Recent Projects Executed by MAPES Key Personnel
New Doha International Airport Project Project Name:
New Doha International Airport Project
Project Owner:
NDIA Steering Committee
Project Duration:
16 Months
Project Value:
USD 52 M
Project Scope:
CP-19 (Emiri Terminal Car park & Mosque)
Scope of Work:
Heating, comfort cooling, ventilation, Low pressure Hot Water based (LPHW) Heating System, LPHW requirements for Calorifier Primary circuit, Chilled water based cooling system, Firefighting systems, Cold Water Storage Tank, drainage system, Hot Water generation and distribution system, Cold Water Storage and distribution System, Main Power distribution from mains Switch board, Small Power Distribution & Communication System, Lightning Protection & Earthing system, Security Control System
Area Involved in:
18
»» Emiri Terminal Car Park »» Substations »» Emiri Terminal Mosque »» Operational Facilities