Transportation . Shoulders Hill Road Widening City Council Goal - Transportation The project provides for the widening of Shoulders Hill Road from approximately 0.3 miles south of Bridge Road to Pughsville Road. The total length is approximately 1.33 miles. The project will widen the corridor from two lanes to a four lane divided roadway with turn lanes, sidewalks, multi-use path and stormwater improvements. The project will continue the roadway section as established at the recently completed Nansemond Parkway/Shoulders Hill Road intersection and is currently under design at the Bridge Road/Shoulders Hill Road intersection. The project is anticipated to be funded with 50% State Revenue Share funds and 50% local funds. FY 20 $0

FY 21 $0

FY 22 $0

FY 23 $0

FY 24 $0

FY 25-29 $46,000,000

Total $46,000,000

Operating Costs: The project will not have an operational impact on the City.

Nansemond Parkway/Wilroy Road Flyover City Council Goal - Transportation The project will provide for a flyover of Nansemond Parkway over the Commonwealth Railway at the intersection of Wilroy Road and Nansemond Parkway. The project will alleviate the conflict between vehicular and rail traffic at this intersection and greatly improve safety. Previous funding of $20.5M has been approved for this project. Federal funds of $8.1M are programmed in FY20, FY21 and FY22.

FY 20 $4,583,162

FY 21 $1,430,050

FY 22 $2,079,488

FY 23 $0

FY 24 $0

FY 25-29 $0

Total $8,092,700

Operating Costs: The project will not have an operational impact on the City.