PROJECT BRIEF EAST Project : ECOSPACE Location : New Town, Kolkata Project Duration : 18 months Consultant : Potential and OBS Graphics Scope of work : Electrical and Fire Fighting Project value : INR 6.97 Cr.

Project : Times Of India (Regioman+Cromoman) Location : Kolkata Project Duration : 12 months PMC : Client ( Bennett, Coleman and Co. Ltd) Consultant : Archivista, Quasar and Albus Scope of work : Electrical, Mechanical and DG Project value : INR 21.45 Cr.

Project brief India’s leading daily, Times of India, decided to massively expand its press capacities by signing a major deal with Manroland Web Systems featuring 7 Regioman Towers and 3 folders for their various production centers in India. One of the Regioman series and Cromoman series was destined for Kolkata which consists of four printing towers and a double folder. Kolkata Press had to be upgraded and expanded such that it meets technical & related requirements of the new installation. Apart from the Kolkata centre, we have even won orders for their Pune, Nagpur & Mumbai Facility. One of the major challenges that we faced in this project was that it had to be executed without affecting their existing production.

Project brief

Ecospace, the Business Park, is an Eco-friendly building complex built according to Gold Rating requirements of LEED. Spread over an area of 20 acres, upon completion will have a built-up area of 2 million sq.ft. Ecospace is divided into two equal independent campuses and has been developed by two different players. We have executed the campus which has been developed by Udayan Greenfield Developers Ltd. of Ambuja Realty Group.

Our Scope Electrical Supply, Installation, Testing and Commissioning of LT Panel, UPS, Point Wiring, Cabling, HT Substations Works including HT Panels, Transformer, Rising Mains, Bus Duct. The entire execution was carried out on a very tight

It AND is a WILSON, 9 - storied IT -Park LETTER OF STERLING ISSUE #3 2013 development

providing 8 IT buildings which is configured around a central, landscaped plaza. All buildings have individual drop-off points and incorporate the concept of lobby in the garden. We started with Tower 4A & 4B and based on our performance, subsequently Block C & Block D was also awarded to us.

Our Scope Electrical

Work package includes SITC of LT Panel, HT Panels, Transformer, HT & LT Bus Duct, Cabling, Common Area Electrification, External Electrical Works Lighting and HT Substation Works.

Fire Fighting

Hydrant System, Sprinkler System, Extinguisher, Fire Detection & Alarm and Fire Water Pumping System at Block C & Block D.

time schedule including availability of restricted shut down.

Mechanical The Process Cooling for press machines of two buildings, air conditioning of press halls, offices and stores. Precision air conditioning of electrical control rooms and ventilation of the entire facility. The plant comprises of 3 X 180 TR Water Cooled Screw Chillers, Cooling Towers, associated pumps for primary & secondary Chilled Water Circuits for both Process Cooling & air conditioning, Condenser Cooling Pumps.

DG Supply, installation & commissioning of 2 X 2500 KVA LT (415 V) DG Sets for un-interrupted power back up for the press. Total press is capable of running on DG Sets. The engines are of MTU, Germany make.