Texas A&M University Agriculture Headquarters Weekly Report: 10/12/09-10/16/09

North View

Shoring for 3rd Floor Deck @ HQ

Bottom of 2nd Floor Deck

Pouring Grid 1-7 on 2nd Deck

Post Tension Cables on 2nd Deck

Reinforcing for the second floor deck.

Poured grid 7-11.5 on the 2nd deck on Wednesday 10.14.09.

Continue to install MEP piping in the crawlspace.

Stripped the forms on the 2nd deck grid 11.5-16.

Post tension stressing for grid 7-11.5 on the 2nd deck is complete.

Installing remainder of the reinforcing, post tensioning cables, and pans for the second floor deck.

Installing MEP rough-in at the remainder of the 2nd floor deck.

Placed the remainder of the 2nd floor deck grid 1-7 on Thursday 10.15.09.

Framing, forming, and reinforcing for the 3rd deck grid 11.5-16 is ongoing.

MEP rough-in for the 3rd deck has started.