Cycle Review of NCN Route 75: Kirknewton - Livingston

Kirknewton Community Development Trust

Plans of Cycle Review of NCN Route 75: Kirknewton - Livingston Route A – Using NCN 75 Plan 1 Kirknewton to level crossing Plan 2 Level crossing to St Pauls School Plan 3 St Pauls School to North Bridge Plan 4 North Bridge to ASDA Livingston © Transport Initiatives LLP 2011 All photos © Transport Initiatives except where stated All mapping based upon Ordnance Survey material with the permission of Ordnance Survey on behalf of the Controller of Her Majesty’s Stationery Office © Crown copyright. Unauthorised reproduction infringes Crown copyright and may lead to prosecution or civil proceedings. West Lothian Council Licence no 100037194 2011

---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------CSSC05 Cycle Review Plans Kirknewton-Livingston Route A TJP Page 1 of 37 transport initiatives


Cycle Review of NCN Route 75: Kirknewton - Livingston

Kirknewton Community Development Trust

Plan 1 – Kirknewton to level crossing

1.12 Surface

1.10 Cycle lanes 1.5 Crossing 1.4 Right turn

1.11 Signs

1.9 Crossing

1.8 Cycle parking

1.1 Cycle Parking

1.7 20 Zone 1.3 Sign 1.6 Cycle lane

1.2 Cycle Parking

1.13 30 mph limit

---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------CSSC05 Cycle Review Plans Kirknewton-Livingston Route A TJP Page 2 of 37 transport initiatives


Cycle Review of NCN Route 75: Kirknewton - Livingston

Kirknewton Community Development Trust

Table 1 Kirknewton to Level Crossing Ref Issue – no cycle parking at Community Development centre 1.1

Recommendation Opportunity for cycle parking along side of Community Development Trust building

Ref Issue – no cycle parking for local shops or formal crossing to shops between parked cars 1.2

Recommendation -Opportunity for cycle parking outside shops and to install a speed table with build outs to slow traffic and help people cross the road

---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------CSSC05 Cycle Review Plans Kirknewton-Livingston Route A TJP Page 3 of 37 transport initiatives


Cycle Review of NCN Route 75: Kirknewton - Livingston

Ref

Issue –Sticker Signing for route easy to miss & two poles near each other

1.3

Kirknewton Community Development Trust

Ref

Issue – Awkward right turn from main road into side road with no signing and drivers will not be expecting cyclists to turn here

1.4

Recommendation Use bigger sign and relocate bus timetable with shelter to reduce clutter

Recommendation Extend drop crossing back to gully so Level 1 cyclists can turn left onto pavement and wait to cross road into side road link. May be safer for more experienced cyclists to use road junction to turn right rather than make the right turn here.

---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------CSSC05 Cycle Review Plans Kirknewton-Livingston Route A TJP Page 4 of 37 transport initiatives


Cycle Review of NCN Route 75: Kirknewton - Livingston

Ref

Issue – good crossing on speed table of side road and no priorities shown to either user

Kirknewton Community Development Trust

Ref

Issue – Cycle lane widths at 1.2m too narrow and encourage vehicles to travel too close to cyclists who are trained to cycle at least 1.0m out from the kerb. Lanes in poor condition with grit and other debris in them

1.6

1.5

Recommendation - Either a) leave as it is or b) consider putting give way markings on road each side of crossing so that pedestrians and cyclists have priority

Recommendation - Either widen cycle lanes to at least 1.5m given that cycle training encourages cyclists to cycle 1.0m out from the kerb or remove the down hill lanes and widen the uphill one.

---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------CSSC05 Cycle Review Plans Kirknewton-Livingston Route A TJP Page 5 of 37 transport initiatives


Cycle Review of NCN Route 75: Kirknewton - Livingston

Ref

Issue – 20 mph zone by school only part time and parking in cycle lanes which are too narrow and poor condition

1.7

Kirknewton Community Development Trust

Ref Issue – cycle parking at school in good location and being used 1.8

Recommendation - Make 20 mph permanent with more speed cushions at start of zone and remove cycle lanes in this section if parking persists or talk to school about staff parking on main road.

Recommendation - Consider covering cycle parking to protect cycles from weather and improve security

---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------CSSC05 Cycle Review Plans Kirknewton-Livingston Route A TJP Page 6 of 37 transport initiatives


Cycle Review of NCN Route 75: Kirknewton - Livingston

Ref

Issue – Build out narrows road and does not slow traffic at School crossing patrol site

1.9

Kirknewton Community Development Trust

Ref

Issue – Cycle lane too narrow by island and along this section and accumulating debris in cycle lane

1.10

Recommendation - Consider installing a speed table at build outs to ensure traffic is travelling slowly at crossing point to assist school crossing patrol cross children to and from school

Recommendation - Sweep grit out of cycle lane in short term and consider if cycle lanes of any benefit on this section as too narrow and consider removing them.

---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------CSSC05 Cycle Review Plans Kirknewton-Livingston Route A TJP Page 7 of 37 transport initiatives


Cycle Review of NCN Route 75: Kirknewton - Livingston

Ref

Issue – Cycle signs cannot easily be read from this direction – can be seen while coming out of station Cycle lane in poor condition and stops short of level crossing

1.11

Kirknewton Community Development Trust

Ref

Issue – Poor road surface on edge of level crossing which could be a hazard to cyclists.

1.12

Recommendation – consider rotating sign for East Calder around a bit on lamppost so it can be seen from road as well Cycle lane – consider if substandard width cycle lane is necessary down hill and remove.

Recommendation – make good surface edge so safe to cycle over

---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------CSSC05 Cycle Review Plans Kirknewton-Livingston Route A TJP Page 8 of 37 transport initiatives


Cycle Review of NCN Route 75: Kirknewton - Livingston

Ref 1.13

Issue – 30 mph limit starts near a junction then changes to 20 zone around the corner

Kirknewton Community Development Trust

20 Mph zone in York with 20 roundel on road and speed cushions at the start of the scheme.

Recommendation – consider extending 20 mph zone up to 30 mph signs and install speed cushions by refuge and at start of zone

---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------CSSC05 Cycle Review Plans Kirknewton-Livingston Route A TJP Page 9 of 37 transport initiatives


Cycle Review of NCN Route 75: Kirknewton - Livingston

Kirknewton Community Development Trust

Plan 2. Kirknewton Level Crossing to St Pauls School 2.9 Parking

2.11 Alternative route to schools

2.7 Signing

2.6 Right turn 2.4 Vegetation

2.8 Surface

2.10 Junction width

2.12 Crossing

2.5 Crossing Lane widths

2.2 Crossing

2.3 Crossing 2.1 Push button ---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------CSSC05 Cycle Review Plans Kirknewton-Livingston Route A TJP Page 10 of 37 transport initiatives


Cycle Review of NCN Route 75: Kirknewton - Livingston

Kirknewton Community Development Trust

Table 2. Kirknewton Level Crossing to St Pauls School Ref Issue – Push button at signal crossing in awkward position to press while on a cycle 2.1

Recommendation – move push button around to face traffic and make it easier to push while waiting to cross

Ref Issue – Crossing – takes a long time to cross road and there is no tactile paving to help partially sighted people recognise there is a crossing here. 2.2

Recommendation - review signalled crossing times for crossing and install tactile paving

---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------CSSC05 Cycle Review Plans Kirknewton-Livingston Route A TJP Page 11 of 37 transport initiatives


Cycle Review of NCN Route 75: Kirknewton - Livingston

Ref

Issue – Crossing very wide and time to cross very long and no tactile paving

2.3

Kirknewton Community Development Trust

Ref

Issue – Vegetation is starting to grow onto cycle path and is narrowing it

2.4

Recommendation – review crossing times to see if they can be improved and consider installing central island to aid crossing in 2 stages and install tactile paving

Recommendation – cut back vegetation

---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------CSSC05 Cycle Review Plans Kirknewton-Livingston Route A TJP Page 12 of 37 transport initiatives


Cycle Review of NCN Route 75: Kirknewton - Livingston

Ref

Issue – Route crosses road which has very narrow traffic lanes and narrow footway

2.5

Kirknewton Community Development Trust

Ref

Issue – Right turn onto NCN 75 – very awkward right turn required to access cycle track on farm path – this is not a manoeuvre that a Level 1 or 2 cyclist would be advised to do on this road

2.6

Recommendation – while this section of road is suitable for Level 3 cyclists it is not for Level 1 and 2 so the section path is a bit isolated

Recommendation – consider if this turn really is a safe option given that the farm track is in poor condition as well. An alternative path is available a bit further into East Calder on a path by the side of the sports centre which has a signalled crossing by it

---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------CSSC05 Cycle Review Plans Kirknewton-Livingston Route A TJP Page 13 of 37 transport initiatives


Cycle Review of NCN Route 75: Kirknewton - Livingston

Ref

Issue – Signing – cycle route signing is good as it has destinations and distance to them but the path it directs cyclists onto is not well surfaced or lit so is not a very attractive option

2.7

Kirknewton Community Development Trust

Ref

Issue – Surface quality – very poor surface along farm track and path which is unmade, rutted with many potholes, puddles and is unlit so not suitable to use at nighttimes’.

2.8

Recommendation – consider if this is the best option to sign cyclists as track surface is poor and it is unlit so not available at night

Recommendation – reconsider if this is the best way to sign route to schools given its poor quality

---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------CSSC05 Cycle Review Plans Kirknewton-Livingston Route A TJP Page 14 of 37 transport initiatives


Cycle Review of NCN Route 75: Kirknewton - Livingston

Ref

Issue – Parking at school times narrows road

2.9

Kirknewton Community Development Trust

Ref

Issue – Junction width – very wide side road to cross at Station Road and the B7031 which feels dangerous to cycle across and is also very far to cross on foot

2.10

Recommendation – encourage parents to walk and cycle to school to reduce road danger outside school and consider another route to the school via surfaced roads and tarmac paths see 2.11

Recommendation – consider tightening up left turn out of junction and or installing large refuge crossing in middle of junction to help cyclists and pedestrians cross the junction

---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------CSSC05 Cycle Review Plans Kirknewton-Livingston Route A TJP Page 15 of 37 transport initiatives


Cycle Review of NCN Route 75: Kirknewton - Livingston

Ref

Issue – alternative route to school – using tarmac path by Sports centre which is lit and overlooked by more houses than farm track

2.11

Kirknewton Community Development Trust

Ref

Issue – Signalled crossing to help cyclist cross to path by sports centre easier to use than right turn by farm track

2.12

Recommendation – consider re signing the NCN down this path which has a better surface and is more useable at nigh time than the existing route.

Recommendation – consider resigning NCN from here as crossing easier and path in better condition

---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------CSSC05 Cycle Review Plans Kirknewton-Livingston Route A TJP Page 16 of 37 transport initiatives


Cycle Review of NCN Route 75: Kirknewton - Livingston

Kirknewton Community Development Trust

Plan 3. St Pauls to North Bridge

3.7 Track width

3.6 Gradient & turns

3.5 Surface

3.8 Headroom 3.10 Surface

3.11 Vegetation 3.4 Gate 3.9 Gradient & turn

3.3 Signs

3.2 Sign

3.12 &13 Gradients Odours!

3.1 Narrow road

---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------CSSC05 Cycle Review Plans Kirknewton-Livingston Route A TJP Page 17 of 37 transport initiatives


Cycle Review of NCN Route 75: Kirknewton - Livingston

Kirknewton Community Development Trust

Table 3. St Pauls School to North Bridge Ref

Issue – Narrow road with 3 short road humps which are uncomfortable to cycle over and not very visible

Ref Issue – Sign for shared use path obscured by vegetation 3.2

3.1

Recommendation – install standard road hump with arrow markings which would be more visible and comfortable to cycle over and more effective at slowing traffic

Recommendation - Cut back vegetation or relocate sign onto side of litter bin to reduce street clutter

---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------CSSC05 Cycle Review Plans Kirknewton-Livingston Route A TJP Page 18 of 37 transport initiatives


Cycle Review of NCN Route 75: Kirknewton - Livingston

Ref Issue– Signing for NCN route on lamppost across road not easy to read from shared use cycle path 3.3

Recommendation – relocate cycle signs to this side of the road

Kirknewton Community Development Trust

Ref Issue– Gate Access – paving suggests a 90 degree turn required to use cycle gap. Cyclists overrunning grass verge to access gap on desire line 3.4

Recommendation – replace gate with a number of bollards whose central one can be removed for vehicle access and which would be easier to cycle and walk through

---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------CSSC05 Cycle Review Plans Kirknewton-Livingston Route A TJP Page 19 of 37 transport initiatives


Cycle Review of NCN Route 75: Kirknewton - Livingston

Ref Issue– Surface – good path surface and nice tree lined avenue but this route is not lit at nighttimes which would be an issue for some users 3.5

Recommendation – make clear on leaflets and information about NCN 75 that the route is not lit over this section

Kirknewton Community Development Trust

Ref Issue– Gradient and sharp left turn – quiet a steep gradient down to bridge with a sharp left turn for cycle route. Coming up hill it is hard to continue cycling momentum resulting in dismounting 3.6

Recommendation – show gradients on route information

---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------CSSC05 Cycle Review Plans Kirknewton-Livingston Route A TJP Page 20 of 37 transport initiatives


Cycle Review of NCN Route 75: Kirknewton - Livingston

Ref Issue– Track width at bridge – very substandard path width of less than 0.5m on bridge approach with right angle railings which could be run into and cause an accident 3.7

Recommendation – widen track to at least 2.0m by decking over stream, remove railings on approach and replace with less angular railings or post and rail with reflective material in them.

Kirknewton Community Development Trust

Ref Issue– Low Headroom on bridge – tall cyclists very likely to hit spars across bridge which are a hazard and there are no warning signs 3.8

Recommendation – replace spars with a curved design to give better clearance or remove them if not needed or put up warning signs

---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------CSSC05 Cycle Review Plans Kirknewton-Livingston Route A TJP Page 21 of 37 transport initiatives


Cycle Review of NCN Route 75: Kirknewton - Livingston

Ref Issue– Gradient and turn – short sharp gradient with turn at top onto bridge another awkward or challenging manoeuvre on route 3.9

Recommendation – regrade slope to get a less steep gradient and reconsider if this is the best route to sign

Kirknewton Community Development Trust

Ref

Issue– Poor path surface – cracked and uneven concrete slabs on bridge approach a potential hazard

3.1 0

Recommendation – remove broken slabs and resurface bridge approach

---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------CSSC05 Cycle Review Plans Kirknewton-Livingston Route A TJP Page 22 of 37 transport initiatives


Cycle Review of NCN Route 75: Kirknewton - Livingston

Ref

Issue– Vegetation blocking path

3.11

Kirknewton Community Development Trust

Ref

Issue– Gradient – section so steep that cyclists dismount signs have been put up – rather defeating the purpose of the cycle route

3.12

Recommendation – remove vegetation. Incidentally the person in the foreground was the only person seen along the route during the audit.

Recommendation – reconsider if this route should be signed as a cycle route on the National Cycle Network given the number of Issues along it.

---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------CSSC05 Cycle Review Plans Kirknewton-Livingston Route A TJP Page 23 of 37 transport initiatives


Cycle Review of NCN Route 75: Kirknewton - Livingston

Ref

Kirknewton Community Development Trust

Issue– Gradients and Odours – very steep gradient with steps with cyclists dismount signs either side of this section of path by sewerage works which smelt unpleasant. Both make the route less attractive

3.13

Recommendation – investigate if a flatter route following the river can be used for this section or reconsider if this is the best route alignment given the number of times it requires cyclists to dismount

---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------CSSC05 Cycle Review Plans Kirknewton-Livingston Route A TJP Page 24 of 37 transport initiatives


Cycle Review of NCN Route 75: Kirknewton - Livingston

Kirknewton Community Development Trust

4.3 Barrier

Plan 4. North Bridge to ASDA

4.1 Dismount Sign 4.4 Flooding

4.6 Signing

4.2 20 Mph zone

4.8 Vegetation

4.10 Barriers

4.5 Signing 4.7 Surface

4.11 Crossing 4.9 Signing 4.12 Crossing

4.13 & 14 Signing

4.15 Wall 4.16 Crossing 4.17 Vegetation 4.18 & 19 Crossings 4.21 & 22 Crossing 4.20 Ramp ---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------CSSC05 Cycle Review Plans Kirknewton-Livingston Route A TJP Page 25 of 37 transport initiatives

4.23 Cycle parking


Cycle Review of NCN Route 75: Kirknewton - Livingston

Kirknewton Community Development Trust

Table 4. North Bridge to ASDA Ref

Issue – Sign – cyclists dismount sign at crossing presumably due to poor forward visibility but road easy to cross off peak and cyclists will be approaching at slow speed due to need to turn

4.1

Ref

Issue – Speed Limit signing – 20 roundel on road an effective signal to drivers of 20 mph zone. Good link in route 75

4.2

Recommendation – remove vegetation to fence level to improve forward visibility, remove Cyclists dismount sign and install give way markings along cycle track by wall and by edge of footway

Recommendation - other 20mph zones in area could benefit from similar 20mph road markings

---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------CSSC05 Cycle Review Plans Kirknewton-Livingston Route A TJP Page 26 of 37 transport initiatives


Cycle Review of NCN Route 75: Kirknewton - Livingston

Ref Issues – Barrier access to shared use path – signing makes change of route easy to pick up and barrier fairly easy to cycle through but does concentrate users into one gap 4.3

Recommendation – consider replacing barrier with a row of staggered bollards to improve access to path

Kirknewton Community Development Trust

Ref

Issues – Flooding – evidence of detritus along bottom of fence which may be from recent flooding which could limit use of path

4.4

Recommendation -.check if path floods regularly and consider drop down signs “Flood” at each end if it does as in York

---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------CSSC05 Cycle Review Plans Kirknewton-Livingston Route A TJP Page 27 of 37 transport initiatives


Cycle Review of NCN Route 75: Kirknewton - Livingston

Ref Issue – Signing – graffiti on sign for route in park which seems to be questioning where it is going. Sign in background cannot be read without stopping due to angle it is placed on pole. Surface quality - Good width path in park with good surface 4.5

Recommendation – check sign locations are correct and rotate sign on lamppost

Kirknewton Community Development Trust

Ref

Issue – Signing - Sign cannot be read without stopping due to angle it is placed on pole

Recommendation - rotate signs slightly so they are easier to read while cycling up to them

---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------CSSC05 Cycle Review Plans Kirknewton-Livingston Route A TJP Page 28 of 37 transport initiatives


Cycle Review of NCN Route 75: Kirknewton - Livingston

Kirknewton Community Development Trust

Ref Issue – Surface quality – mud on path from works on good width path with good surface 4.7

Recommendation – ensure mud is cleared from path during works

---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------CSSC05 Cycle Review Plans Kirknewton-Livingston Route A TJP Page 29 of 37 transport initiatives


Cycle Review of NCN Route 75: Kirknewton - Livingston

Ref Issue – Vegetation and Surveillance – vegetation growing into path and bushes and tress make this section rather lacking in natural surveillance 4.8

Recommendation – cut back vegetation and thin it out so it creates more gaps for natural surveillance from nearby houses

Kirknewton Community Development Trust

Ref Issue – Signing - sign for route on lamppost lacks information on where the route is going and the sign to the left while it has some information it has been spray painted as low down 4.9

Recommendation - review signing of this route as two signing schemes seem to be in place – one sign on the lamppost with destinations and distances to them would do.

---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------CSSC05 Cycle Review Plans Kirknewton-Livingston Route A TJP Page 30 of 37 transport initiatives


Cycle Review of NCN Route 75: Kirknewton - Livingston

Ref

Issue – Barriers – reduce the effective width of the path – and not obvious from site visit what they are for

4.10

Kirknewton Community Development Trust

Ref

Issue – Crossing – route crossings Link Road on good width Toucan but a fairly long delay to wait to cross. Experienced cyclists – Level 3would probably join the road

4.11

Recommendation – review need for barriers along this section of path

Recommendation – count number of cyclists and pedestrians using crossing and review signal timings

---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------CSSC05 Cycle Review Plans Kirknewton-Livingston Route A TJP Page 31 of 37 transport initiatives


Cycle Review of NCN Route 75: Kirknewton - Livingston

Ref

Issues – Crossing – poor surface with lots of grit and a tight turn to use crossing

Kirknewton Community Development Trust

Ref

Issues –Signing - Route direction – not clear where route goes after crossing due to vegetation and lack of signs

4.13

4.12

Recommendation – clear grit from path and consider widening path at the point to improve turning circle to line up for crossing

Recommendation – clear signing needed at crossing as to where route goes

---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------CSSC05 Cycle Review Plans Kirknewton-Livingston Route A TJP Page 32 of 37 transport initiatives


Cycle Review of NCN Route 75: Kirknewton - Livingston

Ref

Issues – Signing – getting overgrown in bushes- signs for NCN 75 and more local signs on same pole

4.14

Kirknewton Community Development Trust

Ref

Issues – Wall along path – high concrete wall between path and high road is rather isolating and would not be pleasant to use at night.

4.15

Recommendation – trim back bushes to signing is clear and review if signs are in easy to see locations and what information they give

Recommendation – check lighting of path at night and consider brightening up grey concrete wall

---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------CSSC05 Cycle Review Plans Kirknewton-Livingston Route A TJP Page 33 of 37 transport initiatives


Cycle Review of NCN Route 75: Kirknewton - Livingston

Ref

Issue – Crossings – good uncontrolled crossing for pedestrians and cyclists on raised speed table

4.16

Kirknewton Community Development Trust

Ref

Issue – Vegetation - growing onto path reducing width and creating a hazard to cyclists

4.17

Recommendation – use more of these types of crossings combined with a zebra

Recommendation – cut back vegetation

---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------CSSC05 Cycle Review Plans Kirknewton-Livingston Route A TJP Page 34 of 37 transport initiatives


Cycle Review of NCN Route 75: Kirknewton - Livingston

Ref

Issue – Subway crossing –wide subway which felt isolated during the day and would be intimidating to use at nighttimes

4.18

Kirknewton Community Development Trust

Ref

Issues – Subway Crossing – wide subway which felt isolated during the day and would be intimidating to use at nighttimes

4.19

Recommendation – review lighting at subways at nighttimes and consider if this is the best route for pedestrians and cyclists to get to the shops

Recommendation – review lighting at subways at nighttimes and consider if this is the best route for pedestrians and cyclists to get to the shops

---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------CSSC05 Cycle Review Plans Kirknewton-Livingston Route A TJP Page 35 of 37 transport initiatives


Cycle Review of NCN Route 75: Kirknewton - Livingston

Ref

Issue – Ramp width – ramp width is a lot less than the subway crossing and walls and railings reduce effective width and creates unnecessary conflict with pedestrians

4.20

Kirknewton Community Development Trust

Ref

Issue – Crossing – lack of space to make turn to line up with to use crossing due to poles and signal controller box

4.21

Recommendation – consider widening ramp to maintain adequate cycle path widths along route

Recommendation – move crossing or widen it to create more path width for cyclists to turn effectively to use crossing

---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------CSSC05 Cycle Review Plans Kirknewton-Livingston Route A TJP Page 36 of 37 transport initiatives


Cycle Review of NCN Route 75: Kirknewton - Livingston

Ref

Issue – Crossing – lack of space on other side of crossing which lines up with a wall, railings and poles causing unnecessary conflict between cyclists and pedestrians

4.22

Kirknewton Community Development Trust

Ref

Issue – Parking – well located and signed cycle parking at ASDA by front entrance and its being used. It could be covered

4.23

Recommendation – can crossing be moved or widened to the left clear of wall to create more space for users to wait

Recommendation – consider covering cycle parking to protect from elements

---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------CSSC05 Cycle Review Plans Kirknewton-Livingston Route A TJP Page 37 of 37 transport initiatives

Profile for Tony Foster

Kirknewton to Livingston - route A using route 75  

Transport Initiatives report for the Kirknewton Development Trust for cycling from Kirknewton to Livingston using route 75

Kirknewton to Livingston - route A using route 75  