Sunshine Coast Public University Hospital construction timetable

September 2012– end 2013 Design development process

mb b

[ 32 ] april/may 14

October 2012 Site establishment and bulk earthworks commence

February 2013– December 2013

June 2013– December 2013

Mid-2013– end 2014

Early 2014– mid-2015

From mid2014

First multi-deck car park

Kawana Way duplication works

Main hospital superstructure

External facade

Internal fit-out and finishes