PHASE 2

PHASE 1

Demolish industrial units

Construct residential and culture hub. Regenerate green space

PHASING

Demolition & phasing 10

Industrial buildings which has no environmental value will be demolished to be replaced through regenerating the urban form. An accumulated area of 48367 square metre will be demolished which takes up to 18 months to comply with safety environmental precautions and not damage the existing hardscape. A series of 3 phases follows, to construct the overall master plan in a manner to sustain financial flow.