PROJECT CONCEPT # 11 Harbor St. & Bridge St.

Project Costs & Timelines

Draft Project Construction Details Construction Timeline: Design/Study Timeline:

120 days

Additional Design:

YES

90 days

Additional Studies:

NO

Per Unit Cost Item

Unit Price

Unit

Quantity

Est. Capital Costs

Curb Extension

$

100.00

/SY

592

$

59,167

ADA Ramp

$ 3,000.00

/EA

1

$

3,000

RRFB

$ 7,500.00

/EA

2

$

15,000

Cross Walk & Stop Lines Refl. $ White (THERMOPLASTIC)

2.25

/SF

96

$

216

6� Reflectorized Yellow Line (THERMOPLASTIC)

1.00

/FT

40

$

40

Sub-total $

77,423

Contingency $

15,485

Total $

92,907

Note: Prices are estimated for construction only, and do not include design or additional studies. Estimates are for Prioritization Plan comparisons only.

$

COMPLETE STREETS I AUG. 2017 47