Mark Twain Riverfront Park Revitalization

Page 63

Appendix I: Cost Estimate

Estimated Cost (000's)

Program Budget costs for the project were developed through consultation with Streeter Associates and are represented in today’s costs. Estimated costs were developed based on conceptual plans and discussions with Don Rottmann of Streeter Associates. Due to the highly conceptual level of plans and the current stage of design development, a 20% contingency was applied for items that have not yet been detailed in the plans. The costs have been provided to provide an order of magnitude feeling for a project budget. Based on the cost study the project budget is suggested at $5.6 million.

Demolition and Clearing 475 General Site work (Landscaping, paths, etc) East of Clemens Center Parkway

600

West of Clemens Center Parkway Pavilion Construction from existing Building

700

Pavilion Patio and Observation Deck

445

New Amphitheater

1,200

Access to River at East end

290

Path at River bed and Kayak tie up

280

Contingency @ 20%

934

680

Suggested Project Budget: 5,604