PROJECT CONCEPT # 18 School St. & Lincoln St.

Project Costs & Timelines

Draft Project Construction Details Construction Timeline:

60 days

Additional Design:

YES

Design/Study Timeline:

90 days

Additional Studies:

NO

Per Unit Cost Item

Unit Price

Unit

Quantity

ADA Ramp

$ 3,000.00

/EA

2

$

6,000

RRFB

$ 7,500.00

/EA

2

$

15,000

/SF

100

$

225

Sub-total $

21,225

Contingency $

4,245

Total $

25,470

Cross Walks & Stop Lines Refl. $ White (THERMOPLASTIC)

Note: Prices are estimated for construction only, and do not include design or additional studies. Estimates are for Prioritization Plan comparisons only.

2.25

Est. Capital Costs