Alberta Oil Sands Industry Fall 2011

Page 13

A L B E R TA O I L SA N DS I N D U S T RY Q UA RT E R LY U P DAT E

REGULATORY STATUS

CAPACITY

START-UP

REGULATORY STATUS

Hangingstone

20,000

TBD

Application

SAGD

Leismer

20,000

TBD

Application

SAGD

Leismer Demonstration

10,000

2010

Operating

SAGD

Leismer Expansion

20,000

TBD

Application

SAGD

Leismer Northwest

20,000

TBD

Application

SAGD

Leismer South

20,000

TBD

Application

SAGD

Thornbury

40,000

TBD

Application

SAGD

Commercial

12,000

2016

Announced

SAGD

Thornbury Expansion

20,000

TBD

Application

SAGD

Pilot

2,500

2012

Approved

SAGD

Phase 1

10,000

2007

Operating

SAGD

Phase 2

10,000

TBD

Approved

SAGD

CURRENT PROJECT

Technology

Chard

START-UP

Technology

Pengrowth Corporation Lindbergh The Lindbergh pilot has received all regulatory approvals to begin construction. First steam is targeted for the first half of 2012. Drilling of SAGD well pairs and facility construction will begin in Q3/2011.

Orion 40,000

TBD

Announced

SAGD

Phase 1

40,000

TBD

Approved

SAGD

Phase 2

40,000

TBD

Approved

SAGD

Meadow Creek

Value Creation Inc. TriStar

PEACE RIVER REGION — IN SITU Bitumen production capacity Andora Energy Corporation Sawn Lake

Value Creation is providing the ERCB with additional information supporting its application.

Pilot

CAPACITY

Royal Dutch Shell plc

Suncor Energy Inc. Phase 1

CURRENT PROJECT

1,000

2012

Application

SAGD

COLD LAKE REGION — IN SITU Bitumen production capacity

Andora Energy owner PanOrient Energy Corp. says Andora’s strategic review process to enhance shareholder value that could result in a sale or merger was expected to be closed in June, but this did not occur. The process is ongoing with a number of parties that have expressed interest.

Canadian Natural Resources Limited SAGD Demonstration

Primrose/Wolf Lake Canadian Natural says that production wells are currently being drilled on pads at Primrose East and South, contributing to strong thermal oil production for the company. Primrose East

32,000

2008

Operating

Primrose North

30,000

2006

Operating

CSS

Primrose South

45,000

1985

Operating

CSS

Wolf Lake

13,000

1985

Operating

CSS

10,000

TBD

Approved

SAGD

CSS

Husky Energy Inc. Caribou Demonstration Tucker

Phase 1

30,000

2006

Operating

SAGD

Imperial Oil Limited Cold Lake Cold Lake achieved production record of 158,000 bpd in Q2/2011, attributed to contributions of new wells steamed in 2011, but offset by cyclic nature of project. Site clearing and road construction underway for Nabiye expansion. LASER CSS Follow-up Process

TBD

2007

Operating

CSS

Phase 1-10

110,000

1985

Operating

CSS

Phase 11-13

30,000

2002

Operating

CSS

Phase 14-16

30,000

2015

Approved

CSS

Koch Exploration Canada Corporation Gemini Commercial Pilot

10,000

TBD

Application

SAGD

1,200

TBD

Application

SAGD

OSUM Oil Sands Corp.

TBD

Approved

SAGD

TBD

TBD

Approved

CSS

Northern Alberta Oil Ltd. Sawn Lake CSS Pilot

Petrobank Energy And Resources Ltd. Dawson Surface facilities from the first two wells at the Kerrobert project are being decommissioned and will be moved to Dawson during Q3. Civil work underway, drilling expected to commence midSeptember. Pre-ignition heating cycle to commence in the fourth quarter, with air injection targeted before year-end. 10,000

TBD

Announced

THAI

TBD

2011

Approved

THAI

Cadotte Lake

12,500

1986

Operating

CSS

Carmon Creek - Phase 1

40,000

2014

Announced

CSS

Carmon Creek - Phase 2

40,000

TBD

Announced

CSS

Phase 2 THAI Demonstration

Husky reports continued progress enhancing its understanding of how to develop the Tucker reservoir. It continues to remediate older wells with new stimulation techniques and develop new well pairs, and is seeing an increase in production rates.

1,400

Royal Dutch Shell plc Peace River­

Southern Pacific Resource Corp. Red Earth In June, Southern Pacific commenced steaming wellbores at Red Earth. The project will be tested throughout the remaining summer and fall, after which the test information will be interpreted and go-forward plans will be prepared. Commercial

10,000

TBD

Announced

CSS

Pilot

1,000

2009

Operating

CSS

Pilot Expansion

3,000

TBD

Announced

CSS

N O RT H AT H A B A S C A R E G I O N — U P G R A D E R Synthetic crude oil production capacity Canadian Natural Resources Limited

Taiga

Horizon

Regulatory approval expected to be received mid-2011. Detailed engineering underway. OSUM says it will be ready to execute in late 2011 or early 2012 subsequent to regulatory approval.

Canadian Natural is reporting that synthetic crude oil shipments from Horizon resumed at the end of August post-fire repairs.

Phase 1

17,500

2014

Application

SAGD

Phase 1

Phase 2

17,500

2016

Application

SAGD

Tranche 1

135,000

2008

Operating

Mining

--

2007

Complete

Engineering/Design

13