MSA. 1675 Larch St. Vancouver, B.C. V6K 3N7 Telephone: (604) 787-1620
Marvin Shaffer & Associates Ltd. Consulting Economists
MEMORANDUM To: From: Date: Re:
Jim Quail Marvin Shaffer November 15, 2017 BCUC Site C Report
The terms of reference for the review of the Site C project called on the BC Utilities Commission (BCUC) to advise on whether the project is on time and on budget, what would be the costs to ratepayers of suspending or terminating the project, and whether there are alternative portfolios of projects and measures that could provide similar benefits at similar or lower cost. Project Schedule The BCUC agreed that Site C is currently on schedule to be completed by November 2024 but found that there are tension crack, river diversion and other risks that could result in delay. It concluded the November 2024 in-service date will most likely not be achieved. A delay in the in-service date will pose no operational problem for BC Hydro. Even under BC Hydro’s medium requirements forecast (which the BCUC concluded is too high), BC Hydro will not need any of the 5100 Gwh of energy Site C will produce until 2028. It is forecasting a shortfall of peak generating capacity by 2023, but BC Hydro has access to the downstream benefits under the Columbia River Treaty and other contingency resources that it could use to meet peak capacity requirements until Site C comes on stream. The main issue with delay is that it adds to the installed cost of completing the project and delays the recovery of any of those costs through surplus sales. Project Cost Deloitte Management (technical consultants to the BCUC) estimated that a one year delay in the schedule would increase the cost of Site C to between $9.1 and $10 billion. Based on its expectation of some delay plus consideration of other uncertainties in the work remaining to be done, the BCUC concluded that the total cost of Site C will increase from the current estimate of $8.9 billion to $10 billion or more.