OUC History Book

Page 22

he 1960s saw advancements in transmitting and pooling electricity. Load dispatchers used the economic loading slide rule, which was the first analog computer at OUC. This helped them determine which units were the most “economical” to run during certain periods of time, based on factors like fuel cost and transmission availability.

Larger, More Efficient Lake Highland Units Come Online In 1958 — after the larger, more efficient

for peaking service. At the time of their

Lake Highland Plant went into operation and

installation, these units were the largest

the Lake Ivanhoe Plant was taken offline —

peaking gas turbines in the world.

the OUC electric system grew rapidly. In just

General Manager Curt Stanton and Plant

one year, load increased 25 percent. In fact,

Engineer Harry Luff co-authored a technical

backup generation to cover the loss of units. For that reason,

OUC was expanding so quickly that its

paper on operation and maintenance of

interconnections provided OUC the ability to connect with

engineering firm recommended installing two

these turbines, which was presented to the

other utilities and back each other up.

gas turbines, in addition to the existing steam

American Society of Mechanical Engineers

units, at the Lake Highland Plant to be used

Gas Turbine Conference in 1961.

Utilities stood on their own and had to have enough

Interconnections were established with Florida Power

Harry Luff, Curt Stanton, Ted Pope.

Corporation in Orlando and later with Florida Power & Light (FPL) on the East Coast near the new plant site on the Indian River. At 2:46 p.m. on October 15, 1963, a 230,000-volt tie between OUC and FPL was energized at the Commission’s Indian River Plant by Curt Stanton, Executive Vice President and GM of OUC, and Alan Wright, Vice President of FPL. “The energizing of this tie represents the completion of another phase of the Orlando Utilities’ overall expansion

OUC Conducts First Long-Range Planning Study As OUC’s service territory continued to

transmission lines that would loop around

expand, the utility undertook the first long-range

Orlando. All recommendations were approved

planning study of its electric system with outside

by the Commission.

engineering firm Black and Veatch to evaluate the system and establish a plan for facilitating growth.

In 1961, the high-voltage transmission loop around the Orlando area was completed —

program to strengthen and increase the capability of its

To increase system reliability, Black and

expanding system,” Stanton said. “This new tie offers a

Veatch recommended that OUC establish

interconnections with other power systems. And

further source of supply of energy in the event of power

interconnections with other power systems,

in 1964, OUC began burying power lines and

failure and increases the total tie capacity to 350,000 kW.”

select a site for a new power plant and install

replacing overhead lines with underground utilities

(Orlando Sentinel, October 16, 1963)

a new generating unit. The study also revealed

along Colonial Drive west to Texas Avenue.

placing OUC in a strong position to add more

the need for new substations and 115 kV

Indian River Plant Hailed as “Marvel of Efficiency and Modern Technology”

Living Better . . . Electrically

In 1960, a new generating plant was designed

reported to have been the largest single project

at the time: “Working to keep electricity your

and constructed in Brevard County along the Indian

money-wise in OUC history (OUC Today, Indian

B.E.S.T. value!”

River. Aptly named the Indian River Plant (IRP), this

River Anniversary Issue, Vol. XXI, No. 1, 1985).

oil- and gas-fired unit was more than twice the size

When IRP opened, local media hailed it as a

provided two strategic advantages: an unlimited

marvel of efficiency and modern technology. With

supply of cooling water for the steam condensers

a nameplate rating of 78.5 MW and the capability

and water transportation for fuel oil deliveries from

system was closed for the first time at 11:53 p.m.

to produce more than 90 MW under peak load

nearby Port Canaveral.

on February 20, 1960. One thousand people

conditions, its generators would power growth in

braved bad weather to attend the dedication of

the area — producing energy at a cost of two cents

oil via Port Canaveral — occurred four years

the new plant, located halfway between Titusville

per kilowatt hour, the lowest price in the history of

later after the completion of the 205-MW Unit 2

and Cocoa. Built at a cost of $16 million, IRP was

the utility, clearly supporting OUC Today’s slogan

at IRP.

of the largest unit at the Lake Highland Plant. The switch connecting IRP to OUC’s electric

As part of a national campaign launched by the electric industry, OUC participated in the Gold Medallion Home program, which touted the built-in advantages of “living better electrically.” Dwellings that were awarded this seal used “low-cost electricity” exclusively for “winter heat, summer cooling, year-around cooking and water-heating, as well as for light and power.”

Page 18

The plant’s location along the Indian River

Page 19

That milestone — the first barge delivery of