PROJECT CONCEPT # 2 Central St., Union St., & School St.

Project Costs & Timelines

Draft Project Construction Details Construction Timeline:

120 days

Additional Design:

YES

Design/Study Timeline:

120 days

Additional Studies:

NO

Per Unit Cost Item

Curb Extension Sign Post Sign Post Removed & Reset Cross Walk & Stop Lines Refl. White (THERMOPLASTIC) 6” Reflectorized White Line (THERMOPLASTIC) 6” Reflectorized Yellow Line (THERMOPLASTIC) Note: Prices are estimated for construction only, and do not include design or additional studies. Estimates are for Prioritization Plan comparisons only.

Unit Price

Unit

Quantity

Est. Capital Costs

$ $ $ $

100.00 65.00 150.00 200.00

/EA /EA /EA /EA

354 3 3 1

$ $

35,422 195 450 200

$

2.25

/SF

467

$

1,051

$

1.00

/FT

240

$

240

$

1.00

/FT

600

$

600

Sub-total $

38,158

Contingency $

7,632

Total $

45,790

COMPLETE STREETS I AUG. 2017 27