January 2014 Biomass Magazine

Page 12

Biomass Power

Pellets

Biogas

Advanced Biofuel

FCPC Renewable Generation LLC Waste-to-Energy Facility

Hometown Bioenergy LLC, Minnesota Municipal Power Agency

Location

Milwaukee, Wis.

Location

Le Sueur, Minn.

Engineer/builder

Symbiont Inc., Miron Construction, Biothane

Engineer/builder

Barr Engineering, I&S Group

Substrate(s)

Food processing waste

Substrate(s)

Ag and food wastes

Digester type

Anaerobic membrane bioreactor

Digester type

Complete mix

Gas cleaning technology

H2S media treatment system

Gas cleaning technology

Biogas production capacity

500 scfm

Biogas production capacity

Biogas end use

CHP

Biogas end use

CHP

Installed power capacity

2 MW

Installed power capacity

8 MW

Groundbreaking date

October 2012

Groundbreaking date

December 2012

Start-up date

Q1 2014

Start-up date

December 2013

Construction is substantially complete and clear water testing is complete. Tanks are being filled in preparation for startup.

Plant commissioning activities are nearly complete. Gensets have been successfully commissioned on biogas; project completion is imminent.

The Plant, Bubbly Dynamics LLC

Sacramento Biodigester, CleanWorld Partners

Location

Chicago, Ill.

Location

Sacramento, Calif.

Engineer/builder

Eisenmann Corp.

Engineer/builder

Peabody Engineering, Otto Construction

Substrate(s)

food, brewery waste

Substrate(s)

Pre-and post-consumer food waste

Digester type

Continuous mixed horizontal plug flow

Digester type

three-stage, high-solids liquid digester

Gas cleaning technology

Biological desulphurization

Gas cleaning technology

BioCNG

Biogas production capacity

42 scfm in phase 1; 83 scfm in phase 2

Biogas production capacity

347 scfm

Biogas end use

CHP

Biogas end use

Power and vehicle fuel

Installed power capacity

500 kW

Installed power capacity

190 kW

Groundbreaking date

November 2012

Groundbreaking date

June 2013

Start-up date

Mid-2014

Start-up date

March 2014

Construction continues on schedule. Once complete, the digester will produce electricity and 700,000 gallons/year equivalent of renewable transportation fuel.

UC- Davis Renewable Energy Anaerobic Digestion, CleanWorld

UW Oshkosh Foundation, Rosendale Biodigester LLC

Location

Davis, Calif.

Location

Rosendale, Wis.

Engineer/builder

Peabody Engineering, Otto Construction

Engineer/builder

BIOFerm Energy Systems

Substrate(s)

food/ag waste, manure, animal bedding

Substrate(s)

Dairy manure

Digester type

Three-stage, high-solids liquid digester

Digester type

Complete mix

Gas cleaning technology

Unison Solutions

Biogas production capacity

123 scfm

Gas cleaning technology

Biological desulphurization, moisture removal, activated carbon filtration

Biogas end use

Power generation

Biogas production capacity

380-475 scfm

Installed power capacity

925 kW

Biogas end use

CHP

Groundbreaking date

May 2013

Installed power capacity

1.4 MW

Start-up date

January 2014

Groundbreaking date

July 2013

Construction continues on schedule. Micro-turbine commissioning has begun with landfill gas.

Start-up date

December 2013

Abengoa Bioenergy Biomass of Kansas LLC, Abengoa Bioenergy US

DuPont Cellulosic Ethanol - Nevada, DuPont

Location

Hugoton, Kan.

Location

Nevada, Iowa

Engineer/builder

Abengoa

Engineer/builder

Fagen

Process technology

Proprietory process

Process technology

Enzymatic hydrolysis

Biofuel product

Cellulosic ethanol

Biofuel products

Cellulosic ethanol

Feedstocks

Corn stover, wheat straw, switchgrass

Feedstocks

Corn stover

Production capacity

25 MMgy

Production capacity

30 MMgy

Type of RIN

D3

Type of RIN

90% D3 RINs

Coproducts

21 MW biomass power

Coproducts

Renewable solid fuel

Goundbreaking date

September 2011

Groundbreaking date

Q4 2012

Start-up date

December 2013

Start-up date

Q3/Q4 2014

The project is 90 percent complete. Boiler and 21-MW cogen plant commissioning is beginning.

12 BIOMASS MAGAZINE | JANUARY 2014

Digesters are mechanically complete and have undergone biological commissioning. CHP has been commissioned, and plant operations commissioning has begun. At At press time, commercial operation was imminent.

Construction is on track for a 2014 opening.