Partnering Magazine September/October 2015

Page 16

BEST PRACTICES

Disputes Cost Money CONSTRUCTION DISPUTES ARE COSTING MORE MONEY AND TAKING LONGER TO RESOLVE, WORLDWIDE

I

n the annual “Global Construction Disputes Report 2015,”1 ARCADIS found that, worldwide, construction projects are getting larger, more complex and as a result, carry more risk. The

report launched earlier this year highlights data gathered by the ARCADIS Construction Claims Consulting and EC Harris Contract Solutions teams that handled disputes in 2014. The research team found that worldwide, the industry has continued to experience growth in construction disputes in both cost (USD $51M on average) and

is completed, the issue becomes a formal dispute. The value of

the length of time required to resolve them (14.3 months).

a dispute includes the “additional entitlement to that which is

The research also revealed that the top causes of disputes—

included in the contract, for the additional work or event that

including errors and omissions; unforeseen site conditions,

is being claimed.” The length of the dispute is from when the

lack of understanding of the work by owner, contractor, or

disagreement becomes formalized under contract to when a

key subcontractors; and a failure to properly administer the

settlement is reached or at the conclusion of a hearing.

contract—are all under the construction team’s control.

Definitions

Overall Findings The research revealed some interesting data about global

The research team defines a “dispute” as any situation where

construction disputes. To IPI, these are the most compelling:

two parties differ on the “assertion of a contractual right, which

• The overall average value of a dispute has climbed since 2012

results in a decision being given under the contract.” Ultimately,

• The overall average length of time required to resolve a

when the project team disagrees on the decision and the project

dispute has climbed since 2012 • 1 in 3 (31%) Joint Ventures end up in a dispute (although

Top 5 Reasons for Disputes Worldwide: 1. Failure

to administer the contract

2. Poorly

drafted or incomplete and unsubstantiated claims

3. Errors

and omissions in the contract document

4. Failure

by team member to understand or comply with

its contractual obligation 5. Failure

to make interim awards on extensions of time

and compensation

averages vary widely worldwide) • The average dispute the ARCADIS and EC Harris teams were exposed to was USD $51M and the largest was valued at $2.13 billion • The most common method used by construction project teams is “party to party” negotiation, followed by Claims Mediation and then Arbitration • The most common cause of disputes worldwide is a failure to administer the contract properly, while in the United States it is errors and omissions in the contract. (Continuted on page 18)

16

Partnering Magazine September/October 2015

www.partneringinstitute.org


Issuu converts static files into: digital portfolios, online yearbooks, online catalogs, digital photo albums and more. Sign up and create your flipbook.