Transportation Harbour View Area Signal Improvements This project will provide upgrades to existing equipment, or new traffic equipment where necessary, and signal coordination along the College Drive, Harbour View Boulevard, and Hampton Roads Parkway corridors. This project is being funded with Federal grant funding.
FY 17 $925,000
FY 18 $0
FY 19 $0
FY 20 $0
FY 21 $0
FY 22-26 $0
Total $925,000
Operating Costs: The project will not have an operational impact on the City.
Rail Crossing Improvements This project provides for improvements to the quality of a select group of at-grade crossings while working collectively with different railroad companies. Asphalt or wood flange crossings at Liberty Street and Nansemond Parkway would be replaced with concrete panel sections resulting in a smoother ride and reducing traffic backups due to vehicles slowing in order to traverse the crossing. Elevated crossings at Suburban Drive, Wellons Street and Harvest Drive would be replaced with concrete panels and have additional improvements made to reduce or eliminate the steep approaches to the rail crossing. FY 17 $65,600
FY 18 $140,400
FY 19 $0
FY 20 $156,800
FY 21 $57,000
FY 22-26 $418,200
Operating Costs: The project will not have an operational impact on the City
264
Total $838,000