PROJECT CONCEPT # 4 Pine St., Central St., & Bridge St.

Project Costs & Timelines

Draft Project Construction Details Construction Timeline:

120 days

Additional Design:

YES

Design/Study Timeline:

150 days

Additional Studies:

YES

Per Unit Cost Item

Unit Price

Unit

Quantity

ADA Ramp

$ 3,000.00

/EA

6

$

18,000

Flexpost - FG336

$

50.00

/EA

29

$

1,450

Cross Walks & Stop Lines Refl. $ White (THERMOPLASTIC)

2.25

/SF

504

$

1,134

6� Reflectorized Yellow Line (THERMOPLASTIC)

$

1.00

/FT

300

$

300

Detectable Warning Pad

$

100.00

/EA

2

$

200

Sub-total $

21,084

Contingency $

4,217

Total $

25,301

Note: Prices are estimated for construction only, and do not include design or additional studies. Estimates are for Prioritization Plan comparisons only.

Est. Capital Costs