Wood Wall cap will utilize typ. dimensions. Lengths will vary so that weathered ends will be exposed and interlace with side boards. Leave no more than 2 mm space between boards. Concrete Block wall 200 mm x 200 mm x 400 mm, typ, Stacked reclaimed wood finish 3000 mm

1850 mm 1550 mm

3800 mm

4

2000 mm

7900 mm

5

WOOD WALL ELEVATION SCALE: NTS

WOOD WALL ELEVATION SCALE: NTS

Varies

Reclaimed wood veneer typ., varying dimensions from 100 mm - 200 mm wide and 50 mm - 10 mm deep. Lengths vary 400-1000 mm (L) x 100-200 mm (W) x 50-100 mm (D), accommodating the curve of the wall. Secure with internal fasteners.

6

1000 mm typ.

*Maintain 150 MM wood veneer below finished grade at all locations

WOOD WALL SECTION SCALE: NTS

95째

8

1000 mm

Domed Indent Concrete frame

Concrete

271 mm 3000 mm 271 mm

Dogstooth Brick

697 mm

Open Brick Lattice

545 mm

Stepped Brick 2750

7

2100 mm

17500 mm

9

12650 mm

BRICK WALL ELEVATION NTS

8

Concrete with domed indents, < 600 mm Dia., > 50 mm Dia. Concrete Block 200 mm x 200 mm x 400 mm, typ. Structural Fill Solid Brick Lattice, maintain spacing pattern through wall width Brick Base, offset .5 brick per step

SHEET TITLE:

CONSTRUCTION DETAILS

*Height varies in relation to area of wall, see Brick Wall Elevation for details

BRICK WALL SECTION SCALE: NTS

Brick SCALE:

Mortar

AS INDICATED

Open Space

BRICK WALL DETAIL SCALE: NTS

L5 PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT

9

SHEET:

PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT

PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT

82째

Metal tie straps every 3 courses

SUMMER 2012SPRING 2013

RAMMED EARTH WALL CONSTRUCTION NTS

6

1000 mm

Step 4: Step 5: successive layers of framework is moist earth are removed leaving the added and rammed earth wall compressed until desired height is reached

QINGDAO, SHANDONG, CHINA 2012-2014

3

Step 3: next layer of moist earth is added

ATHENS, GA

2

RAMMED EARTH WALL SECTION SCALE: NTS

Step 2: the layer of moist earth is compressed

QINGDAO HORTICULTURAL EXPO

Step 1: framework is built and a layer of moist earth is filled in

3750 mm

1

BY

Varies

1000 mm

RAMMED EARTH WALL ELEVATION SCALE: NTS

REVISIONS

GEORGIA GARDEN

1550 mm

1000 mm

visible layers of compacted earth

UNIVERSITY OF GEORGIA

82째

pneumatic backfill tamper

reinforced plywood frame

moist earth: mixture of sand, gravel, clay and concrete


PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT

150 mm Concrete frame

150 mm

2000 mm

Large Pipe OD 500. 00-800.00 mm 4170 mm

1830 mm

1520 mm

760 mm

20000 mm

13

RECYCLE WALL SECTION NTS

NOTE: ALL PIPES SHALL CONFORM TO THE FOLLOWING SIZE SPECIFICATIONS. MOCK UP REQUIRED.

1490 mm

3600 mm

RECYCLE WALL SECTION SCALE: NTS

1210 mm

RECYCLE WALL ELEVATION SCALE: NTS

GROUP SIZE

PIPE SIZE RANGE

MATERIAL

A

UNIFORM

OD ≤ 160 MM

SALVAGED METAL, PVC

B

UNIFORM

200 MM ≤ OD ≤ 250 MM

SALVAGED PVC

C

VARYING

100 MM ≤ OD ≤ 510 MM

SALVAGED CONCRETE AND METAL

2000 mm x 1000 mm x 500 mm stacked and planted Gabions 4500 mm 3500 mm

14

1000 mm 5000 mm 25100 mm

SHEET TITLE:

GREEN WALL ELEVATION SCALE: NTS

CONSTRUCTION DETAILS

1000 mm

Plants placed in growing media contained in geotextile fabric pockets

100 mm

4500 mm

STAGE 1: FILL GABION WITH RUBBLE AND SOIL MATRIX

GREEN WALL SECTION SCALE: NTS

13:1 Slope typ.

16

GREEN WALL CONSTRUCTION SCALE: NTS

Wire wrapped gabion box with lid

STAGE 2: CLOSE GABION, MAKE SMALL X-CUTS IN FABRIC IN A TRIANGULAR PATTERN. PLANT

PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT

Structural Fill Support bolts running through both gabions and structural fill

Rubble

400 mm

Soil matrix pockets placed between stone rubble and exterior facade of gabions

Soil matrix wrapped in geotextile fabric Rubble Wire wrapped gabion box with lid

Soil matrix wrapped in geotextile fabric

2000 mm x 1000 mm x 500 mm Gabions

15

1000 mm

STAGE 3: ALLOW PLANTS TO GROW FOR AT LEAST 1 YEAR

STAGE 4: STACK GABIONS TO COMPLETE WALL

SCALE:

AS INDICATED

SHEET:

L6

PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT

PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT

1390 mm

11

12

Concrete Pipe OD 950. 001050.00 mm

1700 mm

2530 mm

3300 mm 2150 mm

150 mm x 150 mm concrete frame, typ. with #4 rebar 400 mm off center both ways

SUMMER 2012SPRING 2013

150 mm

A

BY

QINGDAO, SHANDONG, CHINA 2012-2014

B

ATHENS, GA

C

QINGDAO HORTICULTURAL EXPO

C

GEORGIA GARDEN

B

C

B

REVISIONS

UNIVERSITY OF GEORGIA

A

3300 mm

C

13

12

Concrete frame Pipessee 8/C5 Concrete Pipe see 8/C5 and legend maintain finished surface 25mm on concrete frame

Concrete frame


PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT

REVISIONS

Concrete Weir

28 L7

Brick, typ.

Concrete Seat

25-40 mm Gritty sand laying course material

Concrete Runnel 230 MM

2000 mm

28

SPILL CHANNEL SECTION SCALE: NTS

Concrete Spill Channel

40 mm

Min. 100 mm Granular sub-base

100 mm

50 MM

Compacted subgrade

31 L7

50 MM

BY

5 MM

19 L7

20

PLAN 450 MM

900 MM

450 MM

BRICK PAVING DETAIL SCALE: NTS Artificial turf

50 mm

Compacted subgrade 150 mm Media Display

Original Grade Soil Mix Original Grade

Media Display

21

Geo-textile Fabric 230 MM 380 MM

Open-graded aggregate

ARTIFICIAL TURF DETAIL SCALE: NTS 50 mm Stabilized granite screening,

Media Display

150 mm Perforated Drain Pipe Wrap in Geotextile; Connect to Storm

150 mm Compacted #4 'Choke' stone

50 mm

550 mm

19

31

WETLAND/ SPILL CHANNEL SECTION SCALE: NTS

SPILL CHANNELSECTION SCALE: NTS

150 mm Compacted subgrade

BENCH SECTION

17

WALL SECTION

22

BRICK WALKWAY

MEDIA WALL CONSTRUCTION SCALE: NTS

GRANITE SCREENING DETAIL SCALE: NTS

GRANITE SCREENING

Planting Bed

GRANITE CURB

7 Gauge Steel Edging Stone Dust

PLANTING BED 263 mm

Top Rail

910 mm STEP

24 L7 Cast Iron Picket 50 mm square

Bottom Rail

STEP

STEP

22 L7

27

FLUSH BAND RUNNEL

Granite Cap 860 mm

STEEL EDGING DETAIL SCALE: NTS

FLUSH BAND

18 L7 80 mm 60 mm 20 mm

180 mm dia. perforated metal pipe cover Granite curb

20 L7

ARTIFICIAL TURF

50 mm

310 mm

150 mm Perforated Drain Pipe Wrap in Geotextile; Connect to Storm VARIES

Core drilled conc. & set railing post in mortar

24 mm 21 L7

Running bond brick veneer SLOPE 1%

200 mm, typ.

Running Bond Brick SLOPE 1%

370 mm

222 mm

20 mm runnel depth

RUNNING BOND STACKED BOND EDGE RUNNING BOND STACKED BOND EDGE RUNNING BOND STACKED BOND EDGE

RUNNING BOND STACKED BOND EDGE

24 mm

RUNNING BOND STACKED BOND EDGE RUNNING BOND

SHEET TITLE:

Concrete

40 mm

SLOPE 1%

Subgrade, Compacted to 95%

SLOPE 1%

SLOPE 1%

23

BRICK STEPS PATTERN DETAIL SCALE: NTS

26

32

TOP RAIL DETAIL SCALE: NTS

DRAIN PIPE SPILLWAY ELEVATION SCALE: NTS

CONSTRUCTION DETAILS

Cast iron picket, 50 MM x 50 MM

18

RAILING AND BRICK STEPS CONSTRUCTION SCALE: NTS

Horizontal iron rail, 10 MM x 50 MM Wrought iron loops,15 MM x 15 MM

25 L7

Vertical iron rail, 15 MM x 15 MM R 400 mm

800 mm, CL

16240 mm 540 mm

3200 mm, CL

310 mm, CL

Iron filigree heart, 15 MM x 15 MM 130 mm, CL

26 L7

18 L7

Bottom iron rail, 10 MM x 50 MM

100 mm, CL

SCALE: 100 mm

550 mm

AS INDICATED

80 mm, CL

SHEET:

CL

*Center iron picket set on centerline of greenwall

25

RAILING ELEVATION DETAIL SCALE: NTS

PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT

24

RAILING ELEVATION SCALE: NTS

L7

PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT

PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT

ELEVATION

SUMMER 2012SPRING 2013

Woven filter fabric

150 mm

QINGDAO, SHANDONG, CHINA 2012-2014

Varies - See Plan & Note #1 and #3

Open graded stone base

ATHENS, GA

28 L7

QINGDAO HORTICULTURAL EXPO

Spill Channel 100 mm

Compacted #4 'Choke' stone

Concrete Seat

GEORGIA GARDEN

30

SPILL CHANNEL PLAN SCALE: NTS

UNIVERSITY OF GEORGIA

29

SPILL CHANNEL/BENCH SECTION SCALE: NTS

Rubber shock pad


Georgia Garden and the Qingdao Horticulture Expo 2014 - Construction Documents