• Poured grid 7-11.5 on the 2nd deck on Wednesday 10.14.09.
• Continue to install MEP piping in the crawlspace.
• Stripped the forms on the 2nd deck grid 11.5-16.
• Post tension stressing for grid 7-11.5 on the 2nd deck is complete.
• Installing remainder of the reinforcing, post tensioning cables, and pans for the second floor deck.
• Installing MEP rough-in at the remainder of the 2nd floor deck.
• Placed the remainder of the 2nd floor deck grid 1-7 on Thursday 10.15.09.
• Framing, forming, and reinforcing for the 3rd deck grid 11.5-16 is ongoing.
• MEP rough-in for the 3rd deck has started.