Projects Department

Monthly Projects Update July 31, 2013

Hickory Slough Detention at Max Rd & Max Rd Sports Complex, Phase 1 Far Northwest Wastewater Plant Improvements Hatfield Basin Trunk Sewer Dolores Fenwick Nature Center, Phase 2 Pearland Parkway Extension Max Road Reconstruction/Widening Convention & Visitors Bureau Office Build Out Cullen Parkway Manhole Rehabilitation

Prepared by: Andrea Brinkley

For Distribution to City Council


Hickory Slough Detention at Max Rd & Max Rd Sports Complex, Phase 1 Design Engineer: Jacobs Engineers, Inc. Contractor: Triple B Services CM: Staff Billed to Date: $4,054,192.91 % Billed: 77% Contract Days Used: 292 % of Contract: 157% Progress this period: • Contractor continues to exceed substantial completion time. • Contractor conducting post-excavation survey to submit to Engineer. • Installing fence and painted pipe at pump station. • Pressure tested and disinfected water line. • Continued Hughes Ranch Rd curb inlet and sidewalk work, placed remaining 60 ft. of roadway. • Completed field drainage work, and fine grading. • Completed the removal dispersive soils and replacement with suitable material. • Completed field lighting conduit installation. • Completed all weather pump station access road. • Staff reviewed 100% Sports Complex PS&E package. • Staff coordinated with architect on lighting and ventilation for restroom building. • Coordinate with CenterPoint Energy for power to pump station and park. • Coordinated with Developer on development and power needs. • Continued reimbursement requests to BDD#4 and Developer. Planned activities for the period ending August 31, 2013: • Complete pump station fence, gate and prepare for power. • Obtain proposal for SCADA installation and programming for pump station. • CPE to initiate power pole installation. • Complete pressure testing of sanitary manholes and mandrel on pipe. • CPE to start installation of streetlights along Hughes Ranch Rd. • Complete field lighting conduit installation. • Install pumps and perform system start up, pending power delivery. • Engineer to complete review post excavation survey. • Complete final work and achieve Substantial completion. • Engineer to make final corrections on Sports Complex plans. • Hold Technical Review Committee meeting for Sports Complex. • Prepare to advertise Sports Complex. Project schedule: • Design: Detention: Nov. 2010 to July 2012; Sports Complex: to July 2013 • Construction: Detention: NTP Sept. 17, 2012, • Sports Complex: August/September 2013

adkb

Page 2 of 6

8/12/2013


Far Northwest Wastewater Treatment Plant Improvements Design Engineer: Binkley & Barfield Inc. Contractor: Industrial TX Corp CM: Binkley & Barfield Inc. Billed to Date: $694,995.00 % Billed: 89.3% Contract Days Used: 166 % of Contract: 63.8% Progress this period: • Sand filter rehabilitation completed, tested and staff training complete. • UV units replaced, completed electrical work and units turned on for testing phase. • UV unit staff training completed. • Motor actuated decanter valves replacement complete. • Staff sent additional sampling and data to manufacturer regarding plant data for effluent optimization. Planned activities for the period ending August 31, 2013: • Accept new UV system and review for spare parts orders. • Substantial completion inspection • Make final payment to contractor • Close out project. • Support Public Works staff regarding effluent optimization. • Support Public Works staff coordination with Decanter manufacturer to schedule work outlined in work plan for Decanter repairs to coordinate with UV and valve repairs. Project schedule: • Design: February 2012 to December 2012. • Construction: February 18, 2013 Notice to Proceed. • Substantial Completion: September 6, 2013. Hatfield Basin Trunk Sewer Design Engineer: Freese & Nichols, Inc. Contractor: SJ Louis Construction of Texas Billed to Date: $0 Contract Days Used: 21

CM: Dannenbaum Engineers % Billed: 0% % of Contract: 0%

Progress this period: • Issued Notice to Proceed, held Pre Construction meeting. • Initiated submittal process, installed construction project signs trailer. • Contractor delivered pipe to job and trailer to laydown yard. • Initiated clearing and grubbing from Magnolia to Mary’s Creek along easement. • Contractor installed SWPPP in work area. • Coordinated with residents in adjacent area. • Coordinated with BDD#4 regarding Mary’s Creek crossing

adkb

Page 3 of 6

8/12/2013


Hatfield Basin Trunk Sewer

(cont’d)

Planned activities for the period ending August 31, 2013: • Continue coordination with BDD#4. • Coordinate with Pipeline company working in adjacent area. • Coordinate with TxDOT regarding FM 518 crossing and traffic control approval. • Coordinate with Emergency services regarding any short term road closures. • Bore under Magnolia Rd to terminal manhole and connect 36 in sanitary. • Initiate installation of 36 in sanitary pipe from bore to Mary’s Creek and cross Mary’s Creek via open cut construction. Project schedule: • Design: February 2011 to November 2012 (delayed due to PER delay). • Draft PER: November 2011 (Delayed due to Fite alternate route) • Final PER: March 2012 • Construction: 2nd quarter 2013 Trails at JHEC (formerly Dolores Fenwick Nature Center), Phase 2 Architect: Randall-Porterfield Architects, Inc. Progress this period: • Geotechnical firm submitted geotechnical report. • Coordinated with board walk system vendor. Planned activities for the period ending August 31, 2013: • Review geotechnical report and finalize. • Convene design progress meetings and coordinate with Parks and KPB staff. • Review contract documents and project for possible phasing, use of grant funds. • Continue with Final Design and complete submittal of 90% plans. Project schedule: • Design: September 2011 – October 2013. • Construction: Pending funding, partial grant funding. Pearland Parkway Extension Design Engineer: HDR Engineers, Inc. Progress this period: • Project advertising via TxDOT Austin, with delayed Notice to Proceed. • Coordinated withBDD4 on Cowart’s Creek easement. • Met with residents regarding barrier fence and received comments. • Obtained proposal for design of barrier fence. • TxDOT continued reimbursements to City. • Coordinated with CPE regarding power pole and streetlight relocation. • Continue to monitor project with TxDOT, maintain schedule.

adkb

Page 4 of 6

8/12/2013


Pearland Parkway Extension (cont’d) Planned activities for the period ending August 31, 2013: • Negotiate design contract for barrier fence. • Initiate property acquisition, pending TxDOT approval. • Monitor TxDOT bid outcome. • Monitor CPE power pole relocation and streetlight adjustment. • Continue to submit and monitor reimbursements. Project schedule: Design: February 2012 – August 2013. Letting: August 2013 Construction: October 2013 – September 2014

Max Road Reconstruction/Widening Design Engineer: Klotz Associates, Inc. Progress this period: • Held Public Meeting July 2nd at Berry Miller Jr. High. • Reviewed property owner comments received at Public Meeting. • Continued to review segments of roadway alignment. • Coordinated with Developer on development and roadway right of way. • Obtained TxDOT approval on bridge foundation design. • Continued design progress meetings. • Engineer submitted 30% Plans and Partial drainage report for staff review. • Draft Environmental document and Public meeting summary submitted. • Submitted reimbursement requests to TxDOT. Planned activities for the period ending August 31, 2013: • Staff continues to review alignment for comments received during Public Meeting. • Finalize alignment and parcel maps for road right of way. • Review Draft Environmental document work. • Review traffic model and signal warranty analyses. • Engineer to submit remaining drainage report and geotechnical report • Engineer to work on next PS&E submittal. • Coordinate with TxDOT and BDD4 on hydraulics and draft drainage report. Project schedule: Design: February 2013 – March 2014. Letting: July 2014 Construction: October 2014 – September 2015

adkb

Page 5 of 6

8/12/2013


Convention & Visitor’s Bureau Office Build Out Architect: Wilson Architectural Group Progress this period: • Completed City and Town Center landlord approval. • Obtained Council approval on July 22nd. • Held Pre Construction meeting July 31st. • Approved office furniture proposal and issued Purchase Order. • IT staff worked on obtaining proposals for phone/cable/internet. Planned activities for the period ending August31, 2013: • Coordinate with IT staff to review pricing on phone/cable/internet systems • Monitor construction of plumbing and slab • Begin furniture and IT /phone procurement process. Project schedule: • Design: May 2013 – June 2013. • Construction: August 2013 – November 2013

Cullen Parkway Manhole Rehabilitation (Fite to FM 518) Engineer: Staff Progress this period: • Completed bid documents and prepared for advertising. • Initiated advertising on July 24th. Planned activities for the period ending August 31, 2013: • Hold Mandatory Pre bid meeting on August 13th. • Open bids on August 20th. • Coordinate with Public Works staff • Prepare for Council award if necessary. Project schedule: • Construction: September 2013 – October 2013

adkb

Page 6 of 6

8/12/2013


City of Pearland

Projects Department

Monthly Projects Update August 1, 2013 Bailey Rd (Veterans to FM1128) Business Center Drive Cowart Creek Diversion Project Old Alvin Road Water Line Shadow Creek Ranch Park SH35 Water Line – FM518 to Magnolia Twin Creek Regional Lift Station

Prepared by: Cara Davis

For Distribution to City Council


Bailey Road (Veterans to FM 1128) Design Engineer: Wilbur Smith Associates (WSA) Original Contract Amount: $1,710,346.00 Current Contract Amount: $1,848,685.00 Billed to Date: $ 1,691,173.50 % Billed: 91.48 Plan Status: 100% Complete Progress this period: • • •

Continued contract negotiations with CDM Smith for contract amendment to update plans to mediate TxDOT comments. Acquisition negotiations/proceedings continued Performed inspections on clearing/grubbing operations. Some items were still left incomplete. Completion and start of contract closeout is expected in early August.

Planned activities for the period ending August 31, 2013: • • •

Condemnation and mediation proceedings for the last two parcels are scheduled for early in August. Complete substantial inspection punch items and close out clearing/grubbing contract. Negotiate a contract amendment with the design consultant to meet new project requirements and update plans.

Project schedule: • • •

Consultant Selection – 2nd thru 3rd Quarter 2008. Design (Completed) – 3rd Quarter 2008 thru 2nd Quarter 2010. Construction – Scheduled for Fiscal Yr 2015

Business Center Drive Design Engineer: Freese & Nichols Contractor: Lazer Construction Company CM: Klotz & Associates As of July 30, 2013 Original Contract Amount: $3,474,998.80 Current Contract Amount: $3,476,348.80 Billed to Date: $2,966,448.90 % Billed: 85.3 Contract Days Used: 278 % of Contract Days: 102.9


Business Center Drive (cont…) Progress this period: • • • • •

The majority of main lane pavement has been placed. There is a median crossing near the construction trailer and main lane paving in front of the Centerpoint power station left to be placed. All southbound lane sidewalks, curb, and pavers have been placed. Work on the northbound components continues. Installation of irrigation system was continued. All underground mainline piping is complete. Streetlight conduit and pullboxes have been installed. Signal poles, mast arms and conduit have been placed for the traffic signal at CR 59.

Planned activities for the period ending August 31, 2013: • • • • •

Complete all pavement placement operations on northbound lanes and median crossings, as well as all driveway aprons. Complete installation of curbs, sidewalk and brick pavers. Adjust inlets and manholes as necessary. Centerpoint should install necessary transformers for the irrigation and streetlights. Meters should be installed for the irrigation and traffic signal. Complete landscape installation including water tap, controller installation and plantings. Complete traffic signal installation and test in preparation for turn on.

Project schedule: • • • •

Consultant Selection – 2nd thru 3rd Quarter 2008. PER – 3rd Quarter 2008 thru 2nd Quarter 2010 Design – 2nd Quarter 2011 thru 3rd Quarter 2012 Construction – 4th Quarter 2012 thru 3rd Quarter 2013.

Cowart Creek Diversion Project – Detention Pond & Diversion Ditch Design Engineer: JKC & Associates, Inc. Contractor: Brazoria Drainage District 4 As of May 29, 2013 Original Contract Amount: $391,457.82 Current Contract Amount: $391,457.82 Billed to Date: $258,199.24 Contract Days Used: N/A

CM: N/A

% Billed: 66 % of Contract Days: N/A


Cowart Creek Diversion Project – Detention Pond & Diversion Ditch (cont….) Progress this period: •

Phase II slope paving activities completed.

Planned activities for the period ending August 31, 2013 • Phase III slope paving and turf establishment pre-bid will be held at the district office on August 8th. Bids will be opened the following Thursday, August 15th. Project Schedule: •

Diversion Ditch: Construction: 3rd Quarter 2011 – 1st Quarter 2014

Cowart Creek Diversion Project – Pump Station Design Engineer: Jones & Carter (formerly Montgomery & Barnes, Inc.) Contractor: Reddico Construction Company CM: Jacobs As of July 20, 2013 Original Contract Amount: $1,083,680.90 Current Contract Amount: $1,072,413.25 Billed to Date: $1,072,413.25 % Billed: 100 Contract Days Used: 208 % of Contract Days: 100 Progress this period: • •

Final closeout paperwork completed. Phone service construction for SCADA completed by AT&T

Planned activities for the period ending August 31, 2013: •

Work with electrician and Public Works to complete final testing of the alarm system as it relates to the auto-dialer.

Project Schedule: • • • •

Council Award: June 11, 2012 NTP: July 23, 2012 Construction: 3rd Quarter 2012 – 2nd Quarter 2013 Substantial Completion: April 19, 2013


Old Alvin Road Water Line Design Engineer: Charles D. Gooden Consulting Engineers, Inc. Contractor: SER Construction Partners, LLC CM: LJA Engineering As of July 20, 2013 Original Contract Amount: $3,398,483.00 Current Contract Amount: $3,398,483.00 Billed to Date: $687,535.10 % Billed: 20.2 Contract Days Used: 37 % of Contract Days: 20.6 Progress this period: • •

Continued submittal review for construction materials. Contractor mobilized on site July 3rd and started laying pipe north of Town Ditch. Water line has been laid from just south of McHard Rd to the north bank of Town Ditch. The contractor mobilized a second crew that started laying pipe from the south at John Lizer. This section has been installed from John Lizer to Mary’s Creek, just north of Alexander middle school. Pipe has also been laid from Plum to the north ROW of FM 518. Contractor is now installing storm sewer in front of the public works center.

Planned activities for the period ending August 31, 2013: • • • •

Continue review of construction material submittals. Contractor to complete installation of storm sewer and continue installation of water line at service center. Water line installation will also continue from the north side of Mary’s Creek to the south ROW of FM 518. Subcontractor to begin work for elevated water line crossings at Mary’s Creek and Town Ditch, i.e. drill shafts and piers. Contractor to begin preparations for bore at FM 518. Bore pit will be prepared and environmental sampling for PPCA’s will be begin. Some intermittent traffic interruptions should be expected at this intersection as equipment and materials move in and out. No lane closures on FM 518 are expected.

Project Schedule: • • • •

Consultant Selection – 4th Quarter 2010. Design/Acquisition – 1st Quarter 2011 thru 1st Quarter 2013 Bid: 1st Quarter 2013. Construction: 2nd Quarter 2013 – 4th Quarter 2013


Shadow Creek Ranch Park Design Engineer: Cobb Fendley, Architect: Randall Porterfield Original Contract Amount: $649,748.50 Current Contract Amount: $649,748.50 Billed to Date: $339,957.63 % Billed: 59.04 Plan Status: 60% Progress this period: • 60% plan comments returned to the engineer for revisions. Latest cost estimate submitted by the engineer is $8,548,224.00 which is approximately 22% over our CIP construction estimate. Staff has requested that the design team look at value engineering options where possible and to provide some suggestions of items that can be eliminated if necessary. Planned activities for the period ending August 31, 2013: • Continue site plan development and structural design for buildings. • Continue drainage analysis and outfall design. USACE permit application will be completed and submitted upon completion of the drainage report. • Hold monthly progress meeting Project Schedule: • • • • •

Consultant Selection – Complete Schematic Land Plan & Programming – October 2012 to April 2013 Design – April 2013 to September 2013 Bid/Award – September/October 2013 Construction – November 2013 to November 2014

SH35 Water Line – FM518 to Magnolia Design Engineer: Brown & Gay Engineers, Inc. Original Contract Amount: $155,200.00 Current Contract Amount: $155,200.00 Billed to Date: $0 % Billed: 0 Plan Status: 0% Progress this period: • Topo survey has been completed. Abstracting is in process. Began putting together plan and profile sheets. Planned activities for the period ending August 31, 2013: • Begin preparation of draft PER. Letter report to be submitted by early September.


SH35 Water Line – FM518 to Magnolia (cont…) Project Schedule: • • • •

Consultant Selection – Complete Design – June 2013 to September 2013 Bid/Award – September/November 2013 Construction – November 2013 to June 2014

Twin Creek Regional Lift Station Design Engineer: IDS Engineering Group (formerly Pate Engineers, Inc.) Contractor: E.P. Brady, Ltd. CM: City of Pearland, Cara Davis As of Jul 25, 2013 Original Contract Amount: $2,371,573.35 Current Contract Amount: $2,371,547.74 Billed to Date: $1,234,387.91 % Billed: 52.05 Contract Days Used: 387 % of Contract Days: 94.4 Progress this period: • • •

Contractor completed 8” sanitary sewer from Woodthrush Drive to Hickory Knoll along Glastonbury. Twin Woods Lift Station has been decommissioned and converted to a manhole. Sanitary sewer installation (15”) has begun from Woodthrush headed towards Bishopton. Asbestos survey has been conducted on old Twin Creek LS that is scheduled for demolition.

Planned activities for the period ending August 31, 2013: • • •

Contractor to continue installation of gravity sewer from Woodthrush toward Bishopton. Peltier Brothers to make waterline connection at Woodthrush and install water meter at LS. Secure contract for asbestos abatement and demolition of the old Twin Creek Lift Station.

Project Schedule: • Consultant Selection – 4th Quarter 2010 • PER – 1st Quarter 2011 thru 3rd Quarter 2011 • Design – 3rd Quarter 2011 thru 2nd Quarter 2012 • Construction – 3rd Quarter 2012 thru 3rd Quarter 2013


City of Pearland

Projects Department

Monthly Projects Update Aug. 6, 2013 Highway 35 Reconstruction Intelligent Traffic System Country Place Bed and Banks Permit Alice Street Plant

Prepared by: Skipper Jones For Distribution to City Council


Highway 35 Reconstruction Design Engineer: S&B Engineers & TxDoT, Contractor: Triple B Construction Billed to Date: $ Contract Days Used:

CM: TxDoT % Billed: % of Contract Days:

Completion Date: per contract Oct. 2012 Projected Completion Date: November, 2013 Progress this period: •

• • • • •

Pavement o The left out areas of mainlane pavement between WalMart intersection and the Town Ditch bridge are now complete. Outside lane remains to be paved. o Mainlane pavement remains to be completed between Knapp and the Beltway Bridges o All three bridges are now complete except for a small portion of the bridge rail o Work remains to tie in pavement bridges to wideflange sections at hickory Slough and Clear Creek bridges Contractor is still working on completing installation of driveways and sidewalks along the east side Street Lights along east side now working and on west side between Orange and Walnut Contractor has scheduled the paving crew to return for second week of August to complete all remaining paving between 518 and the Beltway No schedule yet for median work or for installation of pavers along the east side between 518 and Orange Once paving is completed TxDoT will profileagraph the pavement and require the contractor to grind out non-complying locations.

Intelligent Traffic Management System Design Engineer: AECom and Wilber Smith Contractor: Third Coast Services CM: in House Billed to Date: $ 790,377 % Billed: 24.5 Contract Days Used: 200 45% of Contract Days: Progress this period: •

Processed 7th Contractor Pay Estimate in amount of 290,000

1st Reimbursement Check in the amount of $368,012.05 or 80% of the first payment ($477,533) has been received

Approximately 50% of the conduit for underground fiber has been installed


Received 58 of the 66 total controllers and all of the cabinets and have them stored on site.

Installation of video detections system is continuing at the intersections throughout the project

Contractor is programming equipment components at their shop where mass programming can be done all at one time. Additional work will be done at the City’s Traffic Ops Center for training purposes

Received BNSF railway crossing permit for aerial fiber crossing

Planned Activities for period ending August. 31, 2013 •

Complete installation of video detection systems at intersections

Receive final shipment of signal controllers and perform environmental chamber testing of two controller assemblies

Begin installation of controllers and communications equipment in new cabinets and begin testing these as they are completed in the signal shop at Hillhouse

Continue installation of underground conduit for fiber network

Project Schedule • • •

Notice to proceed issued January 7th, 458 days to Substantial completion, April 10, 2014 548 days to final completion and acceptance, July 9, 2014

Bed and Banks Permit Application Design Engineer: Cobb Fendley Contractor: CM: Billed to Date: $0 % Billed: Contract Days Used: 30 10% of Contract Days: Progress this period: • •

Application has been executed and submitted to TCEQ o The actual application fee will be calculated by TCEQ and requested via invoice, this is expected to be about $500 Completion of the process is anticipated to require approximately one year

City of Houston Connection (W42051) Alice Street Water Plant Design Engineer: Camp Dresser & McKee, Inc. Contractor: Industrial Tx Corp Original Contract Amount: $6,846,000.00

CM: LJA Engineering


Revised Contract Amount: $7,524,030 Billed to Date: $7,524,030 (thru 7/15/13) Original Contract Time: 360 days Revised Contract Time: 429 days Contract Days Used: 515 (thru 11/25/2011) NTP: June 28, 2010

Percent Billed: 100%

Percent Contract Used:120.0%

Progress for period ending July 2013: • Certificate of Final Completion received • Engineer preparing Record Drawings

Planned progress for period ending August 2013: • Receive Record Drawings from Engineer


City of Pearland

Projects Department

Monthly Projects Update July 30, 2013 McHard Road 16� Water Line Westchester Sidewalk and Drainage Walnut Lift Station Westside Library Fire and EMS Administration Building McHard Road Extension

Prepared by: Jennifer Lee

For Distribution to City Council


McHard Road 16” Water Line and Roadway PER Progress this period: • • • • • • •

Attended monthly progress meeting. Prepared the AR for the Advance Funding Agreement for the roadway project to be included on the August 12, 2013 City Council Agenda for consideration. Continued conversations about diverting some of the flows to the south and downsizing the large cross drainage structures. Discussions have identified both pros and cons that will need to be addressed before a final design can be decided. Geotech investigation is complete and the final report is being prepared. Freese Nichols and GC Engineering are reviewing and addressing staff’s comments on the PER and will provide written responses before proceeding. The Phase 1 ESA has been revised and will be included in the next submittal. GC Engineering will finalize the Supplemental Drainage Report based on comments received from staff.

Planned activities for the period ending August 30, 2013: • • • • •

Prepare and attend a monthly progress meeting. Continue utility coordination. Begin surveying coordination. Receive revised Tech Memo from CDMSmith for review. Separate the Waterline and Roadway projects so that beginning in September they will be handled as two distinct projects.

Project Schedule: • • •

Project design is scheduled for twenty-four months. Waterline should bid early 2014. Design is on schedule.

Westchester Sidewalks and Drainage Project Design Engineer: GC Engineering Contractor: Lazer Construction Company, Inc. Contract Amount: $381,206.72 Change Orders to Date: $0.00 Adjusted Contract Total: $381,206.72 Billed to Date: $48,915.14 Contract Duration: 60 Days (Substantial) Contract Days Used: 17 Contract Days Extension: 20 Additional Rain Days: 0

Page 2 of 5

% of Increase: 0 % Billed: 12.8 % of Contract Days: 21.25

8/12/2013


Westchester Sidewalks and Drainage Project (cont.) Progress this period: • •

Attended progress meeting. Project has been suspended because the residents complained about the size and height of the inlets adjacent to their property. Staff, the design engineer, and the contractor have been working on an alternative solution to the large structures necessary to convey the water from the property.

Planned activities for the period ending August 30, 2013: •

Resume project schedule

Walnut Street Lift Station Progress this period: • • •

• •

Attended the monthly progress meeting. GC Engineering submitted 60% drawings. The overall footprint of the new lift station will encroach on the property line therefore, additional ROW will be required. Of particular concern is a structure that is very close to the property line and the construction of the lift station would be greatly hampered by it’s proximately. The additional acquisition of easement will allow the lift station to shift to the west, providing an additional buffer between the structure and the adjoining property to the east. Working with GC Engineering to determine the specific space requirements.

Planned activities for the period ending August 30, 2013: •

Receive appraisal for easements.

Project Schedule: • •

The design of the lift station is behind schedule. The construction phase is expected to take five months.

Westside Library Design Architect: Wilson Architectural Group Contractor: Construction Masters of Houston. Contract Amount: $375,000.00 Change Orders to Date: $4,958.36 Adjusted Contract Total: $379,958.36 Billed to Date: $360,094.32 Contract Duration: 120 Days (Substantial) Contract Days Used: 99 Contract Days Extension: 0 Additional Rain Days: 0 Page 3 of 5

% of Increase: 1.3 % Billed: 94.77 % of Contract Days: 82.5

8/12/2013


Westside Library (cont.) Progress this period: •

The A/C was rebalanced as a result of the original Testing and Balancing Report. More air is being forced to the front of the facility. The new report indicated there has been a 30% increase in the amount of air to the front of the building. This adjustment has greatly improved the air circulation throughout the facility. Released retainage.

Planned activities for the period ending August 30, 2013: • •

Continue to work through Warrant items. Close out P.O.s

Project Schedule: •

Project is complete.

Fire and EMS Administration Building (Old PD Renovation) Design Architect: HBL Architects Contractor: Bass Construction Co. Contract Amount: $1,273,000.00 Change Orders to Date: $0.00 Adjusted Contract Total: $1,273,000.00 Billed to Date: $956,678.14 Contract Duration: 120 Days (Substantial) Contract Days Used: 170 Contract Days Extension: 35 Additional Rain Days:

% of Increase: 0.0 % Billed: 75.15 % of Contract Days: 110.

Progress this period: • •

Contractor has worked through 95% of the punch list items. Most of the remaining items are due to material that has not arrived on site yet. Met with contractor and concrete floor seal vendor to discuss the unacceptable seal that was installed on the floors in the storage areas. It has been determined that re-sealing the floor will not resolve the discoloration issues. The contractor has been asked to credit the city for the unacceptable work and to provide a quote to install another finish on the floors. Staff has also asked for a quote from another contractor. The security system that was designed for the facility cannot be installed on two of the doors. The Sallyport door is too small (2’-6”) and cannot accommodate the door closer and the magnetic locking device. The alternative, strike plate will be installed on this door instead. The front door has the wiring for the handicap buttons overhead and therefore cannot Page 4 of 5

8/12/2013


accommodate the magnetic locking device hardware. The contractor is investigating alternative devices for this door.

Fire and EMS Administration Building (Old PD Renovation) (cont.) • •

The renovation project did not include enough landscaping to satisfy the City’s screening requirement. Landscaping and additional irrigation have been added to the project. The installation should be complete by August 9, 2013. The facility’s staff needs additional Audio Visual work done to make the Training room more efficient. The vendor and contractor have provided quotes to complete this additional work which should be complete by the end of August.

Planned activities for the period ending August 30, 2013: • •

The remaining security system devices should be installed by August 9. Acquire certificate of occupancy.

Project Schedule: • •

Construction to begin in January, 2013. Project has exceeded the construction schedule.

McHard Road Extension Progress this period: • •

Design consultant was selected. Submitted TxDOT’s Advance Funding Agreement for Council consideration on the August 12, 2013 agenda.

Planned activities for the period ending August 30, 2013: •

Continue with the preliminary discussions and submittal of documents to TxDOT.

Project Schedule: •

Construction TBD.

Page 5 of 5

8/12/2013


City of Pearland

Projects Department

Monthly Projects Update July 31, 2013 Garden Road Signal West Oak / Somersetshire Lift Station Retirement Fire & EMS Station 3 SH35 Quiet Zone Barry Rose Wastewater Plant Longwood Wastewater Plant

Prepared by: Cuong Le

For Distribution to City Council


Garden Road Signal (Design) – TR1306 Design Engineer: EPIC Engineering Original Contract Amount: $44,376.50 Current Contract Amount: $44,376.50 Billed to Date: $9,990.45

% Billed: 30

Progress this period: • • • • •

Topographic survey completed in June 2013. Completed site investigation and preliminary signal design with median modification. Project kick-off/work-in meeting July 12, 2013 Staff reviewed 30% plans and provided comments & Traffic Impact Analysis (TIA) to consultant Consultant & City staff met with TxDOT July 30, 2013 for 60% plan review

Planned Activities for period ending August 2013: • •

Consultant address 60% plan review comments and submit to utility companies for initial review. Consultant submit 90% plans and City staff review

Project Schedule •

Design NTP issued May 28, 2013

West Oak & Somersetshire Lift Station Retirement (Preliminary Engineering) – WW1303/1304 Design Architect: ARKK Engineers, LLC. Original Contract Amount: $16,180.00 Current Contract Amount: $16,180.00 Billed to Date: $ 0

% Billed: 0

Progress last period: • City staff reviewed Engineer’s proposed alignment and asked Engineer to proceed with topographic survey. • Topographic survey completed. Planned activities for the period ending August 2013: • Engineer submit letter report of findings from preliminary engineering Project Schedule: • Notice to Proceed – June 3, 2013


Fire & EMS Station 3 (Design) Design Architect: Brown Reynolds Watford Architects, Inc. Original Contract Amount: $265,090.00 Current Contract Amount: $265,090.00 Billed to Date: $ 84,100.49 % Billed: 31.7 Progress last period: • 45% comments submitted to Architect to address. • Finalized traffic pre-emption design submitted to Architect. • Met with Centerpoint to start utility relocation. • Interior/cabinet color scheme agreed by all. • Met with Architect to discuss tree root protection July 30, 2013. Planned activities for the period ending August 2013: • Continue finalizing right of way acquisition. • Architect addresses 45% plan comments and schedule 60% progress meeting. • Architect submits plans to utility companies to start utility coordination. Project Schedule: • Council Award: February 11, 2013 • Notice to Proceed – February 25, 2013

Quiet Zone Crossing and Median Improvements at Broadway at BNSF Railway (Construction) – TR1002 Design Engineer: ARKK Engineers, LLC. Contractor: General Contractor Services, Inc. Original Contract Amount: $141,240.00 Current Contract Amount: $141,240.00 Billed to Date: $0 Contract Days Used: 0

CM: City of Pearland

% Billed: 0 % of Contract Days: 0

Progress last period: • Contractor started submitting submittals for approval. • Contractor submitted additional BNSF insurance requirements; BNSF accepts submitted insurance July 30, 2013. • BNSF will sign contract once the new insurance certificates are applied. Planned activities for the period ending August 2013: • Receive signed BNSF contract signed by all parties • Schedule pre-construction meeting • Issue notice to proceed to contractor


Project Schedule: • Received TxDOT permit March 11, 2013. • Advertisement scheduled for April 4 and 10 • Mandatory Pre-bid April 17, 2013 • Bid April 25, 2013 • Council Award: May 13, 2013

Barry Rose Wastewater Treatment Plant (Construction) – WW1004________ Design Engineer: Binkley & Barfield Contractor: JTR Construction, Inc. Original Contract Amount: $3,143,020.00 Current Contract Amount: $3,060.929.20 Paid to Date: $ 2,907,882.74 Contract Days Used: 384

CM: Binkley & Barfield

% Billed: 95% % of Contract Days: 100%

Progress this period: • • • • •

Final punchlist completed. Executed deductive change order. Project came in 2.6% under budget. Contractor working on minor warranty items. All final O&M manuals submitted to Public Works. All spare parts delivered and verified.

Planned Activities for period ending August 2013: • • • •

Complete minor warranty items. Schedule close out meeting for as-builts. Release retainage to contractor. Schedule 1 year warranty walk through.

Project Schedule • • • • • • •

Design of improvements complete November, 2011. Bid Phase January, 2012. Award Construction Contract March 12, 2012. NTP issued for March 26, 2012. Substantial Completion April 18, 2013 – Completed on time. Substantial punch list completion verified June 3, 2013. Final Walk through June 19, 2013


Longwood Wastewater Treatment Plant (Construction) – WW0902________ Design Engineer: Malcolm Pernie / ARCADIS Contractor: RP Constructors, Inc. CM: Arcadis/Malcom Pernie Original Contract Amount: $2,569,160.00 Current Contract Amount: $2,446,049.00 Billed to Date: $2,416,362.00 % Billed: 94.2 Contract Days Used: 417 % of Contract Days: 114 Progress this period: • • •

Contractor completed 95% of substantial punch list. 95% of final O&M, startup reports and warranty submitted. All spare parts submitted and verified.

Planned Activities for period ending August 2013: • • • • •

Complete SCADA work. Contractor submits all O&M, startup reports and warranty. Complete final completion walk through and final punch list. Complete balancing change order and final pay estimate. Project estimated to be 4.8% under budget. Close out meeting.

Project Schedule • • • • • •

Design NTP issued May 2, 2011 Bid April 2012 - Early by one month Pre-Construction Meeting April 20, 2012 Contractor NTP April 30, 2012 Scheduled Substantial Completion May 31, 2013 Substantial Completion June 24, 2013


City of Pearland

Projects Department

Monthly Projects Update August 7, 2013 Irrigation Improvements on McHard Road at Countyplace Blvd.

Prepared by: Jameson Appel For Distribution to City Council


Irrigation Improvements for McHard Road at Countryplace Blvd. Design Engineer: Huitt-Zollars, Inc. Contractor: To be determined Original Contract Amount: $ 0.00 Current Contract Amount: $0.00 Billed to Date: $ 0.00 Contract Days Used: 0 Plan Status: 100% Complete

% Billed: 0.00 % of Contract Days: 0

Progress this Period: • • •

Perform final review and prepare for bid. Acquire final signatures for encroachment agreement(Kinder Morgan) Project Schedule o 1st Advertisement 7/17 o 2nd Advertisement 7/25 o Pre-Bid 7/25 o Bid Opening 8/1 o Construction 3rd Quarter 2013

Planned activities for the period ending August 31, 2013: • •

Award Bid (if changes in scope can bring project within budget) Possible re-bid if project cost cannot be lowered to within budgeted amount

Current Utility Relocations State Highway 35 reconstruction (TxDOT) •

CPE electric relocation plan approved waiting for plat of property to be able to create blanket easement for CPE

Pearland Parkway Extension •

Centerpoint streetlight relocations (2)