FEASIBILITY

Development Status: Peer = 3 Land: 70.000m2 Construction Cost: 800 $ / m2 Sales Price: 2,300 $ / m2 Project Completion Time: 24 Months Recycling of Money: 20Ay Profit Rate: 64% Construction Area: 70,000 x 3 = 210.000m2 Construction Cost: 210.000m2 x 800 $ = $ 168 million Sales: 210.000m2 x 2300 $ = $ 483 million Cost: Construction Cost + Land + (Project + taxes) = $ 168,000,000 + $ 125,000,000 + $ 2,000,000 = $ 295,000,000 Profit (before tax) = $ 483,000,000 - $ 295,000,000 = $ 188,000,000