• 75% complete on forming, reinforcing, and pouring pile caps for the HQ Building • Installed crawlspace drain and sump pit • Completed two pile caps for the cistern canopy • Started backfilling crawlspace at pile capes • Excavate and pour footings for Visitor’s Center crawlspace walls • Installed sleeve for wall penetrations • Site fills and grading ongoing • Installing 30” storm sewer run-out to inlet boxes North View Pile Cap Reinforcement Cistern Pile Cap