Jeff Luken January 25 , 2011
BiG AIR DENVER 2011


BIG AIR , Page 1
Jeff Luken January 25 , 2011
BiG AIR DENVER 2011 Big Air Denver 2011 By the number: •
107 foot tall 300 foot long man made ski jump.
•
528,345 pounds of scaffold equipment.
•
400,000 pounds of concrete ballast
•
8000 feet of cable
•
3145 Man Hours to erect and dismantle
•
Zero accidents
Challenges: The biggest challenge was time. I was first made aware of the project in late November 2010. The project needed to designed and bid in days over the Thanksgiving holiday. The project did not get released until the January 3, 2011. The final designed needed reviewed by a third party and the final ballast designed need to be approved by the City all before erection could begin January 11, 2011 and the erection need to be completed in 10 days to leave time for the snow to be placed before practice could start January 25, 2011.
This Project was a Great Success for Safway Services , Murphy Productions the City of Denver.
BIG AIR , Page 2