-09

May-09

Jun-09

Jul-09

Aug-09

Sep-09

Oct-09

Nov-09

Dec-09

Jan-10

Feb-10

Mar-10

Apr-10

May-10

Jun-10

Jul-10

Aug-10

Sep-10

MONTHS Plan Monthly Progress (Rev.1 Baseline Schedule)

MONTH Plan Monthly Progress (Rev.1 Baseline Schedule)

Actual Monthly Progress (Rev.1 Baseline Schedule)

Plan Cumullative Progress (Rev.1 Baseline Schedule)

Actual Cumullative Progress (Rev.1 Baseline Schedule)

Mar-09

Apr-09

May-09

Jun-09

Jul-09

Aug-09

Sep-09

Oct-09

Nov-09

Dec-09

Jan-10

Feb-10

Mar-10

Apr-10

May-10

Jun-10

Jul-10

Aug-10

Sep-10

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

18.41%

0.00%

8.46%

2.82%

0.00%

0.00%

69.36%

0.95%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

18.41%

18.41%

26.87%

29.69%

29.69%

29.69%

99.05%

100.00%

100.00%

100.00%

100.00%

100.00%

Actual Monthly Progress (Rev.1 Baseline Schedule) Plan Cumullative Progress (Rev.1 Baseline Schedule) Actual Cumullative Progress (Rev.1 Baseline Schedule)


CONSTRUCTION ‘S’ CURVE REPLACEMENT OF EXISTING OILY AND EFFLUENT WATER LINES WITH RTRP IN GC-23 AND GC-25


REPLACEMENT OF EXISTING OILY & EFFLUENT WATER LINES WITH RTRP IN GC-23 & 25 CONSTRUCTION "S" CURVE

IMCO REF # P87/09

KOC CONTRACT# 39848

100%

30%

90% 25%

70% 20% 60%

50%

15%

40% 10% 30%

CUMULATIV VE PROGRESS (%)

M MONTHLY PROGRESS (%)

80%

20% 5% 10%

0%

0% Mar-09

Apr-09

May-09

Jun-09

Jul-09

Aug-09

Sep-09

Oct-09

Nov-09

Dec-09

Jan-10

Feb-10

Mar-10

Apr-10

May-10

Jun-10

Jul-10

Aug-10

Sep-10

MONTHS Plan Monthly Progress (Rev.1 Baseline Schedule)

MONTH Plan Monthly Progress (Rev.1 Baseline Schedule)

Actual Monthly Progress (Rev.1 Baseline Schedule)

Plan Cumullative Progress (Rev.1 Baseline Schedule)

Actual Cumullative Progress (Rev.1 Baseline Schedule)

Mar-09

Apr-09

May-09

Jun-09

Jul-09

Aug-09

Sep-09

Oct-09

Nov-09

Dec-09

Jan-10

Feb-10

Mar-10

Apr-10

May-10

Jun-10

Jul-10

Aug-10

Sep-10

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.55%

2.21%

2.87%

4.42%

5.16%

7.56%

12.16%

23.99%

21.52%

11.04%

7.91%

0.59%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.55%

2.76%

5.63%

10.06%

15.22%

22.78%

34.94%

58.93%

80.45%

91.50%

99.41%

100.00%

Actual Monthly Progress (Rev.1 Baseline Schedule) Plan Cumullative Progress (Rev.1 Baseline Schedule) Actual Cumullative Progress (Rev.1 Baseline Schedule)


PRECOMMISSIONING & COMMISSIONING ‘S’ CURVE REPLACEMENT OF EXISTING OILY AND EFFLUENT WATER LINES WITH RTRP IN GC-23 AND GC-25


REPLACEMENT OF EXISTING OILY & EFFLUENT WATER LINES WITH RTRP IN GC-23 & 25 PRECOMMISSIONING & COMMISSIONING "S" CURVE

IMCO REF # P87/09

KOC CONTRACT# 39848

100%

40%

90% 35%

80%

70%

25% 60%

50%

20%

40% 15%

30%

CUMULATIV VE PROGRESS (%)

M MONTHLY PROGRESS (%)

30%

10% 20%

5% 10%

0%

0% Mar-09

Apr-09

May-09

Jun-09

Jul-09

Aug-09

Sep-09

Oct-09

Nov-09

Dec-09

Jan-10

Feb-10

Mar-10

Apr-10

May-10

Jun-10

Jul-10

Aug-10

Sep-10

MONTHS Plan Monthly Progress (Rev.1 Baseline Schedule)

MONTH Plan Monthly Progress (Rev.1 Baseline Schedule)

Actual Monthly Progress (Rev.1 Baseline Schedule)

Plan Cumullative Progress (Rev.1 Baseline Schedule)

Actual Cumullative Progress (Rev.1 Baseline Schedule)

Mar-09

Apr-09

May-09

Jun-09

Jul-09

Aug-09

Sep-09

Oct-09

Nov-09

Dec-09

Jan-10

Feb-10

Mar-10

Apr-10

May-10

Jun-10

Jul-10

Aug-10

Sep-10

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

36.36%

33.87%

25.27%

4.50%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

36.36%

70.23%

95.50%

100.00%

Actual Monthly Progress (Rev.1 Baseline Schedule) Plan Cumullative Progress (Rev.1 Baseline Schedule) Actual Cumullative Progress (Rev.1 Baseline Schedule)


OVERALL ‘S’ CURVE REPLACEMENT OF EXISTING OILY AND EFFLUENT WATER LINES WITH RTRP IN GC-23 AND GC-25


REPLACEMENT OF EXISTING OILY & EFFLUENT WATER LINES WITH RTRP IN GC-23 & 25 OVERALL "S" CURVE

IMCO REF # P87/09

KOC CONTRACT# 39848

100%

45%

90%

40%

80%

70% 30% 60% 25% 50% 20% 40% 15% 30%

CUMULATIV VE PROGRESS (%)

M MONTHLY PROGRESS (%)

35%

10% 20%

5%

10%

0%

0% Mar-09

Apr-09

May-09

Jun-09

Jul-09

Aug-09

Sep-09

Oct-09

Nov-09

Dec-09

Jan-10

Feb-10

Mar-10

Apr-10

May-10

Jun-10

Jul-10

Aug-10

Sep-10

MONTHS Plan Monthly Progress (Rev.1 Baseline Schedule)

MONTH Plan Monthly Progress (Rev.1 Baseline Schedule)

Actual Monthly Progress (Rev.1 Baseline Schedule)

Plan Cumullative Progress (Rev.1 Baseline Schedule)

Actual Cumullative Progress (Rev.1 Baseline Schedule)

Mar-09

Apr-09

May-09

Jun-09

Jul-09

Aug-09

Sep-09

Oct-09

Nov-09

Dec-09

Jan-10

Feb-10

Mar-10

Apr-10

May-10

Jun-10

Jul-10

Aug-10

Sep-10

0.00%

0.10%

0.30%

2.63%

0.42%

3.54%

0.00%

9.77%

0.80%

5.43%

3.06%

1.86%

2.72%

40.44%

9.13%

9.57%

5.67%

4.11%

0.44%

0.00%

0.10%

0.40%

3.04%

3.46%

7.00%

7.00%

16.77%

17.57%

23.00%

26.06%

27.92%

30.64%

71.08%

80.22%

89.78%

95.45%

99.56%

100.00%

Actual Monthly Progress (Rev.1 Baseline Schedule) Plan Cumullative Progress (Rev.1 Baseline Schedule) Actual Cumullative Progress (Rev.1 Baseline Schedule)


KOC CONTRACT NO.: 39848

IMCO PROJECT NO.: P87/09

MANPOWER HISTOGRAM REPLACEMENT OF EXISTING OILY AND EFFLUENT WATER LINES WITH RTRP IN GC-23 AND GC-25

P.O. BOX 9309, AHMADI - 61004, KUWAIT – TEL.: +965 23981661/2 – FAX: +965 23984708 E-MAIL: projects@imcokw.com


P 87 - 09 REPLACEMENT OF EXISTING OILY & EFFLUENT WATER LINES WITH RTRP IN GC-23 & 25 MANPOWER HISTOGRAM IMCO REF # P87/09

KOC CONTRACT# 39848

100

PLANNED MANPOWER

ACTUAL MANPOWER

90

80

PEAK MANPOWER

70

60

50

40

30

20

10

0 Mar-09

MONTHS PLANNED MANPOWER

Apr-09

May-09

Jun-09

Jul-09

Aug-09

Sep-09

Oct-09

Nov-09

Dec-09

Jan-10

Feb-10

Mar-10

Apr-10

May-10

Jun-10

Jul-10

Aug-10

Sep-10

Mar-09

Apr-09

May-09

Jun-09

Jul-09

Aug-09

Sep-09

Oct-09

Nov-09

Dec-09

Jan-10

Feb-10

Mar-10

Apr-10

May-10

Jun-10

Jul-10

Aug-10

Sep-10

2

4

5

7

7

7

7

26

50

62

67

78

88

78

75

74

73

73

37

ACTUAL MANPOWER

C:\ Jerry \ 4. Histogram Dir & Indir >Manpower


MAN POWER HISTOGRAM MONTHS

Mar-09

Apr-09

May-09

Jun-09

Jul-09

Aug-09

Sep-09

Oct-09

Nov-09

Dec-09

Jan-10

Feb-10

Mar-10

Apr-10

May-10

Jun-10

Jul-10

Aug-10

Sep-10

PROJECT MANAGER

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

PLANNING ENGINEER

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

INSTRUMENT ENGINEER

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

MECHANICAL ENGINEER

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

CIVIL ENGINEER QA/QC ENGINEER PROCUREMENT ENGINEER QA/QC INSPECTOR

1

1

1

1

1

1

1

1

1

1

1

1

INSPECTION SERVICE ENGINEER

1

1

1

1

1

1

1

1

1

1

1

1

1

SAFETY OFFICER

1

1

1

1

1

1

1

1

1

1

1

1

1

1

ADMINISTRATOR

1

1

1

1

1

1

1

1

1

1

1

1

SECRETARY

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

GENERAL FOREMAN

1

1

1

1

1

1

1

1

1

1

1

1

MECHANICAL FOREMAN

1

1

AUTOCAD DRAFTSMAN

1

1

1

1

INSTRUMENT FOREMAN

1

2

2

2

2

2

2

2

2

1

CIVIL FOREMAN

1

1

1

1

1

1

1

1

1

1

SURVEYOR

1

1

1

1

1

1

1

CIVIL CHARGEHAND

1

1

1

1

1

1

1

1

1

1

1

1

PAINTING CHARGEHAND INSTRUMENT TECHNICIANS

2

2

3

3

3

3

INSTRUMENT FITTERS

2

2

2

2

2

2

ELECTRICIAN

1

1

FABRICATOR

2

6

6

3

3

3

3

3

3

4

4

WELDER

2

6

6

3

3

3

3

3

3

4

4

3

PIPE FITTERS

4

6

6

6

4

4

4

4

3

RIGGER

4

6

6

6

4

4

4

4

2

4

4

4

4

4

2

2

1

RTRP TECHNICIAN

2

4

4

MASON

2

2

2

2

CARPENTER

2

2

2

2

BAR BENDER

2

2

2

2

SAND BLASTER / PAINTER DRIVER

3

3

4

4

4

4

4

4

4

4

4

3

STOREKEEPER

1

1

1

1

1

1

1

1

1

1

1

1

2

2

2

2

2

2

2

2

2

2

4

20

20

20

25

30

26

26

23

21

21

5

26

50

62

67

78

88

78

75

74

73

73

37

OPERATORS LABOURER / HELPER

TOTAL PLANNED

2

C:\ Jerry \ 4. Histogram Dir & Indir >Manpower

4

5

7

7

7

7


KOC CONTRACT NO.: 39848

IMCO PROJECT NO.: P87/09

PROCUREMENT LOG REPLACEMENT OF EXISTING OILY AND EFFLUENT WATER LINES WITH RTRP IN GC-23 AND GC-25

P.O. BOX 9309, AHMADI - 61004, KUWAIT – TEL.: +965 23981661/2 – FAX: +965 23984708 E-MAIL: projects@imcokw.com


REPLACEMENT OF EXSTING OILY & EFFLUENT WATER LINES WITH RTRP IN GC-23 & 25 PROCUREMENT LOG IMCO REF # P87/09

KOC CONTRACT # 39848 Status as on :

SL. NO

MTO DESCRIPTION

CIVIL & STRUCTURAL 1

Structrual Steel Support

2

Civil Materials

MECHANICAL & PIPING 1

CS Pipes & Fittings

2

RTRP Pipe spools

3

Mechanical Valves

4

SS Pipes & Fittings

5

Corrosion Monitoring Fittings

INSTRUMENTATION 1

Control & ESD Valves

2

Temp relief valves

3

Flow Elements

4

Temp Elements & Thermowell

5

Instrument Cables

6

Junction Box

7

Bulk Material

5. Proc Log>Material

PLAN

FORECAST / ACTUAL

TBA SUBMIT PLAN

FORECAST / ACTUAL

TBA APPROV PLAN

FORECAST / ACTUAL

P.O PLAN

FORECAST / ACTUAL

DELIVERY PLAN

FORECAST/ ACTUAL

REMARKS


KOC CONTRACT NO.: 39848

IMCO PROJECT NO.: P87/09

EQUIPMENT DEPLOYMENT PLAN REPLACEMENT OF EXISTING OILY AND EFFLUENT WATER LINES WITH RTRP IN GC-23 AND GC-25

P.O. BOX 9309, AHMADI - 61004, KUWAIT – TEL.: +965 23981661/2 – FAX: +965 23984708 E-MAIL: projects@imcokw.com


P 87 - 09 REPLACEMENT OF EXISTING OILY & EFFLUENT WATER LINES WITH RTRP IN GC-23 & 25 EQUIPMENT DEPLOYMENT PLAN IMCO REF # P87/09

MONTHS

KOC CONTRACT # 39848 Mar-09

Apr-09

May-09

Jun-09

Jul-09

Aug-09

Sep-09

Oct-09

Nov-09

Dec-09

Jan-10

Feb-10

Mar-10

Apr-10

May-10

Jun-10

Jul-10

Aug-10

Sep-10

CRANE‐ 25 TON

2

2

2

2

2

2

2

2

2

1

TRAILER‐ 40 TON

2

2

2

2

2

2

2

2

2

1

FORK LIFT‐ 4 TON

2

2

2

2

2

2

2

2

2

1

BOOM TRUCK

1

1

1

1

1

1

1

1

1

1

HALF LORRY

1

1

1

1

1

1

1

1

1

POTABLE POWER GENERATOR

2

2

2

2

2

2

2

2

2

POWER GENERATOR 

1

1

1

1

1

1

1

1

1

1

1

WELDING M/C

2

6

6

6

6

6

6

6

6

6

6

BEVELLING MACHINE

1

1

1

1

1

1

1

1

1

1

1

COLD CUTTING MACHINE

1

PNEUMATIC JACK HAMMER

2

2

2

2

2

2

2

2

2

AIR COMPRESSOR ‐ 900 CFM

2

2

2

2

2

2

2

2

2

PLATE COMPACTOR

2

2

2

2

2

2

2

2

2

WATER TANKER

2

2

2

2

2

2

2

2

2

DUMP TRUCK

2

2

2

2

2

2

2

2

2

LOADER

2

2

2

2

2

2

2

2

2

SAND BLASTING M/C

1

1

1

AIRLESS PAINTING M/C

1

1

1

PNEUMATIC PAINT MIXER

1

1

1

1

1

FOUR WHEEEL DRIVE JEEP

1

1

1

1

1

1

1

1

1

1

1

1

SALOON CAR

1

1

1

1

1

1

1

1

1

1

1

1

PICK UP

2

2

2

2

2

2

2

2

2

2

2

1

20 SEATER MINI BUS

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

14

36

36

36

36

36

36

39

39

40

40 SEATER BUS TOTAL PLANNED

C:\ Jerry \ 6. Equipment Histogram >Plan

9

10


KOC CONTRACT NO.: 39848

IMCO PROJECT NO.: P87/09

MONTHLY PROGRESS REPORT FORMAT REPLACEMENT OF EXISTING OILY AND EFFLUENT WATER LINES WITH RTRP IN GC-23 AND GC-25

P.O. BOX 9309, AHMADI - 61004, KUWAIT – TEL.: +965 23981661/2 – FAX: +965 23984708 E-MAIL: projects@imcokw.com


KUWAIT OIL COMPANY (K.S.C) MONTHLY PROGRESS REPORT FOR THE MONTH OF XXX

CONTRACT TITLE: Replacement of Existing Oily & Effluent Water lines with RTRP in GC-23 & 25.

CONTRACT NUMBER: 39848 REFERENCE NUMBER: EF/1567/1619

CONTRACT COMMENCEMENT DATE: 22-Mar-09 CONTRACT COMPLETION DATE: 12-Sep-10 CONTRACT DURATION: 540 Calender Days

IMCO ENGINEERING & CONSTRUCTION COMPANY W.L.L.,


KUWAIT OIL COMPANY (K.S.C) CONTRACT TITLE: Replacement of Existing Oily & Effluent Water lines with RTRP in GC-23 & 25. CONTRACT NUMBER: 39848 REFERENCE NUMBER: EF/1567/1619

CONTENTS 1

MANAGEMENT SUMMARY

2

PROGRESS NARRATION

3

AREAS OF CONCERN AND RECOMMENDED ACTIONS

4

PROGRESS SUMMARY

5

PROGRESS MEASUREMENT SYSTEM

6

PROGRESS 'S' CURVE

7

SCHEDULE UPDATES

8

3 MONTHS LOOK AHEAD SCHEDULE

9

MILESTONES

10 PROCUREMENT LOG 11 MANPOWER & EQUIPMENT STATUS 12 SAFETY REPORT 13 QA/QC REPORT 14 INVOICE STATUS


REPLACEMENT OF EXISTING EFFLUENT AND OILY WATER LINES WITH RTRP IN GC-23 AND 25

KOC CONTRACT NO.: 39848

MONTHLY PROGRESS REPORT No. XX

IMCO PROJECT NO.: P87/09

Date: DD/MM/YYYY

1. MANAGEMENT SUMMARY

Page 1 of 15


REPLACEMENT OF EXISTING EFFLUENT AND OILY WATER LINES WITH RTRP IN GC-23 AND 25

KOC CONTRACT NO.: 39848

MONTHLY PROGRESS REPORT No. XX

IMCO PROJECT NO.: P87/09

Date: DD/MM/YYYY

1.1.

MANAGEMENT SUMMARY: 1.1.1.

Project Start Date

22-March-2009

1.1.2.

Project Completion Date

12-September-2010

1.1.3.

Value of Contract

KWD 1,545,000.000

1.1.4.

Duration of Contract

540 Calendar Days (18 Months)

1.1.5.

Time Elapsed (%)

Nil

1.1.6.

Progress Planned (Overall)

Nil

1.1.7.

Progress Achieved (Overall)

Nil

1.1.8.

Cumulative Invoiced Till date

Nil

Progress Statistics as on ------% WT DESIGN & ENGINEERING

4.00

PROCUREMENT

52.00

CONSTRUCTION

36.00

HAZOP, QRA, EIA, PSHER STUDIES

3.00

TESTING, PRECOMM. & COMM.

5.00

OVERALL

100.00

Page 2 of 15

PLANNED

ACHIEVED

VARIANCE


REPLACEMENT OF EXISTING EFFLUENT AND OILY WATER LINES WITH RTRP IN GC-23 AND 25

KOC CONTRACT NO.: 39848

MONTHLY PROGRESS REPORT No. XX

IMCO PROJECT NO.: P87/09

Date: DD/MM/YYYY

2. PROGRESS NARRATION

Page 3 of 15


REPLACEMENT OF EXISTING EFFLUENT AND OILY WATER LINES WITH RTRP IN GC-23 AND 25

KOC CONTRACT NO.: 39848

MONTHLY PROGRESS REPORT No. XX

IMCO PROJECT NO.: P87/09

Date: DD/MM/YYYY

3. AREAS OF CONCERNS AND RECOMMENDED ACTIONS

Page 4 of 15


REPLACEMENT OF EXISTING EFFLUENT AND OILY WATER LINES WITH RTRP IN GC-23 AND 25

KOC CONTRACT NO.: 39848

MONTHLY PROGRESS REPORT No. XX

IMCO PROJECT NO.: P87/09

Date: DD/MM/YYYY

4. PROGRESS SUMMARY

Page 5 of 15


REPLACEMENT OF EXISTING EFFLUENT AND OILY WATER LINES WITH RTRP IN GC-23 AND 25

KOC CONTRACT NO.: 39848

MONTHLY PROGRESS REPORT No. XX

IMCO PROJECT NO.: P87/09

Date: DD/MM/YYYY

5. PROGRESS MEASUREMENT SYSTEM

Page 6 of 15


REPLACEMENT OF EXISTING EFFLUENT AND OILY WATER LINES WITH RTRP IN GC-23 AND 25

KOC CONTRACT NO.: 39848

MONTHLY PROGRESS REPORT No. XX

IMCO PROJECT NO.: P87/09

Date: DD/MM/YYYY

6. PROGRESS ‘S’ CURVE

Page 7 of 15


REPLACEMENT OF EXISTING EFFLUENT AND OILY WATER LINES WITH RTRP IN GC-23 AND 25

KOC CONTRACT NO.: 39848

MONTHLY PROGRESS REPORT No. XX

IMCO PROJECT NO.: P87/09

Date: DD/MM/YYYY

7. SCHEDULE UPDATES

Page 8 of 15


REPLACEMENT OF EXISTING EFFLUENT AND OILY WATER LINES WITH RTRP IN GC-23 AND 25

KOC CONTRACT NO.: 39848

MONTHLY PROGRESS REPORT No. XX

IMCO PROJECT NO.: P87/09

Date: DD/MM/YYYY

8. 3 MONTHS LOOK AHEAD SCHEDULE

Page 9 of 15


REPLACEMENT OF EXISTING EFFLUENT AND OILY WATER LINES WITH RTRP IN GC-23 AND 25

KOC CONTRACT NO.: 39848

MONTHLY PROGRESS REPORT No. XX

IMCO PROJECT NO.: P87/09

Date: DD/MM/YYYY

9. MILESTONES

Page 10 of 15


REPLACEMENT OF EXISTING EFFLUENT AND OILY WATER LINES WITH RTRP IN GC-23 AND 25

KOC CONTRACT NO.: 39848

MONTHLY PROGRESS REPORT No. XX

IMCO PROJECT NO.: P87/09

Date: DD/MM/YYYY

10. PROCUREMENT LOG

Page 11 of 15


REPLACEMENT OF EXISTING EFFLUENT AND OILY WATER LINES WITH RTRP IN GC-23 AND 25

KOC CONTRACT NO.: 39848

MONTHLY PROGRESS REPORT No. XX

IMCO PROJECT NO.: P87/09

Date: DD/MM/YYYY

11.

MANPOWER & EQUIPMENT STATUS

Page 12 of 15


REPLACEMENT OF EXISTING EFFLUENT AND OILY WATER LINES WITH RTRP IN GC-23 AND 25

KOC CONTRACT NO.: 39848

MONTHLY PROGRESS REPORT No. XX

IMCO PROJECT NO.: P87/09

Date: DD/MM/YYYY

12. SAFETY REPORT

Page 13 of 15


REPLACEMENT OF EXISTING EFFLUENT AND OILY WATER LINES WITH RTRP IN GC-23 AND 25

KOC CONTRACT NO.: 39848

MONTHLY PROGRESS REPORT No. XX

IMCO PROJECT NO.: P87/09

Date: DD/MM/YYYY

13. QA/QC REPORT

Page 14 of 15


REPLACEMENT OF EXISTING EFFLUENT AND OILY WATER LINES WITH RTRP IN GC-23 AND 25

KOC CONTRACT NO.: 39848

MONTHLY PROGRESS REPORT No. XX

IMCO PROJECT NO.: P87/09

Date: DD/MM/YYYY

14. INVOICE STATUS

Page 15 of 15


KOC CONTRACT NO.: 39848

IMCO PROJECT NO.: P87/09

INVOICE FORMAT REPLACEMENT OF EXISTING OILY AND EFFLUENT WATER LINES WITH RTRP IN GC-23 AND GC-25

P.O. BOX 9309, AHMADI - 61004, KUWAIT – TEL.: +965 23981661/2 – FAX: +965 23984708 E-MAIL: projects@imcokw.com


IMCO ENGINEERING AND CONSTRUCTION COMPANY P.O Box : 9309 Ahmadi, 61004, Kuwait Tel.:(965) 2398 1661/2, Fax(965) 2398 4708 email : imcokw.com, website : www.imcokw.com

INTERIM PROGRESS INVOICE KOC Contract No.

39848

Contract Title

REPLACEMENT OF EXISTING OILY & EFFLUENT WATER LINES WITH RTRP IN GC-23 & 25

IMCO Contract No.

P87 / 09

Invoice Number Invoice Date Invoice Period / Month

DESCRIPTION

1. Contract Price

AMOUNT

1a.

Original g Contract Price

KD

1b.

Variation Order

KD

Total Contract Price ( 1a+1b)

KD

1,545,000.000 , , 1,545,000.000

2. Invoice Amount

2a.

Work done to date

KD

-

3. Advance Payment

3a.

Advance Payment

KD

-

3b.

Advance Payment Recovery ( 10%)

KD

-

4. Retention

4a.

Retention 5%

KD

-

5. Deductions

5a.

Others

KD

-

( 2a - 3b-4a-5a)

KD

-

Less: Amount Previously Invoiced

KD

-

Amount to be Paid for this Invoice

KD

-

Net Amount Certified to Date

Contractor Representative Amount in Words :

FOR IMCO

signature with date

JC Format / 8. Invoice Format


PROGRESS INVOICE SUMMARY KOC contract#

39848

IMCO Engineering and Constrcution company

IMCO Project#

P87/09

P.O.Box : 9309 Ahmadi,

Invoice#

61004‐Kuwait

Dated#

Tel.:(965) 2398 1661/2

Period

Fax.:(965) 2398 4708 DESCRIPTION

CONTRACT VALUE IN  KD

PREVIOUS PERIOD

CURRENT PERIOD

CUMULATIVE UPTO CURRENT  PERIOD

% COMPLETE

COST IN KD

% COMPLETE

COST IN KD

% COMPLETE

COST IN KD

61,800.000

0.00%

0.000

0.00%

0.000

0.00%

0.000

GC‐23

30,900.000

0.00%

0.000

0.00%

0.000

0.00%

0.000

GC‐25

30,900.000

0.00%

0.000

0.00%

0.000

0.00%

0.000

46,350.000

0.00%

0.000

0.00%

0.000

0.00%

0.000

GC‐23

23,175.000

0.00%

0.000

0.00%

0.000

0.00%

0.000

GC‐25

23,175.000

0.00%

0.000

0.00%

0.000

0.00%

0.000

803,400.000

0.00%

0.000

0.00%

0.000

0.00%

0.000

GC‐23

241,020.000

0.00%

0.000

0.00%

0.000

0.00%

0.000

GC‐25

562,380.000

0.00%

0.000

0.00%

0.000

0.00%

0.000

556,200.000

0.00%

0.000

0.00%

0.000

0.00%

0.000

DESIGN & ENGINEERING

HAZOP STUDIES

PROCRUMENT

CONSTRUCTION GENERAL

28,737.000

0.00%

0.000

0.00%

0.000

0.00%

0.000

GC‐23

180,610.500

0.00%

0.000

0.00%

0.000

0.00%

0.000

GC‐25

346,898.850

0.00%

0.000

0.00%

0.000

0.00%

0.000

77,250.000

0.00%

0.000

0.00%

0.000

0.00%

0.000

GC‐23

30,900.000

0.00%

0.000

0.00%

0.000

0.00%

0.000

GC‐25

46,350.000

0.00%

0.000

0.00%

0.000

0.00%

0.000

PRECOMM. & COMM.

TOTAL  (A) VARIATION ORDER (B) TOTAL CONTRACT PRICE (C=A+B) RETENTION 5% (D)

GRAND TOTAL (C‐D)

1,545,000.000

0.000

0.000

0.000

0.000

0.000

0.000

0.000

1,545,000.000

0.000

0.000

0.000

77,250.000

0.000

0.000

0.000

1,467,750.000

0.000

0.000

0.000

Page 1 of 1

REMARKS


PROGRESS INVOICE DETAILS KOC contract#

39848

IMCO Engineering and Constrcution company

IMCO Project#

P87/09

P.O.Box : 9309 Ahmadi,

Invoice#

61004‐Kuwait

Dated#

Tel.:(965) 2398 1661/2

Period

Fax.:(965) 2398 4708 DESCRIPTION REPLACEMENT OF EXISTING LINES GENERAL COMMON

% WT

CONTRACT  VALUE

100.00 0.00 0.00

Project Start

0.00

Prepare & Submit QA/QC Plan

0.00

Rev. & App. QA/QC Plan

0.00

Prepare & Submit Key Personnels

0.00

Rev. & App. Key Personnels

0.00

Prepare & Submit Sit office loc. & layout

0.00

Rev. & App. Site Office location & layout

0.00

Prepare & Submit Safety Plan

0.00

Rev. & App. Safety Plan

0.00

0.000 0.000

Finish Submittals

0.00

Site Office Mobilization

0.00

DESIGN & ENGINEERING GC‐23

4.00 2.00

61,800.000 30,900.000

0.20

3,090.000

SITE SURVEY Start Engineering Site Survey & Data Collection CIVIL & STRUCTURAL

DESIGN DRAWINGS & DOCUMENTS Preparation of Civil Drawings

0.00 0.20 0.20

3,090.000

0.14

2,163.000

0.00

Approval of Civil Drawings

0.07

Approval of dwg for str. support

0.07

Preparation of Dwg for Str.Support

STRUCTURAL STEEL SUPPORT Prep. & Sub. of Material Spec for Stru. Supports Approval Material Spec for Stru. Support

CIVIL MATERIALS Prep.& Sub. of Material Spec for Civil Matl Approval Material Spec for Civil Matl MECHANICAL & PIPING

0.00

0.03

463.500

0.00 0.03

0.03

463.500

0.00 0.03 1.10

16,995.000

DESIGN DRAWINGS & DOCUMENTS

0.66

10,197.000

Prep.& Sub. of Hydraulic Calculations

0.00

Approval of Hydraulic calculations

0.10

Prep.& Sub. of layout Dwg for CS & SS Pipeline

0.00

Prep.& Sub. of Iso. Drg.for CS & SS Pipeline

0.00

Approve layout Dwg for CS & SS Pipeline

0.17

Approval Iso Drg. for CS & SS Pipeline

0.17

Prep. of layout Drawing for RTRP

0.00

Prep.& Sub. of Stress analysis report

0.00

Approval of Stress Analysis Report

CS PIPES Prep.& Sub. of Material Spec for CS Pipes Approval Material Spec for CS Pipes

CS FITTING Prep.& Sub. of Material Spec for CS Fittings Approval Material Spec for CS Fittings

RTRP PIPE SPOOLS Prep.& Sub. of Material Spec for RTR Pipe spool

0.22

0.08

1,236.000

0.00 0.08

0.08

1,236.000

0.00 0.08

0.08

1,236.000

0.00

Approve Matl. Spec for RTRP Pipe spool

0.08

Sub. Proposal of RTRP Pipeline

0.00

MECH VALVES

COST IN KD % COMPLETE

0.08

Prep.& Sub. of Material Spec for Mech valves

0.00

Approval Material Spec for Mech valves

0.08

1,236.000

Page 1 of 10

PREVIOUS  PERIOD

CURRENT  PERIOD

CUMULATIVE UPTO  CURRENT PERIOD

REMARKS


DESCRIPTION SS PIPES Prep.& Sub. of Material Spec for SS Pipes Approval Material Spec for SS Pipes

SS FITTINGS Prep.& Sub. of Material Spec for SS Fittings

% WT

CONTRACT  VALUE

0.03

463.500

0.00 0.03

0.02

Approval Material Spec for SS Fittings

0.02

0.07

Approv. Matl. Spec‐corrosion mont. fitti INSTRUMENTATION

DESIGN DRAWINGS & DOCUMENTS Prep.& Sub. of P&ID Diagram

0.07 0.50

7,725.000

0.34

5,253.000

0.00 0.00

Prep.& Sub. of Cable Layout Drg

0.00

Approval of P&ID Diagram

0.06

Approval of Instrument Hook up drg

0.06

Approval of Cable layout drg

0.06

Prep.& Sub. of Inst loc plan & cable routing drg

0.00

Approval Inst loc plan & cable routing drg

0.06

Prep. & Sub. of loop diagram

0.00

Approval of loop diagram

0.06

Prep. & Sub. of Cable Schedule

0.00

CONTROL VALVES Prep.& Sub. of Material Spec for Control Valves Approval Material Spec for Control Valve

TEMP RELIEF VALVES Prep.& Sub. of Material Spec for TSV Approval of Material Spec for TSV

FLOW ELEMENTS Prep.& Sub. of Material Spec for Flow Elements Approval Material Spec for Flow Element

TEMP ELEMENTS Prep.& Sub. of Material Spec for Temp.Elements Approval Material Spec for Temp Element

INST. CABLES Prep.& Sub. of Material Spec for Inst. Cables Approval Material Spec for Inst. Cables

JUNCTION BOX Prep.& Sub. of Material Spec for JB's Approval Material Spec for JB's

BULK MATERIAL Prep.& Sub. of Material Spec for Bulk Material Approval of Bulk Material Spec.

GC‐25 SITE SURVEY Site Survey & Data Collection CIVIL & STRUCTURAL

DESIGN DRAWINGS & DOCUMENTS Approval of civil drawings

0.04

0.03 0.03

0.03 0.03

0.03 0.03

0.02

Approval Material Spec for Stru. Support Prep.& Sub. of Material Spec for Civil Matls Approval Material Spec for Civil Matls MECHANICAL & PIPING

309.000

0.00 0.02

0.03

463.500

0.00 0.03

0.00

0.000

0.00 0.00

0.02

309.000

0.00 0.02

2.00

30,900.000

0.20

3,090.000

0.20 0.20

3,090.000

0.14

2,163.000

0.07 0.00

CIVIL MATERIALS

463.500

0.00

0.07

Prep. & Sub. of Material Spec for Stru. Supports

463.500

0.00

Approval of dwg for str. steel support Preparation of Dwg for Str. Steel Support

463.500

0.00

Prep. & Sub. of Civil Drawings

STRUCTURAL STEEL SUPPORT

1,081.500

0.00

Prep.& Sub. of Instrument Hook up Drwgs

Approval of Cable Schedule

309.000

0.00

CORROSION MONITORING FITTING Prep.& Sub. Matl. Spec for corrosion mont. fitti

COST IN KD % COMPLETE

0.00

0.03

463.500

0.00 0.03

0.03

463.500

0.00 0.03 1.10

16,995.000

DESIGN DRAWINGS & DOCUMENTS

0.66

10,197.000

Prep.& Sub. of Hydraulic Calculations

0.00

Approval of Hydraulic calculations

0.10

Prep.& Sub. of layout Dwg for CS & SS Pipeline

0.00

Page 2 of 10

PREVIOUS  PERIOD

CURRENT  PERIOD

CUMULATIVE UPTO  CURRENT PERIOD

REMARKS


DESCRIPTION

% WT

Prep.& Sub. of Iso. Drg.for CS & SS Pipeline

0.00

Approval layout Dwg for CS & SS Pipeline

0.17

Approval Iso Drg. for CS & SS Pipeline

0.17

Prep. of layout Drawing for RTRP line

0.00

Prep.& Sub. of Stress analysis report

0.00

Approval of Stress Analysis Report

CS PIPES Prep.& Sub. of Material Spec for CS Pipes Approval Material Spec for CS Pipes

CS FITTING Prep.& Sub. of Material Spec for CS Fittings Approval Material Spec for CS Fittings

RTRP PIPE SPOOLS Prep.& Sub. of Material Spec for RTR Pipe spool

0.08

0.08 0.08

0.08

Prep.& Sub. of Material Spec for SS Pipes Approval Material Spec for SS Pipes

SS FITTINGS Prep.& Sub. of Material Spec for SS Fittings

0.08 0.08

0.03 0.03

0.02 0.02

DESIGN DRAWINGS & DOCUMENTS Prep.& Sub. of P&ID Diagram

0.07 0.50

7,725.000

0.35

5,407.500

0.00 0.00

Prep.& Sub. of Cable Layout Drg

0.00

Approval of P&ID Diagram

0.06

Approval of Instrument Hook up drg

0.06

Approval of Cable layout drg

0.06

Prep.& Sub. of Inst loc plan & cable routing drg

0.00

Approval Inst loc plan & cable routing drg

0.06

Prep. & Sub. of loop diagram

0.00

Approval of loop diagram

0.06

Prep. & Sub. of Cable Schedule

0.00

ESD VALVES Prep.& Sub. of Material Spec for ESD Valves Approval Material Spec for ESD Valves

CONTROL VALVES Prep.& Sub. of Material Spec for Control Valves Approval Material Spec for Control Valve

FLOW ELEMENTS Prep.& Sub. of Material Spec for Flow Elements Approval Material Spec for Flow Element

TEMP ELEMENTS Prep.& Sub. of Material Spec for Temp.Elements Approval Material Spec for Temp Element

INST. CABLES Prep.& Sub. of Material Spec for Inst. Cables Approval Material Spec for Inst. Cables

JUNCTION BOX Prep.& Sub. of Material Spec for JB's Approval Material Spec for JB's

BULK MATERIAL Prep.& Sub. of Material Spec for Bulk Material Approval of Bulk Material Spec.

HAZOP STUDIES

1,081.500

0.00

Prep.& Sub. of Instrument Hook up Drwgs

Approval of Cable Schedule

309.000

0.00

0.07

Approval Matl. Spec‐corrosion mont. fitti

463.500

0.00

Approval Material Spec for SS Fittings

INSTRUMENTATION

1,236.000

0.00

CORROSION MONITORING FITTING Prep.& Sub. Matl. Spec for corrosion mont. fitti

1,236.000

0.00 0.08

Approval Material Spec for Mech valves

1,236.000

0.00

0.00

SS PIPES

1,236.000

0.00

Approval Matl. Spec for RTRP Pipe spool

Prep.& Sub. of Material Spec for Mech valves

COST IN KD % COMPLETE

0.22

0.08

Sub. Proposal of RTRP Pipelines

MECH VALVES

CONTRACT  VALUE

0.05

0.03

463.500

0.00 0.03

0.03

463.500

0.00 0.03

0.03

463.500

0.00 0.03

0.00

0.000

0.00 0.00

0.03

463.500

0.00 0.03

0.00

0.000

0.00 0.00

0.03

463.500

0.00 0.03

3.00

46,350.000

Page 3 of 10

PREVIOUS  PERIOD

CURRENT  PERIOD

CUMULATIVE UPTO  CURRENT PERIOD

REMARKS


DESCRIPTION GC‐23 Submit Hazop /QRA / EIA report Approval of HAZOP report

GC‐25 Submit Hazop /QRA / EIA report Approval of HAZOP report

PROCRUMENT GC‐23 CIVIL & STRUCTURAL

STRUCTURAL STEEL SUPPORT Processing & Placing of P.O

% WT

CONTRACT  VALUE

1.50

23,175.000

0.00 1.50

1.50 1.50

52.00 15.60

803,400.000 241,020.000

0.00

0.000

0.00

0.000

0.00 0.00

Procurement of Materials

0.00

Sub. & Approval of Technical Proposal

0.00

Material Delivery

0.00

CIVIL MATERIALS

0.00 0.00

Procurement of Materials

0.00

Sub. & Approval of Technical Proposal

0.00

Material Delivery

0.00

CS PIPES Processing & Placing of P.O

15.60

241,020.000

2.00

30,900.000

0.00

Proposal & Technical Bid Analysis

0.00

Procurement of Materials

0.00

Sub. & Approval of Technical Proposal

0.00

Material Delivery

2.00

CS Pipes receipt

CS FITTING

0.00

0.64

Processing & Placing of P.O

0.00

Procurement of Materials

0.00

Proposal & Technical Bid Analysis

0.00

Sub. & Approval of Technical Proposal

0.00

Material Delivery

0.64

CS Fittings receipt

0.00

RTRP PIPE SPOOLS

1.76

Proposal & Technical Bid Analysis

0.00

Sub. & Approval of Technical Proposal

0.00

Processing & Placing of P.O

0.00

Prep. & Sub. of Drg. & Data sheets

0.00

Procurement of Materials

0.00

Approval of Drg. & Data Sheets

0.00

Material Delivery

1.76

RTRP Pipe Spools receipt

0.00

MECH VALVES Processing & Placing of P.O

9.92

Sub. & Appr. of Drg. & Data sheets

0.00 0.00

Material Delivery

9.92

Mech Valves receipt

0.00

Proposal & Technical Bid Analysis

0.00

SS PIPES Processing & Placing of P.O

153,264.000

2,781.000

0.00 0.00

Procurement of Materials

0.00

Sub. & Approval of Technical Proposal

0.00

Material Delivery

0.18

Processing & Placing of P.O

27,192.000

0.00

0.18

Proposal & Technical Bid Analysis

SS FITTINGS

9,888.000

0.00

Procurement of Materials

Sub. & Approval of Technical Proposal

0.000

0.00

Proposal & Technical Bid Analysis

MECHANICAL & PIPING

23,175.000

0.00

Proposal & Technical Bid Analysis

Processing & Placing of P.O

COST IN KD % COMPLETE

0.06

927.000

0.00

Proposal & Technical Bid Analysis

0.00

Procurement of Materials

0.00

Sub. & Approval of Technical Proposal

0.00

Page 4 of 10

PREVIOUS  PERIOD

CURRENT  PERIOD

CUMULATIVE UPTO  CURRENT PERIOD

REMARKS


DESCRIPTION Material Delivery

CORROSION MONITORING FITTING

% WT

CONTRACT  VALUE

0.06

1.04

Proposal & Technical Bid Analysis

0.00

Sub. & Approval of Technical Proposal

0.00

Processing & Placing of P.O

0.00

Sub. & Approv. of Details and Documents

0.00

Procurement of Materials

0.00

16,068.000

Material Delivery

1.04

INSTRUMENTATION

0.00

0.000

CONTROL VALVES

0.00

0.000

Processing & Placing of P.O

0.00

Sub. & Appr. of Drg. & Data sheets

0.00

Procurement of Materials

0.00

Sub. & Approval of Technical Proposal

0.00

Material Delivery

0.00

Control Valves receipt

0.00

Proposal & Technical Bid Analysis

0.00

Finish Procurement

0.00

TEMP RELIEF VALVES

0.00

Processing & Placing of P.O

0.00

Sub. & Appr. of Drg. & Data sheets

0.00

Procurement of Materials

0.00

Material Delivery

0.00

Temp Relief Valves receipt

0.00

Sub. & Approval of Technical Proposal

0.00

0.00

Processing & Placing of P.O

0.00

Procurement of Materials

0.00

Proposal & Technical Bid Analysis

0.00

Material Delivery

0.00

Sub. & Approval of Technical Proposal

0.00

Sub. & Appr. of Drg. & Data sheets

0.00

TEMP ELEMENTS

0.00

Processing & Placing of P.O

0.00

Procurement of Materials

0.00

Proposal & Technical Bid Analysis

0.00

Material Delivery

0.00

Sub. & Approval of Technical Proposal

0.00

Sub. & Appr. of Drg. & Data sheets

0.00

INST. CABLES

0.00

Processing & Placing of P.O

0.00

Procurement of Materials

0.00

Material Delivery

JUNCTION BOX

0.00

Procurement of Materials

0.00

Material Delivery

0.00

BULK MATERIAL

0.00

Processing & Placing of P.O

0.00

Procurement of Materials

0.00

GC‐25 CIVIL & STRUCTURAL

STRUCTURAL STEEL SUPPORT Processing & Placing of P.O

0.000

0.000

0.000

0.000

0.00

36.40

562,380.000

0.00

0.000

0.00

0.000

0.00

Proposal & Technical Bid Analysis

0.00

Procurement of Materials

0.00

Sub. & Approval of Technical Proposal

0.00

Material Delivery

0.00

CIVIL MATERIALS

0.00

Processing & Placing of P.O

0.000

0.00

0.00

Processing & Placing of P.O

Material Delivery

0.000

0.00

Proposal & Technical Bid Analysis

FLOW ELEMENTS

COST IN KD % COMPLETE

0.000

0.00

Proposal & Technical Bid Analysis

0.00

Procurement of Materials

0.00

Page 5 of 10

PREVIOUS  PERIOD

CURRENT  PERIOD

CUMULATIVE UPTO  CURRENT PERIOD

REMARKS


DESCRIPTION

% WT

Sub. & Approval of Technical Proposal

0.00

Material Delivery

0.00

MECHANICAL & PIPING

CS PIPES Processing & Placing of P.O

36.40

562,380.000

4.67

72,151.500

0.00

Procurement of Materials

0.00

Sub. & Approval of Technical Proposal

0.00

Material Delivery

4.67

CS Pipes receipt

0.00

1.49

Processing & Placing of P.O

0.00

Procurement of Materials

0.00

Proposal & Technical Bid Analysis

0.00

Material Delivery

1.49

CS Fittings receipt

0.00

Sub. & Approval of Technical Proposal

RTRP PIPE SPOOLS

0.00

Sub. & Approval of Technical Proposal

0.00

Processing & Placing of P.O

0.00

Prep. & Sub. of Drg. & Data sheets

0.00

Procurement of Materials

0.00

Approval of Drg. & Data sheets

0.00

Material Delivery

4.11

RTRP Pipe spools receipt

0.00

Processing & Placing of P.O

23.16

Sub. & Appr. of Drg. & Data sheets

0.00 0.00

Material Delivery

23.16

Mech Valves receipt

0.00

Proposal & Technical Bid Analysis

0.00

SS PIPES Processing & Placing of P.O

0.00 0.00

Sub. & Approval of Technical Proposal

0.00

Material Delivery

0.41

0.13 0.00

Procurement of Materials

0.00

Sub. & Approval of Technical Proposal

0.00

Material Delivery

0.13

2.43

Proposal & Technical Bid Analysis

0.00

Sub. & Approval of Technical Proposal

0.00

Processing & Placing of P.O

0.00

Sub. & Appr. of Drg. & Data sheets

0.00

Procurement of Materials

0.00

Material Delivery

2.43

Corrosion Monitoring receipt

0.00

INSTRUMENTATION

ESD VALVES Processing & Placing of P.O

0.00

0.000

0.000

0.00

Sub. & Appr. of Drg. & Data sheets

0.00 0.00

Material Delivery

0.00

ESD Valves receipt

0.00

Proposal & Technical Bid Analysis

0.00

CONTROL VALVES

37,543.500

0.00

Procurement of Materials

Sub. & Approval of Technical Proposal

2,008.500

0.00

Proposal & Technical Bid Analysis

CORROSION MONITORING FITTING

6,334.500

0.00

Procurement of Materials

Processing & Placing of P.O

357,822.000

0.00

0.41

Proposal & Technical Bid Analysis

SS FITTINGS

63,499.500

0.00

Procurement of Materials

Sub. & Approval of Technical Proposal

23,020.500

0.00

4.11

Proposal & Technical Bid Analysis

MECH VALVES

COST IN KD % COMPLETE

0.00

Proposal & Technical Bid Analysis

CS FITTING

CONTRACT  VALUE

0.00

0.00

0.000

Page 6 of 10

PREVIOUS  PERIOD

CURRENT  PERIOD

CUMULATIVE UPTO  CURRENT PERIOD

REMARKS


DESCRIPTION

% WT

Processing & Placing of P.O

0.00

Sub. & Appr. of Drg. & Data sheets

0.00

Procurement of Materials

0.00

Material Delivery

0.00

Control Valves receipt

0.00

Proposal & Technical Bid Analysis

0.00

Sub. & Approval of Technical Proposal

FLOW ELEMENTS

0.00

Procurement of Materials

0.00

Material Delivery

0.00

Sub. & Appr. of Drg. & Data sheets

0.00

Proposal & Technical Bid Analysis

0.00

INST. CABLES

0.00

Procurement of Materials

0.00

JUNCTION BOX

0.00

Procurement of Materials

0.00

Material Delivery

0.00

BULK MATERIAL

0.00

Processing & Placing of P.O

0.00

Procurement of Materials

0.00

CONSTRUCTION GENERAL

0.000

0.000

0.00

36.00 1.86

Site Mobilization of Manpower & Equipment

0.00

Start Construction

0.00

Steel Piping Prefabrication, NDE & Hydrotesting

1.86

FBE Coating of CS Pipespools

0.00

GC‐23

0.000

0.00

0.00

Processing & Placing of P.O

Material Delivery

0.000

0.00

0.00

Processing & Placing of P.O Material Delivery

556,200.000 28,737.000

11.69

180,610.500

CIVIL & STRUCTURAL

1.25

19,312.500

DESALTER A&B AREA

0.75

11,587.500

Excavation for UG Piping for Steel PIpes

0.04

Excavation for UG Piping for RTRP

0.19

Installation of new Pipe supports Steel Pipe

0.04

Installation of new Pipe supports RTRP

0.19

Civil Works for Cable Trenches

0.04

Backfilling for All excavations

0.15

Pipe Support Foundation / Valve Pit works

SEPERATOR AREA Pipe Support Foundation / Valve Pit works

0.10

0.50

7,725.000

0.10

Installation of new Pipe supports RTRP

0.20

Backfilling for All excavations

0.20

MECHANICAL & PIPING

4.62

71,379.000

DESALTER A&B AREA

2.86

44,187.000

Installation of all AG Steel Pipes

0.03

Installation of all UG Steel Pipes

0.01

Installation of all AG RTRP Pipes

0.09

Installation of UG RTRP Pipes

0.09

Install Control Valves

1.57

Install Mech Valves

0.42

Hydrotesting of Pipelines

0.13

Painting of A/G Piping & Supports

0.01

Installation of Flow Elements

0.05

Tentative S/D to be discussed with KOC

0.43

Installation of Corrosion Monitoring Fittings

0.03

SEPERATOR AREA Installation of Corrosion Monitoring Fittings

COST IN KD % COMPLETE

0.00

0.00

Processing & Placing of P.O

Sub. & Approval of Technical Proposal

CONTRACT  VALUE

1.76

27,192.000

0.07

Installation of all AG RTRP Pipes

0.20

Install Mech Valves

0.33

Hydrotesting of Pipelines

0.14

Page 7 of 10

PREVIOUS  PERIOD

CURRENT  PERIOD

CUMULATIVE UPTO  CURRENT PERIOD

REMARKS


DESCRIPTION

% WT

Painting of A/G Piping & Supports

0.00

Tentative S/D to be discussed with KOC

1.02

CONTRACT  VALUE

Finish Construction

0.00

INSTRUMENTATION

5.30

81,885.000

5.30

81,885.000

DESALTER A&B AREA Intallation of Temp Elements

0.24

Installation of Temp Relief Valve

2.61

Installation of Inst. cables/ Tubing

0.14

Install Cable Trays

0.32

Glanding & Termination works

0.34

Installation of JB

0.02

Air Supply Piping/ Tubing for Valves

0.70

Shutdown‐ Instrument work

0.82

Calibration of instruments

0.11

DEMOLITION

DESALTER A&B AREA Demolition of Old Redundant Pipe lines

0.52

8,034.000

0.27

4,171.500

0.19

Demolition of Old redundant valves

0.05

Demolition of Old reduntant Instruments & Cables

0.03

SEPERATOR AREA Demolition of Old Redundant Pipe lines

0.25

3,862.500

0.20

Demolition of Old redundant valves

0.05

Finish Demolition

0.00

GC‐25

22.45

346,898.850

CIVIL & STRUCTURAL

3.75

57,983.850

DESALTER A&B AREA

0.16

2,518.350

Installation of new Pipe supports

0.05

Civil Works for Cable Trenches

0.02

Backfilling for All excavations

0.05

Pipe Support Foundation / Valve Pit works

WET CRUDE TANK AREA

0.04

0.92

Excavation for UG Steel Piping

0.32

Installation of new Pipe supports Steel Pipe

0.14

Civil work for Cable trenches

0.05

Fire Proofing Works

0.05

Backfilling for All excavations

0.27

Pipe Support Foundation / Valve Pit works

PIPE WAY

0.33

Excavation of UG RTRP Pipes

0.66

Installation of new Pipe supports Steel Pipe

0.22

Installation of new Pipe supports RTRP

0.22

Civil works for cable trenches

0.11

Backfilling for All excavations

0.33

Pipe Support Foundation / Valve Pit works

33,990.000

0.33

0.47

Installation of new Pipe supports Steel Pipe

0.12

Installation of new Pipe supports RTRP

0.16

Civil works for cable trenches

0.05

Backfilling for All excavations

0.09

Pipe Support Foundation / Valve Pit works

14,214.000

0.09

2.20

Excavation for UG Steel Piping

PUMPING AREA

7,261.500

0.05

MECHANICAL & PIPING

11.92

184,164.000

DESALTER A&B AREA

0.44

6,798.000

Installation of all AG Steel Pipes

0.15

Install Mech Valves

0.09

Hydrotesting of Pipelines

0.01

Painting of A/G Piping & Supports

0.03

Installation of Corrosion Monitoring Fittings

0.01

Installation of Flow Elements

0.05

Tentative S/D to be discussed with KOC

0.10

WET CRUDE TANK AREA Installation of all AG Steel Pipes

COST IN KD % COMPLETE

6.50

100,425.000

0.07

Installation of all UG Steel Pipes

0.45

Install ESD Valves

5.63

Page 8 of 10

PREVIOUS  PERIOD

CURRENT  PERIOD

CUMULATIVE UPTO  CURRENT PERIOD

REMARKS


DESCRIPTION

% WT

Install Mech Valves

0.12

Hydrotesting of Pipelines

0.03

Painting of A/G Piping & Supports

0.01

Tentative S/D to be discussed with KOC

0.18

Installation of Corrosion Monitoring Fittings

PIPE WAY Installation of all AG Steel Pipes

0.36 0.01

Installation of UG RTRP Pipes

0.28

Install Mech Valves

0.07

Hydrotesting of Pipelines

0.40

Painting of A/G Piping & Supports

0.60

Tentative S/D to be discussed with KOC

0.17

Installation of all AG Steel Pipes

58,710.000

1.90

Installation of all UG Steel Pipes

Installation of Corrosion Monitoring Fittings

0.01

1.18

18,231.000

0.05

Installation of all AG RTRP Pipes

0.04

Installation of Corrosion Monitoring Fittings

0.01

Install Control Valves

0.70

Installation of Flow Elements

0.05

Install Mech Valves

0.10

Hydrotesting of Pipelines

0.03

Painting of A/G Piping & Supports

0.02

Tentative S/D to be discussed with KOC

0.18

Finish Construction

0.00

INSTRUMENTATION

6.00

92,700.000

0.40

6,180.000

DESALTER A&B AREA Installation of Inst. cables/ Tubing

0.03

Install Cable Trays

0.11

Glanding & Termination works

0.07

Installation of JB

0.02

Air Supply Piping/ Tubing for Valves

0.05

Shut down ‐ Instrument work

0.10

Calibration of Instruments

0.02

WET CRUDE TANK AREA

2.58

Installation of Inst. cables/ Tubing

0.94

Glanding & Termination works

0.59

Installation of JB

0.03

Air Supply Piping/ Tubing works for Valves

0.46

Shutdown ‐ Instrument work

0.15

Calibration of Instruments

0.02

Installation of Inst. cables/ Tubing

0.63 0.17

Glanding & Termination works

0.13

Installation of JB

0.01

Air Supply Piping/Tubing for valves

0.11

Shutdown ‐ Instrument work

0.07

Calibration of Instruments Installation of Inst. cables/ Tubing

0.07

2.39 0.32

Glanding & Termination works

0.76

Installation of JB

0.01

Air Supply Piping/ Tubing for Valves

0.60

Shutdown ‐ Instrument work

0.25

Calibration of Instruments

0.09

DESALTER A&B AREA Demolition of Old Redundant Pipe lines

36,925.500

0.36

Install Cable Trays

DEMOLITION

9,733.500

0.07

Install Cable Trays

PUMPING AREA

39,861.000

0.39

Install Cable Trays

PIPE WAY

COST IN KD % COMPLETE

0.01

3.80

Installation of all AG RTRP Pipes

PUMPING AREA

CONTRACT  VALUE

0.78

12,051.000

0.18

2,781.000

0.12

Demolition of Old redundant valves

0.04

Demolition of Old reduntant Instruments & Cables

0.02

Page 9 of 10

PREVIOUS  PERIOD

CURRENT  PERIOD

CUMULATIVE UPTO  CURRENT PERIOD

REMARKS


DESCRIPTION WET CRUDE TANK AREA Demolition of Old Redundant Pipe lines

% WT

CONTRACT  VALUE

0.20

3,090.000

0.04

Demolition of Old reduntant Instruments & Cables

0.02

0.20

Demolition of Old Redundant Pipe lines

0.04

Demolition of Old reduntant Instruments & Cables

0.02

Demolition of Old Redundant Pipe lines

0.20 0.04

Demolition of Old reduntant Instruments & Cables

0.02

Finish Demolition

Precommissioning work Commissioning work

SEPERATOR AREA Precommissioning work

3.00 0.75

Precommissioning work

0.53

Commissioning work

EFFLUENT WATER PUMPING DISPOSAL AREA Precommissioning work

0.00

0.00

0.00

11,587.500

0.53 0.22

0.75

11,587.500

0.53 0.22

Finish Commissioning

0.00

Project Finish

11,587.500

0.22

0.75

Commissioning work

PROJECT CLOSEOUT

0.00

0.22

0.75

Precommissioning work

46,350.000 11,587.500

0.53

WET CRUDE TANK AREA Commissioning work

15,450.000

0.70 0.30

EFFLUENT WATER TANK AREA

77,250.000 30,900.000 15,450.000

0.30

1.00

0.00

Commissioning work

3,090.000

0.70

Finish Commissioning

Precommissioning work

3,090.000

0.00

5.00 2.00 1.00

Commissioning work

GC‐25 DESALTER A&B AREA

CUMULATIVE UPTO  CURRENT PERIOD

0.14

Demolition of Old redundant valves

PRECOMMISSIONING & COMMISSIONING GC‐23 DESALTER A&B AREA

CURRENT  PERIOD

0.14

Demolition of Old redundant valves

PUMPING AREA

PREVIOUS  PERIOD

0.14

Demolition of Old redundant valves

PIPE WAY

COST IN KD % COMPLETE

0.00

0.000

0.00

Demobilization

0.00

GC‐23

0.00

Submission of As Built Drawings Submission of As Built Packages

GC‐25

0.00

0.00

Submission of As Built Drawings

0.00

Submission of As Built Packages

0.00

TOTAL (A)

0.000

0.00

100.00

0.000

1,545,000.000

Page 10 of 10

REMARKS


KOC CONTRACT NO.: 39848

IMCO PROJECT NO.: P87/09

CASH FLOW REPLACEMENT OF EXISTING OILY AND EFFLUENT WATER LINES WITH RTRP IN GC-23 AND GC-25

P.O. BOX 9309, AHMADI - 61004, KUWAIT – TEL.: +965 23981661/2 – FAX: +965 23984708 E-MAIL: projects@imcokw.com


REPLACEMENT OF EXISTING OILY & EFFLUENT WATER LINES WITH RTRP IN GC-23 & 25 OVERALL CASH FLOW "S" CURVE

IMCO REF # P87/09

KOC CONTRACT# 39848

700,000.000

1,400,000.000 600,000.000

1,200,000.000

1,000,000.000

400,000.000 800,000.000

300,000.000 600,000.000

CUMUL LATIVE CASH (KWD)

MONTH HLY CASH (KWD)

500,000.000

200,000.000 400,000.000

100,000.000

200,000.000

0.000

0.000 Mar-09

Apr-09

May-09

Jun-09

Jul-09

Aug-09

Sep-09

Oct-09

Nov-09

Dec-09

Jan-10

Feb-10

Mar-10

Apr-10

May-10

Jun-10

Jul-10

Aug-10

Sep-10

MONTHS Plan Monthly Cash (Rev.1 Baseline Schedule)

MONTH Plan Monthly Cash (Rev.1  Baseline Schedule)

Plan Cumullative Cash (Rev.1 Baseline Schedule)

Actual Cumullative Cash (Rev.1 Baseline Schedule)

Actual Monthly Cash (Rev.1 Baseline Schedule)

Mar‐09

Apr‐09

May‐09

Jun‐09

Jul‐09

Aug‐09

Sep‐09

Oct‐09

Nov‐09

Dec‐09

Jan‐10

Feb‐10

Mar‐10

Apr‐10

May‐10

Jun‐10

Jul‐10

Aug‐10

Sep‐10

0.000

1,529.550

4,679.805

40,709.205

6,495.180

54,736.260

0.000

150,948.389

12,286.079

83,944.926

47,269.797

28,695.843

42,041.812

624,865.277

141,122.910

147,802.225

87,580.042

63,517.741

6,774.959

0.000

1,529.550

6,209.355

46,918.560

53,413.740

108,150.000

108,150.000

259,098.389

271,384.468

355,329.394

402,599.191

431,295.034

473,336.847

Actual Monthly Cash (Rev.1  Baseline Schedule) Plan Cumullative Cash (Rev.1  Baseline Schedule) Actual Cumullative Cash (Rev.1  Baseline Schedule)

1,098,202.124 1,239,325.033 1,387,127.258 1,474,707.300 1,538,225.041 1,545,000.000


REPLACEMENT OF EXSTING OILY & EFFLUENT WATER LINES WITH RTRP IN GC-23 & 25 CASH FLOW PLAN IMCO REF # P87/09

DESCRIPTION

KOC CONTRACT # 39848

 CONTRACT  VALUE 

% WT

Mar‐09

Apr‐09

May‐09

Jun‐09

Jul‐09

Aug‐09

1,529.550

4,679.805

40,709.205

6,495.180

8,386.260

Sep‐09

Oct‐09

DESIGN & ENGINEERING            61,800.000

4.00

HAZOP STUDIES

           46,350.000

3.00

PROCRUMENT

        803,400.000

52.00

147,876.869

CONSTRUCTION

        556,200.000

36.00

3,071.520

PRECOMM & COMM

           77,250.000

5.00

TOTAL

    1,545,000.00

100.000

Nov‐09

Dec‐09

Jan‐10

67,975.496

22,659.014

12,286.079 15,969.431

24,610.784

Feb‐10

Mar‐10

Apr‐10

May‐10

557,222.317

7,666.305

67,642.960

133,456.605

Jun‐10

Jul‐10

Aug‐10

Sep‐10

119,715.108 61,416.489

43,994.730

3,298.639

28,087.117

19,523.010

3,476.320

46,350.000

1,529.550 4,679.805

40,709.205

6,495.180 54,736.260

28,695.843 42,041.812

26,163.553

150,948.389 12,286.079 83,944.926 47,269.797 28,695.843 42,041.812 624,865.277 141,122.910 147,802.225 87,580.042 63,517.741 6,774.959

Page 1 of 1

Remarks


KOC CONTRACT NO.: 39848

IMCO PROJECT NO.: P87/09

PROGRESS MEASUREMENT SUMMARY REPLACEMENT OF EXISTING OILY AND EFFLUENT WATER LINES WITH RTRP IN GC-23 AND GC-25

P.O. BOX 9309, AHMADI - 61004, KUWAIT – TEL.: +965 23981661/2 – FAX: +965 23984708 E-MAIL: projects@imcokw.com


REPLACEMENT OF EXISTING OILY AND EFFLUENT WATER LINES WITH RTRP IN GC-23 GC 23 AND 25 IMCO JOB # P87/09

KOC CONTRACT # 39848

PROGRESS MEASUREMENT SYSTEM - SUMMARY Status as of :

Sl. No

Description

WT %

1

Design & Engineering

4.00

2

Procurement

52.00

3

Construction

36.00

4

Hazop,QRA,EIA Studies

3.00

5

Testing,Precommissioning & Commissioning

5.00

Total

Plan % Pl % Progress WT%

100.00

Page 1 of 1

Actual % A t l% Progress WT%

Variance V i Ahead Delay

Remarks


REPLACEMENT OF EXISTING OILY & EFFLUENT WATER LINES WITH RTRP IN GC‐23 & 25 PROGRESS MEASUREMENT SYSTEM IMCO JOB # P87/09

Activity ID

KOC CONTRACT # 39848

Activity Description

% WT

REPLACEMENT OF EXISTING OILY & EFFLUENT LINES

100.00

0.00

GENERAL

0.00

COMMON GENE0100

Project Start

0.00

GENE0190

Prepare & Submit QA/QC Plan

0.00 0.00

GENE0200

Rev. & App. QA/QC Plan

GENE0210

Prepare & Submit Key Personnels

0.00

GENE0220

Rev. & App. Key Personnels

0.00

GENE0250

Prepare & Submit Sit office loc. & layout

0.00

GENE0260

Rev. & App. Site Office location & layout

0.00

GENE0270

Prepare & Submit Safety Plan

0.00

GENE0280

Rev. & App. Safety Plan

0.00

GENE0330

Finish Submittals

0.00

GENE0340

Site Office Mobilization

0.00

4.00

DESIGN & ENGINEERING

2.00

GC‐23 SITE SURVEY

0.20 0 20

ENGS0090

Start Engineering

0.00

ENGS0100

Site Survey & Data Collection

0.20

CIVIL & STRUCTURAL

0.20

DESIGN DRAWINGS & DOCUMENTS

0.14

ENCD0120

Preparation of Civil Drawings

0.00

ENCD0140

Approval of Civil Drawings

0.07

ENCD0150

Approval of dwg for str. support

0.07

ENCD0160

Preparation of Dwg for Str.Support

0.00

STRUCTURAL STEEL SUPPORT

0.03

ENCS0140

Prep. & Sub. of Material Spec for Stru. Supports

ENCS0150

Approval Material Spec for Stru. Support

0.00 0.03

CIVIL MATERIALS

0.03

ENCS0180

Prep.& Sub. of Material Spec for Civil Matl

0.00

ENCS0190

Approval Material Spec for Civil Matl

0.03

MECHANICAL & PIPING

1.10

DESIGN DRAWINGS & DOCUMENTS

0.66

ENMD0080

Prep.& Sub. of Hydraulic Calculations

0.00

ENMD0090

Approval of Hydraulic calculations

0.10

ENMD0100

Prep.& Sub. of layout Dwg for CS & SS Pipeline

0.00

ENMD0110

Prep.& Sub. of Iso. Drg.for CS & SS Pipeline

0.00

ENMD0120

Approval of layout Dwg for CS & SS Pipeline

0.17

ENMD0130

Approval Iso Drg. for CS & SS Pipeline

0.17

ENMD0140

Prep. of layout Drawing for RTRP

0.00

ENMD0220

Prep.& Sub. of Stress analysis report

0.00

ENMD0230

Approval of Stress Analysis Report

0.22

Page 1 of 13

%

ACCURED Weightage

Remarks


Activity ID

Activity Description

% WT

CS PIPES

0.08

ENMS0100

Prep.& Sub. of Material Spec for CS Pipes

ENMS0110

Approval Material Spec for CS Pipes

0.00 0.08

CS FITTING

0.08

ENMS0120

Prep.& Sub. of Material Spec for CS Fittings

0.00

ENMS0130

Approval Material Spec for CS Fittings

0.08

RTRP PIPE SPOOLS

0.08

ENMS0140

Prep.& Sub. of Material Spec for RTR Pipe spool

0.00

ENMS0150

Review & Approve Matl. Spec for RTRP Pipe spool

0.08

MECH VALVES

0.08

ENMS0180

Prep.& Sub. of Material Spec for Mech valves

ENMS0190

Approval Material Spec for Mech valves

0.00 0.08

SS PIPES

0.03

ENMS0240

Prep.& Sub. of Material Spec for SS Pipes

0.00

ENMS0260

Approval Material Spec for SS Pipes

0.03

SS FITTINGS

0.02

ENMS0250

Prep.& Sub. of Material Spec for SS Fittings

0.00

ENMS0270

Approval Material Spec for SS Fittings

0.02

CORROSION MONITORING FITTING

0.07

ENMS0280

Prep.& Sub. Matl. Spec for corrosion mont. fitti

0.00

ENMS0290

Approval of Matl. Spec‐corrosion mont. fitti

0.07

INSTRUMENTATION

0.50

DESIGN DRAWINGS & DOCUMENTS

0.34

ENID0100

Prep.& Sub. of P&ID Diagram

0.00

ENID0110

Prep.& Sub. of Instrument Hook up Drwgs

0.00

ENID0120

Prep.& Sub. of Cable Layout Drg

0.00

ENID0130

Approval of P&ID Diagram

0.06

ENID0140

Approval of Instrument Hook up drg

0.06 0.06

ENID0150

Approval of Cable layout drg

ENID0160

Prep.& Sub. of Inst loc plan & cable routing drg

0.00

ENID0170

Rev. & Appr. Inst loc plan & cable routing drg

0.06

ENID0180

Prep. & Sub. of loop diagram

0.00

ENID0190

Approval of loop diagram

0.06

ENID0200

Prep. & Sub. of Cable Schedule

0.00

ENID0210

Approval of Cable Schedule

0.04

CONTROL VALVES

0.03

ENIS0100

Prep.& Sub. of Material Spec for Control Valves

ENIS0110

Approval of Material Spec for Control Valve

0.03

TEMP RELIEF VALVES ENIS0240

Prep.& Sub. of Material Spec for TSV

ENIS0250

Approval of Material Spec for TSV

0.00

0.03 0.00 0.03

FLOW ELEMENTS

0.03

ENIS0200

Prep.& Sub. of Material Spec for Flow Elements

0.00

ENIS0210

Approval Material Spec for Flow Element

0.03

TEMP ELEMENTS

0.02

ENIS0220

Prep.& Sub. of Material Spec for Temp.Elements

0.00

ENIS0230

Approval Material Spec for Temp Element

0.02

Page 2 of 13

%

ACCURED Weightage

Remarks


Activity ID

Activity Description

% WT

INST. CABLES

0.03

ENIS0140

Prep.& Sub. of Material Spec for Inst. Cables

ENIS0150

Approval Material Spec for Inst. Cables

0.00 0.03

JUNCTION BOX

0.00

ENIS0270

Prep.& Sub. of Material Spec for JB's

0.00

ENIS0280

Approval Material Spec for JB's

0.00

BULK MATERIAL

0.02

ENIS0180

Prep.& Sub. of Material Spec for Bulk Material

0.00

ENIS0190

Approval of Bulk Material Spec.

0.02

2.00

GC‐25 SITE SURVEY ENGS0400

0.20 Site Survey & Data Collection

0.20

CIVIL & STRUCTURAL

0.20

DESIGN DRAWINGS & DOCUMENTS

0.14

ENCD0400

Approval of civil drawings

ENCD0410

Prep. & Sub. of Civil Drawings

0.07 0.00

ENCD0440

Approval of dwg for str. steel support

0.07

ENCD0450

Preparation of Dwg for Str. Steel Support

0.00

STRUCTURAL STEEL SUPPORT

0.03

ENCS0420

Prep. & Sub. of Material Spec for Stru. Supports

ENCS0430

Approval of Material Spec for Stru. Support

0.03

CIVIL MATERIALS ENCS0440

Prep.& Sub. of Material Spec for Civil Matls

ENCS0450

Approval Material Spec for Civil Matls

0.00

0.03 0.00 0.03

MECHANICAL & PIPING

1.10

DESIGN DRAWINGS & DOCUMENTS

0.66

ENMD0400

Prep.& Sub. of Hydraulic Calculations

0.00

ENMD0410

Approval of Hydraulic calculations

0.10

ENMD0420

Prep.& Sub. of layout Dwg for CS & SS Pipeline

0.00

ENMD0430

Prep.& Sub. of Iso. Drg.for CS & SS Pipeline

0.00

ENMD0440

Approval of layout Dwg for CS & SS Pipeline

0.17

ENMD0450

Approval Iso Drg. for CS & SS Pipeline

0.17

ENMD0460

Prep. of layout Drawing for RTRP line

0.00

ENMD0500

Prep.& Sub. of Stress analysis report

0.00

ENMD0510

Approval of Stress Analysis Report

0.22

CS PIPES

0.08

ENMS0400

Prep.& Sub. of Material Spec for CS Pipes

ENMS0410

Approval Material Spec for CS Pipes

0.00 0.08

CS FITTING

0.08

ENMS0420

Prep.& Sub. of Material Spec for CS Fittings

0.00

ENMS0430

Approval Material Spec for CS Fittings

0.08

RTRP PIPE SPOOLS

0.08

ENMS0440

Prep.& Sub. of Material Spec for RTR Pipe spool

0.00

ENMS0450

Approval Matl. Spec for RTRP Pipe spool

0.08

MECH VALVES

0.08

ENMS0460

Prep.& Sub. of Material Spec for Mech valves

0.00

ENMS0470

Approval Material Spec for Mech valves

0.08

Page 3 of 13

%

ACCURED Weightage

Remarks


Activity ID

Activity Description

% WT

SS PIPES

0.03

ENMS0480

Prep.& Sub. of Material Spec for SS Pipes

ENMS0500

Approval Material Spec for SS Pipes

0.00 0.03

SS FITTINGS

0.02

ENMS0490

Prep.& Sub. of Material Spec for SS Fittings

0.00

ENMS0510

Approval Material Spec for SS Fittings

0.02

CORROSION MONITORING FITTING

0.07

ENMS0495

Prep.& Sub. Matl. Spec for corrosion mont. fitti

0.00

ENMS0515

Approv. Matl. Spec‐corrosion mont. fitti

0.07

INSTRUMENTATION

0.50

DESIGN DRAWINGS & DOCUMENTS

0.35

ENID0400

Prep.& Sub. of P&ID Diagram

0.00

ENID0410

Prep.& Sub. of Instrument Hook up Drwgs

0.00

ENID0420

Prep.& Sub. of Cable Layout Drg

0.00

ENID0430

Approval of P&ID Diagram

0.06

ENID0440

Approval of Instrument Hook up drg

0.06

ENID0450

Approval of Cable layout drg

0.06

ENID0460

Prep.& Sub. of Inst loc plan & cable routing drg

0.00

ENID0470

Approval Inst loc plan & cable routing drg

0.06

ENID0480

Prep. & Sub. of loop diagram

0.00

ENID0490

Approval of loop diagram

0.06

ENID0500

Prep. & Sub. of Cable Schedule

0.00

ENID0510

Approval of Cable Schedule

0.05

ESD VALVES

0.03

ENIS0420

Prep.& Sub. of Material Spec for ESD Valves

0.00

ENIS0430

Approval Material Spec for ESD Valves

0.03

CONTROL VALVES

0.03

ENIS0400

Prep.& Sub. of Material Spec for Control Valves

ENIS0410

Approval Material Spec for Control Valve

0.00 0.03

FLOW ELEMENTS

0.03

ENIS0500

Prep.& Sub. of Material Spec for Flow Elements

0.00

ENIS0510

Approval Material Spec for Flow Element

0.03

TEMP ELEMENTS

0.00

ENIS0520

Prep.& Sub. of Material Spec for Temp.Elements

ENIS0530

Approval Material Spec for Temp Element

0.00 0.00

INST. CABLES

0.03

ENIS0440

Prep.& Sub. of Material Spec for Inst. Cables

0.00

ENIS0450

Approval Material Spec for Inst. Cables

0.03

JUNCTION BOX

0.00

ENIS0520

Prep.& Sub. of Material Spec for Temp.Elements

ENIS0530

Approval Material Spec for Temp Element

0.00 0.00

BULK MATERIAL

0.03

ENIS0480

Prep.& Sub. of Material Spec for Bulk Material

0.00

ENIS0490

Approval of Bulk Material Spec.

0.03

ENID0520

Finish Engineering for GC‐23 & GC‐25

0.00

Page 4 of 13

%

ACCURED Weightage

Remarks


Activity ID

Activity Description

% WT

HAZOP STUDIES

3.00

GC‐23

1.50

ENGS0110

Submit Hazop /QRA / EIA report

0.00

ENGS0120

Approval of HAZOP report

1.50

GC‐25

1.50

ENGS0410

Submit Hazop /QRA / EIA report

ENGS0420

Approval of HAZOP report

PROCRUMENT

0.00 1.50

52.00 15.60

GC‐23 CIVIL & STRUCTURAL

0.00

STRUCTURAL STEEL SUPPORT

0.00

PROC0150

Processing & Placing of P.O

PROC0160

Proposal & Technical Bid Analysis

0.00 0.00

PROC0170

Procurement of Materials

0.00

PROC0180

Sub. & Approval of Technical Proposal

0.00

PROC0190

Material Delivery

0.00

CIVIL MATERIALS PROC0250

0.00

Processing & Placing of P.O

0.00

PROC0260

Proposal & Technical Bid Analysis

0.00

PROC0270

Procurement of Materials

0.00

PROC0280

Sub. & Approval of Technical Proposal

0.00

PROC0290

Material Delivery

0.00

MECHANICAL & PIPING

15.60

CS PIPES

2.00

PROM0100

Processing & Placing of P.O

0.00

PROM0110

Proposal & Technical Bid Analysis

0.00

PROM0120

Procurement of Materials

0.00

PROM0130

Sub. & Approval of Technical Proposal

0.00

PROM0140

Material Delivery

2.00

PROM0160

CS Pipes receipt

0.00

CS FITTING

0.64

PROM0150

Processing & Placing of P.O

0.00

PROM0170

Procurement of Materials

0.00

PROM0180

Proposal & Technical Bid Analysis

0.00

PROM0185

Sub. & Approval of Technical Proposal

0.00

PROM0190

Material Delivery

0.64

PROM0280

CS Fittings receipt

0.00

RTRP PIPE SPOOLS

1.76

PROM0175

Proposal & Technical Bid Analysis

0.00

PROM0195

Sub. & Approval of Technical Proposal

0.00

PROM0200

Processing & Placing of P.O

0.00

PROM0210

Prep. & Sub. of Drg. & Data sheets

0.00

PROM0220

Procurement of Materials

0.00

PROM0230

Rev. & Approval of Drg. & Data Sheets

0.00

PROM0240

Material Delivery

1.76

PROM0300

RTRP Pipe Spools receipt

0.00

Page 5 of 13

%

ACCURED Weightage

Remarks


Activity ID

Activity Description

% WT

MECH VALVES

9.92

PROM0250

Processing & Placing of P.O

0.00

PROM0260

Sub. & Appr. of Drg. & Data sheets

0.00

PROM0270

Procurement of Materials

0.00

PROM0290

Material Delivery

9.92

PROM0310

Mech Valves receipt

0.00

PROM0320

Proposal & Technical Bid Analysis

0.00

PROM0330

Sub. & Approval of Technical Proposal

0.00

SS PIPES

0.18

PROM0350

Processing & Placing of P.O

0.00

PROM0360

Proposal & Technical Bid Analysis

0.00

PROM0370

Procurement of Materials

0.00

PROM0380

Sub. & Approval of Technical Proposal

0.00

PROM0390

Material Delivery

0.18

SS FITTINGS

0.06

PROM0400

Processing & Placing of P.O

PROM0410

Proposal & Technical Bid Analysis

0.00 0.00

PROM0420

Procurement of Materials

0.00

PROM0430

Sub. & Approval of Technical Proposal

0.00

PROM0440

Material Delivery

0.06

CORROSION MONITORING FITTING

1.04

PROM0450

Proposal & Technical Bid Analysis

0.00

PROM0460

Sub. & Approval of Technical Proposal

0.00 0.00

PROM0470

Processing & Placing of P.O

PROM0480

Sub. & Approv. of Details and Documents

0.00

PROM0490

Procurement of Materials

0.00

PROM0500

Material Delivery

1.04

PROM0510

Corrosion Monitoring receipt

0.00

INSTRUMENTATION

0.00

CONTROL VALVES

0.00

PROI0250

Processing & Placing of P.O

0.00

PROI0260

Sub. & Appr. of Drg. & Data sheets

0.00

PROI0270

Procurement of Materials

0.00

PROI0280

Sub. & Approval of Technical Proposal

0.00

PROI0290

Material Delivery

0.00

PROI0310

Control Valves receipt

0.00

PROI0330

Proposal & Technical Bid Analysis

0.00

TEMP RELIEF VALVES

0.00

PROI0450

Processing & Placing of P.O

0.00

PROI0460

Proposal & Technical Bid Analysis

0.00

PROI0470

Sub. & Appr. of Drg. & Data sheets

0.00

PROI0480

Procurement of Materials

0.00

PROI0490

Material Delivery

0.00

PROI0510

Temp Relief Valves receipt

0.00

PROI0530

Sub. & Approval of Technical Proposal

0.00

FLOW ELEMENTS

0.00

PROI0350

Processing & Placing of P.O

0.00

PROI0370

Procurement of Materials

0.00

PROI0380

Proposal & Technical Bid Analysis

0.00

Page 6 of 13

%

ACCURED Weightage

Remarks


Activity ID

Activity Description

% WT

PROI0390

Material Delivery

0.00

PROI0410

Sub. & Approval of Technical Proposal

0.00

PROI0560

Sub. & Appr. of Drg. & Data sheets

0.00

TEMP ELEMENTS

0.00

PROI0400

Processing & Placing of P.O

0.00

PROI0420

Procurement of Materials

0.00

PROI0430

Proposal & Technical Bid Analysis

0.00

PROI0440

Material Delivery

0.00

PROI0550

Sub. & Approval of Technical Proposal

0.00

PROI0570

Sub. & Appr. of Drg. & Data sheets

0.00

INST. CABLES

0.00

PROI0100

Processing & Placing of P.O

0.00

PROI0120

Procurement of Materials

0.00

PROI0140

Material Delivery

0.00

JUNCTION BOX

0.00

PROI0500

Processing & Placing of P.O

0.00

PROI0520

Procurement of Materials

0.00

PROI0540

Material Delivery

0.00

BULK MATERIAL

0.00

PROI0300

Processing & Placing of P.O

0.00

PROI0320

Procurement of Materials

0.00

PROI0340

Material Delivery

0.00

36.40

GC‐25 CIVIL & STRUCTURAL

0.00

STRUCTURAL STEEL SUPPORT

0.00

PROC0750

Processing & Placing of P.O

PROC0760

Proposal & Technical Bid Analysis

0.00 0.00

PROC0770

Procurement of Materials

0.00

PROC0780

Sub. & Approval of Technical Proposal

0.00

PROC0790

Material Delivery

0.00

CIVIL MATERIALS PROC0850

0.00

Processing & Placing of P.O

0.00

PROC0860

Proposal & Technical Bid Analysis

0.00

PROC0870

Procurement of Materials

0.00

PROC0880

Sub. & Approval of Technical Proposal

0.00

PROC0890

Material Delivery

0.00

MECHANICAL & PIPING

36.40

CS PIPES

4.67

PROM0700

Processing & Placing of P.O

0.00

PROM0710

Proposal & Technical Bid Analysis

0.00

PROM0720

Procurement of Materials

0.00

PROM0730

Sub. & Approval of Technical Proposal

0.00

PROM0740

Material Delivery

4.67

PROM0760

CS Pipes receipt

0.00

CS FITTING

1.49

PROM0750

Processing & Placing of P.O

0.00

PROM0770

Procurement of Materials

0.00

PROM0780

Proposal & Technical Bid Analysis

0.00

PROM0790

Material Delivery

1.49

Page 7 of 13

%

ACCURED Weightage

Remarks


Activity ID

Activity Description

% WT

PROM0880

CS Fittings receipt

0.00

PROM0920

Sub. & Approval of Technical Proposal

0.00

RTRP PIPE SPOOLS

4.11

PROM0785

Proposal & Technical Bid Analysis

PROM0795

Sub. & Approval of Technical Proposal

0.00 0.00

PROM0800

Processing & Placing of P.O

0.00

PROM0810

Prep. & Sub. of Drg. & Data sheets

0.00

PROM0820

Procurement of Materials

0.00

PROM0830

Rev. & App. of Drg. & Data sheets

0.00

PROM0840

Material Delivery

4.11

PROM0900

RTRP Pipe spools receipt

0.00

MECH VALVES

23.16

PROM0850

Processing & Placing of P.O

0.00

PROM0860

Sub. & Appr. of Drg. & Data sheets

0.00

PROM0870

Procurement of Materials

0.00

PROM0890

Material Delivery

23.16

PROM0910

Mech Valves receipt

0.00

PROM0930

Proposal & Technical Bid Analysis

0.00

PROM0940

Sub. & Approval of Technical Proposal

0.00

SS PIPES

0.41

PROM0950

Processing & Placing of P.O

PROM0960

Proposal & Technical Bid Analysis

0.00 0.00

PROM0970

Procurement of Materials

0.00

PROM0980

Sub. & Approval of Technical Proposal

0.00

PROM0990

Material Delivery

0.41

SS FITTINGS

0.13

PROM1000

Processing & Placing of P.O

0.00

PROM1010

Proposal & Technical Bid Analysis

0.00

PROM1020

Procurement of Materials

0.00

PROM1030

Sub. & Approval of Technical Proposal

0.00

PROM1040

Material Delivery

0.13

CORROSION MONITORING FITTING

2.43

PROM1050

Proposal & Technical Bid Analysis

PROM1060

Sub. & Approval of Technical Proposal

0.00 0.00

PROM1070

Processing & Placing of P.O

0.00

PROM1080

Sub. & Appr. of Drg. & Data sheets

0.00

PROM1090

Procurement of Materials

0.00

PROM1100

Material Delivery

2.43

PROM1110

Corrosion Monitoring receipt

0.00

INSTRUMENTATION

0.00

ESD VALVES

0.00

PROI0800

Processing & Placing of P.O

PROI0810

Sub. & Appr. of Drg. & Data sheets

0.00 0.00

PROI0820

Procurement of Materials

0.00

PROI0840

Material Delivery

0.00

PROI0880

ESD Valves receipt

0.00

PROI1030

Proposal & Technical Bid Analysis

0.00

PROI1050

Sub. & Approval of Technical Proposal

0.00

Page 8 of 13

%

ACCURED Weightage

Remarks


Activity ID

Activity Description

% WT

CONTROL VALVES

0.00

PROI0850

Processing & Placing of P.O

0.00

PROI0860

Sub. & Appr. of Drg. & Data sheets

0.00

PROI0870

Procurement of Materials

0.00

PROI0890

Material Delivery

0.00

PROI0910

Control Valves receipt

0.00

PROI0960

Finish Procurement

0.00

PROI0980

Proposal & Technical Bid Analysis

0.00

PROI1010

Sub. & Approval of Technical Proposal

0.00

FLOW ELEMENTS PROI0950

0.00

Processing & Placing of P.O

0.00

PROI0970

Procurement of Materials

0.00

PROI0990

Material Delivery

0.00

PROI1000

Sub. & Appr. of Drg. & Data sheets

0.00

PROI1060

Proposal & Technical Bid Analysis

0.00

PROI1070

Sub. & Approval of Technical Proposal

0.00

INST. CABLES

0.00

PROI0700

Processing & Placing of P.O

0.00

PROI0720

Procurement of Materials

0.00

PROI0740

Material Delivery

0.00

JUNCTION BOX

0.00

PROI1100

Processing & Placing of P.O

0.00

PROI1120

Procurement of Materials

0.00

PROI1140

Material Delivery

0.00

BULK MATERIAL

0.00

PROI0900

Processing & Placing of P.O

0.00

PROI0920

Procurement of Materials

0.00

PROI0940

Material Delivery

0.00

36.00

CONSTRUCTION

1.86

GENERAL CNGE0100

Site Mobilization of Manpower & Equipment

0.00

CNGE0110

Start Construction

0.00

CNGE0120

Steel Piping Prefabrication, NDE & Hydrotesting

1.86

CNGE0130

FBE Coating of CS Pipespools

0.00

11.69

GC‐23 CIVIL & STRUCTURAL

1.25

DESALTER A&B AREA

0.75

CN3AC0100

Excavation for UG Piping for Steel PIpes

0.04

CN3AC0110

Excavation for UG Piping for RTRP

0.19 0.04

CN3AC0120

Installation of new Pipe supports Steel Pipe

CN3AC0130

Installation of new Pipe supports RTRP

0.19

CN3AC0140

Civil Works for Cable Trenches

0.04

CN3AC0170

Backfilling for All excavations

0.15

CN3AC0180

Pipe Support Foundation / Valve Pit works

0.10

SEPERATOR AREA

0.50

CN3SC0110

Pipe Support Foundation / Valve Pit works

CN3SC0130

Installation of new Pipe supports RTRP

0.10 0.20

CN3SC0170

Backfilling for All excavations

0.20

MECHANICAL & PIPING

4.62

Page 9 of 13

%

ACCURED Weightage

Remarks


Activity ID

Activity Description

% WT

DESALTER A&B AREA

2.86

CN3AM0100

Installation of all AG Steel Pipes

0.03

CN3AM0110

Installation of all UG Steel Pipes

0.01

CN3AM0120

Installation of all AG RTRP Pipes

0.09

CN3AM0130

Installation of UG RTRP Pipes

0.09

CN3AM0140

Install Control Valves

1.57

CN3AM0160

Install Mech Valves

0.42

CN3AM0170

Hydrotesting of Pipelines

0.13

CN3AM0180

Painting of A/G Piping & Supports

0.01

CN3AM0190

Installation of Flow Elements

0.05

CN3AM0210

Tentative S/D to be discussed with KOC

0.43

CN3AM0220

Installation of Corrosion Monitoring Fittings

0.03

SEPERATOR AREA

1.76

CN3SM0110

Installation of Corrosion Monitoring Fittings

0.07

CN3SM0120

Installation of all AG RTRP Pipes

0.20

CN3SM0160

Install Mech Valves

0.33

CN3SM0170

Hydrotesting of Pipelines

0.14

CN3SM0180

Painting of A/G Piping & Supports

0.00

CN3SM0210

Tentative S/D to be discussed with KOC

1.02

CN3SM0220

Finish Construction

0.00

INSTRUMENTATION

5.30

DESALTER A&B AREA

5.30

CN3AI0120

Intallation of Temp Elements

0.24

CN3AI0130

Installation of Temp Relief Valve

2.61

CN3AI0140

Installation of Inst. cables/ Tubing

0.14 0.32

CN3AI0160

Install Cable Trays

CN3AI0170

Glanding & Termination works

0.34

CN3AI0180

Installation of JB

0.02

CN3AI0190

Air Supply Piping/ Tubing for Valves

0.70

CN3AI0200

Shutdown‐ Instrument work

0.82

CN3AI0210

Calibration of instruments

0.11

DEMOLITION

0.52

DESALTER A&B AREA

0.27

CN3AD0100

Demolition of Old Redundant Pipe lines

CN3AD0110

Demolition of Old redundant valves

0.19 0.05

CN3AD0120

Demolition of Old reduntant Instruments & Cables

0.03

SEPERATOR AREA

0.25

CN3SD0100

Demolition of Old Redundant Pipe lines

CN3SD0110

Demolition of Old redundant valves

0.20 0.05

CN3SD0130

Finish Demolition

0.00

22.45

GC‐25 CIVIL & STRUCTURAL

3.75

DESALTER A&B AREA

0.16

CN5AC0120

Installation of new Pipe supports

0.05

CN5AC0160

Civil Works for Cable Trenches

0.02

CN5AC0190

Backfilling for All excavations

0.05

CN5AC0200

Pipe Support Foundation / Valve Pit works

0.04

Page 10 of 13

%

ACCURED Weightage

Remarks


Activity ID

Activity Description

% WT

WET CRUDE TANK AREA CN5WC0100

0.92

Excavation for UG Steel Piping

0.32

CN5WC0120

Installation of new Pipe supports Steel Pipe

0.14

CN5WC0160

Civil work for Cable trenches

0.05

CN5WC0170

Fire Proofing Works

0.05

CN5WC0190

Backfilling for All excavations

0.27

CN5WC0200

Pipe Support Foundation / Valve Pit works

0.09

PIPE WAY

2.20

CN5EC0100

Excavation for UG Steel Piping

0.33

CN5EC0110

Excavation of UG RTRP Pipes

0.66

CN5EC0120

Installation of new Pipe supports Steel Pipe

0.22

CN5EC0140

Installation of new Pipe supports RTRP

0.22

CN5EC0160

Civil works for cable trenches

0.11

CN5EC0190

Backfilling for All excavations

0.33

CN5EC0200

Pipe Support Foundation / Valve Pit works

0.33

PUMPING AREA

0.47

CN5PC0120

Installation of new Pipe supports Steel Pipe

CN5PC0140

Installation of new Pipe supports RTRP

0.12 0.16

CN5PC0160

Civil works for cable trenches

0.05

CN5PC0190

Backfilling for All excavations

0.09

CN5PC0200

Pipe Support Foundation / Valve Pit works

0.05

MECHANICAL & PIPING

11.92

DESALTER A&B AREA

0.44

CN5AM0100

Installation of all AG Steel Pipes

CN5AM0150

Install Mech Valves

0.15 0.09

CN5AM0160

Hydrotesting of Pipelines

0.01

CN5AM0170

Painting of A/G Piping & Supports

0.03

CN5AM0180

Installation of Corrosion Monitoring Fittings

0.01

CN5AM0190

Installation of Flow Elements

0.05

CN5AM0200

Tentative S/D to be discussed with KOC

0.10

WET CRUDE TANK AREA

6.50

CN5WM0100 Installation of all AG Steel Pipes

0.07

CN5WM0110 Installation of all UG Steel Pipes

0.45

CN5WM0140 Install ESD Valves

5.63

CN5WM0150 Install Mech Valves

0.12

CN5WM0160 Hydrotesting of Pipelines

0.03

CN5WM0170 Painting of A/G Piping & Supports

0.01

CN5WM0200 Tentative S/D to be discussed with KOC

0.18

CN5WM0210 Installation of Corrosion Monitoring Fittings

PIPE WAY

0.01

3.80

CN5EM0100

Installation of all AG Steel Pipes

1.90

CN5EM0110

Installation of all UG Steel Pipes

0.36

CN5EM0120

Installation of all AG RTRP Pipes

0.01

CN5EM0130

Installation of UG RTRP Pipes

0.28

CN5EM0150

Install Mech Valves

0.07

CN5EM0160

Hydrotesting of Pipelines

0.40

CN5EM0170

Painting of A/G Piping & Supports

0.60

CN5EM0200

Tentative S/D to be discussed with KOC

0.17

CN5EM0210

Installation of Corrosion Monitoring Fittings

0.01

Page 11 of 13

%

ACCURED Weightage

Remarks


Activity ID

Activity Description

% WT

PUMPING AREA

1.18

CN5PM0100

Installation of all AG Steel Pipes

0.05

CN5PM0120

Installation of all AG RTRP Pipes

0.04

CN5PM0130

Installation of Corrosion Monitoring Fittings

0.01

CN5PM0135

Install Control Valves

0.70

CN5PM0140

Installation of Flow Elements

0.05

CN5PM0150

Install Mech Valves

0.10

CN5PM0160

Hydrotesting of Pipelines

0.03

CN5PM0170

Painting of A/G Piping & Supports

0.02

CN5PM0200

Tentative S/D to be discussed with KOC

0.18

CN5PM0210

Finish Construction

0.00

INSTRUMENTATION

6.00

DESALTER A&B AREA

0.40

CN5AI0140

Installation of Inst. cables/ Tubing