PROJECT CONCEPT # 16 Beach St. Part 1 & Part 2

Project Costs & Timelines

Draft Project Construction Details Construction Timeline:

90 days

Additional Design:

YES

Design/Study Timeline:

90 days

Additional Studies:

NO

Per Unit Cost Item

Unit Price

Unit

Quantity

Est. Capital Costs

Sidewalk Reconstruction

$

125.00

/SY

950

$

118,750

6� Reflectorized White Line (THERMOPLASTIC)

$

1.00

/FT

1250

$

1,250

Park Bench

$ 2,500.00

/EA

6

$

15,000

Sub-total $

120,000

Contingency $

24,000

Total $

144,000