CONSTRUCTION UPDATEÂŚ Gettysburg Energy & Nutrient Recovery Facility, EnergyWorks BioPower, LLC Location

Gettysburg, Pa.

CHP

Yes

Engineer/builder

EnergyWorks, Adolfson & Peterson Construction

Government incentives

Yes

Primary fuel

Egg layer manure

IPP or utility

IPP

Boiler type

Gasifier and thermal oxidizer

Groundbreaking date

December 2011

Nameplate capacity

3.2 MW

Start-up date

Q4 2013

Project construction is in final stage before structural completion. Performance testing is scheduled to begin in October.

Location

Hopewell, Va.

CHP

No

Engineer/builder

Crowder Construction, ESI Inc., Babcock & Wilcox

Government incentives

Federal PTC, RECs

Primary fuel

Wood waste

IPP or utility

Utility

Boiler type

Stoker

Groundbreaking date

August 2012

Nameplate capacity

50 MW

Start-up date

October 2013

PHOTO: DOM POWER

Hopewell Power Station, DOM Power

Hopewell Power Station, DOM Power

Woodyard construction and boiler modifications are complete. Commissioning activities are ongoing. Atlantic Fiber Resources - Chander, Canadian Northern Timber Group

Rothschild Biomass Cogeneration Plant, We Energies Location

Rothschild, Wis.

CHP

Yes

Location

Chandler, Nova Scotia

Fire prevention technology

Firefly

Engineer/builder

Boldt

Government incentives

1603 Program grant

Builder

FW Technologies, Gremmier

Production capacity

240,000 metric tons/yr

Primary fuel

Urban wood waste, mill residue

IPP or utility

Utility

Pellet mill

TBD

Exporting/destination

Sweden, U.K., Germany, Ireland

Boiler type

Circulating fluidized bed

Groundbreaking date

June 2011

Feedstock

Softwood

Groundbreaking date

Q2 2012

Nameplate capacity

50 MW

Start-up date

December 2013

Pellet grade

Super premium

Start-up date

Q2 2015

Project is on hold pending an environmental study. Construction is planned to resume shortly.

Construction is 90 percent complete and the testing phase has started.

Southampton Power Station, DOM Power

German Pellets Louisiana, GmbH

Location

Franklin, Va.

CHP

No

Engineer/builder

Crowder Construction, ESI Inc., Babcock & Wilcox

Government incentives

Primary fuel

Wood waste

Boiler type Nameplate capacity

Location

LaSalle, La.

Fire prevention technology

German Pellet proprietary

Federal PTC, RECs

Builder

German Pellets Louisiana LLC

Production capacity

1.1 million tons/yr

IPP or utility

Utility

Pellet mill

Multiple companies

Exporting/destination

Yes/Europe

Stoker

Groundbreaking date.

October 2012

Feedstock

Softwood

Groundbreaking date

August 2013

50 MW

Start-up date

November 2013

Pellet grade

Industrial and premium

Start-up date

Q1 2014

Wood yard construction and boiler modifications are nearing completion. Biomass operations to begin in November.

Deconstruction of preexisting industrial plant has begun. Equipment has been ordered and construction of new buildings will begin this autumn.

Amite BioEnergy, Drax Biomass International Inc.

Morehouse BioEnergy, Drax Biomass Inernational Inc.

Location

Gloster, Miss.

Fire prevention technology

Fire Eye

Location

Beekman, La.

Fire prevention technology

Fire Eye

Builder

Haskell Company

Production capacity

450,000 metric tons/yr

Builder

Haskell Company

Production capacity

450,000 metric tons/yr

Exporting/destination

Yes/U.K.

Pellet mill

Exporting/destination

Yes/U.K.

Pellet mill Feedstock

Southern yellow pine

Groundbreaking date

August 2013

Feedstock

Southern yellow pine

Groundbreaking date

August 2013

Pellet grade

Industrial premium pellets

Start-up date

Q1 2015

Pellet grade

Industrial premium pellets

Start-up date

Q2 2015

Construction is on schedule.

Construction is on schedule.