Land use Planning System and Housing Development Process in Malaysia

Page 183

159 After getting principle approval from the State Authority, the applicant has to submit the application to the particular local authorities to obtain planning permission approval. This Second Stage SBKS involves a detailed assessment of the layout plan by technical departments. The detailed assessment is required to ensure legislative provisions, planning standards and guidelines, and conditions by technical departments are fulfilled before an approval is granted by the LPA. The approved application will then be forwarded to the State Authority for the final land development or surrender and re-alienation approval (Figure 5.8). Technical Department District Land Office (PTD) State TCPD (JPBD) PWD (JKR) DID (JPS) DoE (JAS) District Office Fire Brigade Department Health Department Labour Department Survey Department Sewerage Department (JPP) TNB SAJ STM

APPLICANT

Application for planning permission LOCAL PLANNING AUTHORITY

Circulated to:

(Section 5, Act 172)

Consideration by the Town Planning Committee at Local Authority Absolute approval or conditional approval or reject Full Council Meeting (Local Authority)

Applicant

Layout Amendments Endorsement of layout plan

State TCPD

FINAL LAND APPLICATION OR SBKS APPROVAL PTG / PTD

Secretary Office to the State Committees

LAND MINES COMMITTEE

STATE EXCO MEETING

Notification

LOCAL AUTHORITY / TECHNICAL DEPARTMENTS

APPLICANT

Figure 5.8: The process of development approval at the Second Stage SBKS Sources: Adapted from Hassan Basery Hamzah (1996) and Alias (2004)