City of Pearland

Projects Department

Monthly Projects Update November 26, 2013

Hickory Slough Detention at Max Rd & Max Rd Sports Complex, Phase 1 Far Northwest Wastewater Plant Improvements Hatfield Basin Trunk Sewer Trails at JHEC (Dolores Fenwick Nature Center, Phase 2) Pearland Parkway Extension Max Road Reconstruction/Widening Convention & Visitors Bureau Office Build Out Cullen Parkway Manhole Rehabilitation Far Northwest Wastewater Treatment Plant Expansion

Prepared by: Andrea Brinkley

For Distribution to City Council


Hickory Slough Detention at Max Rd & Max Rd Sports Complex, Phase 1 Design Engineer: Jacobs Engineers, Inc. Contractor: Triple B Services CM: Staff Billed to Date: $4,311,251.66 % Billed: 81.9% Contract Days Used: 393 % of Contract: 211.3% Progress this period: • Installed Pumps and performed partial Pump Station start up on Nov 12th. • Pumps are now running. • Completed SCADA cabinet and pole installation • Contractor worked on Substantial Completion punch list items. • Met with PECD Director on cost savings, alternates and funding options for Max Road Sports Complex. • Prepared for Council award for Max Rd Sports Complex on November 25th. • Continued reimbursement requests to Developer. Planned activities for the period ending December 31, 2013: • Complete SCADA antennae installation and programming for pump station. • Conduct final inspection on Pump Station and SCADA. • Accept Operation and Maintenance manuals for pump station. • Conduct Substantial Completion Inspection of pump station. • Issue Certificate of Substantial Completion and Conduct Final Inspection. • Negotiate Construction Materials Testing proposal for Max Rd Sports Complex. • Obtain Council approval on Construction contract for Max Rd. Sports Complex. • Issue Notice to Proceed for Max Rd. Sports Complex. • Coordinate with Developer as needed. Project schedule: • Design: Detention: Nov. 2010 to July 2012; Sports Complex: to July 2013 • Construction: Detention: NTP Sept. 17, 2012, • Sports Complex: November/December 2013 Far Northwest Wastewater Treatment Plant Improvements Design Engineer: Binkley & Barfield Inc. Contractor: Industrial TX Corp CM: Binkley & Barfield Inc. Billed to Date: $716,852.89 % Billed: 92.1% Contract Days Used: 255 % of Contract: 92.1% Progress this period: • UV system inspection report discussed with the manufacturer. Parts will be replaced. Contacted CPE to record/investigate power to plant. • Conducted Final Completion Inspection. • Contractor worked on Final Completion punchlist items. • Redlines transferred to Engineer for Record Drawings.

adkb

Page 2 of 6

12/6/2013


Far Northwest Wastewater Treatment Plant Improvements

(cont’d)

Planned activities for the period ending December 31, 2013: • Contractor to complete punchlist. • Make final payment to contractor. • Close out project. Project schedule: • Design: February 2012 to December 2012. • Construction: February 18, 2013 Notice to Proceed. • Substantial Completion: September 6, 2013. Hatfield Basin Trunk Sewer Design Engineer: Freese & Nichols, Inc. Contractor: SJ Louis Construction of Texas Billed to Date: $1,648,482.75 Contract Days Used: 125

CM: Dannenbaum Engineers % Billed: 20.7% % of Contract: 41.7%

Progress this period: • Contractor proposed a solution for Magnolia Manhole connection, staff reviewed and responded. • Contractor removed and replaced pipe from Manhole #2 - #4, replaced concrete cap in Mary’s Creek at crossing. • Staff awaiting pipe grade information from Magnolia tie in to Manhole #2. • Continued placing 36 in. sanitary along Hatfield Rd., working northwards, near Hatfield Rd and Rockland Dr. • Crew hand tunneling under Corrigan Ditch Bypass. • Continued on Willowick segment, completed 21 in. sanitary section along Fite Rd., bored across Centennial Drive, Ashton Park Dr. and bore in progress across McLean Rd, • Coordinated with Parks staff regarding Park and trail on north end of Centennial Park. • Coordinated with area business – Clayton Funeral Home. • Coordinated with PISD regarding school bus routes and drop off locations. • Coordinated with TxDOT regarding FM 518 crossing and traffic control approval. Planned activities for the period ending December 31, 2013: • Continue 36 in. sanitary on Hatfield north to FM 518, with modified traffic control and short term intersection closures. • Complete the 36 in hand tunnel bore across Corrigan Bypass Ditch with casing • Initiate 36 in hand tunnel bore across FM 518. • Continue 21 in. sanitary on Willowick segment, completing bore across McLean, across north side of Centennial Park, south of Willowick subdivision. • Coordinate with Parks staff regarding Centennial Park restroom and grinder pump removal.

adkb

Page 3 of 6

12/6/2013


Hatfield Basin Trunk Sewer • •

(cont’d)

Contractor to maintain Hatfield roadway and provide safe route for school children. Coordinate with Emergency services regarding any short term road closures.

Project schedule: • Design: February 2011 to November 2012 (delayed due to PER delay). • Draft PER: November 2011 (Delayed due to Fite alternate route) • Final PER: March 2012 • Construction: ongoing. Trails at JHEC (formerly Dolores Fenwick Nature Center), Phase 2 Architect: Randall-Porterfield Architects, Inc. Progress this period: • Coordinated with boardwalk manufacturer and piling manufacturer to review sizing, methods piling and boardwalk system. • New pilings reviewed by Geotechnical and Structural Engineers. • Developed planting plan for KPB. • Coordinated with Parks and KPB staff on future solar lights and interpretive signage content for project. • Obtained proposal for environmental requirements of the CIAP grant funds. Planned activities for the period ending December 31, 2013: • Review geotechnical report and finalize or amend for alternate piling. • Coordinate with Brazoria County on grant funding for environmental work. • Conduct environmental work. • Coordinate with boardwalk vendor and review foundation construction with contractors for constructability. • Continue with Final Design and complete submittal of 90% plans. • Prepare to finalize PS&E package and finalize bidding schedule. Project schedule: • Design: September 2011 – October 2013. • Construction: Pending funding, partial grant funding. Pearland Parkway Extension Design Engineer: HDR Engineers, Inc. Progress this period: • TxDOT construction contract authorization provided, contracts are being executed. • Negotiating proposal for design of barrier fence. • Attended Shadycrest HOA meeting.

adkb

Page 4 of 6

12/6/2013


Pearland Parkway Extension (cont’d) • •

TxDOT continued reimbursements to City. Initiated property acquisition.

Planned activities for the period ending December 31, 2013: • Negotiate and enter into a design contract for barrier fence. • Continue property acquisition. • Coordinate with TxDOT and contractor regarding construction start date, and submit reimbursements. Project schedule: Design: February 2012 – August 2013. Letting: August 2013 Construction: October 2013 – September 2014 Max Road Reconstruction/Widening Design Engineer: Klotz Associates, Inc. Progress this period: • Coordinated with Avalon Terrace regarding OHE power, Hughes Ranch Rd signal and intersection. • Continued to review segments of roadway alignment. • Staff reviewed and commented on right of way mapping and parcel maps, Engineer to make corrections. • Coordinated with Engineer on draft Drainage report. • Engineer worked on 30% Plans and Drainage report and Project Manual for submittal to TxDOT. • Awaiting comments on Draft Categorical Exclusion, Public Meeting summary from TxDOT. • Submitted reimbursement requests to TxDOT. Planned activities for the period ending December 31, 2013: • Complete staff updating traffic model for planned conditions and roadway segments. • Engineer to submit for right of way mapping and parcel maps for TxDOT review. • Obtain comments on Environmental document from TxDOT • Finalize alignment and parcel maps for road right of way. • Coordinate with TxDOT and BDD4 on hydraulics and draft drainage report. Project schedule: Design: February 2013 – March 2014. Letting: July 2014 Construction: October 2014 – September 2015

adkb

Page 5 of 6

12/6/2013


Convention & Visitor’s Bureau Office Build Out Architect: Wilson Architectural Group Contractor: Triad Retail Construction CM: Staff Billed to Date: $127,826.68 % Billed: 74.9% Contract Days Used: 96 % of Contract: 106% Progress this period: • TV location required adjustment. Change order negotiated, work completed. • Selected window treatments, worked to obtain proposals. • Completed furniture punch list. Planned activities for the period ending December 31, 2013: • Obtain redlines for record drawings. • Contractor to submit O&M Manual. • Make final payment and close out contract. Project schedule: • Design: May 2013 – June 2013. • Construction: August 2013 – November 2013 Cullen Parkway Manhole Rehabilitation (Fite to FM 518) Engineer: Staff Progress this period: • Executed Change order for Wooten manhole rehabilitation. • Contractor completed Cullen Parkway and additional Wooten Rd location. • Public Works conducted Substantial Completion inspection. Planned activities for the period ending December 31, 2013: • Make final payment. Project schedule: • Construction: September 2013 – October 2013 Far Northwest Wastewater Treatment Plant Expansion Design Engineer: in Negotiation Progress this period: • Finalized negotiation with consultant. • Prepared proposal and professional services agreement for Council consideration and approval on November 25th. Planned activities for the period ending December 31, 2013: • Execute contract and Issue Notice to proceed. Project schedule: • Schedule: TBD

adkb

Page 6 of 6

12/6/2013


City of Pearland

Projects Department

Monthly Projects Update November 27, 2013 Bailey Rd (Veterans to FM1128) Business Center Drive Centennial Park Phase 2 Cowart Creek Diversion Project McHard Road 2nd Outfall Old Alvin Road Water Line Shadow Creek Ranch Park SH35 Water Line – FM518 to Magnolia Trail Connectivity Phase 2 Twin Creek Regional Lift Station

Prepared by: Cara Davis

For Distribution to City Council


Bailey Road (Veterans to FM 1128) Design Engineer: CDM Smith (formerly Wilbur Smith Associates) Original Contract Amount: $1,710,346.00 Current Contract Amount: $2,242,460.00 Billed to Date: $ 1,691,173.50 % Billed: 75.4 Plan Status: 75% Complete Progress this period: • Held design kickoff meeting with CDM Smith and subconsultants. • CDM working to schedule Design Concept Conference with TxDoT and putting together the documentation used in design of current plans • Environmental consultant has drafted a scope document in preparation for Environmental Assessment (EA) submittal Planned activities for the period ending December 31, 2013: • • •

Revise roadway plans for drainage, FM 1128 design modifications, and mixed use path. Prepare alternative routes for EA. Start EA document preparation. Schedule DCC with TxDOT for LGPPP.

Project schedule: • • • •

Consultant Selection – 2nd thru 3rd Quarter 2008. Design (Completed) – 3rd Quarter 2008 thru 2nd Quarter 2010. Redesign/Environmental – 4th Quarter 2013 thru 1rd Quarter 2015. Construction – Scheduled for Fiscal Yr 2015

Business Center Drive Design Engineer: Freese & Nichols Contractor: Lazer Construction Company As of October 25, 2013 Original Contract Amount: $3,474,998.80 Current Contract Amount: $3,482,136.31 Billed to Date: $3,401,672.58 Contract Days Used: 355

CM: Klotz & Associates

% Billed: 97.69 % of Contract Days: 131.48

Progress this period: • •

Continued work on punchlist items. TDLR inspection was scheduled but was canceled due to weather.


Business Center Drive (cont….) Planned activities for the period ending December 31, 2013: • • •

Complete punchlist items and final cleanup. Hold TDLR ADA and Final Completion inspections Close out contract.

Project schedule: • • • •

Consultant Selection – 2nd thru 3rd Quarter 2008. PER – 3rd Quarter 2008 thru 2nd Quarter 2010 Design – 2nd Quarter 2011 thru 3rd Quarter 2012 Construction – 4th Quarter 2012 thru 3rd Quarter 2013.

Centennial Park Phase 2 Design Engineer: Clark Condon Associates Original Contract Amount: $194,882.00 Current Contract Amount: $194,882.00 Billed to Date: $21,684.00 % Billed: 11.1 Plan Status: 15% Progress this period: • Submitted design plan and survey information to Dannenbaum for drainage study related to the Mary’s Creek floodway. • Engineer will to continue to work on elements of the park other than structures, which are directly impacted by the floodway/floodplain. Planned activities for the period ending December 31, 2013: • Continue to work on elements of the park other than structures, which are directly impacted by the floodway/floodplain • Work with Dannenbaum Engineering to determine the extent and a resolution to the floodway issue. Project Schedule: • • • • • •

Consultant Selection – Complete Schematic Land Plan & Programming – June 2013 to January 2014 Design Development – January 2014 to February 2014 Construction Documents – February 2014 to April 2014 Bid/Award – April/May 2014 Construction – May 2014 to December 2014


Cowart Creek Diversion Project – Detention Pond & Diversion Ditch Design Engineer: JKC & Associates, Inc. Contractor: Haddock Construction Co. As of November 25, 2013 Original Contract Amount: $378,618.00 Current Contract Amount: $0 Billed to Date: $0 Contract Days Used: N/A

CM: N/A

% Billed: 0 % of Contract Days: N/A

Progress this period: •

DD4 held pre-construction conference at their offices and issued the NTP for Construction to start in January 2014.

Planned activities for the period ending December 31, 2013 • No planned activity. Project Schedule: •

Diversion Ditch: Construction: 3rd Quarter 2011 – 2nd Quarter 2014

McHard Rd 2nd Outfall Design Engineer: Huitt-Zollars, Inc. Original Contract Amount: $61,600.00 Current Contract Amount: $61,600.00 Billed to Date: $0 Plan Status: 0%

% Billed: 0

Progress this period: • Held meeting with BDD4 regarding outfalls to Clear Creek. Defined an agreed solution to the issue and implementing that into the planning Planned activities for the period ending December 31, 2013: • Continue initial design and prepare Preliminary Drainage report. • Hold monthly progress meeting Project Schedule: • Design – October 2013 to December 2013 • Bid/Award – January/February 2014 • Construction – 2nd Quarter to 3rd Quarter 2014


Old Alvin Road Water Line Design Engineer: Charles D. Gooden Consulting Engineers, Inc. Contractor: SER Construction Partners, LLC CM: LJA Engineering As of October 25, 2013 Original Contract Amount: $3,398,483.00 Current Contract Amount: $3,398,483.00 Billed to Date: $2,679,205.00 % Billed: 78.84 Contract Days Used: 119 % of Contract Days: 66.11 Progress this period: • • • • •

Elevated water line crossing at Town Ditch completed. This completes installation of all 20” water line. Completed pressure testing of the lines. Continued chlorination of lines. Ran Bacteria culture samples Nov. 27 Restoration activities of ROW and affected pavement is in progress. Started making connections to new line.

Planned activities for the period ending December 31, 2013: • • •

Continue chlorination of the line and connections upon receipt of passing bac-T tests. Continue restoration activities. Hold substantial completion inspection and begin project closeout procedures.

Project Schedule: • • • •

Consultant Selection – 4th Quarter 2010. Design/Acquisition – 1st Quarter 2011 thru 1st Quarter 2013 Bid: 1st Quarter 2013. Construction: 2nd Quarter 2013 – 4th Quarter 2013

Shadow Creek Ranch Park Design Engineer: Cobb Fendley, Architect: Randall Porterfield Original Contract Amount: $649,748.50 Current Contract Amount: $649,748.50 Billed to Date: $489,454.23 % Billed: 75.3 Plan Status: 90% Progress this period:


• • •

Received letter of No Objection from HCFCD regarding drainage report review. USACE review is still in progress. Continued site plan development and structural design for buildings. Plans submitted to COP permitting for building permit review.

Planned activities for the period ending December 31, 2013: • Complete site plan development and structural design for buildings. Address any comments from building permit review and acquire permit. • Prepare for bidding pending receipt of USACE permit • Hold monthly progress meeting Project Schedule: • • • • •

Consultant Selection – Complete Schematic Land Plan & Programming – October 2012 to April 2013 Design – April 2013 to December 2013 Bid/Award – January/February 2014 Construction – March 2014 to March 2015

SH35 Water Line – FM518 to Magnolia Design Engineer: Brown & Gay Engineers, Inc. Original Contract Amount: $155,200.00 Current Contract Amount: $155,200.00 Billed to Date: $109,835.75 Plan Status: 60%

% Billed: 70.7

Progress this period: • 60% plan review comments returned to the engineer. • Began the easement acquisition process Planned activities for the period ending December 31, 2013: • Continue plan design and reviews. • Continue coordination adjacent utilities. Project Schedule: • • • •

Consultant Selection – Complete Design – June 2013 to December 2013 Bid/Award – January/February 2014 Construction – March 2014 to October 2014


Trail Connectivity Phase 2 Design Engineer: Clark Condon Associates Original Contract Amount: $89,844.50 Current Contract Amount: $89,844.50 Billed to Date: $31,075.00 % Billed: 34.6 Plan Status: 20% Progress this period: • Submitted design plan and survey information to Dannenbaum for drainage study related to the Mary’s Creek floodway • Schematic design of the trail has been submitted to the City for review. Planned activities for the period ending December 31, 2013: • Finalize schematic design and move the design development phase • Work with Dannenbaum Engineering to determine the extent and a resolution to the floodway issue. Project Schedule: • • • • • •

Consultant Selection – Complete Schematic Land Plan & Programming – June 2013 to October 2013 Design Development – November 2013 to January 2014 Construction Documents – January 2014 to February 2014 Bid/Award – February/March 2014 Construction – March 2014 to September 2014

Twin Creek Regional Lift Station Design Engineer: IDS Engineering Group (formerly Pate Engineers, Inc.) Contractor: E.P. Brady, Ltd. CM: City of Pearland, Cara Davis As of October 25, 2013 Original Contract Amount: $2,371,573.35 Current Contract Amount: $2,371,547.74 Billed to Date: $1,660,656.56 % Billed: 70.11 Contract Days Used: 475 % of Contract Days: 100.42 Progress this period: • •

Paving sub has mobilized on site and begun subgrade preparation for reclaim activities and asphalt overlay. Contracting in progress for the demolition of the old Twin Creek LS building and site.


Twin Creek Regional Lift Station (cont….) Planned activities for the period ending December 31, 2013: • • • •

El Dorado will complete asphalt reclamation and placement activities. Peltier will complete site elements of the LS. EP Brady will complete site restoration elements. Begin project closeout procedures.

Project Schedule: • Consultant Selection – 4th Quarter 2010 • PER – 1st Quarter 2011 thru 3rd Quarter 2011 o Design – 3rd Quarter 2011 thru 2nd Quarter 2012 • Construction – 3rd Quarter 2012 thru 4th Quarter 2013


City of Pearland

Projects Department

Monthly Projects Update November 27, 2013 Highway 35 Reconstruction Intelligent Traffic System Country Place Bed and Banks Permit Alice Street Plant

Prepared by: Skipper Jones For Distribution to City Council


Highway 35 Reconstruction Design Engineer: S&B Engineers & TxDoT, Contractor: Triple B Construction Billed to Date: $ Contract Days Used:

CM: TxDoT % Billed: % of Contract Days:

Completion Date: per contract Oct. 2012 Projected Completion Date: January 2014 Progress this period: •

Pavement o Northbound lanes opened to traffic November 11th o Contractor is still working on curbs and ADA ramps throughout the project o Most of the sidewalks are complete, remaining gaps are directly associated with incomplete ramps and concrete riprap is now complete o Northbound grinding has been completed but in the next few weeks grinding will begin in the southbound lanes. This will necessitate a rolling one lane closure along the southbound lanes to allow for this work once it begins Bridges o Bridge medians are schedule to begin the week after Thanksgiving. The sub will provide two crews to expedite the work. o Also fabrication of pedestrian hand rails for the bridges are nearly completed and are scheduled to begin installation once the bridge median/ sidewalk work is completed Traffic Signals o Signals on the north end of the job east side remain incomplete. • Contractor’s plan in September was to have all signals completed and operational by the end of October. This has not occurred, signals on sides streets are not complete and none of them are operational at this time. Median work o Contractor has installed concrete barrier along the median work area and has scheduled excavation of the asphalt and base from those areas although no work has been started as of this report due to weather delays. o Landscaping work is scheduled to begin immediately after Thanksgiving with the installation of irrigation taps and meters Contractor is now projecting a mid-January completion for the project. It should be noted however, that this projection was made before the rain during the last week of November.


Intelligent Traffic Management System Design Engineer: AECom and Wilber Smith Contractor: Third Coast Services CM: in House Billed to Date: $ 1,445,158 % Billed: 37 Contract Days Used: 262 57% of Contract Days: Progress this period: •

Processed & Paid 10th Contractor Pay Estimate in amount of $23,205

Continue to replace controllers in existing cabinets and tying in new camera systems. Installing upgraded equipment in each cabinet as this process progresses.

Continuing to work on installation of underground conduit and pull boxes throughout the project limits

Mobilization for overhead fiber installation has been delayed again. Contractor has assured the City that this is not a scheduling problem.

Beginning work to take fiber into the server at PSB and from there across Cullen and into Hillhouse TOC facility. This has been slightly delayed as well

Coordinating fiber installation with site plans for fire station #3 is now complete and a full plan has been devised

Electrical Subcontractor has begun work at water tower locations preparing for installation of Access Point radios

Planned Activities for period ending December. 30, 2013 •

Contractor projects that fiber installation will now begin in December

Controller change out will continue along with installation of other equipment within the controller cabinets

Plan to execute a Change Order to add two additional cabinet replacements, totaling just under $20,000 and will include preparations for the inclusion of the Garden Road signal into the integrated network

Continue work installing wireless communications systems o Work to begin at water towers. Contractor must find and contract with a certified climbing installer or certify his own personnel for work at heights. City Safety personnel will inspect climb equipment prior to tower work. o Electrical work at towers will continue

Project Schedule • • •

Notice to proceed issued January 7th, 458 days to Substantial completion, April 10, 2014 548 days to final completion and acceptance, July 9, 2014


Bed and Banks Permit Application Design Engineer: Cobb Fendley Contractor: N/A CM: In House Billed to Date: $6,840 68% Billed: Contract Days Used: % of Contract Days: Progress this period: • • • • •

Application was executed and submitted to TCEQ in late July, 2013 TCEQ provided response questionnaire requesting additional information. This indicates that the application is in the review process. They have determined that a water conservation plan is required for the irrigation system. Cobb Fendley met with CPMCA to discuss and obtain information on the planned system. Staff have responded to those items required to be furnished by the city, including an application fee in the amount of $412 and all indications are that the completed response will be returned by Dec. 9 Based on the requested additional information there appear to be no problems or delays at this time.

City of Houston Connection (W42051) Alice Street Water Plant Design Engineer: Camp Dresser & McKee, Inc. Contractor: Industrial Tx Corp CM: LJA Engineering Original Contract Amount: $6,846,000.00 Revised Contract Amount: $7,524,030 Billed to Date: $7,524,030 (thru 7/15/13) Percent Billed: 100% Original Contract Time: 360 days Revised Contract Time: 429 days Contract Days Used: 515 (thru 11/25/2011) Percent Contract Used:120.0% NTP: June 28, 2010 Progress for period ending November 2013: • Final punch list items completed • Engineer preparing Record Drawings on Pipeline and plant

Planned progress for period ending December 2013: • Received Record Drawings from Engineer • Close out project.


City of Pearland

Projects Department

Monthly Projects Update November 26, 2013 McHard Road 16� Water Line Westchester Sidewalk and Drainage Walnut Lift Station McHard Road Extension City Hall Complex Renovations Lower Kirby Urban Center Regional Detention Regency Park Subdivision Paving and Drainage

Prepared by: Jennifer Lee

For Distribution to City Council


McHard Road 16” Water Line and Roadway PER Progress this period: • • • • •

• •

Attended monthly progress meeting. CL Davis is continuing to prepare the easements. This work is running a little behind schedule. The parcel count has increased to 28. The Modern Green Ivy Development is not progressing as fast as earlier presumed, but it has been determined that the current proposed infrastructure will be sufficient for Phase I of the development. We are proceeding with the plan to break the waterline project up into multiple phases. Phase I will extend from Business Center Drive to Cullen and from Mykawa to SH 35. Both areas are already owned by the city. This phase should be ready to advertise by the beginning of the second quarter of 2014 with construction starting mid to late May. TCE will need to be acquired in some areas along the alignment. The Utility Coordination meeting was held on November 19. Several Utility Companies attended and/or submitted their as-built drawings for the area. Utility conflicts were identified and work-around solutions were discussed.

Planned activities for the period ending December 31, 2013: • • • •

Prepare and attend a monthly progress meeting. Prepare for and attend a utility coordination meeting with TxDOT which is tentatively set for December 3. Began BNSF approvals. Continue surveying coordination.

Project Schedule: • • •

Project design is scheduled for twenty-four months with scheduled completion February 2014. Waterline Project will be divided into two phases, the first phase will bid in April 2014. Design is on schedule.

Westchester Sidewalks and Drainage Project Design Engineer: GC Engineering Contractor: Lazer Construction Company, Inc. Contract Amount: $381,206.72 Change Orders to Date: $5,001.00 Adjusted Contract Total: $386,207.72 Billed to Date: $279,300.01 Contract Duration: 60 Days (Substantial) Contract Days Used: 147 Contract Days Extension: 45 Additional Rain Days: 9 Page 2 of 5

% of Increase: 1.31 % Billed: 72 % of Contract Days: 140

12/6/2013


Westchester Sidewalks and Drainage Project (cont.) Progress this period: • • • • • •

Attended progress meeting. Contractor has completed the installation of all storm sewer pipe. Contractor has completed the installation of all inlets and surrounds. Contractor has installed 80% of the driveways. Contractor has installed 90% of sidewalks. Contractor is working six days a week to complete project.

Planned activities for the period ending December 31, 2013: • • •

Complete the installation of sidewalks. Begin grading and restoration. Close out project.

Walnut Street Lift Station Progress this period: • • • • •

Attended the monthly progress meeting. Odor logger has been installed to determine an odor generation baseline. Results will determine what, if anything will be required for odor control at this location. Public Works is revising the specifications for the lift station and sanitary sewer lines. An agreement has been reached with the property owner for the acquisition of the additional property to extend the footprint of the lift station. GC Engineering is addressing 60% comments from staff. Should have all comments answered by second week in December along with 90% plans.

Planned activities for the period ending December 31, 2013: • • •

Receive 90% plans. 100% plans should be received three weeks after 90 % comments addressed. Set up TRC meeting to be held in December.

Project Schedule: • • •

The design of the lift station is behind schedule. Construction is expected to begin first quarter of 2014 The construction phase is expected to take five months.

Page 3 of 5

12/6/2013


McHard Road Extension Progress this period: • •

Attended progress meeting. Continuing to work with Freese and Nichols on the design scope, sub-consultant scope, and fees.

Planned activities for the period ending December 31, 2013: • • •

Continue negotiations with Freese and Nichols to finalize the scope, proposal and fee. Prepare and submit AR for Design Consultant for Council consideration and approval Continue with the preliminary discussions and submittal of documents to TxDOT.

Project Schedule: • •

Design to begin January 2014. Construction to begin September 2016.

City Hall Complex Renovations Progress this period: • •

Met with Hall Barnum Lucchesi Architects to discuss the scope of the project. Received a proposal for Hall Barnum Lucchesi for pre-design services which will include programming, mechanical and structural assessment and recommendation and a conceptual floor plan.

Planned activities for the period ending December 31, 2013: • •

Complete negotiations with Hall Barnum Lucchesi Architect for the scope, proposal and fee. Begin programming meetings with department heads.

Project Schedule: • •

Pre-design should be complete the second quarter 2014 Construction to begin third quarter of 2014.

Page 4 of 5

12/6/2013


Lower Kirby Urban Center Regional Detention Progress this period: • •

The City and the Management District are working on an agreement for the use of the TxDOT ditch. Continued negotiating the scope and fees.

Planned activities for the period ending December 31, 2013: • • •

Complete negotiations with LJA Engineering for the scope, proposal and fee. Begin surveying project limits. Begin coordination with HCFCD and TxDOT.

Project Schedule: • •

Design to begin first quarter 2014 Construction to begin third quarter of 2014.

Regency Park Subdivision Paving and Drainage Progress this period: • • •

Reviewed the drainage issues and complaints for this subdivision. Made a site visit to investigate the existing conditions. Began negotiating the scope and fees with Binkley and Barfield Consulting Engineers to provide preliminary engineering services for the paving and drainage project.

Planned activities for the period ending December 31, 2013: • • •

Complete negotiations with Binkley and Barfield Consulting Engineering for the scope, proposal and fee. Prepare a contract for preliminary engineering services for Binkley and Barfield Consulting Engineers to assess and recommend improvements to the paving and drainage for the subdivision. Plan and attend the Kickoff meeting for the Regency Park Subdivision Paving and Drainage Project.

Project Schedule: • •

Project to begin December 2013 Construction to begin second quarter of 2014. Page 5 of 5

12/6/2013


City of Pearland

Projects Department

Monthly Projects Update November 22, 2013 Garden Road Signal West Oak / Somersetshire Lift Station Retirement Fire Station 3 Fire Station 2 Fite Road (LGPP) SH35 Quiet Zone Barry Rose Wastewater Plant Longwood Wastewater Plant

Prepared by: Cuong Le

For Distribution to City Council


Garden Road Signal (Design) – TR1306 Design Engineer: EPIC Engineering Original Contract Amount: $44,376.50 Current Contract Amount: $44,376.50 Billed to Date: $26,641.20

% Billed: 67

Progress this period: •

100% plans submitted to TxDOT for review.

Planned Activities for period ending December 2013: • •

Receive TxDOT’s comments and finalize drawings. Advertise project for bid.

Project Schedule • • •

Design NTP issued May 28, 2013 Bid – January 2014 Signal in operation by April 2013

West Oak & Somersetshire Lift Station Retirement (Preliminary Engineering) – WW1303/1304 Design Architect: ARKK Engineers, LLC. Original Contract Amount: $16,180.00 Current Contract Amount: $19,304.00 Billed to Date: $ 17,465.00

% Billed: 90.47

Progress last period: • PER finalized and distributed. • Engineer submitted design proposal for staff to review. Planned activities for the period ending December 2013: • Finalize design scope and proceed with design. • Coordinate with utility billing on water meter replacement if necessary. Project Schedule: • Notice to Proceed – June 3, 2013 • Final PER – October 2013 • Start design – December 2013


Fire Station 3 (Design) Design Architect: Brown Reynolds Watford Architects, Inc. Original Contract Amount: $265,090.00 Current Contract Amount: $265,090.00 Billed to Date: $ 185,645.83 % Billed: 70.0 Progress last period: • Confirmed current design to meet some Centerpoint’s SCORE program. • Staff’s 90% plan review comments submitted to Architect. • Adapted City’s standard bid documents to accommodate for Sealed Competitive Proposal process and to provide for this use in the future. Planned activities for the period ending December 2013: • Complete right of way agreement. • Submit Centerpoint utility relocation agreement. • Finalize competitive seal proposal package. • Submit 90% specification comments to Architect. • Architect submits 100% plans and specifications for City review. Project Schedule: • Council Award: February 11, 2013 • Notice to Proceed – February 25, 2013 • 100% Plans & Spec – November 2013 • Bid – January 2014

Fire Station 2 (Design) Design Architect: Brown Reynolds Watford Architects, Inc. Original Contract Amount: $211,465.00 Current Contract Amount: $211,465.00 Billed to Date: $ 0.0 % Billed: 0.0 Progress last period: • Notice to Proceed issued for site analysis study October 29, 2013. • Council approved design contract November 25, 2013. Planned activities for the period ending December 2013: • BRW submits final site analysis report. • Issue Notice to Proceed for design contract. • City to review report and select site. • Start right of way acquisition. Project Schedule: • Council Award: November 25, 2013


Fite Road – LGPP (Design) – TR1202_______________________________ Design Engineer: Cobb Fendley & Associates Original Contract Amount: $513,560.18 Current Contract Amount: $513,560.18 Paid to Date: $ 0

% Billed: 0%

Progress this period: • • • • • •

Topo file completed and ready. Two schematics of road now available. Engineer completed turning movement counts for McLean and Veterans. Met with TxDOT to obtain drainage requirements. TxDOT reviewing contract amendment for additional environmental work. Data collection for environmental work already started.

Planned Activities for period ending December 2013: • • • •

Engineer submits Traffic Signal Warrant Analysis. Submits geotech report. Hold DCC meeting with TxDOT. Execute amendment with environmental consultant.

Project Schedule • •

Design NTP issued for August 12, 2013. TxDOT Kick Off Meeting August 26, 2013.


Quiet Zone Crossing and Median Improvements at Broadway at BNSF Railway (Construction) – TR1002 Design Engineer: ARKK Engineers, LLC. Contractor: General Contractor Services, Inc. Original Contract Amount: $141,240.00 Current Contract Amount: $141,240.00 Billed to Date: $122,960.00 Contract Days Used: 68

CM: City of Pearland

% Billed: 87.1 % of Contract Days: 74.7

Progress last period: • Completed substantial walk through November 4, 2013. • Contractor completed substantial punchlist. • Conducted final walk through November 21, 2013. • Final punchlist completed. • Railroad installed hot-mix asphalt transition. • TxDOT installed pre-emption conductors to new traffic signal box. • Project completed under budget and early. Planned activities for the period ending December 2013: • Railroad to complete concrete panel installation without road closure for west bound FM 518. • After TxDOT completes signal at SH 35 and FM 518 intersection, City able to submit request to declare three crossings as official Quiet Zone. • Balancing change order with close out meeting. Project Schedule: • Received TxDOT permit March 11, 2013. • Advertisement scheduled for April 4 and 10 • Mandatory Pre-bid: April 17, 2013 • Bid: April 25, 2013 • Council Award: May 13, 2013 • BNSF Contract: August 8, 2013 • Pre-Construction: August 22, 2013 • Notice to Proceed: September 16, 2013 • Substantial Completion: November 4, 2013


Barry Rose Wastewater Treatment Plant (Construction) – WW1004________ Design Engineer: Binkley & Barfield Contractor: JTR Construction, Inc. Original Contract Amount: $3,143,020.00 Current Contract Amount: $3,060.929.20 Paid to Date: $ 3,060.929.20 Contract Days Used: 384

CM: Binkley & Barfield

% Billed: 100% % of Contract Days: 100%

Progress this period: •

Project is complete and is in one year warranty period.

Planned Activities for period ending December 2013: • •

Close out Construction Management contract after one year walk through. One year walk through scheduled for March 18, 2014.

Project Schedule • • • • • • • •

Design of improvements complete November, 2011. Bid Phase January, 2012. Award Construction Contract March 12, 2012. NTP issued for March 26, 2012. Substantial Completion April 18, 2013 – Completed on time. Substantial punch list completion verified June 3, 2013. Final Walk through June 19, 2013. Warranty walk through March 18, 2014.


Longwood Wastewater Treatment Plant (Construction) – WW0902________ Design Engineer: Malcolm Pernie / ARCADIS Contractor: RP Constructors, Inc. CM: Arcadis/Malcom Pernie Original Contract Amount: $2,569,160.00 Current Contract Amount: $2,446,049.00 Billed to Date: $2,446,049.00 % Billed: 100 Contract Days Used: 417 % of Contract Days: 114 Progress this period: •

Project is complete and is in one year warranty period.

Planned Activities for period ending December 2013: • •

Close out Construction Management contract after one year walk through. One year walk through scheduled for May 20, 2014.

Project Schedule • • • • • • • •

Design NTP issued May 2, 2011 Bid April 2012 - Early by one month Pre-Construction Meeting April 20, 2012 Contractor NTP April 30, 2012 Scheduled Substantial Completion May 31, 2013 Substantial Completion June 24, 2013 Final Walk through August 12, 2013 Warranty walk through May 20, 2014.


City of Pearland

Projects Department

Monthly Projects Update December 2, 2013 Irrigation Improvements on McHard Road at Countyplace Blvd.

Prepared by: Jameson Appel For Distribution to City Council


Irrigation Improvements for McHard Road at Countryplace Blvd. (Construction) Design Engineer: Huitt-Zollars, Inc. Contractor: Hydrozone Landscape Corporation Original Contract Amount: $ 90,615.00 Current Contract Amount: $72,919.31 Billed to Date: $ 7,880.90 % Billed: 10.8 Contract Days Used: 22 % of Contract Days: 73.3 Plan Status: 100% Complete

Project Schedule o 1st Advertisement 7/17 o 2nd Advertisement 7/25 o Pre-Bid 7/25 o Bid Opening 8/1 o Construction 3rd Quarter 2013 o AR for Council set of 9/9/13 o Substantial Completion Date November 12, 2013 o Final Completion Date November 27, 2013

Progress this Period: • • •

18 of 37 zones completed North side of median irrigation zones completed Trenching completed on both north and south side of median

Planned activities for the period ending December 31, 2013: • • •

Install remaining irrigation zones Substantial walk though, create punch list Complete substantial walk though punch list items

Current Utility Relocations Fire/EMS Station 3 •

CPE electric relocation plan approved waiting for plat of property to be able to create blanket easement for CPE


November Monthly Report 2013