Building DePauw updates on campus construction progress

compiled by F.A. Wilhelm Construction Company

It’s exciting to know the students will soon return to use the pool, and we hope they enjoy the new fields and parking lot for the first home football game in September. — Bill Spitler Project Manager

ATHLETICS CAMPUS

This football season, as the Tigers take the field, they will play with new, highperformance synthetic turf beneath their cleats. This month, teams start practicing on the Blackstock Stadium and Multisport Stadium fields featuring the bold DePauw logos and University colors. APRIL 2013

Excavated football field

AUG. 2013 JUNE 2013

Started running track

Complete track surface Soccer field turf installation

TIMELINE

FEB. 2013

DEC. 2013

JULY 2013

Turf field completed at Blackstock Stadium

F.A. Wilhelm Construction Company

TRAFFIC Watch for traffic instructions around Hanna Street near the Athletics Campus this month.

EVENTS FIRST GAMES AT THE NEW FACILITIES

F.A. WILHELM CONSTRUCTION COMPANY

LILLY CENTER

With the new roof being completed over the natatorium, the next step of the renovation is preparing the pool for swim season. Scaffolding that covered the area has been dismantled to expose the new structure, and the pool will be open when students return to campus. APRIL 2013

AUG. 2013

Removed natatorium roof

Saturday, Sept. 14 1 p.m. Field Hockey vs. Kenyon Blackstock Stadium

TIMELINE

Saturday, Sept. 21 1 p.m. Football vs. Wittenberg Blackstock Stadium

JUNE 2013

NOV. 2012

New roof and exterior walls Turn on hot water OCT. 2014

Began erecting structural steel frame JULY 2013

New natatorium roof and ceiling Outside utilities installed Structural steel erection began First concrete floor slab poured F.A. WILHELM CONSTRUCTION COMPANY