PAYMENT

COMPLETE VERIFICATION ENROLLMENT PLAN REVIEW APPLICATION

CMFNH Receive Application Collect background project  information

DEVELOPER

HERS

Contract wtih  Developer Collect initial project  details

Apply Meet  CMFNH qualification and hire HERS rater

Plans Review Initial comparison between Title 24 documentation and developer  blueprints

Enrollment Register project  detials and team

Energy Assessment Prepare required Title 24  compliance documents and  calculations

Dry Wall Installation Before drywall is hung, coordinate  wtih HERS rater to verify building  measures.

Collect Project Documents &  Distribute Incentives Collect all final forms, distribute  recalculated incentives

Contract wtih  Developer Collect initial project 

Verify HERS measures HERS rater visits project to  document HERS measures  installed

Collect Documents & Reports Compare measures installed  with initial plans

Recalculate incentive Based on "as‐built" proejct 

ENERGY CONSULTANT

Collect Initial incentive CMFNH progam pays  half of total incentive

Update Documentation Consultant updates Title 24  compliance documentation with  "as built" data

Request for Incentive Agree to and sign RFI based on  "as‐built" project

Project Built Receive incentive check  from CMFNH

HERS Rating  Complete Receive incentive 

Project complete Receive incentive check