PROJECT CONCEPT # 10 Tappan St. & Sea St.

Project Costs & Timelines

Draft Project Construction Details Construction Timeline:

120 days

Additional Design:

YES

Design/Study Timeline:

150 days

Additional Studies:

YES

Per Unit Cost Item

Unit Price

Unit

Quantity

Est. Capital Costs

Sidewalk Reconstruction

$

125.00

/SY

667

$

83,333

Sign

$

65.00

/EA

6

$

390

Post

$

150.00

/EA

4

$

600

Sub-total $

84,323

Contingency $

16,865

Total $

101,188

Note: Prices are estimated for construction only, and do not include design or additional studies. Estimates are for Prioritization Plan comparisons only.

COMPLETE STREETS I AUG. 2017 45